Professional Documents
Culture Documents
Economic Selection Criteria PDF
Economic Selection Criteria PDF
S ELECTION C RITRIA
CAPITAL BUDGETING
Project managers are often called upon to be active participants during the
evaluate projects that include the purchase of major fixed assets such as
CAPITAL BUDGETING
1) Present value
4) Payback period
5) Benefit-cost ratio.
FV
PV =
Where:
(1+i)n
PV: Present Value
FV: Future Value
i : Interest rate
n: number of time periods
Example
What is the present value of $300,000 received three years from now if we expect the interest
rate to be 10 percent?
300000
PV = = $225,394
(1+0.1)3
Example
You have two projects to choose from. Project A will take three years to complete and has an
NPV of $45,000. Project B will take six years to complete and has an NPV of $85,000. Which
one would you prefer?
Project “B”
Example
Cash flow as follow with interest 10%.
NPV?
0 0 0 200 200
1 50 45 100 91
2 100 83 0 0
3 300 225 0 0
FV
0= ∑ - Initial investment
(1+k+i)n
Where:
i: Rate of return
Example
You have two projects to choose from; Project A with an IRR of 21 percent will be
completed in 4 years or Project B with an IRR of 15 percent will be completed in one year.
Which one would you prefer?
Project “A”
Although the project B has a smaller duration than project A does not
matter because time is already taken into account in IRR calculations
4. Payback Period
The payback period is the length of time required to recover an initial investment through
The shorter the time period, the better the investment opportunity.
Payback period is the least precise of all capital budgeting methods because the calculations
are in dollars and not adjusted for the time value of money.
Initial Investment
Payback Period=
(Annual cash inflows)
100,000
Payback Period= = 4 years
25,000
Example
Project A has an investment of $ 500,000 and payback period of 3 years. Project B has an
investment of $ 300,000 and payback period of 5 years. Using the payback period criteria,
which project will you select?
Project “A”
Years 0 1 2 3 4
Cash flow -1000 500 400 300 100
Net Cash flow -1000 -500 -100 200 300
Example
Years 0 1 2 3 4
Cash flow -1000 100 300 400 600
Net Cash flow -1000 -900 -600 -200 400
Example
Project A has an investment of $ 500,000 and BCR of 2.5 Project B has an investment of $
300,000 and BCR of 1.5 Using the Benefit Cost Ratio criteria, which project will you select?
Project “A”
Although the project B has a smaller investment than project A will not impact the selection
Exercise:
IRR 13 % 17 % B
Example
Project A had initial budget of $ 1,000 out of which $ 800 has already been spent. To
complete project A, we will need additional $ 500. Another Project B will require $ 1200
for completion. Which project do you want to select?
Project “A”
$ 800 spent in project A i.e it is sunk cost – hence should be ignored. So, at this point of
time,
Cost of completing project A = $ 500
Cost of completing project B = $ 1200
Key selection: Ignore the sunk costs “because they have already been incurred and cannot be avoided”
Example
You have two projects to choose from: Project A with an NPV of $45,000 or Project B with
an NPV of $85,000. What is the opportunity cost of selecting project B?
Project “$45,000”
Working Capital
The amount of money the company has available to invest, including investment in
projects.
Net Working Capital = Current assets - Current liabilities for an organization.