SOP BHGN Perancangan Semakan Dokumen Seblm Penyerahan PDF
SOP BHGN Perancangan Semakan Dokumen Seblm Penyerahan PDF
1
FASA SEMAKAN DOKUMEN SEBELUM PRA PENYERAHAN PROJEK
6. Penyerahan projek
2
CARTA ALIRAN FASA SEMAKAN DOKUMEN
SEBELUM PRA PENYERAHAN PROJEK
MULA
Penyerahan projek
TAMAT
3
LAMPIRAN 1
Contract document
Bill of Quantities
Breakdown cost of asset /
Complete volume of system / equipment
1
document (1 set)
Certificate of Practical
Completion (CPC)
Borang Pengesahan
Penyerahan Projek
DRAWINGS
Master list of drawings
Location plan
Complete
Site plan
ARCHITECTURE as-
built drawings Building plan
2
approved by Architect
(A.R) (2 hardcopy & Landscape plan
softcopy) Detail drawings /
fabrication drawings
Others:
Master list of drawings
Site plan
Earthwork
Air-conditioning &
Complete ventilation system (ACMV)
MECHANICAL as-built
drawings approved by Fire fighting & protection
4
Professional Engineer system
(P.E) (2 Vehicle transportation
hardcopy & softcopy)
Vertical transportation
Medical gas pipeline
system
4
Liquid petroleum gas (LPG)
and pipeline
Laboratory gas system
Pneumatic tube system
BAS / BSS / BMS
Autoclave & sterilizing
system
Domestic water supply
system
Hot & cold water supply
system
Decay tank system
Others:
Master list of drawings
External lighting, cable
route and line
High voltage electrical
system
Low voltage electrical
system
Lightning protection
system
Standby power system /
Genset
Acoustic system
TV antenna system
Complete ELECTRICAL ICT system
as-built drawings &
schematics approved Telephone /
5 telecommunication system
by Professional
Engineer (P.E) (2 Projector & visual system
hardcopy & softcopy)
PA system
Conferencing / video
conference system
CCTV system
Access card system
Nurse call system
Uninterrupted power
supply (UPS) system
Isolated power supply (IPS)
Surge protection device
(SPD)
Others:
Others:
5
OPERATION & MANUAL
Floor finishing
ARCHITECTURAL
Operation & Curtain wall
Maintenance Manual
7 Landscape
(O&M) (3 sets
including original
copy) Others:
Air-conditioning &
ventilation system (ACMV)
6
Telephone /
telecommunication system
Acoustic system
Projector & visual system
PA system
Conferencing / video
conference system
Access card system
Nurse call system
Isolated power supply (IPS)
Surge protection device
(SPD)
Others:
Radiology
Laboratory
Diagnostic
Therapeutic
Power Supply / Power
ELECTRONIC / Distributor (Highend
BIOMEDICAL system)
Operation &
10 Maintenance Manual Uninterrupted power
(O&M) (3 sets supply (UPS) system
including original (Individual)
copy) Chiller / Cooling system
(Individual)
Dental chair compressor
(Individual)
Wiring system (Operation
Theatre Light)
Others:
TESTING & COMMISSIONING / FUNCTIONALITY
Master list of drawings
Air-conditioning &
ventilation system (ACMV)
7
Hot & cold water supply
system
Decay tank system
Others:
HT Switchgear
Transformer
Standby power system /
Genset
Uninterrupted power
supply (UPS) system
Main switch board (MSB)
Electrical system / electrical
component
Lightning protection &
earthing system
ICT system
ELECTRICAL Testing &
Commissioning (T&C) Telephone /
12
/ Functionality Result / telecommunication system
Report(2 sets)
Acoustic system
Projector & visual system
PA system
Conferencing / video
conference system
Access card system
Nurse call system
Isolated power supply (IPS)
Surge protection device
(SPD)
Others:
Incoming supply
measurement (1 / 3 phase)
Point of power distributor
(Highend system)
ELECTRONIC /
Insulation
BIOMEDICAL Testing
& Commissioning Earth bonding test
13
(T&C) / Functionality
Result / Report (2 Electrical safety test
sets) Performance test /
Quantitative task
Qualitative task
Others:
WARRANTY LETTER / CERTIFICATE
Wall paint
ARCHITECTURAL
Warranty Letter / Roof
14
Certificate (1 original Fire rated door
set)
Others:
8
Others:
Master list of drawings
Air-conditioning &
ventilation system (ACMV)
9
BIOMEDICAL Test tool
Warranty Letter /
Certificate (1 original
set)
Others:
LICENSE & STATUTORY CERTIFICATE
ARCHITECTURAL SIRIM
License & Statutory
19 BOMBA
Certificate (1 original
set) Others:
Lift (PMA No.) (JKKP)
Autoclave (JKKP)
Air receiver (JKKP)
Air compressor (JKKP)
Calorifier (JKKP)
MECHANICAL License
Boiler (JKKP)
20 & Statutory Certificate
(1 original set) Dumb waiter (JKKP)
Gas installation
(Suruhanjaya Tenaga)
Others:
Genset (DOE)
Genset installation
ELECTRICAL License &
Exit & Emergency light
21 Statutory Certificate
(BOMBA)
(1 original set)
Suruhanjaya Tenaga
Others:
ASSET REGISTRATION
Architectural
Civil & Structural (C&S)
Mechanical
- Fire suppression /
protection system
10
KEY & ACCESS CARD
Inventory - key
List of Key & Access
Room - key / access card /
24 Card
password
(1 master + 3 sets)
Others:
DEFECTS
Architectural
Civil & Structural (C&S)
25 List of Defects (2 sets) Mechanical
Electrical
Electronic / Biomedical
WARRANTY MANAGEMENT
Log book (Plant room)
PPM schedule
Maintenance
26 Meter reading (Utility -
Document (2 sets)
Water & Electricity)
Others:
CONTACT INFORMATION
Wall paint
Metal cladding
Roof
Door
ARCHITECTURAL
27 Contact Information Window
(3 sets)
Glass panel
Tiles
Sanitary fittings
Others:
Roof trusses
CIVIL & STRUCTURAL Water proofing
28 (C&S) Contact
Information (3 sets) Anti-termite
Others:
Master list of drawings
Air-conditioning &
ventilation system (ACMV)
11
Autoclave & sterilizing
system
Domestic water supply
system
Hot & cold water supply
system
Decay tank system
Others:
HT Switchgear
Transformer
Standby power system /
Genset
Uninterrupted power
supply (UPS) system
Main switch board (MSB)
Electrical system / electrical
component
Lightning protection &
earthing system
ICT system
ELECTRICAL Contact
Telephone /
30 Information
telecommunication system
(3 sets)
Acoustic system
Projector & visual system
PA system
Conferencing / video
conference system
Access card system
Nurse call system
Isolated power supply (IPS)
Surge protection device
(SPD)
Others:
Incoming supply
measurement (1 / 3 phase)
Point of power distributor
(Highend system)
ELECTRONIC / Insulation
BIOMEDICAL Contact
Earth bonding test
Information (3 sets)
31
Electrical safety test
Performance test /
Quantitative task
Qualitative task
Others:
Consultant's declaration
Room-to-room inspection
Other Supplementary
prepared by Client during
32 Document(s)
pre-delivery process
(2 sets)
(signed by Consultant)
Site diary
12
Training Schedule
Paid utility bills
CONSUMABLES
Full Not full
Medical gas - VIE tank
Medical gas - LPG
* Perincian ini lebih kepada projek Hospital dan bagi fasiliti kesihatan lain tanda yang berkaitan
sahaja.
Adalah dengan ini disahkan bahawa kami telah menyemak Dokumen-Dokumen sepertimana
senarai di atas dan didapati ianya lengkap dan teratur / tidak lengkap.
1 ………………………………………… …………………………………………
Nama Nama
Jawatan Jawatan
Kontraktor / Konsultan Kontraktor / Konsultan
2 …………………………………………
Nama
Jawatan
JKR CKK
3 …………………………………………
Nama
Jawatan
Bahagian Perkhidmatan Kejuruteraan,
KKM
4 …………………………………………
Nama
Jawatan
Bahagian Pembangunan, KKM
13
5 …………………………………………
Nama
Jawatan
JKN / Hospital / PKD
14