PROCESSING OF VARIATION ORDERS UNDER FIDIC RED BOOK 4TH EDITION 1992
N

Does Contractor seek Does Engineer deem


VO from Engineer (CL N N necessary to issue VO
13 or 20) (CL 51.1)

Y No VO Y

Is Engineer required
Does Contractor Contractor has no Authority to Engineer to Certify Dayworks Not
to seek Employers
notify Engineer N make VO or to suspend the N Amounts in Interim Entitled to
Approval before
accordingly Works (CL 51.2) Certificates Dayworks
issuing VO (CL 2.1(b))

Y Y

Does Engineer Does Engineer consider


Does Engineer Issue
it impractical to submit
Y VO in accordance N Consult with Y such statements (CL
with CL 51.1 Employer
Engineer to proceed to 52.4)
authorise payment to
N Y Contractor subject to being
Does Engineer issue satisfied the resources
N VO in accordance together with rates and
with CL 51.1 prices are fair and reasonable
(CL 52.4) Has Contractor
submitted Monthly
Y N
priced statement (CL
Contractor may request the Y
52.4)
Engineer to Issue VO in Does Employer grant
accordance with CL 51.1 N Engineer approval to
issue VO

Y
Engineer to countersign one duplicate copy of the
Dayworks Records Submitted by Contractor and
Possible dispute between Engineer and return the same to the Contractor (CL 52.4)
Requisite Approval Deemed No VO
Employer. Contractor is under no obligation
provided by Employer for
to question this matter and approval is
Engineer to Issue VO (CL 2.1)
deemed provided by Engineer issuing VO

Y Y

Are the Dayworks Can Engineer &


Records correct and N Contractor Agree on N
The Engineer may make any VO in the form, quality or quantity of the Works or any part thereof that may in the opinion of the Engineer be necessary or appropriate and shall Agreed (CL 52.4) details
have the authority to instruct the Contractor to vary the Works

Contractor shall vary the Any additional costs which


Is the VO as a result of Contractor to submit Dayworks records as the works proceed each day to the Engineer together with duplicate lists of workmen, materials and plant engaged in
Works as instructed in VO (CL result from the VO shall be
a default by the Y execution of the Works. (CL 52.4)
51.1) borne by the Contractor in
Contractor
accordance with CL 51.1

N
Contractor shall furnish proof of all payments made by him to the Engineer and obtain the Engineers approval before the ordering of materials under Dayworks
(CL 52.4)

Are varied Works


The VO shall not in any way
under VO to be
vitiate or invalidate the Y The Engineer shall certify varied works instructed under the VO under the terms set out in the Day Works Schedule as included within the Contract and at the
executed under
Contract (CL 51.1) rates and prices stated therein (CL 52.4)
Dayworks (CL 52.4)

Does Contractor Give Engineer may choose not to


notice of extra Value the VO (other than
N
payment or varied omitted Works) in accordance

MALCONLAW
rate with CL 52.3

Does the VO render


rates or prices
Y
inappropriate or
inapplicable

Engineer to Value the VO in END


accordance with CL 52.1

Does Contract contain Does Engineer deem Is Sum Acceptable


N
N applicable rates and Y rates and prices Y
prices (CL52.1) appropriate (CL 52.1)

Start of
Dispute or
Claim (CL
Engineer to Adjust Final Contract Price & 53 & 67)
The rates and prices as contained in the Certify accordingly
Varied Works under VO shall
Contract shall be used as basis to value the
be valued at rates and prices
contained in Contract (CL
52.1)

Engineer to consult with Contractor & Employer to agree suitable


rates and prices for varied Works under VO (CL 51.1) Engineer to determine and notify adjustments with
copy issued to Employer and Contractor

Are the rates and


prices acceptable to
Y
the Contractor

Is Agreement Y
Reached on prices N
Y
and rates
Engineer to Consult with Contractor and Employer in
Is Agreement reached
respect of adjustment of rates and Prices due to N
Contract Price variance (CL 52.3)
N
Start of
Dispute or
Claim (CL
53 & 67)

Engineer shall fix appropriate rates and prices and notify Contractor Y
Apply the Agreed rates and
with copy to Employer (CL 52.1)
prices
N Do rates require
No further Adjustment to VO adjustment due to 15%
N
Rates and Prices Required variance of Contract
Are the rates and amount as CL 52.3
prices acceptable to
the Contractor

Y
Is Agreement on rates Engineer to determine
Y and prices agreed N provisional rates and prices
(CL 52.2) Y

Has Engineer issued


Taking over certificate
Await Contract Completion N
for whole of Works
(CL 48.1)
Engineer to Certify amounts in
Interim Payment Certificates