Professional Documents
Culture Documents
Construction of Bituminous Layers BBMP PDF
Construction of Bituminous Layers BBMP PDF
LAYERS
Dr. Anjaneyappa
RV College of Engineering
anjaneyappa@rvce.edu.in
Balancing Production
HMA Paving
Facility
Trucking Compaction
Delivery Construction 2
Flexible Pavements / Bituminous Pavements
1. Fill/ Subgrade - Soil Layers
2. Granular Layers ( Subbase & base layer) -GSB, WBM,
WMM, CRM
3. Bituminous Layers
3.1 Interface treatments
3.2 Thin Surface Layers
3.3 Thick Surface layers
4. Bituminous Binder Courses & Surface Courses
5. Functional & Structural Layers
Bituminous Layers _ Thick Layers
• Grouted / Penetration / Sprayed
Built Up Spray Grout
Penentration Macadam
• Bituminous Precoated Layers
Bituminous Macadam
Dense Bituminous Macadam
Bituminous Concrete
Bituminous Thin Layers - Structural Layer
• Semi Dense Bituminous Concrete - 25 mm
Asphalt
Aggregate
1 hour
60 C
1 hour 10 hours
25 C
Stiffness (Response to Load)
elastic
viscous
elastic fluid
solid
viscous
-30 25 60 135
Temperature, C
Grading DBM – Grade I DBM – Grade 2 BC – Grade 1 BC – Grade 2
Nominal Size (mm) 40 25 19 13
Layer Thickness 80-100 mm 50-75 mm 50-65 30-45
(mm)
Sieve Size (mm) % Passing
45 100 -
37.5 95-100 100
26.5 63-93 90-100 100
19 - 71-95 79-100 100
13.2 55-75 56-80 59-79 79-100
9.5 - - 52-72 70-88
Cleaniness Grain size Analysis Min.5% passing 0.075 Min.5% passing 0.075
mm mm
Particle Shape Flakiness & Max. 35% Max. 30%
Elongation
Strength LAA Max. 35% Max. 30%
AIV Max. 27% Max. 24%
Durability Soundness Max.12% ( Sod.Sul) Max.12% ( Sod.Sul)
Max .18% (Mg Sul) Max .18% (Mg Sul)
Compaction 75 75
( # of blows)
Air Voids (%) 3-6 3-6
9.5 14 15 16
12.5 13 14 15
19.0 12 13 14
25.0 11 12 13
37.5 10 11 12
Requirements of Mix – modified bitumen
Properties Requirement
Deficiencies in Paving
Segregation at Plant
Hang –up of feeders in bins ( moisture)
Prime Coat
Tack Coat
Crack Prevention Courses
Purpose of Priming
Rolling 115-155
Transportation of Mix
Delivery Construction 41
Tarping Loads
Delivery Construction 42
Laying of Mix
Delivery Construction 43
Delivery Construction 44
Tracto
r
Hopper
Depth
Crank
Screed
Push
Rollers Tow Point Conveyors Augers
Side Arm
Construction Placement 47
Correct Depth of
Mat Maintained
Construction Placement 48
Auger
Correct Overloaded Auger
Elevation Underloaded
Construction Placement 49
Construction Placement 50
Construction Placement 51
Compaction
Construction Compaction 52
Types of Rollers
Contact area
Road surface
Vibratory Rollers
Load
Amplitude
Frequency
Impact Spacing
Operation
Impact Spacing
FREQUENCY
DIRECTION OF TRAVEL
Transverse joint
Preferably Vertical Joint
Staggering of joints at least by 2 meters
Spraying of bitumen on face
Heating of Screed
Longitudinal Joint
Not be located on same line
At 150 mm offset
Vertical face
Overlap of 25 to 50 mm with previously laid surface
Rolling operations
Depends on
Thickness
Speed
Number of rollers
Rolling Sequence
Transverse Joint
Longitudinal Joint
Overlap of 150-175 mm
Lower to Higher edge
Rolling Operation
Rolling zone at 50 m
Intermediate Rolling
After breakdown rolling when mix still in plastic
state
Pneumatic rollers more suitable
Pneumatic rollers may not increase the density
substantially
It does increase the stability of mix by kneading and
reorientation of particles
More uniform compaction
Sealing of layer ( tire pressure 0.7 to 0.9 Mpa)
Finish Rolling
Carried out while material still in warm condition
For removal of tire marks
Precautions for Rolling
Uniform speed
Never allow compactor to stand
Jerky start , sudden braking, sharp changes not
to be made
Change of lane to made only on already
compacted surface
Steel wheels / pneumatic wheels cause loss of
heat
Small amount of detergent / Vegetable oil
Laying of DBM Binder Course -
Compaction by Vibratory Roller and
Pneumatic Roller in Progress
High
Passing
Density
Density
Low
1 2 3 4 5 6
Roller Passes
Construction Compaction Equipment 73
Dense Bituminous Madacam/ Semi Dense Bituminous
Concrete/ Bituminous Concrete
Quality of Binder Two Samples per lot to be
subjected to all or some tests as
directed by the Engineer
Aggregate Impact Value One Test per 350 m3 of Aggregate
Water Absorption of - do -
Aggregates
Marshall test and binder content for each 400
tonnes of mix subject to minimum two test per
day
Density for every 700 sqm area
Construct trail stretch for Project Conditions
and fix up guidelines
Not to adopt the guidelines of constructions
adopted for projects constructed elsewhere /
others
MAX. PERMISSIBLE ROUGHNESS VALUES (mm/km) –
IRC:SP-16 : 2004