PROJEK MASS RAPID TRANSIT LEMBAH KELANG - JAJARAN SUNGAI BULOH

Pasdec Bina Sdn Bhd KAJANG Date: 12/08/2016


MRT Feeder Bus Desa Tun Razak Depot
Ref No. Inspection and Test Plan Temporary Hoarding Rev No.:00 Page 1 of 1

Inspection Point
No. Inspection / Test Activity Controlling Document Frequency Acceptance Criteria Verifying Document
WPC SC MRTC

Compliance to: Material Submission


Prior commencement the
1 Material Submission Approval Material Submission for Approval Contract specification Approval Form H H R
work.
Approved construction drawing

Method Statement Temporary


Compliance to:
Hoarding Prior commencement the
2 Method Statement Contract specification Method Statement H R R
KVMRT/PASB/SBK/BDT2/OVPR/MS work.
Approved construction drawing
T/CIVS/000002
Survey Quality Plan
KVMRT/PASB/SBK/BDT2/OVPR/PLN
Compliance to:
/SVY/000001
Before and during Contract specification Request For Inspection
3 Setting out survey Earthwork Layout Plan - H S S
commencement the work Approved construction drawing Quality Control Checklist
KVMRT/LASB/SBK/BDT2/OVPR/C&S
Approved Method Statement
/EW/GE/000005/D00
Temporary Hoarding Layout Plan
Method Statement Temporary Compliance to:
Installation of HW Post, HW Strut ,HW
Hoarding During commencement Contract specification Request For Inspection
4 Bracing, HW runner, Spacer and bolt H S S
KVMRT/PASB/SBK/BDT2/OVPR/MS the work Approved construction drawing Quality Control Checklist
& nut
T/CIVS/000002 Approved Method Statement

Method Statement Temporary Compliance to:


Installation of Metal sheet cladding Hoarding During commencement Contract specification Request For Inspection
5 H S S
panels KVMRT/PASB/SBK/BDT2/OVPR/MS the work Approved construction drawing Quality Control Checklist
T/CIVS/000002 Approved Method Statement

Legend
WPC Work Package Contractor
SC Supervising Consultant
MRTC Mass Rapid Transit Corporation
Remarks
Hold Point Inspection point where SC has to be notified. Inspection point where no further works shall be proceed without written approval from SC
No notification to SC require. Point where the SC representative monitor the WPC activities to the degree necessary for confident that the work process / method is in
Surveillance
compliance with establish criteria.