You are on page 1of 11

HOME

Processing of Magnetite Iron Ores Comparing Grinding


Options
B McNab1, A Jankovic2, D David3 and P Payne4

ABSTRACT Compared to direct ship haemetite ores mined from the upper
regolith, magnetite deposits require significant beneficiation,
Although the majority of current steel production is supported by iron ore
sourced from high-grade haemetite deposits, the long-term growing which typically involves grinding to a particle size where
demand for steel has led to higher raw material prices and opened the magnetite is liberated from its silicate matrix. Many banded iron
way for many new magnetite deposits to also be developed. formation deposits in the Pilbara and Yilgarn cratons within
There is a rich and long history of magnetite ore processing in Western Western Australia and the Gawler craton within South Australia
countries, including large operations such as Cleveland Cliffs in the USA are very fine grained, often requiring a final concentrate grind
and LKAB in Sweden, as well as smaller operations like Savage River in size P80 (80 per cent passing size) of 25 - 35 m. The amount of
Tasmania. The challenge for virtually all magnetite operations is to energy required to produce a magnetite product suitable for sale as
minimise operating costs, which is dominated by the cost of power pellet plant feed is substantially more than an equivalent direct
required to fine grind the ore in order to achieve acceptable concentrate ship lump (<32 mm >6 mm) and fines (<6 mm) haemetite project.
iron grade together with low impurity content. This remains the case
today and will be even more important in the future when a carbon tax is
expected to become a significant addition to the operating costs for MAGNETITE ORE GRINDING OPTIONS
magnetite deposits.
Various magnetite ore grinding flow sheets have been
Historically, the lowest operating cost was achieved by multistage fully implemented in the past, including:
autogenous grinding with integrated magnetic separation steps between
the stages. The major benefit of fully autogenous grinding is the conventional three (and four) stage crushing followed by
elimination of steel grinding media costs and the need to discriminate primary and secondary milling,
between steel and magnetite in coarse magnetic separation. The
separation step between grinding stages progressively reduces the amount primary crushing followed by wet semi-autogenous grinding
of material to be ground. (SAG) or autogenous (AG) milling and ball or pebble
Application of more efficient grinding technologies developed in the milling, and
last 20 years, including high pressure grinding rolls (HPGR) for fine air swept AG milling (for coarse grinding).
crushing and stirred milling for fine grinding, has provided opportunities
to further reduce the operating costs associated with comminution. Both Historically, the lowest operating cost for fine-grained ores
technologies are already implemented in some magnetite processing was achieved by multi stage fully autogenous grinding
operations, although in limited capacity. (Koivistoinen et al, 1989) with integrated magnetic separation
The results of a theoretical option study for high capacity processing of steps between the stages. The major benefit of fully autogenous
a hard, fine-grained silica-rich magnetite ore is presented in this paper, grinding is the elimination of steel grinding media costs and the
with the emphasis on comminution circuit options. Several circuit options need to discriminate between steel and magnetite in coarse
are ranked based on a net present value analysis incorporating an estimate magnetic separation ahead of pebble crushing. The separation
of carbon tax added in the operating cost. The study demonstrates the step between grinding stages progressively reduces the amount
significant advantages of applying more efficient autogenous grinding of material to be ground and in many cases reduces the abrasive
technologies.
properties of the concentrate.
Four North American subsidiaries of Cleveland-Cliffs Inc
INTRODUCTION employ autogenous milling. The original autogenous milling
World iron ore resources are estimated to exceed 800 billion circuit, consisting of an AG mill followed by cobber magnetic
tonnes and world iron ore production in 2006 was 1690 Mt. New separation of pebbles, pebble milling of the magnetic
iron ore mining capacity taken into operation in 2007 reached concentrate, a finisher magnetic separation stage and silica
almost 130 Mt globally (United Nations Conference on Trade flotation, was installed at Empire Mines in 1963 and had six
and Development, 2008). In Australia, magnetite is mined at the individual concentrating lines with a capacity of 1.6 Mt/a of
Savage River mine with reserves of 22 Mt of magnetite ore at pellets (Weiss, 1985). There have been three expansions since
and, in the 1990s, Empire Mines had a total of 24 individual
52 per cent Fe and the Iron Magnet deposit which has 300 Mt of
concentrating lines and a total plant capacity of 8 Mt/a of pellets.
magnetite ore reserves grading 37 per cent Fe. There are at
The target grind size of the circuit varies between the 90 -
least 4.5 billion tonnes of magnetite resources grading 33.5 -
95 per cent minus 500 mesh (32 m) depending on the ore and
36.5 per cent Fe in Western Australia, 1.5 billion tonnes at 31 - operating conditions (Rajala, Suardini and Walqui, 2007).
50 per cent Fe in South Australia and 700 Mt at 25 - 52 per cent
Fe in Tasmania and Queensland (Clout et al, 2004). LKABs Kiruna is the worlds largest, most modern
underground iron ore mine. Ore is mined using sublevel caving,
with sublevels spaced at 28.5 m vertically. After primary
crushing and hoisting to surface, the ore is processed in Kirunas
1. MAusIMM, GRD Minproc Limited, GPO Box Z5266, Perth WA
6831. Email: brian.mcnab@minproc.com.au complex consisting of a sorting plant, two concentrators and two
pellet plants to give pellet and sinter fines products (see
2. MAusIMM, GRD Minproc Limited, The Precinct 2, Level 2, http://www.lkab.com/). Magnetite ore is ground using AG mills
10 Browning Street, West End Qld 4101. followed by cobber magnetic separation and pebble milling of
Email: alex.jankovic@minproc.com.au
the magnetic concentrate (Hahne, Palsson and Samskog, 2003).
3. MAusIMM, GRD Minproc Limited, GPO Box Z5266, Perth WA The target grind size is around 80 per cent minus 45 m
6831. Email: dean.david@minproc.com.au depending on the ore and operating conditions (Tano et al, 2006).
4. GRD Minproc Limited, GPO Box Z5266, Perth WA 6831. Application of more efficient grinding technologies developed
Email: phil.payne@minproc.com.au in the last 20 years, including high pressure grinding rolls

Iron Ore Conference Perth, WA, 27 - 29 July 2009 277


B McNAB et al

(HPGR) for fine crushing and stirred milling for fine grinding, A minimum set of ore comminution properties are required for
has provided opportunities to further reduce the operating costs a conceptual design. An example is provided in Table 1 and is
associated with grinding. At Empire Mines a HPGR is installed used as the basis for this theoretical study.
for processing crushed pebbles and its introduction has resulted
in a primary AG mill throughput increase in the order of TABLE 1
20 per cent (Dowling et al, 2001). Application of Vertimill fine
Ore design parameters.
grinding technology at Hibbing Taconite Company enabled
processing of lower grade ores and increased the concentrate Ore grade % FeT 32.2
production (Pforr, 2001). Drop weight index (DWi) kWh/m3 11.1
The Whyalla magnetite plant in South Australia is specific
Ore specific gravity 3.40
because it utilises the HPGR technology for comminution of the
primary ore. The HPGR circuit is closed with a 3 mm aperture Concentrate specific gravity 4.30
wet screen with the undersize reporting to the rougher magnetic Bulk density t/m3 2.01
separators (RMS). Banded iron formation (BIF) ores at Whyalla Bond ball mill work index (BBWi) kWh/t 17.2
allow a relatively large silica rejection to the RMS tailings stream
and so are well suited to the particle size that can be effectively Bond abrasion index (BAi) 0.3
generated by a commercial size closed circuit HPGR system. Bond rod mill work index (BRWi) kWh/t 17.7
Figure 1 shows the plant feed bin (left of photo) and the high Bond crushing work index (BCWi) kWh/t 20.6
pressure grinding rolls.
Point load index (PLI) MPa 14.8
Unconfined compressive strength (UCS) MPa 355
Fibrous mineral content Nil

The magnetite concentrate weight recovery, specific gravity


(SG), predicted Bond abrasion index (BAi), iron and silica
content were based on the following relationships:
Concentrate weight recovery% = 10.737 ln(P80) - 3.0945
Concentrate iron content Fe% = -8.4667 ln(P80) + 98.455
(% Fe 518
. ) % Fe 3.0
Concentrate SG = 0.84 + 1
724 724

Concentrate Ai = 0.05(%Si020.4332)
Concentrate silica content Si02 % = 9.6966 ln(P80) - 29.571
The fine-grained nature of this hypothetical ore results in a
FIG 1 - High pressure grinding rolls at Whyalla magnetite relatively late release or liberation curve as illustrated in Figure 2.
concentrator plant (Morgan, 2007). This fundamental property of a magnetite ore is generally one of
the most salient drivers of flow sheet design and therefore flow
STUDY OPTIONS sheet option generation. For example, it is not uncommon for
magnetite banded iron formation ores to exhibit two distinct
An option study for a 10 Mt/a ore processing plant for a liberation zones, a coarse size consistent with the inherent silica
consistently hard, fine-grained silica-rich magnetite ore was banding width and a finer size related to the unlocking of
carried out, with the emphasis on comminution circuit options. A silicates within the magnetite bands.
capacity of 10 Mt/a was selected to simplify the comparison by For the ore considered, only 20 - 30 per cent of feed mass can
keeping within the current single processing line limitations of the be rejected magnetically in the size range typical for closed
worlds largest AG mill capabilities. In practice, GRD Minproc circuit HPGR operation. Conversely, significant mass up to
has undertaken studies of Australian concentrators from 10 Mt/a approximately 50 per cent can be rejected to tails at a P80 of
up to 80 Mt/a, whereby the level of design, layout and operation 150 m which could be achievable with a closed circuit AG mill
complexity significantly appreciates when multiple trains of operation.
worlds largest equipment need to be integrated.
For the purpose of the study, the concentrator was assumed to FLOW SHEET OPTIONS
be located in the Pilbara of Western Australia within 100 km of a Four circuit options were considered for comparison with the
port suitable for facilitating equipment delivery. It was assumed following acronyms used to identify the primary unit process
that there were no restrictions on spatial layout and that the within each:
process facility would be built on ground of a sound geotechnical
character. Any subsequent differences in tailings disposal, water COS coarse ore stockpile,
recovery, operation and cost were not considered. SC secondary crush,
The approach taken in comparing various flow sheet options HPGR high pressure grinding roll,
was in line with GRD Minprocs typical conceptual or scoping
level assessment methodology and delivers a plus or minus AGC autogenous mill in closed circuit with cyclones and
35 per cent capital and operating cost accuracy. Such an exercise pebble crusher,
is recommended at the commencement or prior to the RMS rougher magnetic separation,
prefeasibility study phase of a magnetite project. To enable a
meaningful study a minimum required level of comminution and
CMS cleaner magnetic separation,
beneficiation test work should have been undertaken beforehand. CMS2 second cleaner magnetic separation,

278 Perth, WA, 27 - 29 July 2009 Iron Ore Conference


PROCESSING OF MAGNETITE IRON ORES COMPARING GRINDING OPTIONS

90

y = 10.737ln(x) - 3.0945
80 R = 0.9705

Mass % of feed to magnetic concentrate


70

60

50

40

30
10 100 1000 10000

P80 Size (m)

FIG 2 - Grind versus liberation.

PM pebble mill, In Option 3 secondary crushing and HPGR effectively replace


AG milling with pebble crushing. Application of HPGR, stirred
PC primary crusher, milling and additional magnetic separation stage reduces the
SM stirred mill, and power requirements compared to Options 1 and 2. The flow sheet
TSF tailings storage facility. is similar to that applied at Project Magnet south of Whyalla in
South Australia and the proposed Gindalbie Project east of
Geraldton in Western Australia.
Option 1 PC/AGC/RMS/PM/CMS
A P80 of 2300 m was nominated for the RMS feed, 75 m for
Primary crushing AG milling in closed circuit with the CMS feed and 30 m for the CMS2 feed. This would
hydrocyclones and pebble crushing rougher magnetic separation necessitate wet screening to close the HPGR circuit.
pebble milling cleaner magnetic separation (see Figure 3).
Option 1 resembles the well known fully autogenous LKAB Option 4 PC/SC/O HPGR/PM1/RMS/PM2/CMS1/
and Cleveland Cliffs style operations. Absence of steel grinding SM/CMS2
media significantly reduces the operating cost. Pebble mill
control and pebble transport and handling requirements add Primary crushing secondary crushing screening open
complexity to the design and operation. A P80 of 250 m was HPGR coarse pebble milling rougher magnetic separation
nominated for the RMS feed. fine pebble milling first cleaner magnetic separation tertiary
milling using autogenous stirred mills second cleaner magnetic
Option 2 PC/AGC/RMS/BM/CMS/SM/CMS2 separation (see Figure 6).
Primary crushing AG milling in closed circuit with Option 4 is an attempt to design a circuit with the lowest
hydrocyclones and pebble crushing rougher magnetic operating cost through increased grinding energy efficiency
separation ball milling cleaner magnetic separation tertiary using three stages of magnetic separation, traditional
milling using stirred mills second cleaner magnetic separation. autogenous milling, HPGR and stirred milling technology. In
(see Figure 4) this conceptual flow sheet steel grinding media is eliminated.
Option 2 has an additional grinding and magnetic separation Circuit complexity is partially reduced by open circuit
stage compared to Option 1 and is considered to be simple in secondary crushing, HPGR grinding and stirred milling
design and operation. In respect to the grinding flow sheet, it is operation although recovery, storage and control of three
similar to the Savage River operation although the AG mill is separate sized media streams is introduced. It is assumed that a
closed with hydrocyclones rather than screens, there is no magnetic selection process is applied to collect each media
hydroseparator and a third stage of comminution has been added stream thereby maximising the power drawn thus capability of
in respect of the finer liberation requirement. For reasons of cost the downstream autogenous grinding unit.
estimation and layout simplicity hydrocyclones have been A P80 of 500 m was nominated for the RMS feed, 75 m for
selected rather than screens to close the AG mill circuit for both the CMS feed and 30 m for the CMS2 feed.
Options 1 and 2.
A P80 of 250 m was nominated for the RMS feed, 75 m for
the CMS feed and 30 m for the CMS2 feed. ENERGY COMPARISON
With the exception of the primary crushing module, which is
Option 3 PC/C SC/C HPGR/RMS/BM/CMS1/SM/ consistent between options, estimates were developed for the
CMS2 total power drawn in the comminution, classification and
Primary crushing closed circuit secondary crushing closed magnetic separation areas of each circuit. Energy consumed by
circuit HPGR rougher magnetic separation ball milling first material transport machinery related to pumping between areas
cleaner magnetic separation tertiary milling using stirred mills was not considered at this level of study. A summary of the
second cleaner magnetic separation (see Figure 5). resultant unit circuit energy for each option is shown in Figure 7.

Iron Ore Conference Perth, WA, 27 - 29 July 2009 279


B McNAB et al

FIG 3 - Option 1 flow sheet.

FIG 4 - Option 2 flow sheet.

280 Perth, WA, 27 - 29 July 2009 Iron Ore Conference


PROCESSING OF MAGNETITE IRON ORES COMPARING GRINDING OPTIONS

FIG 5 - Option 3 flow sheet.

FIG 6 - Option 4 flow sheet.

Iron Ore Conference Perth, WA, 27 - 29 July 2009 281


B McNAB et al

35
33.0
31.6

30

25.0 24.7
25

Circuit Energy (kWh/feed tonne)


20

15

10

0
Option 1 Option 2 Option 3 Option 4

FIG 7 - Circuit energy comparison.

A significant circuit energy reduction is predicted with


Options 3 and 4, which include HPGR and stirred milling. Some TABLE 2
33 per cent of additional energy separates the most energy Key operating cost inputs.
efficient option (Option 4) from the least efficient, the two
Power $/MWh 120
stage AGC Pebble circuit, Option 1. In todays market and the
projected energy market during the life cycle of a typical Ball mill steel media $/t delivered 1501
magnetite concentrator the magnitude of this difference is Stirred mill steel media $/t delivered 1814
significant unless the cost of power is negligible (<$20/MWh), Labour on-cost % 50
which is very rarely the case.
Total HPGR cost $/t of HPGR feed 0.35
Interestingly if weighted averages are calculated for the
combined tailings from each circuit the outcomes for Options 3
and 4 do not parallel the energy consumption comparison. The estimates as summarised below are judged to have an
Option 3 with the coarse feed to the RMS has an average tail P80 accuracy of 35 per cent. Unit cost breakdowns are presented
of 736 m and Option 4 284 m. Some economic advantages and shown graphically in Figure 8:
may be realised by the coarser tails product although are beyond
the scope of this comparison.
Option 1 $6.17,
According to Seidel et al (2006), the basic comminution Option 2 $6.42,
energy requirement for the Boddington HPGR circuit option was Option 3 $6.66, and
14 per cent lower than the SAG option; however, the overall
energy requirement including conveying, screening, etc, was
Option 4 $5.38.
only five per cent lower. The Boddington copper gold ore is of The most significant operating cost variables between options
similar rock competency to that selected for this study and so are those relating to power, media and liner consumption. The two
provides a good contrast between comminution processes options including AG mill circuits have between 27 - 32 per cent
designed to liberate minerals for flotation, in which the whole higher power consumption cost relative to Option 4. Or looking
ore is ground to fine size, and comminution designed to reject from the other perspective, application of new technologies
silicates via magnetic processes. In the latter case energy resulted in an average 25 per cent energy consumption reduction.
efficiency between flow sheet options can be far more extreme. Grinding media and wear lining costs range between $0.41/t
and $1.82/t. Option 3 has the highest media and wear lining cost
PROCESS OPERATING COST as two ball mills of 8.8 MW installed power are required to grind
8 Mt/a of RMS concentrate from P80 2.3 mm to P80 75 m. This
Albeit a high-level comparison, a fairly rigorous approach was is the largest ball milling duty of all options being some 2.8
taken to the development of operating costs for each option. times larger than the Option 2 requirement.
Consumption rates for power, wear and other consumables,
labour and maintenance and materials were generated A carbon tax is expected to be introduced in the near future
considering each process flow sheet from the COS reclaim and would add a significant cost to the operation. For this
feeders to either the final magnetic separator concentrate exercise a simplified estimate of the effect of carbon tax is
discharge or the magnetic separator tailings discharge. As such, considered. It was assumed that the carbon tax would be applied
no concentrate or tailings handling, filtration or storage costs to total circuit energy and steel consumption relating to media
were considered. For simplicity, some minor operating costs such and comminution equipment wear liners. The following criteria
as metallurgical test work and analysis, which is considered were applied for the carbon tax estimate:
common to all options, have been omitted. Unit costs for power, CO2 emission, 5 t per 1 t of steel media (Price et al, 2002); and
grinding media, wear consumables and labour were referenced
from average values within the GRD Minproc database for CO2 emission, 1.0 kg per kWh of electricity, CO2 tax, $23 per
similar sized and located projects. A factoring approach from tonne of CO2 (Australian Government, 2008).
direct capital cost was used to develop cost estimates for Table 3 shows a summary of calculations related to carbon
maintenance materials. Key assumptions are listed in Table 2. All emission and carbon tax effect on OPEX. It can be observed that
costs are estimated in Australian dollars and are presented as first the introduction of carbon tax at $23/t would increase OPEX in
quarter 2009 costs. the order of nine to 11 per cent. The majority of carbon emission

282 Perth, WA, 27 - 29 July 2009 Iron Ore Conference


PROCESSING OF MAGNETITE IRON ORES COMPARING GRINDING OPTIONS

00
7.
00
6.
Operating Costs ($/feed t)

00
5.
00
4.
00
3.
00
2.
00
1.
00
0.

Option 1
Option 2
Option 3
Option 4

Option 1 Option 2 Option 3 Option 4


MISCELLANEOUS 0.17 0.18 0.17 0.17
LABOUR 0.80 0.85 0.87 0.90
MAINTENANCE MATERIALS 0.83 0.86 0.81 0.79
GRINDING MEDIA & WEAR LINERS 0.41 0.74 1.82 0.66
POWER 3.95 3.79 2.99 2.86

FIG 8 - Operating cost comparison.

Indirect costs
TABLE 3
Carbon emissions and carbon tax summary. Indirect costs are those expenditures covering engineering,
procurement and construction management (EPCM) services
Option 1 Option 2 Option 3 Option 4 together with the supervision of the commissioning of the works.
Power CO2 t/a 329 503 315 768 248 757 238 328 Contract works and goods in transit insurance have also been
included. Temporary construction facilities have been included in
Steel CO2 t/a 5804 18 256 37 300 8306 Indirects.
Total CO2 t/a 335 307 334 023 286 057 246 634
CO2 tax $/t 0.77 0.77 0.66 0.57 Contingencies (growth allowance)
OPEX $/t (no CO2 tax) 6.17 6.42 6.66 5.38 Contingencies have been assigned as an overall percentage to the
CO2 tax % OPEX 11.1 10.7 9.0 9.3 total estimate. Contingency has been applied to the estimate to
make allowance for the following risks:
is from electrical energy consumption while indirect contribution minimal design input,
from steel consumption (dominated by grinding media) is in preliminary scope definition,
the order of five to 16 per cent for Options 2 and 3 that utilise
ball milling.
quantity survey errors and omissions,
material and labour rate accuracy,
PROCESS CAPITAL COST equipment budget costing, and
The scope of the estimates follows the work breakdown structure incorrect bulks factor application.
developed specifically for the study and considers each flow
sheet from the COS reclaim feeders to either the final magnetic Estimation methodology
separator concentrate discharge or the magnetic separator tailings
An industry standard methodology for a conceptual level
discharge. As such, no concentrate or tailings handling, filtration estimate has been applied for the cost comparison and includes,
or storage was considered. For simplicity some equipment or bulk quantities, equipment and platework, freight, capital
costs considered common to all options have been omitted. spares, temporary facilities, indirect costs, temporary facilities
The estimate is developed based on the premise that the process and EPCM and contingencies (growth allowance).
is located inland in north-west Western Australia. All costs are A detailed equipment list has been prepared and imported into
estimated in Australian dollars and are presented as first quarter the estimate. For each item of equipment costs have been entered
2009 costs. They are judged to have an accuracy of 35 per cent, as per the basis outlined above. Budget quotes have been received
which is commensurate with the accuracy requirements for a high for certain items of major equipment. GRD Minprocs database
level options study of this nature. information (or allowances) has been used for other equipment
The capital cost estimates have been structured into three items appropriately factored and escalated where necessary.
major categories, detailed below. The estimates are summarised and tabulated in Table 4:
Option 1 $346.6 M,
Direct costs
Option 2 $356.9 M,
Direct costs are those expenditures that include supply of
equipment and materials, freight to site and construction labour Option 3 $321.3 M, and
relevant to the particular option. Option 4 $312.6 M.

Iron Ore Conference Perth, WA, 27 - 29 July 2009 283


B McNAB et al

Total estimated capital costs for each circuit are within 14 per deficit relative to Option 4. This option is disadvantaged by both
cent, which does not infer any one option is a standout from a high capital and operating cost.
capital cost perspective. Due to the higher power drawn by The all autogenous Option 4 flow sheet is $94 M lower than
Options 1 and 2, which include AG mill circuits, a lower capital the next best option, Option 1. The conclusion drawn from this
cost to power consumption ratio results. Option 1 offers the financial evaluation is that highly energy efficient autogenous
lowest ratio with $8.4 k/kW consumed, Option 2 has $9.0 k/kW processing routes can offer significant benefits for competent
consumed and Options 3 and 4 with $10.3 k/kW $10.1 k/kW magnetite ores requiring fine grinding. Were this hypothetical
respectively (refer Table 4). process design to be advanced, piloting test work would be well
justified to explore the validity of the key autogenous unit
processes proposed within Option 4.
FINANCIAL COMPARISON
Having established a relative NPV comparison a variability
Applying a ten per cent discount rate over 12 years of operation, analysis was undertaken to understand each flow sheet options
high level, pre-tax, net present value (NPV) determinations were sensitivity to two key operating cost inputs namely power and
calculated for Options 1 to 3 relative to the base case, Option 4, ball mill media. The outcomes are presented graphically in
which returned the lowest capital and operating cost. Figure 9 Figures 10 and 11.
compares these outcomes. Not surprisingly, Options 1 and 2, which are the most energy
Options 1 and 3 have a similar NPV outcome ranging between intensive circuits, are found to be highly sensitive to power cost
negative $94 - 95 M relative to Option 4. A $1 M variance is when compared relative to Option 4. Only in the case that power
viewed as being immaterial relative to the accuracy of the study. could be supplied at a zero cost could Option 1 (AGC/RMS/
Option 2 shows the least favourable outcome with a $118 M NPV PM/CMS) approach the NPV value of Option 4.

TABLE 4
Capital cost comparison.

Area number Area description Option 1 Option 2 Option 3 Option 4


Direct costs $ $ $ $
001 Coarse ore feed 7 237 040 7 237 040 7 151 313 6 241 940
002 AG mill grinding 80 068 915 88 965 461
002 Secondary crushing 18 809 132 13 923 099
002A Tertiary crushing 11 969 442
003 Pebble recycle crushing 17 704 056 14 972 636
003 HPGR circuit 34 215 535 20 430 750
003A Pebble mill grinding and pebble storage 36 389 765
004 Rougher magnetic separation 2 272 362 2 272 362 3 282 300 2 524 846
005 Ball mill grinding 18 264 249 48 448 884
005 Pebble mill grinding 90 872 360 27 801 316
006 Concentrate separation and fine milling 76 680 928 76 680 928 66 959 736
006 Concentrate separation 2 758 989
Total process plant 200 913 722 208 392 675 188 588 092 186 240 895
Site preparation and improvements 2 098 103 2 083 927 1 885 881 1 862 409
Control aystems 4 552 915 4 586 582 3 668 577 3 463 224
Total plant infrastructure 6 651 018 6 670 509 5 554 458 5 325 633
First fill reagents and consumables (allowance) 0 2 646 705 3 413 705 0
Ocean freight 10 180 855 10 095 453 7 373 659 7 405 066
Spares 5 630 444 5 612 860 4 325 727 4 219 437
Mobilisation/demobilisation and preliminaries 6 447 027 6 287 927 6 554 941 6 759 735
Commissioning assistance 2 098 103 2 083 927 1 885 881 1 862 409
Total miscellaneous 24 356 429 26 726 872 23 553 914 20 246 647
Total direct cost 231 921 169 241 790 056 217 696 463 211 813 176
Indirect costs
Temporary facilities 19 265 417 19 343 204 17 415 717 16 945 054
EPCM 36 122 657 36 268 508 32 654 469 31 771 976
Total indirect costs 55 388 074 55 611 713 50 070 186 48 717 031
Total costs (net) 287 309 243 297 401 769 267 766 649 260 530 207
Growth, contingency, risk 59 241 158 59 480 354 53 553 330 52 106 041
Total costs (overall) 346 550 401 356 882 123 321 319 979 312 636 248
Delta total cost relative to Option 4 33 914 153 44 245 875 8 683 731 0
Total cost/kW drawn 8414 9041 10 289 10 108

284 Perth, WA, 27 - 29 July 2009 Iron Ore Conference


PROCESSING OF MAGNETITE IRON ORES COMPARING GRINDING OPTIONS

-140

-120

Delta NPV Relative to Option 4 ($M)


-100

-80

-60 -118

-94 -95
-40

-20

0
Option 1 Option 2 Option 3

FIG 9 - Net present value (NPV) (comparison).

$0

-$20,000,000

-$40,000,000
Delta NPV Relative to Option 4 ($)

-$60,000,000 Option 1

Option 2
-$80,000,000

Option 3
-$100,000,000

-$120,000,000

-$140,000,000

-$160,000,000
0 20 40 60 80 100 120 140 160 180 200
Power Cost ($/MWh)

FIG 10 - Net present value sensitivity to power cost.

$0

-$20,000,000
Delta NPV Relative to Option 4 ($)

-$40,000,000

Option 1
-$60,000,000

Option 2
-$80,000,000

Option 3
-$100,000,000

-$120,000,000

-$140,000,000
700 800 900 1000 1100 1200 1300 1400 1500 1600 1700

Ball Mill Media Cost ($/t)

FIG 11 - Net present value sensitivity to ball mill media cost.

Iron Ore Conference Perth, WA, 27 - 29 July 2009 285


B McNAB et al

Ball mill media cost is only relevant to Options 2 and 3 as the requisite test work is completed prior to undertaking comparative
other circuits include autogenous grinding. Figure 11 highlights conceptual or prefeasibility studies. This approach infers test
the high NPV sensitivity to ball mill media cost for Option 3, work and study planning need to be suitably timed to ensure an
which considers the largest ball milling duty. Although the NPV adequate basis is available at the commencement of a study
relationship shown is steep, Option 3 would not become period. The rapid pace of project evaluation and development
economically equivalent to Option 4 even at a zero ball mill experienced during the 2006 to 2008 mining boom did not
media cost. always permit this strategy and in many cases has led to higher
project risk, inefficient engineering practices and slow
DISCUSSION commissioning and ramp up. Further information describing
Some clear understanding of the economic merits of process GRD Minprocs approach to geometallurgy and analysis can be
circuit options can be gleaned by developing a comparative study referenced in David (2007).
as illustrated by this paper. In this case it was found that highly
energy efficient autogenous processing routes can offer CONCLUSION
significant benefits for fine-grained competent magnetite ores.
The traditional AG mill and pebble mill style comminution The primary conclusion drawn from this financial evaluation is
circuit or those requiring significant steel grinding media to that highly energy efficient autogenous processing routes with
operate have been found to be suboptimal from a pure economic multiple separation stages offer significant financial benefits for
perspective. Circuit options favouring multistage magnetic fine-grained hard magnetite ores. For the ore type evaluated, the
separation and with energy efficient autogenous comminution application of HPGR and stirred mill technology is indicated to
equipment are more likely to add project value. reduce energy consumption by up to 25 per cent compared to
The approach taken in this paper to compare flow sheet conventional flow sheets with wet tumbling mills.
options was purely economic and to a large degree simplified by Flow sheet design and option selection should be tailored to
assumptions. In practice there are many other flow sheet the magnetite ore comminution and liberation characteristics. For
selection drivers that can become relevant or even exclusively fine-grained ores the addition of a third grinding stage which
dominant. Some examples of these from recent GRD Minproc utilises energy efficient stirred milling benefits the economics in
experience include: two ways: reducing the amount of material that need to be fine
the identification of fibrous minerals within the ore; ground and grinding at high energy efficiency. The application of
the availability/cost of water; HPGR technology significantly reduces the energy consumption
compared to AG milling. A synergy of HPGR and primary
the capability of the project owner to accept risk; pebble milling, as proposed for Option 4, can result in a very
spatial layout constraints, ground slope and geotechnical effective circuit from a capital and operating point of view with
characteristics; HPGR working in open circuit feeding the primary pebble mill
a prescribed study and development schedule that does not which in addition to grinding, generates grinding media
allow sufficient time or budget for comparative test work (pebbles) for the secondary pebble milling circuit. The product
programs; from the primary pebble mill is much finer than what can be
practically obtained from a closed HPGR circuit and thus the tail
variability in rock competency or magnetite liberation;
rejection at the RMS is higher which significantly reduces the
social and environmental risks relating to dust and the costs duty of the following pebble milling stage.
associated in dust collection and control; The magnetite market in general and the required scale of
the effect of moisture on HPGR performance and caking magnetite concentrator capacity is rapidly expanding and as a
properties of HPGR product; result will amplify the importance and value of sound
metallurgical investigation and process design. To this end a well
long-term predictions for the cost of power and grinding
structured and scheduled study and evaluation period is of
media; and
considerable importance if the objective is to maximise life cycle
the cost impacts of tailings including capital, operating cost project value and mitigate financial and stakeholder risk.
and environmental risks. An introduction of a carbon tax at levels indicated by the
To expand further on the final point other capital and operating Australian government is predicted to increase the operating cost
costs components related to different options for tails disposal for this type of operation significantly, in the order of nine to
would need evaluation in the next phase of study. Options which 11 per cent or $0.57 - $0.77/t of ore.
allow coarse RMS tailings, such as Options 3 and 4 in this paper,
offer the potential to be inexpensively dewatered and either ACKNOWLEDGEMENT
conveyed or transported by dump truck to be either comingled
with mining waste or dumped in a separate tailings storage The authors acknowledge the permission of GRD Minproc to
facility (TSF). Cost savings in process water consumption and publish this paper and the assistance of James Higgie in
TSF capital may be realised with this approach. compiling flow sheets and operating costs during his student
vacation work period.
The justification and value of this type of evaluation process is
reflected by the magnitude of the NPV delta produced. In this
case a $118 M delta resulted between the options considered. It REFERENCES
is therefore not unreasonable to expect that flow sheet selection Australian Government, 2008. Carbon Pollution Reduction Scheme:
has the potential to vary project value by up to one billion dollars Australias Low Pollution Future White Paper, volume 1,
for the worlds largest scale magnetite projects being considered. December.
In comparison, the total cost of sample collection, metallurgical Clout, J M F, Trudu, A, Zhu, D, Holmes, R J and Young, J, 2004.
bench and pilot scale test work and engineering studies becomes Australian magnetite resources and pellet plants, in Proceedings
2004 Pelletizing Conference, Dalian, China, 19 - 22 August.
inconsequential for such projects.
David, D, 2007. The importance of geometallurgical analysis in plant
GRD Minproc places a high importance on developing and study, design and operational phases, in Proceedings Ninth Mill
understanding geometallurgical relationships during the project Operators Conference 2007, pp 241-248 (The Australasian Institute
evaluation phase and as such would recommend that the of Mining and Metallurgy: Melbourne).

286 Perth, WA, 27 - 29 July 2009 Iron Ore Conference


PROCESSING OF MAGNETITE IRON ORES COMPARING GRINDING OPTIONS

Dowling, E C, Corpi, P A, McIvor, R E and Rose, D J, 2001. Application Price, L, Sinton, J, Worrell, E, Phylipsen, D, Huc, X and Li, J, 2002.
of high pressure grinding rolls in an autogenous Pebble milling Energy use and carbon dioxide emissions from steel production in
circuit, in Proceedings SAG 2001 Conference, Vancouver, vol III, China, Energy, 27(2002):429-446.
pp 194-201. Rajala, G, Suardini, G and Walqui, H, 2007. Improving secondary
Government of India, 2007. Comprehensive industry document on iron grinding capacity at Empire Concentrator, SME Annual Meeting,
ore mining, Ministry of Environment and Forest, Government of Denver, 25 - 28 February.
India [online]. Available from: <http://www.cpcb.nic.in> [Accessed: Seidel, J, Logan, T C, LeVier, K M and Veillette, G, 2006. Case study
2007-08]. Investigation of HPGR suitability for two gold/copper prospects, in
Hahne, R, Palsson, B I and Samskog, P O, 2003. Ore characterization for Proceedings SAG 2006 Conference, Vancouver, vol IV, pp 140-153.
and simulation of primary autogenous grinding, Minerals Tano, K T, Plsson, B I, Alatalo, J and Lindquist, L, 2006. The use of
Engineering, 16:13-19. process simulation technology in process design when time and
Koivistoinen, P, Virtanen, M, Eerola, P and Kalapudas, R, 1989. A performance is critical, SME Annual Meeting, Denver, February.
comminution cost comparison of traditional metallic grinding, United Nations Conference on Trade and Development, 2008. The Iron
semiautogenous grinding (SAG) and two stage autogenous grinding, Ore Market 2007 - 2009 [online]. Available from:
in Proceedings SAG 1989 Conference, Vancouver. <http://www.unctad.org/infocomm/Iron/covmar08.htm#abstract>.
Morgan, A, 2007. Project Magnet HPGRs [online]. Available from: Weiss, N L (ed), 1985. SME Minerals Processing Handbook, pp 20-27
<http://www.amped.net.au/2007_06_01_archive.html>. (Society for Mining, Metallurgy and Exploration, Inc: Littleton).
Pforr, B, 2001. Fine screen oversize grinding at Hibbing Taconite
Company, SME Annual Meeting, Denver, February.

Iron Ore Conference Perth, WA, 27 - 29 July 2009 287

You might also like