You are on page 1of 1

PROPERTY CONSTRUCTION

ENVIRONMENT PLANNING

FREE TRIAL OF LEXISPSL

FREE DOWNLOADS

Managing
environmental risks in
construction
contracts
June 13, 2016 By Guest Blogger — Leave a Comment

! Tweet " Share # Share

How do environmental provisions in


construction contracts work in
practice? Andrew Waite, environmental
law consultant at Ashurst, and Michael
Weissman, senior associate in Ashurst’s
construction team, comment on the key
environmental concerns and risks in
building contracts.
What are the key environmental concerns in
construction
! $ projects?
% & ' #
The key environmental concerns in UK construction
projects are:

contamination—particularly, whose
responsibility it is to deal with and pay for
historic contamination on the site
waste—including minimising waste and reusing
material onsite as far as possible as well as
managing waste arising in accordance with
legal requirements
water pollution—water pollution from
construction sites is a major issue
nuisance claims and noise (these can be the
subject of intervention by the local authority—
section 60 construction site noise notices—as
well as complaints by neighbours)

What environmental provisions are


commonly being found in building
contracts? How is risk apportioned between
the parties?

Environmental provisions in building contracts for


relatively sophisticated projects commonly put the
responsibility for minimising or avoiding liability
relating to environmental issues on the contractor.
Although commonly used standard forms of
construction contract do not directly refer to speciLc
environmental issues, employers/developers will
often introduce provisions through the schedule of
amendments.

With regard to contamination, well-advised


employers would normally seek to place the risk on
the contractor although there is often some
negotiation. Contractors will be keener on accepting
only ‘known risk’. If, as is usual, a level of risk as to
ground conditions is placed on the contractor, there
may be some qualiLcation to that position. For
example, under the relevant ‘compensation event’ in
respect of physical conditions under the NEC
contract (clause 60.1(12)), it is assumed that the
contractor has taken into account various site
information and publicly available information,
information obtainable from a visual inspection of
the site and other information which an experienced
contractor could reasonably be expected to have or
to obtain.

By contrast, the unamended JCT contracts (with the


exception of the JCT Major Project Construction
Contract) are silent on ground conditions and
assume that the contractor takes on the
responsibility for having to deal with unanticipated
conditions. The precise wording will depend on the
particular standard form/amendments to it and the
relative sophistication of the parties. In some cases,
employers/developers are prepared to accept a
degree of risk if they have experience of dealing with
land contamination. However, the normal approach
of employers and developers is that the risk should
rest with the contractor because the contractor has
the operational responsibility for it.

How about development agreements?

In development agreements, the environmental risks


(including contamination) are typically placed on the
developer in the expectation that they in turn step
them down to the contractor.

Although the standard forms tend to be drawn up by


construction industry bodies, ultimately the
environmental provisions in the contracts that we
frequently see/negotiate tend to be driven by the
requirements of the employer or developer as
appropriate.

How receptive are contractors to their


inclusion?

Usually, contractors are relatively amenable to taking


on the environmental liabilities, including those for
contamination, but that depends to a large extent on
how comfortable they are about the risk, and on the
negotiation of price between the contractor and the
employer. For example, if the site has been
remediated previously by reputable contractors they
are much more likely to be prepared to take on the
risk—subject to doing investigations and obtaining
site reports and other site information that they can
rely upon.

How are environmental issues being


managed in the supply chain?

Increasingly, suppliers up the chain are being required


to provide materials which are sustainably sourced.

How controversial does the wording of the


provisions prove in negotiations?

While the standard wording tends to favour


contractors, there will inevitably be push back/mark
up on behalf of developers and employers. As noted
at above, these parties will often seek amendment of
the standard forms to make them more favourable to
their position. It will no doubt be in both parties’
interests to ensure that environmental liabilities are
kept to a minimum.

Interviewed by Nicola Laver.

The views expressed by our Legal Analysis


interviewees are not necessarily those of the
proprietor.

Filed Under: Construction, Environment

Leave a Reply
Your email address will not be published. Required
Lelds are marked *

Comment

Name *

Email *

Website

POST COMMENT

SIGN UP
For FREE bespoke content, written by
LexisNexis Lawyers, leave your details below:

First Name

Last Name

E-Mail Address

SIGN UP

SEARCH THE PURPOSE BUILT BLOG

Search the site ...

NICOLA JOHNS

Solicitor and Head of LexisPSL


Built Environment

Nicola is a commercial property


lawyer who joined Lexis®PSL in
September 2013. Nicola qualiLed as
a solicitor in 2004 and trained and
gained her post-qualiLcation
experience in the London o`ce of
US law Lrm Dorsey & Whitney
before joining SJ Berwin LLP (now King & Wood Mallesons)
in July 2008. Nicola has a range of commercial real estate
experience in portfolio management, transactional work and
development work. Nicola has worked across a number of
industry sectors including industrial, o`ce and retail,
undertaking secondments at Daimler and The Crown Estate.

CATEGORIES

Construction (57)

Environment (74)

Planning (43)

Property (117)

Property Disputes (1)

Uncategorized (7)

RECENT POSTS

Exploring possible changes to construction


retentions and the HGCRA 1996

Lexis®PSL Environment Newscast—January 2018

Carillion’s insolvency—infrastructure and


construction

Construction—state of the industry review

FIDIC Red, Yellow and Silver Books 2017 launched

Copyright ©2014 Reed Elsevier (UK) Limited, trading as LexisNexis. All


rights reserved.
Reed Elsevier (UK) Ltd - Registered in England - Number 2746621 -
Registered Office 1-3 Strand, London WC2N 5JR
Privacy and Cookies | Terms and Conditions

You might also like