WORK PROGRAM FOR PIER PROTECTION WORKS

ID Task Duration Start Finish Predecessors '17 '18 '19


Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
1 Commencement of Pier Protection Works 0d Wed 15-11-17 Wed 15-11-17 15-11
2 Preparatory works 44 d Wed 15-11-17 Thu 28-12-17
3 Documentation 44 d Wed 15-11-17 Thu 28-12-17
4 Preparation of Construction Drawings 25 d Wed 15-11-17 Sat 09-12-17 1
5 Preparation of Construction Methodology 9d Wed 20-12-17 Thu 28-12-17 4FS+10 d
6 Documentation Finish 0d Thu 28-12-17 Thu 28-12-17 5 28-12
7 Construction Work 190.5 d Tue 02-01-18 Wed 11-07-18
8 P18 Pier Protection work 111.5 d Tue 02-01-18 Mon 23-04-18
9 30mm Steel Casing Drive 100 d Tue 02-01-18 Wed 11-04-18
39 Boring work 104 d Sat 06-01-18 Fri 20-04-18
68 Concrete Pouring 103 d Mon 08-01-18 Sat 21-04-18
97 Fixing MS angles 90 d Tue 23-01-18 Mon 23-04-18
102 P18 Pier Protection Finish 0d Mon 23-04-18 Mon 23-04-18 101 23-04
103 P17 Pier Protection work 88.5 d Sat 14-04-18 Wed 11-07-18
104 30mm Steel Casing Drive 76 d Sat 14-04-18 Thu 28-06-18
105 Pier Protection 76 d Sat 14-04-18 Thu 28-06-18
132 Boring work 78 d Fri 20-04-18 Sat 07-07-18
159 Concrete Pouring 77 d Sun 22-04-18 Sun 08-07-18
186 Fixing MS angles 65 d Mon 07-05-18 Wed 11-07-18
191 P17 Pier Protection Finish 0d Wed 11-07-18 Wed 11-07-18 190 11-07
192 Completion of Pier Protection Works for Main Bridge 0d Wed 11-07-18 Wed 11-07-18 191,102 11-07
Piers

LONGJIAN ROAD & BRIDGE CO., LTD. Task Summary Task


Paira Bridge (Lebukhali Bridge) Construction Project Milestone Critical Task