You are on page 1of 1

LOS ANG E LE S CO MMUNI TY CO LLE GE DI S TRI CT

DEPARTMENT OF FACILITIES PLANNING AND DEVELOPMENT


SUSTAINABLE BUILDING PROGRAM

CONSENT OF SURETY/FINAL PAYMENT

TO OWNER:
(Name, address)      
PROJECT NO.:      
PROJECT:
(Name, address)      
CONTRACT DATED:      

In accordance with the provisions of the Contract between the Owner and the Contractor (or Design
Builder) as indicated above, the      
(Insert name and address of Surety)

, SURETY,
on bond of      
(Insert name and address of Contractor (or Design Builder)

, CONTRACTOR (or Design Builder),


hereby approves of the final payment to the Contractor or Design Builder, and agrees that final payment to
the Contractor or Design Builder shall not relieve the Surety of any of its obligations to      
(Insert name and address of Contractor)

The Surety agrees that such reduction in or partial release of retainage to the Contractor or Design Builder
shall not relieve the Surety of any of its obligations to      
(Insert name and address of Owner)

, OWNER,
as set forth in said Surety’s bond.

IN WITNESS WHEREOF, the Surety has hereunto set its hand on this date:
(Insert in writing the month followed by the numeric date and year.)

     
(Surety)

     
(Signature of authorized representative)

     
(Printed name and title)

cc: College Project Manager


Inspector of Record
Program Manger

Form CC-0120 Page 1 of 1 Rev.1.23.2010