You are on page 1of 28

Fdration Internationale des Ingnieurs-Conseils

THE FIDIC CONTRACTS


AND THEIR USE

Presentation by Daniel Ivarsson


Managing Director of FIDIC
FIDIC CONTRACTS
Fdration Internationale des Ingnieurs-Conseils

CONSTRUCTION

PLANT AND DESIGN-BUILD

EPC/TURNKEY PROJECTS

SHORT FORM OF CONTRACT

CLIENT/CONSULTANT MODEL SERVICES AGREEMENT


WHICH BOOK TO USE?
Fdration Internationale des Ingnieurs-Conseils

CONDITIONS
STRAIGHTFORWARD OF
PROJECT ? EMPLOYER DESIGN ? CONTRACT
no yes FOR
yes
CONSTRUCTION
SHORT no
FORM CONTRACTOR DESIGN
CONTRACT fixed price - lump sum
little employer involvement plant and/or high
no major unforeseen risks no unforeseen risks
no yes yes

Conditions of
Conditions of
DISCUSS IN DETAIL Contract Contract for
Plant and
Employer s requirements for EPC
Design Build
with the Contractor, and
Turnkey Projects
negotiate a modified
FIDIC contract
FEATURES AND ADVANTAGES
Fdration Internationale des Ingnieurs-Conseils

BALANCED
fair apportioning of risks, rights and obligations between the parties

WELL TRIED
long case history for earlier contracts

ACCEPTED
known and recognised; in wide use for international contracts

SUPPORTED
recommended or required by development banks, ISPA, etc.

EFFECTIVE

clear and complete conditions; time limits; provisions for adjudication


Key points: CONSTRUCTION
Fdration Internationale des Ingnieurs-Conseils

Employer responsible for design

Engineer, working for the Employer

Drawings, specifications, Bill of Quantities

Payments based upon measurements

Certification of payments by Engineer


Key points: PLANT & DESIGN-BUILD
Fdration Internationale des Ingnieurs-Conseils

Contractor responsible for design

Engineer, working for the Employer

Employers requirements

Lump sum pricing

Payments according to progress

Certification of payments by Engineer


Key points: EPC/TURNKEY PROJECTS
Fdration Internationale des Ingnieurs-Conseils

Contractor responsible for design and takes full


responsibility

Employer may appoint a Representative

Fixed price, to cover risks taken on by Contractor

Payments according to progress

No certification of payments
Key points: SHORT FORM
Fdration Internationale des Ingnieurs-Conseils

Simple projects

Design by either party

Employer may appoint a Representative

Valuation as appropriate; to be agreed

Payments according to value of Works executed and


Materials and Plant delivered to site

No certification of payments
Key points: CLIENT/CONSULTANT
Fdration Internationale des Ingnieurs-Conseils

Agreed Scope of Services: Appendix A

Normal, Additional and Exceptional Services

Normal Services priced as agreed

Additional and Exceptional Services at rates agreed

Payment schedule as agreed


STRUCTURE: 3 MAIN CONTRACTS
Fdration Internationale des Ingnieurs-Conseils

General Conditions
Guidance for the Preparation of the Particular Conditions
Letter of Tender
Contract Agreement
Dispute Adjudication Agreements
Twenty main clauses, covering similar matters
Exceptions: Clauses 3, 5 and 12:
Construction: Plant and D-B: EPC/Turnkey:
3. Engineer Engineer Employers Admin.
5. Subcontractors Design Design
12. Measurement Tests after Compl. Tests after Compl.
STRUCTURE: SHORT FORM
Fdration Internationale des Ingnieurs-Conseils

Agreement
General Conditions
Particular Conditions
Rules for Adjudication
Notes for Guidance
STRUCTURE: CLIENT/CONSULTANT
Fdration Internationale des Ingnieurs-Conseils

Agreement
General Conditions
Particular Conditions
Appendix A: Scope of Services
Appendix B: Personnel, equipment, facilities and services
of others to be provided by the client
Appendix C: Remuneration and payment
THE 1992 (OLD) AND 1999 (NEW) RED BOOKS
SOME DIFFERENCES
Fdration Internationale des Ingnieurs-Conseils
THE 1992 (OLD) AND 1999 (NEW) RED BOOKS
SOME DIFFERENCES
Fdration Internationale des Ingnieurs-Conseils
Fdration Internationale des Ingnieurs-Conseils

INNOVATIONS FAVOURING THE CONTRACTOR


Fdration Internationale des Ingnieurs-Conseils

INNOVATIONS FAVOURING THE EMPLOYER


SCHEDULE OF RESPONSIBILITIES: FIDIC 1999
Some major responsibilities
Fdration Internationale des Ingnieurs-Conseils

EMPLOYER

Clause 2.1 Grant access

Clause 2.2 Assist with Permits, Licenses, Approvals

Clause 2.4 Establish and maintain appropriate financial arrangements

- Issue Letter of Acceptance

Clause 3.1 Appoint the Engineer

Clause 3.4 Replace the Engineer

Clause 14.2 Advance Payment

Clause 14.7 Payment

Clause 15.2 Termination

Clause 17.3 Employers Risks

Clause 18.1 Insurance

Clause 20.2 Dispute Adjudication Board Agree in appointment and pay


costs

Clause 20.1 / Settle dispute


20.5
SCHEDULE OF RESPONSIBILITIES: FIDIC 1999
Fdration Internationale des Ingnieurs-Conseils

CONTRACTOR

Clause 4.1 Execute and complete the Works in accordance with the
Contract (including design to the extent specified).

Clause 4.2 Performance Security

Clause 4.3 Contractors Representatives

Clause 4.4 Sub-Contractors

Clause 4.6 Co-operate

Clause 4.8 Safety Procedures


Fdration Internationale des Ingnieurs-Conseils

SCHEDULE OF RESPONSIBILITIES: FIDIC 1999


SCHEDULE OF RESPONSIBILITIES: FIDIC 1999
Fdration Internationale des Ingnieurs-Conseils

DISPUTE ADJUDICATION BOARD

Clause 20.2 Accept Appointment and the obligations pertaining thereto

Clause 20.4 Adjudicate on Disputes hand down decisions


Fdration Internationale des Ingnieurs-Conseils

SCHEDULE OF RESPONSIBILITIES: FIDIC 1999


Fdration Internationale des Ingnieurs-Conseils

QUALITY OF DESIGN & DOCUMENTATION


QUALITY OF DESIGN & DOCUMENTATION
Fdration Internationale des Ingnieurs-Conseils

Suggestions to Improve:

1. One boss for design / documentation production.

2. Avoid over specification; adopt standards.

3. Take particular care at overlaps between sections


of the work.

4. Identify RISKS and set down formal procedures


for managing these.

5. Quality Management System.

6. Peer Review.
QUALITY CONTROL
QUALITY ASSURANCE
Fdration Internationale des Ingnieurs-Conseils

The traditional contract (eg FIDIC 1992) is based on


Quality Control (QC) that is, materials and operations
are to subject to inspection and acceptance and/or
rejection by the Engineer (or his Representative.
Clauses 36-39 of FIDIC 1992.

Recent contracts have adopted a Quality Assurance


approach, that is, the Contractor is required to put in
place a Quality Management System which is designed
to assure compliance with Contract requirements; and
the Contractor is obliged to ensure that his work so
complies; the Engineer only undertakes an auditing
role, but nevertheless may reject completed works.
FIDIC GUIDES
Fdration Internationale des Ingnieurs-Conseils

The FIDIC Contracts Guide

The White Book Guide

Guide for the preparation of particular conditions


(in the major contracts)

Notes for Guidance (in the Short Form of Contract)

Tendering Procedure and Pre-qualification forms

Quality Based Selection


USE OF FIDIC CONTRACTS
Fdration Internationale des Ingnieurs-Conseils

Match contract and project

Decide early

Appoint DAB early

Draft by professionals

Do not touch the General Conditions

Buy originals
PREPARATION OF PROCUREMENT
Fdration Internationale des Ingnieurs-Conseils

Determination of needs and objectives


Determination of constraints
Identification of parties
Planning, budgeting, financing
Contract type
Selection procedure
Requirements / Specifications / Bills of Quantities /
Terms of Reference
Pre-qualification and evaluation criteria
Particular conditions
Publicity
Tender documents
CONTRACT ADMINISTRATION
Fdration Internationale des Ingnieurs-Conseils

Supervision
Enforcement
Quality and quantity
Invoice verification
Payments
Extensions, variation orders, amendments
Termination
Disputes and their resolution

You might also like