Professional Documents
Culture Documents
Relay Assisted Commissioning
Relay Assisted Commissioning
Relay-assisted commissioning
by Casper Labuschagne and Normann Fischer, Schweitzer Engineering Laboratories (SEL)
Power transformer differential relays were among the first protection relays to use digital technology. These new relays offered improvements
such as automatic calculation of TAP values, and the use of calculations instead of current transformer (CT) connections. This allows immediate
and conclusive confirmation of the correctivness of relay wiring, and the integrity of differential element configuration settings.
This paper describes an algorithm that Although excessive operating current selection. Table 2 shows the various
checks for correct CT polarities, consistent indicates commissioning errors, it cannot differential current values for each 30°
CT ratios, and the existence of any crossed indicate the specific cause of the phase shift .With the correct compensation
phase wiring errors, provided minimum, unbalance, and other measurements selection on both windings, the differential
b a l a n c e d l o a d c u r r e n t f l o w s. O t h e r are needed to identify this. Table 1 shows current is (ideally) zero. With 250 mA
algorithms [2, 3] describe systems that test the measurement methods used in the secondar y current flowing, differential
for similar wiring errors, but fail to calculate algorithm. current resulting from a 30° phase error
an alternate vector-group compensation (150° instead of 180°, for example) is
Measurement quantities ± 130 mA which is substantially larger than
setting if the existing setting is incorrect.
The algorithm includes a vector-group The relay uses operating current to select any relay error, and the relay can make
compensation calculation. After verifying the correct vector group compensation. correct compensation selections.
CT connections, the algorithm calculates Because the selection resulting can be Current compensation
the correct CT compensation connections applied as a relay setting, all possible
for the particular vector group. ambiguities and error sources must be Current compensation consists of three
eliminated. To avoid errors resulting from parts: vector group compensation
Commissioning protection equipment
primary or secondary current injection, at (phase-angle correction); zero-sequence
involves verification of physical connections
least 250 mA (for a 5 A secondary relay) removal; and scaling (TAP). Vector-group
(cabling, wiring, etc.), relay settings, and
of balanced-load current is required compensation and zero-sequence removal
proper operation of the complete system.
(approximately 5% of full load) instead of can be achieved either by appropriate
To verify the complete system, a number of
injected current. CT connections or by mathematical
measurements are taken during injection
calculations. In numerical relays, actual
testing and compared against expected 250 mA load current is specified, as CT compensation transformer taps do not exist,
values. Differences in excess of pre- characteristics can var y significantly
determined margins indicate errors, and and calculations are used to determine TAP
among phases at low current values. (Eqn. 1 or Eqn. 2).
further tests are performed to determine For greater current magnitudes, CTs
their cause. Electromechanical relays require
operate where the CT characteristics are
The operating current of the current delta-connected CTs to compensate
substantially similar to each other, and
differential element is used to determine for wye-connected power transformer
the secondary currents from the CTs are
whether commissioning errors exist. However, windings, whereas wye-connected CTs
balanced. It is important to have balanced
using this as a catchall method can result in generally provide more information.
load current, as symmetrical components
ambiguous conclusions. For example, both Because numerical relays compensate
are used in some of the tests (see Table 1),
incorrect CT polarity and a CT connected to for input currents mathematically, delta-
and unbalanced load current can distort connected CTs are no longer necessary.
the incorrect CT tap result in the presence test results.
of operating current which can also exist The algorithm this paper describes assumes
in an error-free installation [3]. Although The value of 250 mA also ensures that relay that all CTs are wye-connected, regardless
numerical relays compensate for most errors do not obscure proper compensation of the transformer vector group.
unbalances, TAP compensation can result
in operating current. Because standard CT Error Measuring method
ratios seldom match the full load current of
Insufficient load current Current magnitude measurement
the transformer, relays adjust each phase
current to compensate for the mismatch. To Two crossed phases Negative-sequence current measurement
determine the adjustment for each phase CT connected to the incorrect tap Expected current to measured current magnitude comparison;
current, the relay uses either Eqn. 1 or Eqn. 2 negative sequence current measurement
to calculate a scaling factor called TAP.
Incorrect CT polarity Angular comparison between a reference phase and all other
phases
(1)
Vector-group compensation Operating current and phase angle measurement
selection
(6)
(7)
(8)
(9)
Matrix 2
IOPA(pu) IOPB(pu) IOPC(pu) IRTA(pu) IRTB(pu)
IRTC(pu)
0,12 0,12 0,12 0,47 0,47 0,47.
.
Matrix 12
IOPA(pu) IOPB(pu) IOPC(pu) IRTA(pu) IRTB(pu)
IRTC(pu)
0,12 0,12 0,12 0,47 0,47 0,48