Structural Design Calculation

TECHNOCAST PRECAST L.L.C.


REV 0
5-May-14
QP 7.3 FORM 3

DESIGN CALCULATION SHEET

PROJECT PRECAST BOUDARY WALL

CONTRACT NO. CT-457

CLIENT MR. MOHAMED AL QUBAISI

CONSULTANT AL DANA ENGINEERING CONSULTANCY

CONTRACTOR -
Structural Design Calculation

a) Parameters

Contruction Live Load = 1.00 kN/m


Contruction dead Load = 3.00 kN/m (deck selfweight + fresh concrete
Length ( L) = 1.00 m
Total Uniform load (W) = 4.00 kN/m
Modulus of Elasticity = 200000.00 Mpa
Moment of Inertia = 379905.00 mm4
Section Modulus = 17590.00 mm3
Fy = 275.00 Mpa

(b) Maximum moment (M)

Mmax = WL/8
Mmax = 4.00 x 1.00^2 / 8
Mmax = 0.50 KN.m

Fb = M /Sx
M = Fb . Sx
M = 2902350.00 N.mm
M = 2.90 kN.m

(c) Maximum shear (V)

V1 = 0.5 WL
V1 = 0.5 x 4.00 x 1.00
V1 = 2.00 KN

Vd = 0.40 fy dc tw
Vd = 4400.00 N
Vd = 4.40 KN

dc= 50 mm
tw = 0.80 mm

(d) Deflection

i = 0.013 W L^4
EI
i = 0.013 x 4.00 x 1,000.00^4
200,000.00 x 379,905.00

2
Structural Design Calculation

i = 0.68 mm

3
Structural Design Calculation

eight + fresh concrete)

4
Structural Design Calculation