Professional Documents
Culture Documents
2124a
Ultrathin Whitetopping -~
HISTORY The following three basic factors are required for UTW overlays to
perform (6):
The first UTW experimental project in the United States was on a
landfill disposal facility near Louisville, Kentucky, beginning Sep- 1. Bond between UTW and existing asphalt pavement,
tember 1991 (3).The overlay was constructed on an existing asphalt 2. Short joint spacing, and
access road that served 400 to 600 trucks per day, 5.5 days per week. 3. Appropriately thick asphalt layer.
The existing asphalt pavement was milled to obtain a uniform p m
file. The experiment consisted of two concrete thicknesses-90 and
50 mm. The Wmm section had joints at 1.83 m. The 50-mm test sec- Bond
tion had joints cut at 1.83 m in one area and at 0.61 m in another area.
Bonding allows the concrete and asphalt layers to perform as a com-
American Concrete Pavement Association, 5420 Old Orchard Road, Suite posite section. This causes the layers to act monolithically and share
A100, Skokie, IL 60077-1059. the load. With bonding, the neutral axis in the concrete shifts from
40 TRANSPORTATION RESEARCH RECORD 1610
the middle of the slab down toward the bottom of the concrete slab. partially bonded systems. Consequently, as bond decreases, the
The shifting down of the neutral axis lowers the stresses at the bot- asphalt carries less load and the asphalt-stiffness to concrete-stiffness
tom of concrete and brings the stresses into a range the concrete can ratio (DJD,) needs to be even higher for the critical load location to
withstand (3-6). remain at the comer. If bond is ever lost, the critical load location will
The composite section has opposing effects on the comer stress. be the edge.
There is a decrease in the concrete stresses because the whole pave- One question that many people have raised is about the develop-
ment section is thicker. However, because the comer behaves as a ment of shear stress at the concrete-asphalt interface. Shear stresses
cantilever, its maximum stresses occur at the top of the slab, and the are maximum at the neutral axis and, for this reason, some designers
shifting down of the neutral axis increases the distance between the have questioned whether the development of high shear stresses will
extreme fiber and the neutral axis. Essentially then, the comer detract from performance. To date, this has not appeared to be a prob-
stresses decrease because the bonding action creates a thicker sec- lem. There have been no failures due to shearing at the concrete-
tion, but they increase because the neutral axis shifts away from the asphalt interface. Still, this may cause problems in the future and
top surface. should be fiuther investigated.
If the neutral axis shifts low enough in the concrete, the critical load
location may move from the edge to the comer depending on the
materials and layer characteristics. This explains why many of the Joint Spacing
UTW projects have developed comer cracking. Therefore, to deter-
mine the critical load location, the designer must look at both the edge All pavement systems must absorb the energy of the applied load by
and the comer. Figure 1 indicates how bonding decreases on slab either bending or deflecting. Traditional concrete pavements are
stresses for a 75-mm UTW over 100 mm of asphalt concrete (AC). designed to absorb the energy by bending and thus are made thick
To estimate where the critical load location may be, the stiffness of enough to resist stresses induced by bending. With UTW, short joint
the concrete layer can be compared with the asphalt layer. Stiffness of spacings are used so that energy is absorbed by deflection instead of
a layer, D, is defined as bending. The short joint spacing reduces the moment arm of the
applied load and minimizes the stresses due to bending. The short
Eh3 joint spacing also minimizes stresses due to curling and warping by
D=- decreasing the amount of slab that can curl or warp.For the UTW
12(1- p')
overlays, the short joint spacing, in effect, forms a minipaver block
For a fully bonded system, when the stifhess of the asphalt is approx- system, which transfers loads to the flexible pavement through
imately 20 percent of the stiffness of the concrete (DJD,= 0.20). the deflection instead of bending (Figure 2) (2,3).
critical loading shifts from the edge to the comer for a fully bonded Typical joint spacings that have performed well on UTW projects
system. However, according to Wu et al. (7). these systems are only are somewhere between 0.6 and 1.5 m. It is recommended that the
0.6 m 0.6 m
-.- 0.6 m 3.0 m
---
- A
I I
maximum joint spacing for UTW be 12 to 15times the slab thickness structure of the asphalt surface can open and grab the cement paste
in each direction (8.9). For example. for a 75-mm UTW project, for bonding.
joints should be cut into concrete at 0.9- to 1.125-m squares. Once a surface is cleaned it is extremely important to keep it clean
until paving commences. This includes any dust, dirt, and debris that
falls or blows onto the surface to be paved. If the surface is cleaned
Asphalt Thickness the day before paving, air cleaning may be required the day of
paving to remove any dust that settled on the surface overnight. If
After surface preparation. there needs to be enough asphalt present traffic is allowed on the milled surface, the surface must be
to form a sufficient composite section that can carry the load. There recleaned before paving.
must be enough asphalt to protect the concrete (minimize stresses), Paving a UTW is no different from paving any other concrete
and enough concrete must be placed to protect the asphalt (minimize pavement. Conventional slip-form and fixed-form pavers, as well as
strains). It is recommended that the minimum asphalt thickness after handheld equipment such as vibrating screeds have all been used suc-
milling be greater than 75 mm. cessfully, without major modifications. The only real change is that
The thicker asphalt pavement section improves the load-canying the concrete layer is thinner than normal. As on any other concrete
capacity of the system because it creates a thicker final UTW pave- pavement, normal finishing and texturing procedures apply.
ment structure. The thicker asphalt section also decreases the criti- Proper curing is critical to avoiding shrinkage cracking and
cal concrete stresses because it carries a larger portion of the load. debonding between the asphalt and concrete. Curing compound
As stated above, the bonding action between the asphalt and UTW should be applied at twice the normal rate (2.5 m2/L). Because the
overlay shifts the neutral axis down in the concrete, which decreases overlay is a thin concrete slab, it has a high surface-area-to-volume
the concrete stresses. Along these same lines, the thicker the asphalt ratio and can lose water rapidly due to evaporation. The compound
section, the more load it carries, and the farther down the neutral axis must be applied to all exposed edges and the surface without running.
shifts. This is indicated in Figure 3. As the asphalt layer gets thicker, Care must be used during application to avoid spraying curing com-
it carries more load, and the neutral axis shifts downward (5,6). pound on a prepared surface, which would decrease bonding. Joint
sawing should be accomplished with lightweight saws as early as pos-
sible to control cracking. These saws saw joints 3 mm wide that assist
CONSTRUCTION OF UTW PAVEMENTS in keeping incompressibles out of the joint. The saw depth should
be in the one-quarter to one-third depth range of overlay. Typically,
Construction of a UTW consists of four fundamental steps (2,10): the joints are not sealed. They have performed well without sealant
because the compactness of the slabs minimizes joint movement.
1. Prepare surface by milling and cleaning, water, or abrasive Performance to date shows no benefit from sealant use (2.10).
blasting.
2. Place, finish, texture, and cure by using conventional tech-
niques and materials. Mix Design
3. Use early saw joints to prevent cracking.
4. Open to traffic. The concrete mix selected for a particular project is matched to the
traffic conditions and opened-for-traffic requirements. A normal
A clean surface is required for proper bond. Milling the surface fol- mix design includes cementitious materials (cement and fly ash),
lowed by cleaning improves bond because it opens the pore surface coarse aggregate, fine aggregate, air entraining agent, admixtures
of the asphalt pavement. The milling basically creates a rough sur- (water reducers or plasticizers for a low water-to-cement ratio), and
face that grabs the concrete and creates the mechanical bond synthetic fibers. The fibers are added to increase the postcrack
between the two layers. If milling is not done, the surface should be integrity of the panels. Fast-Track paving mixes typically use a
cleaned with water or abrasive blasting. When water blasting is higher cement content and other adjustments in the mix to produce
used, the surface must be allowed to air dry so that the roughened compressive strengths over 20.7 MPa within 24 h.
Concrete
Tension
100 m m
Table 1 indicates mix designs used for several recent projects in tionally, a composite numerical index from 0 to 100 is calculated.
the United States (2). This composite index is called the pavement condition index (PCI).
The PCI values and their general ratings are as follows:
(D=design),(A-actual)
State Route 21, Iowa, 1994- Normal mix for openingto n 5 7 days
-
Tennessee 8 Dekalb Co.. GA Fast Track mix for opening to traffic 24 hours or less
with no unexpected change in traffic loadings, will serve 8 to 2. Ultra-thin Whitetopping Promotion Guide. Part of Product Num-
12 years before the PCI drops below 55 (Good) (11). ber SP126P. American Concrete Pavement Association, Skokie, 111..
1996.
3. Risser, R. I., S. P. LaHue, G. F. Voigt, and J. W. Mack. Ultra-Thin Con-
crete Overlays on Existing Asphalt Pavement. In Proceedings of the
SUMMARY Fifh International Conference on Concrete Pavement Design and
Rehabilitation. Vol. 2, Purdue University, West Lafayette, Ind., 1993,
A snapshot of the current state of the practice for U l W is presented. pp. 247-254.
4. Cole, L. W., and J. P. Moshen. Ultra-thin Concrete Overlays on
Although many areas are covered, this is not intended to be a trea-
Asphalt. Presented at 1993 Transportation Association Annual Confer-
tise that answers all questions about UTW. Instead, it is intended to ence, American Concrete Pavement Association, Skokie, Ill., 1993.
show the basics of how UTWs behave and how they are constructed 5. Mack, J. W., L. W. Cole, and J. P.Moshen. Analytical Considerations
as well as to describe their initial performance. for Thin Concrete Overlays on Asphalt. In Transporration Research
UTW is a relatively new technique for resurfacing deteriorated Record 1388, TRB, National Research Council, Washington, D.C.,
1993, pp. 167-173.
asphalt pavements. It involves placing very thin concrete slabs (50 6. Mack, J. Presented at the ACPA Annual Convention, Rancho Mirage,
to 100 mm thick) on old asphalt pavements to form bonded com- Calif., Dec. 4, 1996.
posite pavements. The reduction in thickness is justified by the bond 7. Wu, C.-L., S. Tarr, T. Refai, M. Nagi. and M. Sheehan. Development of
between the concrete and the existing asphalt pavement, close joint Ultra-thin Whitetopping Design Procedure. PCA R&D Serial No. 2124.
Portland Cement Association. Skokie, Ill., 1997.
spacings, and use of high-quality concrete.
8. Concrete Intersections: A Guidefor Design and Construction. TB019P.
Construction of a UTW varies little from construction of a nor- American Concrete Pavement Association, Skokie, Ill., 1997.
mal concrete overlay. The only extra step is that the existing asphalt 9. Whitetopping-Stateof the Practice (draft). EB210P. American Concrete
surface must be milled and cleaned to promote bonding between the Pavement Association, Skokie. 111.. 1997.
concrete and asphalt layers. The performance of UTW overlays to 10. Hawbaker, L. Ultra-Thin Whitetopping. The Construction Specijer,
Alexandria Va., Aug. 1995, pp. 61-62.
date has been very encouraging. Current data suggest that UTW 11. Cole, L. Pavement Condition Surveys of Ultrathin Whitetopping Proj-
overlays will provide long-lasung durable surfaces for low-volume ects. Presented at Sixth International Purdue Conference on Concrete
pavement applications such as city streets; intersections; general- Pavements, American Concrete Pavement Association, Skokie, Ill.,
aviation taxiways, runways, and aprons, and parking areas. 1997.
12. Shahin, M. Y., and J. A. Walther. PavementMaintenanceManagement
f o r Roads and Streets Using the PAVER System. USA CERL TR
M-90/05. U.S. Army Corps of Engineers Construction Engineering
REFERENCES Research Laboratory, Champaign, Ill., 1990.