BILL OF MATERIALS
NO. DESCRIPTION OF MATERIAL QUANTITY UNIT UNIT COST TOTAL COST
CONCRETE WORKS AND FORMWORKS : FOUNDATION, CONCRETE COLUMNS, BEAMS, CONCRETE HOLLOWBLOCK
I. WALLS, FLOOR SLAB, PLASTERING WITH PLAIN CEMENT AND SCAFFOLDING ₱ 19,838,534.12
PORTLAND CEMENT 20,144.10 Bag ₱ 250.00 ₱ 5,036,024.25
SAND 1,117.90 Cu. M. ₱ 1,300.00 ₱ 1,453,271.30
GRAVEL OR CRUSHED STONES 1,924.75 Cu. M. ₱ 1,300.00 ₱ 2,502,168.50
CONCRETE HOLLOW BLOCKS (CHB) 10cm x 20cm x 40cm 30,387.50 Piece ₱ 20.00 ₱ 607,750.00
STEEL REINFORCING STEEL BARS
10mm x 6.00 meters 18,320 Pieces ₱ 130.00 ₱ 2,381,600.00
12mm x 6.00 meters 14,112 Piece ₱ 220.00 ₱ 3,104,640.00
16mm x 6.00 meters 10,008 Piece ₱ 380.00 ₱ 3,803,040.00
WIRE NO. 16 FOR TYING 783 Kilo ₱ 60.00 ₱ 46,980.00
COMMON WIRE NAILS
50mm (2”) 183 Kilo ₱ 45.00 ₱ 8,235.00
75mm (3”) 122 Kilo ₱ 45.00 ₱ 5,490.00
100mm (4”) 113 Kilo ₱ 42.00 ₱ 4,746.00
125mm (5”) 101 Kilo ₱ 50.00 ₱ 5,050.00
FINISHING NAILS
31mm (1-1/4”) 87 Kilo ₱ 45.00 ₱ 3,915.00
5omm (5”) 69 Kilo ₱ 49.00 ₱ 3,381.00
63mm (2-1/2”) 90 Kilo ₱ 45.00 ₱ 4,050.00
CONCRETE NAILS 75mm (3”) 58 Kilo ₱ 90.00 ₱ 5,220.00
SCAFFOLDINGS AND FORMS - LUMBER (Coco Lumber)
50mm x 75mm x 3.60mm (2” x 3” x 12’) 5,299 Bd-ft. ₱ 13.00 ₱ 68,887.00
50mm x 50mm x 3.60mm (2” x 2” x 12’) 53,241.05 Bd-ft. ₱ 9.00 ₱ 479,169.41
WATERPROOF PLYWOOD (6mm x 1.2m x 2.4m) 1,049.72 Sheet ₱ 300.00 ₱ 314,916.67
LABOR (40%) MATERIAL COST ₱ 7,935,413.65
II. CEILING WORKS, ROOF FRAMINGS AND ROOFING SYSTEM ₱2,759,070.00
GOOD LUMBER
(2” x 6” x 14’) 895 Bd-ft. ₱ 45.00 ₱ 40,275.00
(2” x 6” x 12’) 1834 Bd-ft. ₱ 42.00 ₱ 77,028.00
53
SUMMARY COST ESTIMATES FOR MATERIAL, LABOR AND OTHER CONSTRUCTION EXPENSES
A. ESTIMATED COST OF MATERIAL ₱ 61,929,549.65
I. CONCRETE WORKS AND FORMWORKS ₱ 19,838,534.12
II. CEILING WORKS, ROOF FRAMINGS AND ROOFING SYSTEM ₱ 2,759,070.00
III. PLUMBING WORKS (PLUMBING PIPES AND FITTINGS) ₱ 20,646,360.12
IV. ELECTRICAL WORKS ₱ 4,086,527.00
V. DOORS AND WINDOWS ₱ 1,351,418.00
VI. TILEWORKS ₱ 502,920.00
VII PAINTING WORKS ₱ 707,675.00
VIII. MISCELLANEOUS MATERIALS (LUMP SUM ESTIMATES) ₱ 5,000,000.00
IX. GREEN ENGINEERING APPLICATION ₱ 7,037,045.40
B. ESTIMATED COST OF LABOR ₱ 20,976,478.32
C. ESTIMATED EXPENSES FOR CONTINGENCIES ₱ 5,000,000.00
D. RENTAL COST ₱ 1,000,000.00
E. DIRECT COST ₱ 88,906,027.96
Professional Engineering Cost (10% Direct Cost) ₱ 8,890,602.80
F. INDIRECT COSTS ₱ 10,865,000.00
Temporary Facility ₱ 15,000.00
Natatorium (Swimming Pool Accesories) ₱ 200,000.00
Basketball Accesories ₱ 100,000.00
Dinning Materials & Equipment ₱ 100,000.00
Dancing Studio Materials & Equipment ₱ 150,000.00
Land Cost ₱ 10,000,000.00
Function Hall Materials & Equipment ₱ 300,000.00
`` G. GENERAL AND ADMINISTRATIVE COST ₱ 5,000,000.00
Project Overhead (15% Direct Cost) ₱ 13,335,904.19
General Overhead (15% Direct Cost) ₱ 13,335,904.19
TOTAL ESTIMATED COST ₱ 140,333,439.15