You are on page 1of 4

OWNER KONSULTAN KONTRAKTOR / SUB KONTRAKTOR

DESIGN & BUILD AKSESIBILITAS DARAT FLY OVER & TAPPER TERMINAL TELUK LAMONG

TIME SCHEDULE FABRICATION & ERECTION UNIBRIDGE GIRDER

Based On Drawing Rev. 9 1-4 5 - 11 12 - 1819 - 2526 - 1 2 - 8 9 - 15 16 - 2223 - 2930 - 6 7 - 13 14 - 2021 - 2728 - 3 4 - 10 11 - 1718 - 2425 - 1 2 - 8 9 - 15 16 - 2223 - 2930 - 5 6 - 12 13 - 1920 - 26 27 - 2 3 - 9 10 - 1617 - 23 24 - 301 - 7 8 - 14 15 - 2122 - 2829 - 4 5 - 11 12 - 1819 - 2526 - 2 3 - 9 10 - 1617 - 2324 - 30

Month - 1 Month - 2 Month - 3 Month - 4 Month - 5 Month - 6 Month - 7 Month - 8 Month - 9 Month - 10

NO DESCRIPTION START FINISH Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18

I II III IV I II III IV V I II III IV I II III IV V I II III IV I II III IV I II III IV V I II III IV I II III IV V I II III IV V

START Monday, March 5, 2018

DESIGN & BUILD AKSESIBILITAS DARAT FLY OVER &


Monday, March 5, 2018 Monday, December 24, 2018
TAPPER TERMINAL TELUK LAMONG

1 PREPARATION WORK

1.1 Tools & Equipment Mobilization

1.1.1 Rotary Trolley For Loading Box Girder

Foundation Railway Monday, April 2, 2018 Monday, April 30, 2018

Blasting & Rotary Trolly Assembly Monday, April 9, 2018 Sunday, June 3, 2018

1.1.2 Jig Assembly & Tools Monday, April 9, 2018 Sunday, June 3, 2018

1.1.3 New Otomatic Blasting Machine

Foundation Machine Monday, April 2, 2018 Monday, April 30, 2018

Instalation Machines Wednesday, May 2, 2018 Thursday, May 31, 2018

1.1.4 Reamer Machines

Incoming Machines Monday, June 4, 2018 Saturday, June 30, 2018

Instalation & Testing Reamer Machine Monday, July 2, 2018 Monday, July 16, 2018

1.2 Area Clearance

1.2.1 Clearing Jig Existing Area Assembly Tuesday, March 6, 2018 Saturday, March 31, 2018

1.2.2 Clearing Erection Area Monday, July 2, 2018 Saturday, July 21, 2018

1.3 Marking Out Monday, July 23, 2018 Sunday, December 9, 2018

1.4 Traffic Management Monday, July 23, 2018 Sunday, December 9, 2018

1.5 Engineering

1.5.1 Fix Design Tuesday, March 6, 2018 Monday, April 30, 2018

1.5.2 MTO Monday, April 16, 2018 Sunday, May 6, 2018

1.5.3 Design Drawing Tuesday, March 6, 2018 Monday, April 30, 2018

1.5.4 Shop Drawing Monday, April 16, 2018 Friday, May 11, 2018

1.5.5 Cutting Plan Tuesday, May 15, 2018 Monday, July 2, 2018

1.6 K3 Monday, July 23, 2018 Friday, August 31, 2018

1.7 Direksi Keet Monday, July 23, 2018 Friday, August 31, 2018

1.8 FAT Saturday, August 18, 2018 Friday, August 31, 2018

2 PROCUREMENT

2.1 Raw Material

Section 2

2.1.1 P4-P3 (61 M) Saturday, March 31, 2018 Thursday, May 31, 2018

2.1.2 P5-P4 (41,35 M) Monday, April 23, 2018 Thursday, May 31, 2018

2.1.3 P6-P5 (41,35 M) Monday, April 23, 2018 Thursday, May 31, 2018

2.1.4 P7-P6 (41,35 M) Monday, April 23, 2018 Thursday, May 31, 2018

2.1.5 P8-P7 (41,35 M) Monday, April 23, 2018 Thursday, May 31, 2018

2.1.6 P9-P8 (40,20 M) Monday, April 23, 2018 Thursday, May 31, 2018

2.1.7 P10-P9 (40,20 M) Monday, April 23, 2018 Thursday, May 31, 2018

2.1.8 P11-P10 (41,35 M) Monday, April 23, 2018 Thursday, May 31, 2018

2.1.9 P12-P11 (41,35 M) Monday, April 23, 2018 Thursday, May 31, 2018

2.1.10 P13-P12 (41,35 M) Monday, April 23, 2018 Thursday, May 31, 2018

2.1.11 P14-P13 (41,35 M) Monday, April 23, 2018 Thursday, May 31, 2018

Section 3

2.1.12 P15-P14 (61 M) Saturday, March 31, 2018 Thursday, May 31, 2018

2.1.13 P16-P15 (61 M) Saturday, March 31, 2018 Thursday, May 31, 2018

2.1.14 P17-P16 (41,35 M) Monday, April 23, 2018 Thursday, May 31, 2018

2.1.15 P18-P17 (41,35 M) Monday, April 23, 2018 Thursday, May 31, 2018

2.1.16 P19-P18 (41,35 M) Monday, April 23, 2018 Thursday, May 31, 2018

2.1.17 P20-P19 (41,35 M) Monday, April 23, 2018 Thursday, May 31, 2018

2.1.18 P21-P20 (46,8 M) Monday, April 23, 2018 Thursday, May 31, 2018

Section 4

2.1.19 P22-P21 (61 M) Saturday, March 31, 2018 Thursday, May 31, 2018

2.1.20 P23-P22 (46,8 M) Monday, April 23, 2018 Thursday, May 31, 2018

2.2 Ears & Pins

Section 2

2.2.1 P4-P3 (61 M) Friday, June 22, 2018 Friday, July 6, 2018 9 18 13
2.2.2 P5-P4 (41,35 M) Friday, July 6, 2018 Friday, July 13, 2018 5 13
2.2.3 P6-P5 (41,35 M) Friday, July 13, 2018 Friday, July 20, 2018 5 13
2.2.4 P7-P6 (41,35 M) Friday, July 20, 2018 Friday, July 27, 2018 5 13
2.2.5 P8-P7 (41,35 M) Friday, July 27, 2018 Friday, August 3, 2018 5 13
Page 1 of 4
OWNER KONSULTAN KONTRAKTOR / SUB KONTRAKTOR

DESIGN & BUILD AKSESIBILITAS DARAT FLY OVER & TAPPER TERMINAL TELUK LAMONG

TIME SCHEDULE FABRICATION & ERECTION UNIBRIDGE GIRDER

Based On Drawing Rev. 9 1-4 5 - 11 12 - 1819 - 2526 - 1 2 - 8 9 - 15 16 - 2223 - 2930 - 6 7 - 13 14 - 2021 - 2728 - 3 4 - 10 11 - 1718 - 2425 - 1 2 - 8 9 - 15 16 - 2223 - 2930 - 5 6 - 12 13 - 1920 - 26 27 - 2 3 - 9 10 - 1617 - 23 24 - 301 - 7 8 - 14 15 - 2122 - 2829 - 4 5 - 11 12 - 1819 - 2526 - 2 3 - 9 10 - 1617 - 2324 - 30

Month - 1 Month - 2 Month - 3 Month - 4 Month - 5 Month - 6 Month - 7 Month - 8 Month - 9 Month - 10

NO DESCRIPTION START FINISH Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18

I II III IV I II III IV V I II III IV I II III IV V I II III IV I II III IV I II III IV V I II III IV I II III IV V I II III IV V

2.2.6 P9-P8 (40,20 M) Friday, August 3, 2018 Friday, August 10, 2018 5 13
2.2.7 P10-P9 (40,20 M) Friday, August 10, 2018 Friday, August 17, 2018 5 13
2.2.8 P11-P10 (41,35 M) Friday, August 17, 2018 Friday, August 24, 2018 5 13
2.2.9 P12-P11 (41,35 M) Friday, August 24, 2018 Friday, August 31, 2018 5 13
2.2.10 P13-P12 (41,35 M) Friday, August 31, 2018 Friday, September 7, 2018 14 4
2.2.11 P14-P13 (41,35 M) Friday, September 7, 2018 Friday, September 14, 2018 14 4
Section 3

2.2.12 P15-P14 (61 M) Friday, September 14, 2018 Friday, September 21, 2018 23 17
2.2.13 P16-P15 (61 M) Friday, September 21, 2018 Friday, October 5, 2018 1 27 12
2.2.14 P17-P16 (41,35 M) Friday, October 5, 2018 Friday, October 12, 2018 6 12
2.2.15 P18-P17 (41,35 M) Friday, October 12, 2018 Friday, October 19, 2018 15 3
2.2.16 P19-P18 (41,35 M) Friday, October 19, 2018 Friday, October 26, 2018 15 3
2.2.17 P20-P19 (41,35 M) Monday, October 22, 2018 Friday, October 26, 2018 18
2.2.18 P21-P20 (46,8 M) Monday, October 22, 2018 Friday, November 2, 2018 6 18
Section 4

2.2.19 P22-P21 (61 M) Friday, November 9, 2018 Thursday, November 15, 2018 27 13
2.2.20 P23-P22 (46,8 M) Thursday, November 15, 2018 Friday, November 23, 2018 5 27
2.3 LRB Friday, June 1, 2018 August 31, 2018

3 UNIBRIDGE FABRICATION

3.1 FABRICATION

Section 2

3.1.1 P4-P3 (61 M) Monday, June 25, 2018 Monday, August 6, 2018

3.1.2 P5-P4 (41,35 M) Monday, July 23, 2018 Monday, August 13, 2018

3.1.3 P6-P5 (41,35 M) Monday, July 30, 2018 Monday, August 13, 2018

3.1.4 P7-P6 (41,35 M) Monday, August 6, 2018 Sunday, August 19, 2018

3.1.5 P8-P7 (41,35 M) Monday, August 6, 2018 Monday, August 27, 2018

3.1.6 P9-P8 (40,20 M) Monday, August 13, 2018 Monday, August 27, 2018

3.1.7 P10-P9 (40,20 M) Monday, August 20, 2018 Monday, September 3, 2018

3.1.8 P11-P10 (41,35 M) Monday, August 20, 2018 Monday, September 3, 2018

3.1.9 P12-P11 (41,35 M) Monday, August 27, 2018 Monday, September 10, 2018

3.1.10 P13-P12 (41,35 M) Monday, September 3, 2018 Monday, September 10, 2018

3.1.11 P14-P13 (41,35 M) Monday, September 3, 2018 Monday, September 17, 2018

Section 3

3.1.12 P15-P14 (61 M) Monday, September 10, 2018 Monday, September 17, 2018

3.1.13 P16-P15 (61 M) Monday, September 17, 2018 Monday, October 8, 2018

3.1.14 P17-P16 (41,35 M) Monday, October 1, 2018 Monday, October 15, 2018

3.1.15 P18-P17 (41,35 M) Tuesday, October 9, 2018 Monday, October 22, 2018

3.1.16 P19-P18 (41,35 M) Monday, October 15, 2018 Monday, October 29, 2018

3.1.17 P20-P19 (41,35 M) Monday, October 22, 2018 Monday, October 29, 2018

3.1.18 P21-P20 (46,8 M) Monday, October 22, 2018 Monday, November 5, 2018

Section 4

3.1.19 P22-P21 (61 M) Monday, November 5, 2018 Monday, November 19, 2018

3.1.20 P23-P22 (46,8 M) Monday, November 19, 2018 Monday, November 26, 2018

4 UNIBRIDGE DISTRIBUTION

Section 2

4.1 P4-P3 (61 M) Monday, July 30, 2018 Sunday, August 12, 2018

4.2 P5-P4 (41,35 M) Monday, August 6, 2018 Sunday, August 19, 2018

4.3 P6-P5 (41,35 M) Monday, August 6, 2018 Sunday, August 19, 2018

4.4 P7-P6 (41,35 M) Monday, August 13, 2018 Sunday, August 26, 2018

4.5 P8-P7 (41,35 M) Monday, August 20, 2018 Sunday, September 2, 2018

4.6 P9-P8 (40,20 M) Monday, August 27, 2018 Sunday, September 2, 2018

4.7 P10-P9 (40,20 M) Monday, August 27, 2018 Sunday, September 9, 2018

4.8 P11-P10 (41,35 M) Monday, September 3, 2018 Sunday, September 9, 2018

4.9 P12-P11 (41,35 M) Monday, September 3, 2018 Sunday, September 16, 2018

4.10 P13-P12 (41,35 M) Monday, September 10, 2018 Sunday, September 16, 2018

4.11 P14-P13 (41,35 M) Monday, September 10, 2018 Sunday, September 23, 2018

Section 3

4.12 P15-P14 (61 M) Monday, September 17, 2018 Sunday, September 23, 2018

4.13 P16-P15 (61 M) Monday, September 24, 2018 Sunday, October 14, 2018

4.14 P17-P16 (41,35 M) Monday, October 8, 2018 Sunday, October 21, 2018

4.15 P18-P17 (41,35 M) Monday, October 15, 2018 Sunday, October 28, 2018

Page 2 of 4
OWNER KONSULTAN KONTRAKTOR / SUB KONTRAKTOR

DESIGN & BUILD AKSESIBILITAS DARAT FLY OVER & TAPPER TERMINAL TELUK LAMONG

TIME SCHEDULE FABRICATION & ERECTION UNIBRIDGE GIRDER

Based On Drawing Rev. 9 1-4 5 - 11 12 - 1819 - 2526 - 1 2 - 8 9 - 15 16 - 2223 - 2930 - 6 7 - 13 14 - 2021 - 2728 - 3 4 - 10 11 - 1718 - 2425 - 1 2 - 8 9 - 15 16 - 2223 - 2930 - 5 6 - 12 13 - 1920 - 26 27 - 2 3 - 9 10 - 1617 - 23 24 - 301 - 7 8 - 14 15 - 2122 - 2829 - 4 5 - 11 12 - 1819 - 2526 - 2 3 - 9 10 - 1617 - 2324 - 30

Month - 1 Month - 2 Month - 3 Month - 4 Month - 5 Month - 6 Month - 7 Month - 8 Month - 9 Month - 10

NO DESCRIPTION START FINISH Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18

I II III IV I II III IV V I II III IV I II III IV V I II III IV I II III IV I II III IV V I II III IV I II III IV V I II III IV V

4.16 P19-P18 (41,35 M) Monday, October 22, 2018 Sunday, November 4, 2018

4.17 P20-P19 (41,35 M) Monday, October 29, 2018 Sunday, November 4, 2018

4.18 P21-P20 (46,8 M) Monday, October 29, 2018 Sunday, November 11, 2018

Section 4

4.19 P22-P21 (61 M) Monday, November 12, 2018 Sunday, November 25, 2018

4.20 P23-P22 (46,8 M) Monday, November 26, 2018 Sunday, December 2, 2018

5 UNIBRIDGE ERECTION

5.1 Mobilization Monday, July 23, 2018 Monday, December 24, 2018

5.1.1 Launcher Girder 1 Monday, July 23, 2018 Monday, December 24, 2018

5.1.2 Mobile Crane 150t 1 Monday, August 13, 2018 Sunday, December 16, 2018

5.1.3 Mobile Crane 50t 2 Monday, July 30, 2018 Sunday, December 16, 2018

5.2 Erection Work Saturday, August 11, 2012 Monday, December 24, 2018

5.2.1 Bearing Pad Saturday, August 11, 2018 Thursday, November 1, 2018

Section 1

5.2.1.1 P3 Saturday, August 11, 2018 Monday, August 13, 2018

Section 2

5.2.1.2 P4 Tuesday, August 14, 2018 Friday, August 17, 2018

5.2.1.3 P5 Saturday, August 18, 2018 Tuesday, August 21, 2018

5.2.1.4 P6 Wednesday, August 22, 2018 Saturday, August 25, 2018

5.2.1.5 P7 Sunday, August 26, 2018 Wednesday, August 29, 2018

5.2.1.6 P8 Thursday, August 30, 2018 Sunday, September 2, 2018

5.2.1.7 P9 Monday, September 3, 2018 Thursday, September 6, 2018

5.2.1.8 P10 Friday, September 7, 2018 Monday, September 10, 2018

5.2.1.9 P11 Tuesday, September 11, 2018 Friday, September 14, 2018

5.2.1.10 P12 Saturday, September 15, 2018 Tuesday, September 18, 2018

5.2.1.11 P13 Wednesday, September 19, 2018 Saturday, September 22, 2018

5.2.1.12 P14 Sunday, September 23, 2018 Wednesday, September 26, 2018

Section 3

5.2.1.13 P15 Thursday, September 27, 2018 Monday, October 1, 2018

5.2.1.14 P16 Tuesday, October 2, 2018 Friday, October 5, 2018

5.2.1.15 P17 Saturday, October 6, 2018 Tuesday, October 9, 2018

5.2.1.16 P18 Wednesday, October 10, 2018 Saturday, October 13, 2018

5.2.1.17 P19 Sunday, October 14, 2018 Wednesday, October 17, 2018

5.2.1.18 P20 Thursday, October 18, 2018 Sunday, October 21, 2018

5.2.1.19 P21 Monday, October 22, 2018 Thursday, October 25, 2018

Section 4

5.2.1.20 P22 Friday, October 26, 2018 Monday, October 29, 2018

5.2.1.21 P23 Tuesday, October 30, 2018 Thursday, November 1, 2018

5.2.2 Erection Unibridge Girder Sunday, August 26, 2018 Friday, December 7, 2018

Section 2

5.2.2.1 P4-P3 (61 M) Sunday, August 26, 2018 Friday, August 31, 2018

5.2.2.2 P5-P4 (41,35 M) Saturday, September 1, 2018 Wednesday, September 5, 2018

5.2.2.3 P6-P5 (41,35 M) Thursday, September 6, 2018 Monday, September 10, 2018

5.2.2.4 P7-P6 (41,35 M) Tuesday, September 11, 2018 Saturday, September 15, 2018

5.2.2.5 P8-P7 (41,35 M) Sunday, September 16, 2018 Thursday, September 20, 2018

5.2.2.6 P9-P8 (40,20 M) Friday, September 21, 2018 Tuesday, September 25, 2018

5.2.2.7 P10-P9 (40,20 M) Wednesday, September 26, 2018 Sunday, September 30, 2018

5.2.2.8 P11-P10 (41,35 M) Monday, October 1, 2018 Friday, October 5, 2018

5.2.2.9 P12-P11 (41,35 M) Saturday, October 6, 2018 Wednesday, October 10, 2018

5.2.2.10 P13-P12 (41,35 M) Thursday, October 11, 2018 Monday, October 15, 2018

5.2.2.11 P14-P13 (41,35 M) Tuesday, October 16, 2018 Saturday, October 20, 2018

Section 3

5.2.2.12 P15-P14 (61 M) Sunday, October 21, 2018 Friday, October 26, 2018

5.2.2.13 P16-P15 (61 M) Saturday, October 27, 2018 Thursday, November 1, 2018

5.2.2.14 P17-P16 (41,35 M) Friday, November 2, 2018 Tuesday, November 6, 2018

5.2.2.15 P18-P17 (41,35 M) Wednesday, November 7, 2018 Sunday, November 11, 2018

5.2.2.16 P19-P18 (41,35 M) Monday, November 12, 2018 Friday, November 16, 2018

5.2.2.17 P20-P19 (41,35 M) Saturday, November 17, 2018 Wednesday, November 21, 2018

5.2.2.18 P21-P20 (46,8 M) Thursday, November 22, 2018 Monday, November 26, 2018

Section 4

5.2.2.19 P22-P21 (61 M) Tuesday, November 27, 2018 Sunday, December 2, 2018

Page 3 of 4
OWNER KONSULTAN KONTRAKTOR / SUB KONTRAKTOR

DESIGN & BUILD AKSESIBILITAS DARAT FLY OVER & TAPPER TERMINAL TELUK LAMONG

TIME SCHEDULE FABRICATION & ERECTION UNIBRIDGE GIRDER

Based On Drawing Rev. 9 1-4 5 - 11 12 - 1819 - 2526 - 1 2 - 8 9 - 15 16 - 2223 - 2930 - 6 7 - 13 14 - 2021 - 2728 - 3 4 - 10 11 - 1718 - 2425 - 1 2 - 8 9 - 15 16 - 2223 - 2930 - 5 6 - 12 13 - 1920 - 26 27 - 2 3 - 9 10 - 1617 - 23 24 - 301 - 7 8 - 14 15 - 2122 - 2829 - 4 5 - 11 12 - 1819 - 2526 - 2 3 - 9 10 - 1617 - 2324 - 30

Month - 1 Month - 2 Month - 3 Month - 4 Month - 5 Month - 6 Month - 7 Month - 8 Month - 9 Month - 10

NO DESCRIPTION START FINISH Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18

I II III IV I II III IV V I II III IV I II III IV V I II III IV I II III IV I II III IV V I II III IV I II III IV V I II III IV V

5.2.2.20 P23-P22 (46,8 M) Monday, December 3, 2018 Friday, December 7, 2018

5.3 Finishing Work Monday, November 26, 2018 Monday, December 24, 2018

5.3.1 Final Check Monday, November 26, 2018 Monday, December 24, 2018

5.3.2 Finishing Work Monday, November 26, 2018 Monday, December 24, 2018

FINISH Monday, December 24, 2018

Mengetahui, Diperiksa Oleh, Dibuat Oleh,

Ronny H. Susanto Kunto Dwi W Danang Wibawa S Riza Agus Faisal


Manager Proyek Pelaksana Utama Kasie Engineering & P4 Staff P4

Page 4 of 4

You might also like