Professional Documents
Culture Documents
Mobile Offshore Drilling Units 2016: Rules For Building and Classing
Mobile Offshore Drilling Units 2016: Rules For Building and Classing
The following Rule Changes were approved by the ABS Rules Committee on 23 May 2016 and
become EFFECTIVE AS OF 1 JULY 2016.
(See http://www.eagle.org for the consolidated version of the Rules for Building and Classing Mobile Offshore
Drilling Units 2016, with all Notices and Corrigenda incorporated.)
Notes - The date in the parentheses means the date that the Rule becomes effective for new construction based
on the contract date for construction. (See 1-1-4/3.3 of the ABS Rules for Conditions of Classification
– Offshore Units and Structures (Part 1).)
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016 1
Notice No. 1 – July 2016
2 ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Notice No. 1 – July 2016
1.1 General
1.1.3 Air Clearance and Creepage Distance (1 July 2016)
(Revise Item 4-3-5/1.1.3(d), as follows:)
1.1.3(d) Creepage Distances (1 July 2016).
i) The minimum creepage distances for main switchboards and generators are given in the
Table below:
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016 3
Notice No. 1 – July 2016
1.9.3 Cables
(Revise Item 4-3-5/1.9.3(h), as follows:)
1.9.3(h) Test after Installation (1 July 2016). A voltage withstand test is to be carried out on each
completed cable and its accessories before a new high voltage installation, including additions to
an existing installation, is put into service.
An insulation resistance test is to be carried out prior to the voltage withstand test being conducted
For cables with rated voltage (Uo/U) above 1.8/3 kV (Um = 3.6 kV) an AC voltage withstand test
may be carried out upon advice from high voltage cable manufacturer. One of the following test
methods to be used:
i) An AC test voltage for 5 min with the phase‐to‐phase voltage of the system applied
between the conductor and the metallic screen/sheath.
ii) An AC voltage test for 24 h with the normal operating voltage of the system.
iii) A DC test voltage equal to 4Uo may be applied for 15 minutes.
For cables with rated voltage (Uo/U) up to 1.8/3 kV (Um = 3.6 kV), a DC voltage equal to 4Uo
shall be applied for 15 minutes.
After completion of the test, the conductors are to be connected to earth for a sufficient period in
order to remove any trapped electric charge.
The insulation resistance test is then repeated.
The above tests are for newly installed cables. If due to repairs or modifications, cables which
have been in use are to be tested, lower voltages and shorter durations should be considered.
4 ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Notice No. 1 – July 2016
15.3.3 Transformers
(Revise Item 6-1-7/15.3.3(a), as follows:)
15.3.3(a) Application. Provisions of 6-1-7/15.3.3 are applicable to power transformers for essential
services. See also 6-1-7/11. Items 6-1-7/15.3.3(c) and 6-1-7/15.3.3(d) are applicable to transformers
of the dry type only. These requirements are not applicable to transformers intended for the following
services:
• Instrument transformers.
• Transformers for static converters.
• Starting transformers.
Dry type transformers are to comply with the applicable Parts of the IEC Publication 60076-11.
Liquid filled transformers are to comply with the applicable Parts of the IEC 60076 Series. Oil
immersed transformers are to be provided with the following alarms and protections:
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016 5
Notice No. 1 – July 2016
PART 7 SURVEYS
CHAPTER 2 SURVEYS AFTER CONSTRUCTION
APPENDIX 1 LAY-UP AND REACTIVATION OF LAID-UP MOBILE OFFSHORE DRILLING
UNITS
6 ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016