Professional Documents
Culture Documents
Overcurrent Relay Coordination For Phase and Earth Faults Using Etap
Overcurrent Relay Coordination For Phase and Earth Faults Using Etap
Abstract- Power system protection and control has always been a subject of concern during emergency conditions in a
power system like a zero power condition or blackout. Therefore in order to prevent such conditions, protection system
needs to be strong and reliable. Relays form the basis of any power system protection system whose operation settings
should be in such a way that it provide correct discrimination and prevent any power blackout. In this paper, coordination of
over current relays for a66KVindustrialsystem is done using ETAP (Electrical Transient Analysis Program) software for
phase and ground faults. The star view of ETAP software is its unique feature which is helpful in coordinating the
overcurrent relays correctly. The load flow results for the system are also shown in the paper.
Index Terms- Overcurrent Relay, Relay Coordination, Radial System, ETAP software
I. INTRODUCTION
Overcurrent Relays are the simplest type of protective one generator. There are three generators in the plant,
devices available. It is easy to set the pick up values of which one is under maintenance, one in cold
of individual relays but the problem arises when each standby and one is running. The system is shown in
relay has to be coordinated with every other relay in Fig.1. All the three generators have same ratings i.e.
the system. This problem is further aggravated when 7.8 MW, 18% steady state reactance, connected to the
there are large interconnected systems. The unique 6.6 KV bus. The two transformers present in the
feature of ETAP software i.e. the star view is very system also have same ratings of 25 MVA, 66/6.6
useful in case of large interconnected power systems. KV, %Z = 15.63%.The loads which are connected to
Thus, this paper shows the overcurrent relay the system, mainly consist of motor loads. Here these
coordination of a given system using ETAPs star are assumed to be lumped loads of 5.4 MVA and 4.5
view. The important characteristics of an overcurrent MVA respectively.Two capacitors of 4 MVar ratings
relay are: selectivity, reliability and discrimination. are present on the two sides of sectionalizing circuit
For any kind of fault be it symmetrical or breaker. Firstly load flow analysis is performed on
unsymmetrical, the overcurrent relay has to operate the system to check its load generation balance.
efficiently and provide correct discrimination. The
overcurrent relay settings must be set such that it III. LOAD FLOW REPORT
operates for only the faults nearby it or the primary
faults.Also these relays should operate after a certain Results of the load flow are shown in appendix 1.
time lag and act as back up protection for other
relays. IV. RELAY COORDINATION CONCEPT
II. SYSTEM DESCRIPTION The basic rules for correct relay co-ordination can
generally be stated as follows [1]:
A system is delivering 7.7 MW to its loads of which a. whenever possible, use relays with the same
5.2 MW is fed from the grid and 2.5 MW is fed from operating characteristic in series with each other
Proceedings of 7th IRF International Conference, 27th April-2014, Pune, India, ISBN: 978-93-84209-09-4
57
Overcurrent Relay Coordination for Phase and Earth faults using ETAP
b. make sure that the relay farthest from the source V. RELAY COORDINATION SETTINGS
has current settings equal to or less than the relays
behind it, that is, that the primary current required to The relay current setting is given by Plug Setting
operate the relay in front is always equal to or less Multiplier (PSM) and the time settings are given by
than the primary current required to operate the relay the Time Dial Settings.
behind it.
The formula for finding the PSM is given by:
Also following parameters for the various devices PSM = (Through Fault Current)/(CT Ratio)*(Relay
connected to the system must be considered [2]: current setting)
1.a.The overcurrent relay coordination curve for the For example the overcurrent relay (51 & 51G)
feeder must lie below the feeder overload and feeder settings are shown below for 66KV Incomer relay:
short circuit damage curve on the time current 66KV Incomer Relay
characteristics graph. GROUP -51
Relay type used = 7SJ80
1.b. Also the overcurrent relay coordination curve for CT ratio Primary = 800 A
the feeder must lie above the ampacity curve of the Secondary = 1 A
feeder.
Backup Calculation :
2.a.The overcurrent relay coordination curve for the
transformer must lie below the transformer through Ampacity of the cable = 705 A
fault mechanical and thermal damage curve. Current seen by the CT = 705/800 = 0.88125
O/C PSM with margin at 110% = 0.96
2.b. Also the overcurrent relay coordination curve for Time Setting = 0.13
the transformer must lie above the ampacity curve Curve type= Inverse
and the magnetizing inrush points of the transformer.
GROUP -51G
3.a.The overcurrent relay coordination curve for the
generator must lie above the generator full load Relay type used = 7SJ80
ampere curve of the generator. CT ratio Primary = 800 A
Secondary = 1 A
3.b. Also the overcurrent relay coordination curve for
the generator must lie below the decrement curve and Backup Calculation:
the overload curve.
Ampacity of the cable = 705 A
Current seen by the CT = 705/800 = 0.88125
The flowchart for the relay coordination procedure is
O/C PSM with margin at 120% = 1.05
shown in figure 2 below.
TMS = 0.14
Curve type = Inverse
REFERENCES
Proceedings of 7th IRF International Conference, 27th April-2014, Pune, India, ISBN: 978-93-84209-09-4
59
Overcurrent Relay Coordination for Phase and Earth faults using ETAP
[7] http://electrical-engineering-portal.com/connections-of- [13] LT/HT Power & Control Cables, Havells Industrial
overcurrent-relay-part-2 Catalogue
[8] Jaime Anthony Ybarra, Calculations Of Protective Relay [14] Charles J. Mozina , Power System Instability What
Settings For A Unit Generator Following Catastrophic Relay Engineers Need to Know, Beckwith Electric
Failure, December 2011 Company 6190-118th Avenue North, Largo, FL 33773
[9] K. Prabha. Power System Stability and Control. McGraw- [15] Load Shedding, Load Restoration and Generator Protection
Hill, New York, USA, 1994. Using Solid-state and Electromechanical Underfrequency
Relays, General Electric guide.
[10] C.L. Wadhwa. Electrical Power System.John Wiley and
Sons, New Delhi, India, 1991. [16] Speed Droop and Power Generation, Woodward
[11] B.Ram, D N Vishwakarma, Power System Protection and [17] Anatomy of a Short-Circuit, Tech Topics, Siemens
Switchgear. Tata McGraw-Hill, New Delhi 2011.
[18] Badrul H. Chowdhury, Load-flow Analysis In Power
[12] Edwin Pho, Overcurrent Coordination Study, M.Tech Systems, University Of Missouri-rolla
thesis 2009
Proceedings of 7th IRF International Conference, 27th April-2014, Pune, India, ISBN: 978-93-84209-09-4
60