OBSERVED CONSTRUCTION PRODUCTIVITY NORMS

Crude & Hydrotreating Complex

Civil:

Carpenters 4 - 6 m2/Day for Fdns ( Aprox. 1.5 - 2 m3/Day).


2 - 4 m2/Day for S.Structures ( Aprox.0.6 - 0.9 m3/Day).
Bar Binders 180 - 200 Kg/Day.
Masons 2 - 3 m3/Day.
Others & Helpers 4 nos/m3.

Structural steel:
Per day --> Fab./ MT Ercn./MT
Welders 2 0.75
Fitters 2 1
Gas Cutters 1 1
Grinders 1 0.5
Riggers 2 3
Helpers & Others 2 2

1 of 1 Observed_norms, norms (2)