You are on page 1of 97

Certified Associate in Project Management

Sample Questions

Herbert G. Gonder, PMP


Oliver F. Lehmann, PMP
CAPM® Test Questions th
Test Version based on PMBOK® Guide 4 Edition

Questions in the real exam: 150


Scoring questions: 135
Non-scoring questions (pre-test): 15

Questions in this prep test: 162

______________
Your result: correct answers
______________

Prep test passed: … (121 or more)


Prep test not passed: … (120 or less)

Prep test questions provided by: Oliver F. Lehmann, PMP

Contact: www.oliverlehmann.com

CAPM® Credential
Handbook: www.pmi.org/PDF/pdc_capmhandbook.pdf

Contents:

Questions: ........................................ Q - 1 to Q - 88
Answers: ............................................. A - 1 to A – 5

© Oliver F. Lehmann, PMP www.oliverlehmann.com


Munich, Bavaria, Germany

This document may be freely distributed and the questions may be used in other materials as long as
this copyright attribution remains unchanged.
CAPM® Preparation

Certified Associate in Project Management


Sample Questions

Herbert G. Gonder, PMP


Oliver F. Lehmann, PMP
CAPM Certification

Chapter 1 – Introduction

4%, PMBOK Guide pages 3 - 14

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q-1 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Introduction

A Project is…
CAPM Certification

a) …an ongoing endeavor to create repetitive products, services, or


results.
b) …a unique service undertaken to create a temporary product or
result.
c) …a unique endeavor undertaken to create a temporary product,
service, or result.
d) …a temporary endeavor undertaken to create a unique product,
service, or result

Introduction

What is true for the types of work in an organization?


CAPM Certification

a) The purpose of a project is to achieve its objective and then to


end.
b) The purpose of a project is to attain its objective and then to
obtain another one.
c) The purpose of a project is to constantly sustain the business.
d) The purpose of ongoing work is to conclude when its specific
objectives have been attained.

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q-2 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Introduction

The Project manager is the person…


CAPM Certification

a) …assigned by the performing organization to achieve the project


objectives.
b) …responsible for meeting the organization’s strategic goals.
c) …responsible for an organization’s level of profitability.
d) …responsible for an organization’s overall productivity.

Introduction

A Program is…
CAPM Certification

a) …a group of related projects managed in a coordinated way.


b) …a project for which earned value management is used.
c) …projects grouped together to facilitate effective management of
their work to meet business objectives.
d) …a way of effectively handling change control in a group of related
projects.

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q-3 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Introduction

The areas of expertise that a project manager should at least


CAPM Certification

master does not include


a) General management knowledge and skills
b) Attitudes and leadership
c) Knowledge about project management
d) Tools for operational optimization

Introduction

Enterprise environmental factors includes all of the following


CAPM Certification

except
a) Organizational culture
b) Political climate
c) Physical environment
d) Work authorization system

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q-4 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Introduction

A PMO (Project management office) is an organizational unit


CAPM Certification

to…
a) …centralize and coordinate management of projects under its
domain.
b) …ensure proper payment of acquired project human resources.
c) …ensure customer satisfaction during the handover of
deliverables.
d) …manage sub-project work under the domain of the project
manager.

Introduction

The Project manager is the person


CAPM Certification

a) Assigned by the Performing organization to ensure that the


project meets the strategic plan goals.
b) Assigned by the Performing organization as the project’s quality
expert.
c) Assigned by the Performing organization as the project’s technical
expert.
d) Assigned by the Performing organization to achieve the project
objectives.

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q-5 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

P Certification
CAPM
CAPM
CA Cer c tion
t ffiica
e ti

Chapter 2 – Project Lifecycle and Organization

4%, PMBOK Guide pages 15 - 33

Lifecycle and Organization

Projects and operations share the following characteristics


CAPM Certification

EXCEPT:
a) Both are performed by people.
b) Both are ongoing and repetitive.
c) Both are constrained by limited resources.
d) Both are performed to achieve organizational objectives.

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q-6 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Lifecycle and Organization

The Project life cycle…


CAPM Certification

a) …documents the costs caused by the project at certain point in


time.
b) …is presales, project execution, product handover and
documentation.
c) …is a technique especially for extreme programming and agile
project management.
d) …is a collection of sequential or overlapping Project phases.

Lifecycle and Organization

At the start of the project the level of uncertainty…


CAPM Certification

a) …is highest and decreases over the life of the project.


b) …cannot be predicted unless the Project charter has been signed.
c) …is lower than at the end of the project.
d) …similar to the level of uncertainty at the end of the project.

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q-7 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Lifecycle and Organization

The ability of the stakeholders to influence the project…


CAPM Certification

a) …is always due to the soft skills of the project manager.


b) …is highest at the start and gets progressively lower as the project
continues.
c) …does not change over time unless a change request has been
initiated.
d) …remains constant over the entire running time of the project.

Lifecycle and Organization

A Project phase is characterized by…


CAPM Certification

a) …a ringing bell at the moment of final completion.


b) …the instruction email of the managing director.
c) …the completion and approval of one or more deliverables.
d) …reaching the predicted milestone in your project plan.

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q-8 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Lifecycle and Organization

The sequence of phases in a project life cycles is…


CAPM Certification

a) …often a basis for project governance.


b) …necessarily sequential.
c) …necessarily overlapping.
d) …necessarily iterative.

Lifecycle and Organization

What is true for Stakeholders of a project?


CAPM Certification

a) All stakeholders belong to the performing organization.


b) The project team is not regarded as a key stakeholder.
c) Identifying stakeholders can be difficult but critical.
d) The sponsor of the project is not regarded as a key stakeholder.

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q-9 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Lifecycle and Organization

Projectized organizations…
CAPM Certification

a) …are those whose most resources are involved in project work.


b) …usually lack skills and competence in project management.
c) …usually have a strong hierarchically built functional organization.
d) …give usually weak authority to their project managers.

Lifecycle and Organization

Which of the following is NOT typical for Weak matrix


CAPM Certification

organizations?
a) The project managers role is part-time.
b) The project managers authority is high.
c) Resource availability is limited.
d) The project managers authority is limited.

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 10 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Lifecycle and Organization

What is true on organizational cultures and styles?


CAPM Certification

a) They should be influenced by software that helps draw GANTT-


Charts and PERT Networks and calculate Earned value.
b) They are mainly reflected in the schedule, which the project
manager explains to team members in weekly review meetings.
c) They are emanating from the range of incentives and bonuses,
which project team members will receive at the end of the project.
d) Cultures and styles may have a strong influence on a project’s
ability to meet its objectives.
CAPM Certification

Chapter 3 – Project Management Processes for a


Project

11%, PMBOK Guide pages 35 - 65

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 11 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Processes for a Project

In order for a project to be successful, it is usually NOT


CAPM Certification

necessary for a project team to…


a) …use a defined approach required to meet the project objectives.
b) …buy highly sophisticated project management software and train
project team members in its application.
c) …comply with the requirements to meet the stakeholder needs
and expectations.
d) …balance the competing demands of scope, time, cost, quality,
resources, and risk to produce the specified product.

Processes for a Project

Project management is the application of…


CAPM Certification

a) …specific project management software in an enterprise


environment.
b) …motivational and developmental techniques to team-members
and other stakeholders.
c) …the chain of command in order to ensure timely completion of
all project activities.
d) …knowledge, skills, tools, and techniques to project activities to
meet project requirements.

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 12 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Processes for a Project

The five Project management process groups are:


CAPM Certification

a) Planning, auditing, directing, monitoring, and closing.


b) Selling, planning, staffing, executing, and documenting.
c) Initiating, planning, executing, monitoring and controlling, and
closing.
d) Initiating, executing, controlling, reviewing, and closing.

Processes for a Project

A process is …
CAPM Certification

a) …a legal act where project managers are blamed in court for


material or repudiatory breach of contract.
b) …a set of interrelated actions and activities performed to achieve a
pre-specified product, result, or service.
c) …something mystical which is comprehensible only to well-trained
experts from the project management disciple.
d) …something that cannot be explained without a sound
understanding of standardized project phase models.

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 13 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Processes for a Project

What is true for Project management processes?


CAPM Certification

a) They are limited to the processes of design, development,


deployment and maintenance.
b) All processes described must always be applied uniformly in all
projects without tailoring.
c) The project manager is responsible for determining which
processes are appropriate for the project.
d) They are fully independent of the Product-oriented processes that
may also be part of the project.

Processes for a Project

The purpose of the Project management processes is to…


CAPM Certification

a) …initiate, plan, execute, monitor and control, and close a project.


b) …safe as much money of the customer as possible.
c) …please the stakeholders and sponsors.
d) …show the project manager that he is in charge.

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 14 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Processes for a Project

The PMBOK Guide presents the project management processes


CAPM Certification

as...
a) ...discrete elements with well defined interfaces.
b) …stochastic elements with well defined interfaces.
c) ...unique black elements of process control graphs.
d) ...scatter diagrams and process flow charts.

Processes for a Project

The application of Project management processes is...


CAPM Certification

a) ...only done at the beginning of a project when not much


knowledge is available.
b) …only done by project managers without experience and standing
in the organization.
c) ...recommended but not necessary unless the management
requires it.
d) ...iterative and many processes are repeated during the project.

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 15 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Processes for a Project

Project Management processes and product-oriented


CAPM Certification

processes...
a) ...are both fully described in the PMBOK Guide, 4th edition.
b) …overlap and interact throughout the life of a project.
c) ...do not show any differences.
d) ...are not described up to now.

Processes for a Project

On each project the Project management process groups are...


CAPM Certification

a) ...usually performed in a random sequence or not at all.


b) …are guides for applying appropriate project management
knowledge and skills during the project.
c) ...performed in a very specific sequence decided in alignment with
the progress of the current project phase.
d) ...performed in a sequence determined by the key stakeholder.

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 16 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Processes for a Project

What is true for Project management process groups and


CAPM Certification

Knowledge areas?
a) The Project quality management Knowledge area includes most
processes.
b) The Monitoring and controlling Process group includes most
processes.
c) Each process is an element of exactly one Process group and one
Knowledge area.
d) Process groups are another term for Project phases and should
thus be done in sequence.

Processes for a Project

The Process group that provides feedback to implement


CAPM Certification

corrective or preventive action is:


a) Testing
b) Planning
c) Executing
d) Monitoring and Controlling

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 17 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Processes for a Project

In multi-phase projects, the processes defined in the process


CAPM Certification

group would be...


a) ...done only once during the whole project.
b) ...normally repeated for each phase.
c) ...done only in the early phases.
d) ...done only in fixed price contracts.

Processes for a Project

The Closing Process group consists of those processes...


CAPM Certification

a) ...performed to finalize all activities across all Project management


process groups to formally complete the project, phase, or
contractual obligations.
b) ...that signal to the team may come together again and have a
night together at a post mortem project barbeque.
c) ...that support advertising of the product in order to let everyone
know how successful and efficient the team worked.
d) ...that reward the customers for their investment, the patience
with the team and the preparation to support change control.

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 18 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Processes for a Project

The processes of which Process group are often done external


CAPM Certification

to the project‘s scope of control?


a) Planning
b) Testing
c) Initiating
d) Executing

Processes for a Project

Which document formally authorizes the project?


CAPM Certification

a) Project scope statement


b) Project charter
c) Work breakdown structure
d) Cost management plan

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 19 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Processes for a Project

The Project scope statement is the primary output of which


CAPM Certification

process:
a) Define Scope
b) Verify Scope
c) Create WBS
d) Define Activities
CAPM Certification

Chapter 4 – Project Integration Management

11%, PMBOK Guide pages 71 - 102

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 20 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Integration Management

The Knowledge area of Project Integration Management


CAPM Certification

includes the project management processes:


a) Define Activities, Create WBS.
b) Develop Project Charter, Define Scope.
c) Collect Requirements, Define Activities.
d) Develop Project Charter, Close Project or Phase.

Project Integration Management

Which process uses Expert judgment?


CAPM Certification

a) Verify Scope
b) Develop Project Charter
c) Conduct Procurements
d) Report Performance

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 21 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Integration Management

Approved change requests may require:


CAPM Certification

a) Stakeholder expectations
b) Expert judgment
c) Implementation of preventive or corrective actions
d) Cost estimating

Project Integration Management

The stimuli for chartering and authorizing a project include


CAPM Certification

usually all of the following EXCEPT:


a) Customer needs
b) Business needs
c) Need for a new product, service or result
d) Project selection

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 22 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Integration Management

Application of additional padding material, due to a legally


CAPM Certification

enacted emission protection regulation, which requires


increased wall insulation for a building, is an example for a...
a) ...market demand.
b) ...business need.
c) ...social need.
d) ...legal requirement.

Project Integration Management

Which document indicates that a project manager has been


CAPM Certification

assigned and formally authorized to apply organizational


resource to project activities?
a) Stakeholder register
b) Project management plan
c) Work breakdown structure
d) Project charter

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 23 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Integration Management

Which of the following is NOT an input for the process Develop


CAPM Certification

Project Charter?
a) Project statement of work
b) Enterprise environmental factors
c) Organizational process assets
d) Requirements documentation

Project Integration Management

A contract signed by an external customer …


CAPM Certification

a) ...is developed concurrently to the Project charter.


b) ...is input to the Develop Project Charter process .
c) ...describes only the consideration on the contractor side.
d) ...lays down the organizational standard processes applied.

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 24 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Integration Management

The Business case is created as a result of one or more of the


CAPM Certification

following EXCEPT:
a) Market demand
b) Enterprise environmental factors
c) Customer request
d) Organizational need

Project Integration Management

In developing the Project charter, expert judgment may come


CAPM Certification

from all of the following EXCEPT:


a) Industry groups
b) Other units within the organization
c) Project team and Project management team
d) Stakeholders, including customers or sponsors

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 25 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Integration Management

The Project statement of work…


CAPM Certification

a) ...is a graphical description of products or services to be delivered


by the project.
b) ...is commonly developed by the project team to document
common understanding.
c) ...can be provided by a project initiator, sponsor, or the project
customer.
d) ...can generally never be provided as a part of a bid document.

Project Integration Management

Which process is used to implement approved change requests?


CAPM Certification

a) Perform Integrated Change Control


b) Verify Scope
c) Close Project or Phase
d) Direct and Manage Project Execution

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 26 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Integration Management

The Direct and Manage Project Execution process requires the


CAPM Certification

project manager and the project team to perform multiple


actions to perform work defined in the Project management
plan EXCEPT...
a) Developing of a Project charter.
b) Performing activities to accomplish project requirements.
c) Implementing the planned methods and standards.
d) Managing sellers and suppliers.

Project Integration Management

Deliverables are an outcome of which process?


CAPM Certification

a) Direct and Manage Project Execution


b) Develop Project Charter
c) Create WBS
d) Control Scope

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 27 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Integration Management

Approved change requests are...


CAPM Certification

a) ...the documented, authorized changes to expand or reduce


project scope.
b) ...changes to enhance the profit of the performing organization.
c) ...activities delegated by the project manager to the project
coordinator.
d) ...requested changes before a final decision on their rejection has
been made.

Project Integration Management

Concerning deliverables, which of the following statements is


CAPM Certification

true?
a) Deliverables must be produced and provided to complete a
process, phase or project .
b) Clearly defined deliverables are nice to have, but not necessary.
c) Responsible team-members perform without stated deliverables.
d) A deliverable is any item, which pleases the customer.

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 28 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Integration Management

A Configuration management plan documents...


CAPM Certification

a) ...how change management will be performed.


b) ...how changes will be monitored and controlled.
c) ...how configuration management will be performed.
d) ...none of the above.
CAPM Certification

Chapter 5 – Project Scope Management

11%, PMBOK Guide pages 103 - 128

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 29 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Scope Management

Define Scope is the process of...


CAPM Certification

a) ...developing the Work breakdown structure.


b) ...developing a detailed description of the project and product.
c) ...creating the Project management plan.
d) ...creating the Project scope management plan.

Project Scope Management

Create WBS is the process of...


CAPM Certification

a) ...subdividing the project deliverables and project work into


smaller, more manageable components.
b) ...preparing and performing the product acceptance and verifying
the correct administrative closure of a project.
c) ...assigning work levels, resources, durations, budgets, and begin
and end data to identified activities.
d) ...delegating schedule activities to project management team
members, to departments or to contractors.

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 30 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Scope Management

In the project context, the term scope can refer to...


CAPM Certification

a) ...managing and controlling activities.


b) ...customer scope as well as to stakeholder scope.
c) ...product scope as well as to project scope.
d) ...none of the above.

Project Scope Management

The Scope baseline of the project contains...


CAPM Certification

a) ...the approved detailed Project scope statement, WBS and its


associated WBS dictionary.
b) ...a Preliminary scope statement and its associated WBS and WBS
dictionary.
c) ...the customers wishes for additional scope during the time of
project execution.
d) ...legal regulations and public standards on necessary scope
elements.

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 31 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Scope Management

The Project scope statement includes, either directly, or by


CAPM Certification

reference to other documents all of the following EXCEPT:


a) Product scope description
b) Product acceptance criteria
c) Project deliverables
d) The Project charter

Project Scope Management

What is true for the Scope management plan?


CAPM Certification

a) The Scope management plan and the Project management plan


are independent from each other.
b) The Scope management plan and the Scope baseline are virtually
the same.
c) The Scope management plan and the Scope statement are always
not related.
d) The Scope management plan describes how the project scope will
be managed and controlled.

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 32 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Scope Management

Product breakdown, systems analysis, requirements analysis


CAPM Certification

and value engineering are included in what technique?


a) Forced identification
b) Project deliverables
c) Product analysis
d) Project constraints

Project Scope Management

Constraints are analyzed for all of the following EXCEPT:


CAPM Certification

a) Completeness
b) Additional risks
c) Assumptions
d) Approved changes

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 33 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Scope Management

Which is a commonly used method for alternatives


CAPM Certification

identification?
a) Factor analysis
b) Rule of seven
c) Brainstorming
d) Root-cause analysis

Project Scope Management

All of the following are usually part of the Project scope


CAPM Certification

statement EXCEPT:
a) Project deliverables
b) Project exclusions
c) Project documentation
d) Project constraints

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 34 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Scope Management

Which is an explicit statement that describes what is excluded


CAPM Certification

from the project, in case of the assumption of a stakeholder that


a particular product, service, or result might be a component of
the project?
a) A project constraint
b) A project exclusion
c) A project deliverable
d) A project requirement

Project Scope Management

The WBS is ...


CAPM Certification

a) ...deliverable oriented.
b) ...activity oriented.
c) ...result oriented.
d) ...none of the above.

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 35 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Scope Management

What is Decomposition?
CAPM Certification

a) The process of breaking down schedule activities into work


packages.
b) The subdivision of project deliverables into smaller, more
manageable components.
c) The aggregation of activities to more manageable units.
d) The process of fragmentation of activities to allow parallel
processing.

Project Scope Management

The lowest level of the WBS is called...


CAPM Certification

a) ...authorization level
b) ...cost account
c) ...deliverables
d) ...work packages

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 36 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Scope Management

What technique is usually applied if a deliverable in a WBS can


CAPM Certification

only be decomposed in the future?


a) Prototyping
b) Quality function deployment
c) Cost accounting
d) Rolling wave planning

Project Scope Management

All of the following are Group creativity techniques EXCEPT:


CAPM Certification

a) Brainstorming
b) Nominal group technique
c) Delphi technique
d) Estimation technique

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 37 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Scope Management

Approved changes can result from which of the following


CAPM Certification

processes?
a) Control Scope
b) Define Scope
c) Create WBS
d) Collect Requirements

Project Scope Management

Requirements documentation is input for which Project scope


CAPM Certification

management processes?
a) Define Scope, Collect Requirements, Control Scope
b) Verify Scope, Define Scope , Collect Requirements
c) Define Scope, Create WBS, Verify Scope, Control Scope
d) Report Performance, Define Scope, Collect Requirements

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 38 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

CAPM Certification
CAPM
CA C erti
Cer
er ttiion
cati
ttiifiica n

Chapter 6 – Project Time Management

11%, PMBOK Guide pages 129 - 164

Project Time Management

All of the following are outputs of the Define Activities process


CAPM Certification

EXCEPT:
a) Activity attributes
b) Activity list
c) Milestone list
d) Work breakdown structure

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 39 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Time Management

What statement is true?


CAPM Certification

a) A Milestone may be mandatory or optional.


b) A Milestone is always a phase finish event.
c) Milestones are inputs to define activities.
d) Milestone is a term synonymous to Deadline.

Project Time Management

What is Rolling wave planning?


CAPM Certification

a) It is a way to earn additional revenues.


b) It is a signal for poor initial planning.
c) It is a form of progressive elaboration planning.
d) It is a method no longer in use today.

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 40 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Time Management

Work and effort performed within a work package...


CAPM Certification

a) ...is not reported to the senior management.


b) ...is gathered in high level items called activities.
c) ...is further decomposed into single activities.
d) ...should be always contracted out to external vendors.

Project Time Management

The Activity list...


CAPM Certification

a) ...includes all Schedule activities that are required on the project.


b) ...does not include the Schedule activities that are required on the
project.
c) ...does only include activities which are unrelated to the WBS work
packages.
d) ...is always a personal list for the project manager‘s eyes only.

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 41 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Time Management

The Milestone list...


CAPM Certification

a) ...identifies all Work packages of the WBS.


b) ...is the list of Activity attributes.
c) ...identifies all Milestones.
d) ...is part of the project selection process.

Project Time Management

Which of the following is not among the Tools and techniques of


CAPM Certification

the Sequence Activities process?


a) Precedence Diagramming Method (PDM)
b) Dependency determination
c) Applying leads and lags
d) Critical chain method

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 42 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Time Management

All of the following are inputs of the Sequence Activities process


CAPM Certification

EXCEPT:
a) Project scope statement
b) Project charter
c) Activity list
d) Milestone list

Project Time Management

Which of the following is NOT an output of the Estimate Activity


CAPM Certification

Resources process?
a) Activity resource requirements
b) Resource breakdown structure
c) Project document updates
d) Schedule network diagrams

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 43 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Time Management

The Resource breakdown structure (RBS) is ...


CAPM Certification

a) ... a hierarchical structure of the identified resources.


b) ... a database showing human resources‘ skills.
c) ... a breakdown of scope by assigned resources.
d) ... an output of the process Activity Sequencing.

Project Time Management

PDM stands for:


CAPM Certification

a) Power distance management


b) Precedence diagramming method
c) Project data management
d) Performance distribution method

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 44 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Time Management

AON stands for:


CAPM Certification

a) Advanced online network


b) Annual order negotiation
c) Activity on node
d) Assessment of nonconformance

Project Time Management

PDM uses all of the following EXCEPT:


CAPM Certification

a) Finish-to-start relationships
b) Leads and lags
c) Dummy activities
d) Finish-to-finish relationships

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 45 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Time Management

Dependency determination uses all of the following types of


CAPM Certification

dependencies EXCEPT:
a) External dependencies
b) Mandatory dependencies
c) Discretionary dependencies
d) Relational dependencies

Project Time Management

All of the following are true EXCEPT: Precedence diagramming


CAPM Certification

method (PDM)...
a) ... uses nodes to represent the dependencies.
b) ...may require application of leads and lags.
c) ...is a method used in Critical Path Method (CPM).
d) ...uses boxes or rectangles to represent activities.

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 46 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Time Management

Common estimating methods in the process Estimate Activity


CAPM Certification

Durations are all of the following EXCEPT:


a) Analogous estimating
b) Parametric estimating
c) Three-point estimates
d) Six-point estimates

Project Time Management

Analogous estimating...
CAPM Certification

a) ...means estimating by comparing with well designed experiments.


b) ...uses the activity dates taken from a previous project.
c) ...uses historical information and expert judgment.
d) ...does not need information from previous, similar projects.

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 47 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Time Management

CPM stands for:


CAPM Certification

a) Change project manager


b) Critical path methodology
c) Cost performance measurement
d) Critical power maintenance
CAPM
APM
CA t fication
Certification
M Certi

Chapter 7 – Project Cost Management

9%, PMBOK Guide pages 165 - 188

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 48 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Cost Management

Project Cost Management includes all of the following processes


CAPM Certification

EXCEPT:
a) Acquire project team
b) Estimate costs
c) Determine budget
d) Control costs

Project Cost Management

Inputs for the Estimate Costs process are all of the following
CAPM Certification

EXCEPT:
a) Scope baseline
b) Project schedule
c) Human resource plan
d) Resource calendars

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 49 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Cost Management

Vendor bid analysis is among the tools and techniques of which


CAPM Certification

process?
a) Determine budget
b) Plan Costs
c) Control Costs
d) Estimate costs

Project Cost Management

The Cost performance baseline is an output of which process?


CAPM Certification

a) Estimate costs
b) Determine budget
c) Control costs
d) Estimate activity durations

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 50 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Cost Management

The accuracy of Parametric estimating depends on the following


CAPM Certification

EXCEPT:
a) Sophistication of the technique
b) Underlying data
c) Statistical relationship with historical data
d) Creation without inputs from external stakeholders

Project Cost Management

Which process has Cost performance baseline (updates) as an


CAPM Certification

output?
a) Estimate Costs
b) Determine Budget
c) Control Costs
d) Perform Integrated Change Control

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 51 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Cost Management

Company A is working on a project. The project‘s budget is


CAPM Certification

$10,000. The Planned value as of Data date is $4,000. The


project is 30% completed. 60% of the budget has been spent to
Data date.
The Earned value (EV) of the project is:
a) $600
b) $3,000
c) $5,000
d) $6,000

Project Cost Management

Company A is working on a project. The project‘s budget is


CAPM Certification

$10,000. The Planned value as of Data date is $4,000. The


project is 30% completed. 60% of the budget has been spent to
data date.
The Actual cost (AC) to date for the project is:
a) $6,000
b) $2,400
c) $3,000
d) $5,000

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 52 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Cost Management

Company A is working on a project. The project‘s budget is


CAPM Certification

$10,000. The Planned value as of Data date is $4,000. The


project has an Earned value of $3,500 and Actual costs of
$4,500.
Which statement is correct?
a) The project is behind schedule.
b) The project is ahead of schedule.
c) The project is finished.
d) The project is on schedule.

Project Cost Management

Company A is working on a project. The project‘s budget is


CAPM Certification

$10,000. The Planned value as of Data date is $4,000. The


project has an Earned value of $3,500 and Actual costs of
$4,500.
What is the Cost variance of the project?
a) - $1,000
b) $500
c) -500
d) $1,000

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 53 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Cost Management

Company A is working on a project. The project‘s budget is


CAPM Certification

$10,000. The Planned value as of Data date is $4,000. The


project is 30% completed. 60% of the budget has been spent.
If the company continues to spend money at the same rate,
what will the project cost (EAC)?
a) $10,000
b) $20,000
c) $6,000
d) $4,000

Project Cost Management

Company A is working on a project. The project‘s budget is


CAPM Certification

$10,000. The Planned value as of Data date is $4,000. The


project is 30% completed. 60% of the budget has been spent.
If cost variances of the future are expected at the same rate as
they have occurred in the past, what is the Estimate to
complete (ETC)?
a) $10,600
b) $14,000
c) $7,000
d) $2,400

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 54 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Cost Management

Examining project performance over time to determine if


CAPM Certification

performance is improving or deteriorating is called:


a) Variance analysis
b) Trend analysis
c) Earned value technique
d) Cost benefit analysis

Project Cost Management

All of the following are outputs of the Control Costs process


CAPM Certification

EXCEPT:
a) Project management plan updates
b) Organizational process assets updates
c) Work performance measurements
d) Work performance information

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 55 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

PM Certification
CAPM
CAPM Certi cation
rt fiica

Chapter 8 – Project Quality Management

7%, PMBOK Guide pages 189 - 214

Project Quality Management

Project Quality Management processes include all of the


CAPM Certification

following processes EXCEPT:


a) Plan Quality
b) Perform Quality Assurance
c) Perform Qualitative Risk Analysis
d) Perform Quality Control

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 56 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Quality Management

Each process of Project Quality Management occurs ______ in


CAPM Certification

every project and occurs ______ of the project phases, if the


project is divided into phases.
a) At least once / in one or more.
b) At least twice / in one or more.
c) Sometimes / in all
d) At least once / in all

Project Quality Management

Which of the following is true?


CAPM Certification

a) Quality is “the degree of customer satisfaction achieved by


meeting stated and implicit wishes”.
b) Quality is “the degree of stakeholder satisfaction achieved by
meeting explicit requirements”.
c) Quality is “the degree to which a set of inherent requirements
meets client needs”.
d) Quality is “the degree to which a set of inherent characteristics
fulfill requirements”.

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 57 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Quality Management

Which of the following statements about quality and grade is


CAPM Certification

true?
a) Low quality may not always be a problem.
b) Projects should always deliver high grade.
c) Quality and grade are basically the same thing.
d) Low grade may not always be a problem.

Project Quality Management

All of the following statements about precision and accuracy are


CAPM Certification

true EXCEPT:
a) Precision means that the values of repeated measurements are
clustered and have little scatter.
b) Accuracy means that the measured values are close to the true
value.
c) Precision and accuracy are equivalent in that they are gained using
the same methods.
d) The project management team must determine appropriate levels
of precision and accuracy.

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 58 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Quality Management

Quality management recognizes the importance of each of the


CAPM Certification

following EXCEPT:
a) Customer satisfaction
b) Inspection over prevention
c) Management responsibility
d) Continuous improvement

Project Quality Management

Which of the following is a direct Input to the Perform Quality


CAPM Certification

Assurance process?
a) Project scope baseline
b) Quality audits
c) Quality metrics
d) Process analysis

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 59 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Quality Management

One of the fundamental tenets of modern quality management


CAPM Certification

states that:
a) Quality is planned, desired, and built in – not inspected in.
b) Quality is not planned, designed, and built in – only inspected in.
c) Quality is planned, designed, and built in – not inspected in.
d) Quality has to be planned, designed, built in, and inspected in.

Project Quality Management

Which of the following is a direct input to Plan Quality?


CAPM Certification

a) Quality metrics
b) Quality management plan
c) Design of experiments
d) Cost performance baseline

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 60 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Quality Management

Which of the following is not among the tools and techniques of


CAPM Certification

the Plan Quality process:


a) Cost-benefit analysis
b) Benchmarking
c) Brainstorming
d) Design of experiments

Project Quality Management

The upper (UCL) and lower (LCL) control limits for repetitive
CAPM Certification

processes are usually set at:


a) +/- 6 sigma
b) +/- 3 sigma
c) +/- 2 sigma
d) +/- 1 sigma

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 61 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

CAPM Certification

Chapter 9 – Project Human Resources Management

7%, PMBOK Guide pages 215 - 242

Project Human Resources Management

The project management team is...


CAPM Certification

a) …a supervising or controlling team.


b) …a subset of the project team.
c) …the project team contingency.
d) …none of the above.

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 62 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Human Resources Management

All of the following are processes of Project Human Resource


CAPM Certification

management EXCEPT:
a) Develop Human Resource Plan
b) Select Sellers
c) Develop Project Team
d) Manage Project Team

Project Human Resources Management

All of the following are direct inputs to the Develop Human


CAPM Certification

Resource Plan process EXCEPT:


a) Enterprise environmental factors
b) Organizational process assets
c) Project scope statement
d) Activity resource requirements

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 63 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Human Resources Management

Which of the following is not a subset of the Human resource


CAPM Certification

plan:
a) Roles and responsibilities
b) Project organization charts
c) Pre-assignment
d) Staffing management plan

Project Human Resources Management

Examples of Enterprise environmental factors that can influence


CAPM Certification

the Develop Human Resource Plan process are all of the


following EXCEPT:
a) Estimating techniques
b) Organizational structure
c) Personnel administration policies
d) Existing human resources

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 64 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Human Resources Management

OBS stands for:


CAPM Certification

a) Organizational breakdown structure


b) Organizational billing system
c) Open bargaining subject
d) Operational break-even status

Project Human Resources Management

RACI is an acronym for:


CAPM Certification

a) Resource, accountability, consult, inform


b) Responsible, accountable, consult, inform
c) Resource, acquirable, consult, instruct
d) Responsible, accountable, confirm, inform

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 65 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Human Resources Management

All of the following are inputs to the Develop Project Team


CAPM Certification

process EXCEPT:
a) Performance reports
b) Project staff assignments
c) Project management plan
d) Resource calendars

Project Human Resources Management

Co-location strategies can include all of the following EXCEPT:


CAPM Certification

a) Conveniences that enhance communication


b) A team meeting room
c) Building virtual teams
d) Places to post schedules

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 66 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Human Resources Management

The evaluation of a team‘s effectiveness can include indicators


CAPM Certification

such as the following EXCEPT:


a) Improvements in skills that allow individuals to perform
assignments more effectively.
b) Improvements in competencies that help the team perform better
as a team.
c) Reduced staff turnover rate.
d) Participation in regular after work parties and other socializing
events.
CAPM
A
CA Certifi
er tion
Certification
f cati
tio

Chapter 10 – Project Communications Management

7%, PMBOK Guide pages 243 - 271

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 67 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Communications Management

Which of the following is NOT a process of Project


CAPM Certification

Communications Management?
a) Manage Stakeholder Expectations
b) Plan Communications
c) Distribute Information
d) Manage Project Team

Project Communications Management

Acknowledgement means that...


CAPM Certification

a) ...the receiver signals receipt of the message, but not necessarily


agreement with the message.
b) ...the receiver signals receipt of the message, and necessarily
agreement with the message.
c) ...the receiver chooses writing-style to document the reception of
the message, and the agreement with the message.
d) ...the receiver nods to the message, and agrees with the message.

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 68 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Communications Management

In the communication model, who is responsible for encoding


CAPM Certification

the initial message?


a) The receiver
b) The receiver and the sender
c) The sender
d) The receiver or the sender

Project Communications Management

The process Plan Communications uses the following inputs


CAPM Certification

EXCEPT:
a) Enterprise environmental factors
b) Organizational process assets
c) Stakeholder management strategy
d) Human resource calendar

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 69 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Communications Management

Stakeholder communication requirements are provided in the


CAPM Certification

output of which process?


a) Report Performance
b) Develop Human resource plan
c) Distribute Information
d) Plan Communications

Project Communications Management

You have to coordinate 10 team members. How many


CAPM Certification

Communication channels are there on your project during that


time?
a) 10
b) 45
c) 50
d) 100

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 70 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Communications Management

Expert judgment is among tools and techniques of which


CAPM Certification

process?
a) Performance Reporting
b) Communications Planning
c) Identify Stakeholders
d) Manage Stakeholders

Project Communications Management

Communication activity includes all of the following potential


CAPM Certification

dimensions EXCEPT:
a) internal
b) formal
c) messy
d) written

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 71 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Communications Management

All of the following are outputs of the Report Performance


CAPM Certification

process EXCEPT:
a) Performance reports
b) Organizational process assets updates
c) Change requests
d) Implemented corrective actions

Project Communications Management

Which is not an example of Writing styles?


CAPM Certification

a) Active versus passive voice


b) Sentence structure
c) Face-to-face meetings
d) Word choice

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 72 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Communications Management

Communication technology is a tool and technique of which


CAPM Certification

process?
a) Report Performance
b) Plan Communications
c) Distribute Information
d) Manage stakeholder expectations
CAPM
CA C cat on
Certification
c ti
C PM Certifica

Chapter 11 – Project Risk Management

11%, PMBOK Guide pages 273 - 312

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 73 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Risk Management

A project risk is a(n) _______ event or condition that, if it occurs,


CAPM Certification

has a __________________ effect on at least one project


objective.
a) Certain / negative or positive
b) Uncertain / negative and positive
c) Uncertain / negative or positive
d) Unkown / neither negative nor positive

Project Risk Management

Which is used as tool and technique for the process Plan Risk
CAPM Certification

Management?
a) Tornado diagramming
b) Decision tree analysis
c) Monte-Carlo simulation
d) Planning meetings and analysis

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 74 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Risk Management

Against risks for which it may not be cost-effective or possible to


CAPM Certification

develop a proactive response a prudent response can be...


a) To allocate a contingency reserve
b) To build reserves
c) To do nothing
d) To ask your sponsor

Project Risk Management

Which document is established and updated along the Project


CAPM Certification

Risk Management processes from Identify Risks through Plan


Risk Responses and Monitoring and Control Risks ?
a) List of risk triggers
b) Risk register
c) Risk mitigation
d) Decision tree

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 75 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Risk Management

The Output of the process Plan Risk Management will be


CAPM Certification

summarized in?
a) The quality baseline
b) The project scope management plan
c) The risk management plan
d) In none of the above

Project Risk Management

An item typically included in the Risk management plan is:


CAPM Certification

a) Potential responses
b) Identified risks
c) Risk management methodology
d) Root causes

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 76 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Risk Management

In relation to the process Risk Management Planning, RBS


CAPM Certification

stands for:
a) Reserve budget settlement
b) Risk brain storming
c) Risk baseline support
d) Risk breakdown structure

Project Risk Management

Information gathering techniques used during the process


CAPM Certification

Identify Risks include all of the following EXCEPT:


a) Brainstorming
b) Delphi technique
c) Interviewing
d) Assumptions analysis

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 77 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Risk Management

Typical Diagramming techniques used for the process Identify


CAPM Certification

Risks include all of the following EXCEPT:


a) System or process flow charts
b) Cause-and-effect diagrams
c) Influence diagrams
d) Delphi technique

Project Risk Management

The process Perform Qualitative Risk Analysis includes:


CAPM Certification

a) Risk urgency assessment


b) Sensitivity analysis
c) Checklist analysis
d) Probability distribution

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 78 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Risk Management

Data developed during the process Perform Quantitative Risk


CAPM Certification

Analysis often leads to what type of probability distributions?


a) S-curves
b) 4-peak distributions
c) Continuous distributions
d) Tornado distributions

Project Risk Management

Commonly used Quantitative risk analysis and modeling


CAPM Certification

techniques include all of the following EXCEPT:


a) Sensitivity analysis
b) Expected monetary value analysis
c) Decision tree analysis
d) Assumptions analysis

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 79 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Risk Management

Strategies for negative risks or threats include all of the


CAPM Certification

following EXCEPT:
a) Convince
b) Avoid
c) Transfer
d) Mitigate

Project Risk Management

Examples of risk mitigation include:


CAPM Certification

a) Building a prototype
b) Contingencies
c) Insurance
d) Warranties

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 80 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Risk Management

All of the following strategies are strategies for positive risks or


CAPM Certification

opportunities EXCEPT:
a) Exploit
b) Share
c) Transfer
d) Enhance

Project Risk Management

The process Monitor and Control Risks includes all of the


CAPM Certification

following EXCEPT:
a) Risk reassessments
b) Risk audits
c) Technical performance measurements
d) Modeling and simulation

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 81 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Risk Management

All of the following are updated during the process Monitor and
CAPM Certification

Control Risks EXCEPT:


a) Risk register
b) Risk audit
c) Organizational process assets
d) Project management plan
CAPM Certification

Chapter 12 – Project Procurement Management

7%, PMBOK Guide pages 313 - 344

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 82 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Procurement Management

All of the following are tools and techniques of the process Plan
CAPM Certification

Procurements EXCEPT:
a) Make-or-buy analysis
b) Expert judgment
c) Advertising
d) Contract types

Project Procurement Management

All of the following are arrangements under which the buyer


CAPM Certification

must precisely specify the product or services being procured


EXCEPT:
a) Firm fixed price contracts
b) Fixed price incentive fee contracts
c) Fixed price with economic price adjustment contracts
d) Cost plus award fee contracts

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 83 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Procurement Management

Your company is in the process of selling consulting services to a


CAPM Certification

new buyer. The contract type with lowest risk for your company
in this situation is:
a) Firm fixed price
b) Time and material
c) Cost plus fixed fee
d) Cost plus incentive fee

Project Procurement Management

Source selection criteria are input to which process?


CAPM Certification

a) Plan procurements
b) Conduct procurements
c) Administer procurements
d) Close procurements

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 84 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Procurement Management

A Bidder conference is typically held during what process?


CAPM Certification

a) Close Procurements
b) Plan Procurements
c) Administer Procurements
d) Conduct Procurements

Project Procurement Management

All of the following are tools and techniques to select a seller


CAPM Certification

EXCEPT:
a) Proposal evaluation techniques
b) Contract change control system
c) Independent estimates
d) Bidder conference

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 85 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Procurement Management

The Contract change control system...


CAPM Certification

a) ...is an input to the Plan Procurements process.


b) ...requests changes to the project management plan.
c) ...lists the types of contract to be used.
d) ...defines the processes by which the procurement can be
modified.

Project Procurement Management

A Contract change control system is often among the tools and


CAPM Certification

techniques in what process?


a) Plan procurements
b) Conduct procurements
c) Administer procurements
d) Select sellers

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 86 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Procurement Management

Updates in Organizational process assets in the Administer


CAPM Certification

Procurements process contain all of the following EXCEPT:


a) Correspondence
b) Payment schedules and requests
c) Seller performance evaluation documentation
d) Requested changes

Project Procurement Management

Depending on contract terms and conditions, early termination


CAPM Certification

of a contract may occur for all of the following reasons EXCEPT:


a) Default of either party
b) Completion of the project
c) Mutual agreement
d) Convenience

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 87 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM® Preparation

Project Procurement Management

A Procurement audit is often held during what process?


CAPM Certification

a) Verify Scope
b) Verify Product
c) Close Contract
d) Close Procurements

© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany


PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Q - 88 www.oliverlehmann.com
Newtown Square, PA, USA, which are registered in the USA and in other nations.
CAPM Prep Questions

Answers

PMBOK
Right Guide,
Chapter Slide answer page
1 3 d 5
1 4 a 5
1 5 a 13
1 6 a 9
1 7 d 13
1 8 c 14
1 9 a 11
1 10 d 13

PMBOK
Right Guide,
Chapter Slide answer page
2 12 b 22
2 13 d 15
2 14 a 17
2 15 b 17
2 16 c 19
2 17 a 20
2 18 c 24
2 19 a 30
2 20 b 28
2 21 d 27

PMBOK
Right Guide,
Chapter Slide answer page
3 23 b 37
3 24 d 37
3 25 c 39
3 26 b 37
3 27 c 38
3 28 a 39
3 29 a 39
3 30 d 39
3 31 b 38
3 32 b 39
3 33 c 43
3 34 d 59
3 35 b 41
3 36 a 64
3 37 c 45
3 38 b 45
3 39 a 49

Herbert G. Gonder, PMP


Oliver F. Lehmann, PMP
© 2009 A- 1 Germany
CAPM Prep Questions

Answers

PMBOK
Right Guide,
Chapter Slide answer page
4 41 d 71
4 42 b 74
4 43 c 85
4 44 d 77
4 45 d 75
4 46 d 73
4 47 d 74
4 48 b 14
4 49 b 75
4 50 c 77
4 51 c 75
4 52 d 99
4 53 a 83
4 54 a 84
4 55 a 85
4 56 a 87
4 57 c 82

PMBOK
Right Guide,
Chapter Slide answer page
5 59 b 112
5 60 a 116
5 61 c 456
5 62 a 456
5 63 d 115
5 64 d 126
5 65 c 114
5 66 d 112
5 67 c 114
5 68 c 115
5 69 b 115
5 70 a 116
5 71 b 118
5 72 d 118
5 73 d 120
5 74 d 108
5 75 a 128
5 76 c 104

Herbert G. Gonder, PMP


Oliver F. Lehmann, PMP
© 2009 A- 2 Germany
CAPM Prep Questions

Answers

PMBOK
Right Guide,
Chapter Slide answer page
6 78 d 133
6 79 a 136
6 80 c 135
6 81 c 133
6 82 a 135
6 83 c 136
6 84 d 136
6 85 b 136
6 86 d 142
6 87 a 145
6 88 b 138
6 89 c 138
6 90 c 138, 140
6 91 d 139, 140
6 92 a 138
6 93 d 149, 150
6 94 c 149
6 95 b 138

PMBOK
Right Guide,
Chapter Slide answer page
7 97 a 165
7 98 d 169
7 99 d 169
7 100 b 175
7 101 d 172
7 102 c 188
7 103 b 182
7 104 a 182
7 105 a 182
7 106 a 182
7 107 b 184
7 108 b 184
7 109 b 186
7 110 d 180

Herbert G. Gonder, PMP


Oliver F. Lehmann, PMP
© 2009 A- 3 Germany
CAPM Prep Questions

Answers

PMBOK
Right Guide,
Chapter Slide answer page
8 112 c 189
8 113 a 189
8 114 d 190
8 115 d 190
8 116 c 190
8 117 b 190, 191
8 118 c 202
8 119 c 190
8 120 d 191
8 121 c 191
8 122 b 196

PMBOK
Right Guide,
Chapter Slide answer page
9 124 b 215
9 125 b 215
9 126 c 217
9 127 c 222, 223
9 128 a 219
9 129 a 220
9 130 b 221
9 131 a 230
9 132 c 234
9 133 d 235

PMBOK
Right Guide,
Chapter Slide answer page
10 135 d 243
10 136 a 255
10 137 c 255
10 138 d 253
10 139 d 257
10 140 b 253
10 141 c 250
10 142 c 245
10 143 d 266
10 144 c 258
10 145 b 244

Herbert G. Gonder, PMP


Oliver F. Lehmann, PMP
© 2009 A- 4 Germany
CAPM Prep Questions

Answers

PMBOK
Right Guide,
Chapter Slide answer page
11 147 c 275
11 148 d 279
11 149 a 304
11 150 b 274
11 151 c 277
11 152 c 279
11 153 d 287
11 154 d 286, 287
11 155 d 287
11 156 a 289
11 157 c 297
11 158 d 298, 299
11 159 a 303, 304
11 160 a 304
11 161 c 304, 305
11 162 d 308
11 163 b 308

PMBOK
Right Guide,
Chapter Slide answer page
12 165 c 317
12 166 d 322-324
12 167 c 323
12 168 b 329
12 169 d 329
12 170 b 331, 332
12 171 d 338
12 172 c 335
12 173 d 340
12 174 b 342
12 175 d 342

Herbert G. Gonder, PMP


Oliver F. Lehmann, PMP
© 2009 A- 5 Germany

You might also like