DESIGN & BUILD AKSESIBILITAS DARAT FLY OVER & TAPPER TERMINAL TELUK LAMONG
Based On Drawing Rev. 9 1-4 5 - 11 12 - 1819 - 2526 - 1 2 - 8 9 - 15 16 - 2223 - 2930 - 6 7 - 13 14 - 2021 - 2728 - 3 4 - 10 11 - 1718 - 2425 - 1 2 - 8 9 - 15 16 - 2223 - 2930 - 5 6 - 12 13 - 1920 - 26 27 - 2 3 - 9 10 - 1617 - 23 24 - 301 - 7 8 - 14 15 - 2122 - 2829 - 4 5 - 11 12 - 1819 - 2526 - 2 3 - 9 10 - 1617 - 2324 - 30
Month - 1 Month - 2 Month - 3 Month - 4 Month - 5 Month - 6 Month - 7 Month - 8 Month - 9 Month - 10
NO DESCRIPTION START FINISH Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18
I II III IV I II III IV V I II III IV I II III IV V I II III IV I II III IV I II III IV V I II III IV I II III IV V I II III IV V
1 PREPARATION WORK
Blasting & Rotary Trolly Assembly Monday, April 9, 2018 Sunday, June 3, 2018
1.1.2 Jig Assembly & Tools Monday, April 9, 2018 Sunday, June 3, 2018
Instalation & Testing Reamer Machine Monday, July 2, 2018 Monday, July 16, 2018
1.2.1 Clearing Jig Existing Area Assembly Tuesday, March 6, 2018 Saturday, March 31, 2018
1.2.2 Clearing Erection Area Monday, July 2, 2018 Saturday, July 21, 2018
1.3 Marking Out Monday, July 23, 2018 Sunday, December 9, 2018
1.4 Traffic Management Monday, July 23, 2018 Sunday, December 9, 2018
1.5 Engineering
1.5.1 Fix Design Tuesday, March 6, 2018 Monday, April 30, 2018
1.5.3 Design Drawing Tuesday, March 6, 2018 Monday, April 30, 2018
1.5.4 Shop Drawing Monday, April 16, 2018 Friday, May 11, 2018
1.5.5 Cutting Plan Tuesday, May 15, 2018 Monday, July 2, 2018
1.7 Direksi Keet Monday, July 23, 2018 Friday, August 31, 2018
1.8 FAT Saturday, August 18, 2018 Friday, August 31, 2018
2 PROCUREMENT
Section 2
2.1.1 P4-P3 (61 M) Saturday, March 31, 2018 Thursday, May 31, 2018
2.1.2 P5-P4 (41,35 M) Monday, April 23, 2018 Thursday, May 31, 2018
2.1.3 P6-P5 (41,35 M) Monday, April 23, 2018 Thursday, May 31, 2018
2.1.4 P7-P6 (41,35 M) Monday, April 23, 2018 Thursday, May 31, 2018
2.1.5 P8-P7 (41,35 M) Monday, April 23, 2018 Thursday, May 31, 2018
2.1.6 P9-P8 (40,20 M) Monday, April 23, 2018 Thursday, May 31, 2018
2.1.7 P10-P9 (40,20 M) Monday, April 23, 2018 Thursday, May 31, 2018
2.1.8 P11-P10 (41,35 M) Monday, April 23, 2018 Thursday, May 31, 2018
2.1.9 P12-P11 (41,35 M) Monday, April 23, 2018 Thursday, May 31, 2018
2.1.10 P13-P12 (41,35 M) Monday, April 23, 2018 Thursday, May 31, 2018
2.1.11 P14-P13 (41,35 M) Monday, April 23, 2018 Thursday, May 31, 2018
Section 3
2.1.12 P15-P14 (61 M) Saturday, March 31, 2018 Thursday, May 31, 2018
2.1.13 P16-P15 (61 M) Saturday, March 31, 2018 Thursday, May 31, 2018
2.1.14 P17-P16 (41,35 M) Monday, April 23, 2018 Thursday, May 31, 2018
2.1.15 P18-P17 (41,35 M) Monday, April 23, 2018 Thursday, May 31, 2018
2.1.16 P19-P18 (41,35 M) Monday, April 23, 2018 Thursday, May 31, 2018
2.1.17 P20-P19 (41,35 M) Monday, April 23, 2018 Thursday, May 31, 2018
2.1.18 P21-P20 (46,8 M) Monday, April 23, 2018 Thursday, May 31, 2018
Section 4
2.1.19 P22-P21 (61 M) Saturday, March 31, 2018 Thursday, May 31, 2018
2.1.20 P23-P22 (46,8 M) Monday, April 23, 2018 Thursday, May 31, 2018
Section 2
2.2.1 P4-P3 (61 M) Friday, June 22, 2018 Friday, July 6, 2018 9 18 13
2.2.2 P5-P4 (41,35 M) Friday, July 6, 2018 Friday, July 13, 2018 5 13
2.2.3 P6-P5 (41,35 M) Friday, July 13, 2018 Friday, July 20, 2018 5 13
2.2.4 P7-P6 (41,35 M) Friday, July 20, 2018 Friday, July 27, 2018 5 13
2.2.5 P8-P7 (41,35 M) Friday, July 27, 2018 Friday, August 3, 2018 5 13
Page 1 of 4
OWNER KONSULTAN KONTRAKTOR / SUB KONTRAKTOR
DESIGN & BUILD AKSESIBILITAS DARAT FLY OVER & TAPPER TERMINAL TELUK LAMONG
Based On Drawing Rev. 9 1-4 5 - 11 12 - 1819 - 2526 - 1 2 - 8 9 - 15 16 - 2223 - 2930 - 6 7 - 13 14 - 2021 - 2728 - 3 4 - 10 11 - 1718 - 2425 - 1 2 - 8 9 - 15 16 - 2223 - 2930 - 5 6 - 12 13 - 1920 - 26 27 - 2 3 - 9 10 - 1617 - 23 24 - 301 - 7 8 - 14 15 - 2122 - 2829 - 4 5 - 11 12 - 1819 - 2526 - 2 3 - 9 10 - 1617 - 2324 - 30
Month - 1 Month - 2 Month - 3 Month - 4 Month - 5 Month - 6 Month - 7 Month - 8 Month - 9 Month - 10
NO DESCRIPTION START FINISH Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18
I II III IV I II III IV V I II III IV I II III IV V I II III IV I II III IV I II III IV V I II III IV I II III IV V I II III IV V
2.2.6 P9-P8 (40,20 M) Friday, August 3, 2018 Friday, August 10, 2018 5 13
2.2.7 P10-P9 (40,20 M) Friday, August 10, 2018 Friday, August 17, 2018 5 13
2.2.8 P11-P10 (41,35 M) Friday, August 17, 2018 Friday, August 24, 2018 5 13
2.2.9 P12-P11 (41,35 M) Friday, August 24, 2018 Friday, August 31, 2018 5 13
2.2.10 P13-P12 (41,35 M) Friday, August 31, 2018 Friday, September 7, 2018 14 4
2.2.11 P14-P13 (41,35 M) Friday, September 7, 2018 Friday, September 14, 2018 14 4
Section 3
2.2.12 P15-P14 (61 M) Friday, September 14, 2018 Friday, September 21, 2018 23 17
2.2.13 P16-P15 (61 M) Friday, September 21, 2018 Friday, October 5, 2018 1 27 12
2.2.14 P17-P16 (41,35 M) Friday, October 5, 2018 Friday, October 12, 2018 6 12
2.2.15 P18-P17 (41,35 M) Friday, October 12, 2018 Friday, October 19, 2018 15 3
2.2.16 P19-P18 (41,35 M) Friday, October 19, 2018 Friday, October 26, 2018 15 3
2.2.17 P20-P19 (41,35 M) Monday, October 22, 2018 Friday, October 26, 2018 18
2.2.18 P21-P20 (46,8 M) Monday, October 22, 2018 Friday, November 2, 2018 6 18
Section 4
2.2.19 P22-P21 (61 M) Friday, November 9, 2018 Thursday, November 15, 2018 27 13
2.2.20 P23-P22 (46,8 M) Thursday, November 15, 2018 Friday, November 23, 2018 5 27
2.3 LRB Friday, June 1, 2018 August 31, 2018
3 UNIBRIDGE FABRICATION
3.1 FABRICATION
Section 2
3.1.1 P4-P3 (61 M) Monday, June 25, 2018 Monday, August 6, 2018
3.1.2 P5-P4 (41,35 M) Monday, July 23, 2018 Monday, August 13, 2018
3.1.3 P6-P5 (41,35 M) Monday, July 30, 2018 Monday, August 13, 2018
3.1.4 P7-P6 (41,35 M) Monday, August 6, 2018 Sunday, August 19, 2018
3.1.5 P8-P7 (41,35 M) Monday, August 6, 2018 Monday, August 27, 2018
3.1.6 P9-P8 (40,20 M) Monday, August 13, 2018 Monday, August 27, 2018
3.1.7 P10-P9 (40,20 M) Monday, August 20, 2018 Monday, September 3, 2018
3.1.8 P11-P10 (41,35 M) Monday, August 20, 2018 Monday, September 3, 2018
3.1.9 P12-P11 (41,35 M) Monday, August 27, 2018 Monday, September 10, 2018
3.1.10 P13-P12 (41,35 M) Monday, September 3, 2018 Monday, September 10, 2018
3.1.11 P14-P13 (41,35 M) Monday, September 3, 2018 Monday, September 17, 2018
Section 3
3.1.12 P15-P14 (61 M) Monday, September 10, 2018 Monday, September 17, 2018
3.1.13 P16-P15 (61 M) Monday, September 17, 2018 Monday, October 8, 2018
3.1.14 P17-P16 (41,35 M) Monday, October 1, 2018 Monday, October 15, 2018
3.1.15 P18-P17 (41,35 M) Tuesday, October 9, 2018 Monday, October 22, 2018
3.1.16 P19-P18 (41,35 M) Monday, October 15, 2018 Monday, October 29, 2018
3.1.17 P20-P19 (41,35 M) Monday, October 22, 2018 Monday, October 29, 2018
3.1.18 P21-P20 (46,8 M) Monday, October 22, 2018 Monday, November 5, 2018
Section 4
3.1.19 P22-P21 (61 M) Monday, November 5, 2018 Monday, November 19, 2018
3.1.20 P23-P22 (46,8 M) Monday, November 19, 2018 Monday, November 26, 2018
4 UNIBRIDGE DISTRIBUTION
Section 2
4.1 P4-P3 (61 M) Monday, July 30, 2018 Sunday, August 12, 2018
4.2 P5-P4 (41,35 M) Monday, August 6, 2018 Sunday, August 19, 2018
4.3 P6-P5 (41,35 M) Monday, August 6, 2018 Sunday, August 19, 2018
4.4 P7-P6 (41,35 M) Monday, August 13, 2018 Sunday, August 26, 2018
4.5 P8-P7 (41,35 M) Monday, August 20, 2018 Sunday, September 2, 2018
4.6 P9-P8 (40,20 M) Monday, August 27, 2018 Sunday, September 2, 2018
4.7 P10-P9 (40,20 M) Monday, August 27, 2018 Sunday, September 9, 2018
4.9 P12-P11 (41,35 M) Monday, September 3, 2018 Sunday, September 16, 2018
4.10 P13-P12 (41,35 M) Monday, September 10, 2018 Sunday, September 16, 2018
4.11 P14-P13 (41,35 M) Monday, September 10, 2018 Sunday, September 23, 2018
Section 3
4.12 P15-P14 (61 M) Monday, September 17, 2018 Sunday, September 23, 2018
4.13 P16-P15 (61 M) Monday, September 24, 2018 Sunday, October 14, 2018
4.14 P17-P16 (41,35 M) Monday, October 8, 2018 Sunday, October 21, 2018
4.15 P18-P17 (41,35 M) Monday, October 15, 2018 Sunday, October 28, 2018
Page 2 of 4
OWNER KONSULTAN KONTRAKTOR / SUB KONTRAKTOR
DESIGN & BUILD AKSESIBILITAS DARAT FLY OVER & TAPPER TERMINAL TELUK LAMONG
Based On Drawing Rev. 9 1-4 5 - 11 12 - 1819 - 2526 - 1 2 - 8 9 - 15 16 - 2223 - 2930 - 6 7 - 13 14 - 2021 - 2728 - 3 4 - 10 11 - 1718 - 2425 - 1 2 - 8 9 - 15 16 - 2223 - 2930 - 5 6 - 12 13 - 1920 - 26 27 - 2 3 - 9 10 - 1617 - 23 24 - 301 - 7 8 - 14 15 - 2122 - 2829 - 4 5 - 11 12 - 1819 - 2526 - 2 3 - 9 10 - 1617 - 2324 - 30
Month - 1 Month - 2 Month - 3 Month - 4 Month - 5 Month - 6 Month - 7 Month - 8 Month - 9 Month - 10
NO DESCRIPTION START FINISH Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18
I II III IV I II III IV V I II III IV I II III IV V I II III IV I II III IV I II III IV V I II III IV I II III IV V I II III IV V
4.16 P19-P18 (41,35 M) Monday, October 22, 2018 Sunday, November 4, 2018
4.17 P20-P19 (41,35 M) Monday, October 29, 2018 Sunday, November 4, 2018
4.18 P21-P20 (46,8 M) Monday, October 29, 2018 Sunday, November 11, 2018
Section 4
4.19 P22-P21 (61 M) Monday, November 12, 2018 Sunday, November 25, 2018
4.20 P23-P22 (46,8 M) Monday, November 26, 2018 Sunday, December 2, 2018
5 UNIBRIDGE ERECTION
5.1 Mobilization Monday, July 23, 2018 Monday, December 24, 2018
5.1.1 Launcher Girder 1 Monday, July 23, 2018 Monday, December 24, 2018
5.1.2 Mobile Crane 150t 1 Monday, August 13, 2018 Sunday, December 16, 2018
5.1.3 Mobile Crane 50t 2 Monday, July 30, 2018 Sunday, December 16, 2018
5.2 Erection Work Saturday, August 11, 2012 Monday, December 24, 2018
5.2.1 Bearing Pad Saturday, August 11, 2018 Thursday, November 1, 2018
Section 1
Section 2
5.2.1.9 P11 Tuesday, September 11, 2018 Friday, September 14, 2018
5.2.1.10 P12 Saturday, September 15, 2018 Tuesday, September 18, 2018
5.2.1.11 P13 Wednesday, September 19, 2018 Saturday, September 22, 2018
5.2.1.12 P14 Sunday, September 23, 2018 Wednesday, September 26, 2018
Section 3
5.2.1.16 P18 Wednesday, October 10, 2018 Saturday, October 13, 2018
5.2.1.17 P19 Sunday, October 14, 2018 Wednesday, October 17, 2018
5.2.1.18 P20 Thursday, October 18, 2018 Sunday, October 21, 2018
5.2.1.19 P21 Monday, October 22, 2018 Thursday, October 25, 2018
Section 4
5.2.1.20 P22 Friday, October 26, 2018 Monday, October 29, 2018
5.2.2 Erection Unibridge Girder Sunday, August 26, 2018 Friday, December 7, 2018
Section 2
5.2.2.1 P4-P3 (61 M) Sunday, August 26, 2018 Friday, August 31, 2018
5.2.2.3 P6-P5 (41,35 M) Thursday, September 6, 2018 Monday, September 10, 2018
5.2.2.4 P7-P6 (41,35 M) Tuesday, September 11, 2018 Saturday, September 15, 2018
5.2.2.5 P8-P7 (41,35 M) Sunday, September 16, 2018 Thursday, September 20, 2018
5.2.2.6 P9-P8 (40,20 M) Friday, September 21, 2018 Tuesday, September 25, 2018
5.2.2.7 P10-P9 (40,20 M) Wednesday, September 26, 2018 Sunday, September 30, 2018
5.2.2.9 P12-P11 (41,35 M) Saturday, October 6, 2018 Wednesday, October 10, 2018
5.2.2.10 P13-P12 (41,35 M) Thursday, October 11, 2018 Monday, October 15, 2018
5.2.2.11 P14-P13 (41,35 M) Tuesday, October 16, 2018 Saturday, October 20, 2018
Section 3
5.2.2.12 P15-P14 (61 M) Sunday, October 21, 2018 Friday, October 26, 2018
5.2.2.13 P16-P15 (61 M) Saturday, October 27, 2018 Thursday, November 1, 2018
5.2.2.15 P18-P17 (41,35 M) Wednesday, November 7, 2018 Sunday, November 11, 2018
5.2.2.16 P19-P18 (41,35 M) Monday, November 12, 2018 Friday, November 16, 2018
5.2.2.17 P20-P19 (41,35 M) Saturday, November 17, 2018 Wednesday, November 21, 2018
5.2.2.18 P21-P20 (46,8 M) Thursday, November 22, 2018 Monday, November 26, 2018
Section 4
5.2.2.19 P22-P21 (61 M) Tuesday, November 27, 2018 Sunday, December 2, 2018
Page 3 of 4
OWNER KONSULTAN KONTRAKTOR / SUB KONTRAKTOR
DESIGN & BUILD AKSESIBILITAS DARAT FLY OVER & TAPPER TERMINAL TELUK LAMONG
Based On Drawing Rev. 9 1-4 5 - 11 12 - 1819 - 2526 - 1 2 - 8 9 - 15 16 - 2223 - 2930 - 6 7 - 13 14 - 2021 - 2728 - 3 4 - 10 11 - 1718 - 2425 - 1 2 - 8 9 - 15 16 - 2223 - 2930 - 5 6 - 12 13 - 1920 - 26 27 - 2 3 - 9 10 - 1617 - 23 24 - 301 - 7 8 - 14 15 - 2122 - 2829 - 4 5 - 11 12 - 1819 - 2526 - 2 3 - 9 10 - 1617 - 2324 - 30
Month - 1 Month - 2 Month - 3 Month - 4 Month - 5 Month - 6 Month - 7 Month - 8 Month - 9 Month - 10
NO DESCRIPTION START FINISH Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18
I II III IV I II III IV V I II III IV I II III IV V I II III IV I II III IV I II III IV V I II III IV I II III IV V I II III IV V
5.3 Finishing Work Monday, November 26, 2018 Monday, December 24, 2018
5.3.1 Final Check Monday, November 26, 2018 Monday, December 24, 2018
5.3.2 Finishing Work Monday, November 26, 2018 Monday, December 24, 2018
Page 4 of 4