Professional Documents
Culture Documents
Cost Evaluation of Large Sacale Hydrogen Production For Aviation PDF
Cost Evaluation of Large Sacale Hydrogen Production For Aviation PDF
Paul Stadler
Supervisors:
Priscilla Caliandro
Claudio Leonardi
Dr. Jan Van Herle
January 9, 2014
Abstract
The Clip-Air is novel aircraft concept which is based on a single wing design and multiple
passenger and/or cargo vessels. In order to face both economical and environmental issues,
the airplane is considered to fly on liquid hydrogen (LH2). The aim of this study is to assess
the daily fuel requirement of a small Clip-Air fleet and to select the most suited solution for
its generation. A production plant is finally designed in order to evaluate the different costs
related to the cryogenic fuel preparation. Since no greenhouse gases should be released during
the entire cycle, solely conversion methods using renewable energy sources are considered in
this paper.
TABLE OF CONTENTS
Table of contents
1 Introduction 2
2 Fuel assessment 4
2.1 Scenario . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
2.2 Conclusion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
3 Production technologies 8
3.1 Fossil fuels . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
3.2 Renewable energies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
3.3 Technology selection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
6 Delivery costs 43
6.1 Delivery methods . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43
6.2 Methods selection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44
6.3 Delivery cost assessment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
6.4 Conclusion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46
7 Conclusion 47
7.1 Hydrogen cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 47
7.2 Further work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 48
8 References 49
List of Figures 51
List of Tables 52
1
1 INTRODUCTION
1 Introduction
Since its beginning in the last half century, commercial air travel has continuously grown all
over the globe, developing itself into a safe, comfortable and fast type of transportation. The
economic liberalization of the airline industry which has gradually spread through all countries
since the 1980s, has generated an aggressive market with low entry barriers and an extremely
high level of competition. The resulting drop in airfares enabled some companies to target a
wider range of customers, making air travel more accessible for the general public. The following
democratization has led to a further strong increase of demand, making air travel one of the
most popular means of transportation existing.
Nevertheless, regarding today’s environmental issues, the aviation industry is constrained to
react; increasing political and economical pressure has pushed companies to produce more and
more fuel-efficient planes. Recent designs such as the Boeing 787 Dreamliner or the Airbus 350
have shown the improvements feasible by introducing composite materials in most parts of the
fuselage and wings.
Nevertheless, these innovative improvements are considered to be insufficient for agencies
such as NASA and the Advisory Council for Aeronautic Research in Europe (ACARE). Indeed,
recent forecasts from the International Air Transport Association (IATA) showed that the future
growth in air travel traffic is going to skyrocket1 and therefore, despite the latest efficiency
improvements, leading to an overall increase of fuel demand. For these ecological and economical
reasons, ACARE has targeted the following objectives for the year 20202 :
Regarding these objectives, the novel aircraft concept Clip-Air has been designed. Unlike
traditional airplane designs, it is composed of a single wing under which up to three capsules
can be attached. Due to the lower drag of the wing shape and the high modularity resulting
from its unique sizing system, significant fuel savings can been made by operating such type of
airplane. Indeed, the aircraft capacity can be instantaneously modified by removing or adding
a passenger/cargo capsule just before the flight.
2
1 INTRODUCTION
In order to further reduce the production of toxic exhaust gases, the Clip-Air project is
studying the feasibility of using liquid hydrogen (LH2) as a substitute to the current Jet-A
fuel. Since hydrogen is an unstable element, it still presents strong challenges for many of
its production steps, its transportation and storage. This report reviews the different existing
technologies for hydrogen generation and tries to give a preliminary cost evaluation for a specific
chosen case, when used in the airline industry.
3
2 FUEL ASSESSMENT
2 Fuel assessment
The objective of this paper is to evaluate the costs of hydrogen production for commercial
air travel use. Instead of analyzing various existing technologies and processes for hydrogen
generation, a particular scenario and the related fuel consumption has been defined in order to
selected the most suitable solution. The aim of this chapter is to assess the daily amount of
liquid hydrogen (LH2) required for a given Clip-Air fleet size and a specific type of operation.
2.1 Scenario
In order to predict the social and economical impact of the Clip-Air concept in the airline
industry, several scenarios have been developed. Specific simulations made by Atasoy et al. [1]
have shown the different types of performances achievable through the Clip-Air system. By
varying parameters such as the network type, fleet and plane sizes, the study brought to light
significant advantages and drawbacks of this novel aircraft concept.
As the Clip-Air plane does not exist yet, major assumption concerning the operating costs
(fuel consumption, crew cost, airport and air navigation charges) have been made by considering
similarities of an A320 since their fuselages are almost identical. By using the weight difference
between each Clip-Air configuration and the respective capacity of A320, the proportional fuel
consumption increase/decrease can be defined. As presented in Table 2.1, Clip-Air is lighter
than the respective number of A320 planes when flying with three capsules but heavier when it
is flying with less capacity. Similarly to the fuel consumption approximation, the navigation and
crew charges were determined by using analogies with existing cost functions, although they are
not relevant for this study.
Table 2.1: Clip-Air and A320 specific weight [1]
Clip-Air A320
Total seat capacity [-] 450 150
Turbofans [-] 3 2
Maximum takeoff 1 plane/capsule 139 (+78%) 78
weight [mt] 2 planes/capsules 173.5 (+11%) 156
3 planes/capsules 208 (-11%) 234
4
2 FUEL ASSESSMENT
Figure 2.1: A320-100/200 fuel consumption (FC) graph fitting for the respective flight distance (FD)
assuming a landing weight of 57 [mt]
Error analysis
Degrees of freedom 6
Sum of squared residuals 4207.46
Mean of squared error 701.343
5
2 FUEL ASSESSMENT
operation types and the resulting economical impact generated by the utilization of a Clip-
Air fleet. The peer-to-peer network showed itself to be the most suitable solution in terms of
revenues, transported passengers and aircraft usage. In this type of network, the airports are
connected pairwise which enables to change the number of capsules after each flight and hence,
a more efficient capacity management. Consequently, a profit increase of 4.1% was achieved by
carrying 2.8% more customers with 21.3% less seat capacity.
In light of these results, a fleet of five Clip-Air wings operating under a similar network
scheme is considered in this study (Table 2.4). The number of daily destinations is set to
10 which corresponds to two return flights, one short-haul and one medium-haul, per aircraft
respectively. Since the airline hub is the Geneva International Airport (LSGG), the selected flight
range enables thus to target most of the Western European cities which are highly popular and
profitable (Figure 2.2). Furthermore, in order to assess the maximum fuel requirements, each
wing is assumed to fly with full seat capacity (i.e. with three capsules) although the demand
varies strongly during the day and between destinations.
Fleet properties
Number of Clip-air wings [-] 5
Number of destinations [day−1 ] 10
Consumption [mt day−1 ]
Sum of short-haul return flights [day−1 ] 5 116.1
Sum of medium-haul return flights [day−1 ] 5 187.7
Total Jet-A [day−1 ] 10 303.8
6
2 FUEL ASSESSMENT
2.2 Conclusion
This chapter presented the different elements and assumptions considered throughout the sce-
nario elaboration. Based on various economical simulations, specific parameters such as network
type, operation strategy and fleet size were selected. Consequently, the daily utilization of liquid
hydrogen for the resulting model amounts to 109.4 mt. A 10% margin is added to this value in
order to take in account losses due to leakage, transportation and boil-off, hence leading to a
total requirement of 120 mt day−1 (4000 MWh day−1 ).
7
3 PRODUCTION TECHNOLOGIES
3 Production technologies
Since hydrogen is an extremely abundant element, various feedstocks can be used for its gen-
eration. Nowadays, it is mostly generated by using processes involving fossil fuels such as coal
and natural gas. Nevertheless, considering both the ecological impact trough greenhouse gases
and the limited amount of available resources, the present production paths are highly unsus-
tainable. Consequently, alternative technologies and processes using renewable energy sources
must be considered in order to adress both economical and environmental issues.
Cost Since methane steam reforming and partial methane oxidation are well-developed pro-
cesses, the cost of hydrogen production is highly depend on the cost of natural gas. The following
equation proposed by [26] presents this relationship as follows:
H2 [$/kg] = 0.286 × NG price[$/MMBtu] + 0.15 (3.4)
Given the NG price of 13.2$/MMBtu (45$/MWh) for 2013 in Switzerland [29], the hydrogen
production cost reaches 3.93$/kg.
8
3 PRODUCTION TECHNOLOGIES
3.1.2 Coal
Coal can be converted into hydrogen by a variety of endothermic gasification processes; fixed
bed, fluidized bed and entrained flow (Figure 3.1). The selection of the appropriated technology
depends on various parameters like the reactor size, the desired gas utilization and quality.
Large scale applications such as an IGCC (Integrated Gasification Combined Cycle) power plant
require a high and stable conversion rate and hence, fluidized bed or entrained flow gasifiers
are the most suitable solutions. Furthermore, entrained flow gasification, compared to fixed
and fluidized bed gasification, takes place at temperatures above the ash fusion point [24] and
consequently, generates a superior gas quality.
In a typical gasification reaction, the injected fuel and gasification agent are converted into a
mixture mainly composed of carbon monoxide and hydrogen (3.5). Similarly to steam reforming,
the CO can be further processed by using the water-gas shift reaction (3.2) in order to form
CO2 and H2 .
C + H2 O −−→ CO + H2 (3.5)
Cost Hydrogen generation from coal gasification is a mature technology and commercially
available. However, the cost of the different plants varies widely. While sophisticated designs
such as combined cycles (CC) and advanced facilities using solid oxide fuel cells (SOFC) pro-
vide the lowest hydrogen cost (especially due to electricity co-production), smaller cycles using
heat recovery steam generators (HRSG) to power the plant require a lower investments costs
[3]. In order to reduce greenhouse gas emissions, these plants can be equipped with a carbon
sequestration system, increasing further the production costs.
Rutkowski et al. [18] evaluated the hydrogen production cost from coal gasification. In-
cluding a sequestration system, the plant investment expenses reach US$ 612.3 millions and
produces 255400 kg/day of hydrogen at a cost of 1.83$/kg.
9
3 PRODUCTION TECHNOLOGIES
H2 O −−→ H2 + 21 O (3.6)
Alkaline electrolysis is a commercially mature technology and globally present on the hydro-
gen production market. The high gas production rate, the long stack lifetime and the relatively
high efficiency (Table 3.1) make it an interesting candidate for large scale and stationary appli-
cations.
Cathode - Anode +
H2 1
2 O2
OH−
2H+
Diaphragm
However, despite these attractive characteristics, some drawbacks are usually associated with
alkaline electrolysis [5]. Indeed, the diaphragm is not entirely impermeable to the generated gases
10
3 PRODUCTION TECHNOLOGIES
which highly influences the efficiency of the system since the oxygen will react with the hydrogen
present at the cathode to form water again. Especially at low operating points, cross-diffusion
represents a serious safety issue due to the increasing concentration of hydrogen on the anode
side which might reach dangerous levels. A second disadvantage of alkaline electrolysis are the
strong ohmic losses created by the separation membrane and the aqueous electrolytic solution,
therefore limiting the current density throughout the stack.
Table 3.1: State of the art for specifications of Alkaline and PEM electrolysis [5]
Polymer electrolyte membrane electrolysis PEM electrolyzer use a solid polymer mem-
brane as electrolyte which highly improves the conductivity issues related to the utilization of a
liquid electrolyte. During operation (Figure 3.3), the water is decomposed at the anode where it
releases electrons in order to form oxygen and hydrogen ions. After crossing the separation mem-
brane, the protons are combined with the supplied electrons to produce the desired hydrogen
gas which can be easily collected afterwards.
The half and overall reactions of PEM electrolysis can be written as
Anode H2 O −−→ 1
2 O2 + H+ + 2 e− (3.8b)
1
Sum H2 O −−→ 2 O2 + H2 (3.8c)
The positive aspects of PEM electrolysis are mainly related to its solid polymer electrolyte
type and thickness [5]. Indeed, compared to alkaline electrolysis, the thin electrolyte provides
an excellent proton conductivity and thus, higher achievable current densities which lead to a
reduction in operating and equipment costs. Furthermore, the low cross-diffusion rate enables
PEM electrolyser to work under a wider range of operating points and to adapt to the actual
production demand.
However, since the membrane impermeability decreases with pressure, thicker and more
resistant electrolytes are required at higher operating conditions (above 100 bar [5]) which
therefore increases electrical resistance. Additionally, due to the harsh environment in a PEM,
only a few expensive materials can be used for the different cell components, leading to a higher
system cost [5]. With short membrane lifetime and low production capacity (Table 3.1), current
PEM electrolysers are not as developed as alkaline electrolyzers [25] and less attractive for large
scale applications.
11
3 PRODUCTION TECHNOLOGIES
Cathode - Anode +
H2 1
2 O2
H+
H2 O
Membrane
Solid oxide electrolysis Based on the solid oxide fuel cell principle, solid oxide electrolyzer
cells (SOEC) operate at high temperature, typically between 973 and 1273 K where the reaction
becomes more reversible [25]. Since the electrical energy required to split water decreases with
temperature (Figure 3.4), part of the heat available for electricity generation can directly be used
by the system. Indeed, the molar Gibbs energy of reaction ∆G falls from 1.23 V at ambient
conditions to about 0.96 V at 1123 K [4] which represents a drop of 22%. This important amount
of energy can be provided by an available heat source (nuclear, solar, geothermal), avoiding thus
a penalizing heat-to-electricity conversion loss
Figure 3.4: Energy of reaction (∆ H, red) and Gibbs energy of reaction (∆ G, gray) in function of the
steam inlet temperature
During the process (Figure 3.5), superheated steam is injected into the cathode side where
it is decomposed into hydrogen and oxide ions. After passing through the electrolyte, generally
yttria-stabilized zirconia [4], the oxide ions release electrons at the anode in order to form oxygen.
The half and overall reactions of solid oxide electrolysis can be written as
Since their introduction in the 1980s, solid oxide electrolyzers have gathered much interest
around the world, especially due to their huge potential for hydrogen mass production. Prelim-
12
3 PRODUCTION TECHNOLOGIES
inary lab-scale studies have shown the strong advantages of high temperature water-splitting
[5]:
• High efficiency - the electrical-to-hydrogen conversion efficiency can exceed 100% depend-
ing on the system operation mode (exothermal, thermoneutral and endothermal) [4]
• High pressure operation
• No noble materials required
Despite the fact that SOECs are currently available on the market, further research and devel-
opment are necessary in order to meet the required performances for sustainable and profitable
hydrogen generation. Indeed, issues regarding durability, manufacturing and production costs of
the different ceramic components still need to be solved [5]. However, considering that the tech-
nology is not commercially mature and economies of scale have not been achieved yet, SOECs
remain an extremely attractive conversion process in the long term.
Cathode - Anode +
2H2 O2
O−2
2H2 O
Solid Oxide
13
3 PRODUCTION TECHNOLOGIES
Sulfur - Iodine The sulfur-iodine cycle is composed of three distinct sections and was first
presented by General Atomics in the 1970s [13]. Based on the HHV of hydrogen, the heat-to-
hydrogen efficiency of sulfur-iodine cycles is predicted to reach over 40% (34% if considering
the hydrogen LHV), depending on peak temperature of decomposition reaction [14]. The main
reactions can be written as:
Section I Bunsen reaction
H2 O
Section I Section II
I2
I2 + SO2 + 2 H2 O −−→ 2 HI + H2 SO4 2 HI −−→ I2 + H2
H2 O
Separator
H2 O, I2 , HI H2
SO2 , H2 O
14
3 PRODUCTION TECHNOLOGIES
The water input is injected into the Bunsen reactor which operates at 100◦ C and releases
heat which can be recovered and used elsewhere in the cycle (Figure 3.6). The output stream is
then separated into two streams, the aqueous sulfuric acid flow and the hydrogen iodine solution.
In the second section, the sulfuric acid is recycled at 850◦ C by being decomposed into sulfur
dioxide and water which are then fed into the Bunsen reactor again. Finally, the hydrogen iodine
is split into the desired hydrogen and iodine at 450◦ C in the last section of the cycle.
Sulfur Hybrid The sulfur acid hybrid thermochemical cycle (SAHT) is composed of only two
distinct sections and was first developed by Westinghouse [14]. The SAHT cycle is ”hybrid” due
to the second production step (3.11b) which consists of an electrochemical reaction. Similarly
to the sulfur-iodine cycle, the SAHT cycle is expected to be very efficient (over 45% based on
the HHV or 38% if considering the LHV of hydrogen [14]) which makes it extremely attractive
for large scale hydrogen production. The main reactions can be written as follows:
The water input is injected into the sulfur dioxide electrolyzer which operates at about 373
[K] at an overall cell voltage of 0.67 [V] [14]. The required electrical energy is indeed much lower
than for conventional water splitting through electrolysis (see Section 3.2.1) increasing hence,
the hydrogen production efficiency. The generated by-product, sulfuric acid, is then recycled by
using the decomposition reaction in order to form sulfuric dioxide again.
Hybrid Copper Chloride The hybrid copper-chloride cycle is a recent thermochemical cycle
which exists in various types, depending on the different intermediate reaction steps. The
number of steps, which can vary from two to five, highly influences large-scale design challenges
and the overall efficiency of the setup. Indeed, multiple studies have shown major economical
and technological advantages and drawbacks related to the increase/decrease of process steps.
Based on an idealized process assumption, Lewis et al [16] predicted a five step cycle efficiency
of 50% (LHV). The main reactions occurring in a five step Cu-Cl cycle can be written as:
Step I Chlorination
CuCl2 (aq) + nf H2 O(l) −−→ CuC2 l(s) · nh H2 O(s) + (nf −nh )H2 O at 303-353 K (3.12c)
Step IV Hydrolysis
2 CuCl2 · nf H2 O(s) + H2 O(g) −−→ Cu2 OCl2 (s) + 2 HCl(g) + nh H2 O at 648 K (3.12d)
Step V Decomposition
15
3 PRODUCTION TECHNOLOGIES
where nf ≥ 7.5 is the amount of water in the aqueous solution of CuCl2 and nh = 0-4 the water
quantity in the dry CuCl2 hydrate.
Given the objective of this paper, following parameters need to be considered during the
technology selection:
Regarding the different characteristics of each conversion process, the copper-chloride ther-
mochemical cycle is selected. Indeed, both the sulfur-iodine and the SAHT cycle are rejected
due to safety issues (large scale handling of hazardous chemicals such as H2 SO4 , SO4 , HI, I2 ) and
3
Power to drive pumps, compressors and other utilities not included
16
3 PRODUCTION TECHNOLOGIES
the high graded heat requirements for the sulfuric acid decomposition. Since only concentrated
solar energy is able to generated these high temperatures (nuclear power does not fall into the
category of renewable energy sources), a thermal storage utility need to be designed in order to
enable ”around-the-clock” operation. However the required temperature exceeds the operation
limit of the nitrate salt (about 570◦ C) which are currently used as heat storage medium. This
issue also applies to the solid oxide electrolysis which requires the preparation of superheated
steam and hence, SOECs are eliminated from the technology list.
Finally, both alkaline and PEM electrolysis are rejected due to their lower conversion effi-
ciency and short stack lifetime respectively. Consequently, solely the Cu-Cl cycle is considered
for hydrogen production throughout the following chapters. It is important to note that recent
technologies such as biophotolysis, photolysis, high temperature decomposition and biomass con-
version have not being included in the down-selection due to lack of time or/and low potential
for large scale hydrogen production.
17
4 H2 PRODUCTION PLANT DESIGN
• Advantages
– Fewer equipment material challenges
– Less steps, less equipment
– Reduced complexity
• Disadvantages
– Higher heat grade and intensity
– More equipment material challenges
– Lower reaction yield (undesirable side products)
– Lower efficiency
Regarding the multiple benefits and drawbacks of varying the step number, only the four-
step copper-chloride cycle will be studied throughout the following chapters since it represents
the best trade-off between thermal efficiency and viability. The main reactions occurring in a
four-step cycle are presented in Table 4.1.
18
4 H2 PRODUCTION PLANT DESIGN
O2 (g)
4.2.1 Electrolysis
In the first section, hydrogen is produced from an electrochemical reaction of hydrogen chloride
and copper(I) chloride. At the anode, the copper ion Cu(I) is oxidized to Cu(II) while at the
cathode, hydrogen ions H+ are reduced in order to form the desired product. The half and
overall reactions taking place in the electrolyzer stack (Figure 4.2) can be written as:
The copper(I) chloride which is dissolved in a hydrogen chloride solution, is pumped to the
anode side of the electrolyzer, whereas an aqueous HCl solution is fed to the cathode section.
Hydrogen ions migrate through the membrane, from the anode to the cathode where they react
with the available electrons in order to form hydrogen gas. The produced aqueous CuCl2 is then
collected and send to the crystallization unit.
19
4 H2 PRODUCTION PLANT DESIGN
2e−
Anode + Cathode -
4.2.2 Crystallization
The anode outlet stream flows from the electrolyzer system to the next section which is the crys-
tallization unit. Wand et al. [30] presented the different benefits and drawbacks of two existing
drying methods which are considered for this process step; spray drying and crystallization. In
order to classify each solution, two important parameters have been identified.
The first variable, the amount of water in the aqueous solution of CuCl2 is represented by nf
(Table 4.1) which has a minimum value of 7.5 if the solution is saturated. The second variable
nh denominates the hydrate water quantity in the dry copper(II) chloride. It can vary from
0, when the CuCl2 exists in anhydrous form after drying, to 4. Obviously, the value of nh
highly depends on major parameters such the drying method and their operating conditions
(temperature, carrier gas velocity).
Table 4.2: Heat grade and quantity required for precipitate drying [30]
Parameter Value
Heat required ∆H [kJ/kmol H2 ] 122
Heat grade ∆T [◦ C] 30 → 100
Given the lower heat grade and heat amount required, the crystallization technology has
been selected for this study. The energy requirements of the desired crystallization unit are
reported in Table 4.2.
4.2.3 Hydrolysis
After exiting the crystallizer, the CuCl2 particles are heated up to 673 K and, in addition to
superheated steam at same temperature level, injected into the hydrolysis reactor (Figure 4.3).
Due to the large pressure drop of 23 bar, the CuCl2 stream forms a free jet at the top of the
spray reactor. Since the jet expands, it aspirates the superheated steam into the jet and hence,
highly improves the heat and mass transfer between both reactants [20]. The solid Cu2 OCl2
settles at the bottom of the hydrolysis reactor where it is removed afterwards. Finally, the
hydrogen chloride and the remaining amount of steam leave the reactor in form of gas before
being cooled for separation.
20
4 H2 PRODUCTION PLANT DESIGN
Cu2 OCl2
Nevertheless, in order to achieve stoichiometric yield of HCl or Cu2 OCl2 , the amount of
H2 O injected into the hydrolysis reactor must largely exceed the stoichiometric steam quantity.
Indeed, past studies [30] have shown that an optimal steam-to-copper (S/Cu) ratio of 17 is
required in order to reach a conversion yield higher than 95%. Hence, the main objective of
CuCl2 hydrolysis step development is to maximize the copper oxychloride production rate while
reducing as much as possible the steam input. The energy requirements of the hydrolysis unit
are reported in Table 4.3.
Table 4.3: Heat grade and quantity required for the hydrolysis reaction [21, 20]
Parameter Value
Heat required ∆H [kJ/kmol H2 ] 116.6
Heat grade T [◦ C] 375
4.2.4 Decomposition
The generated copper oxychloride flows from the hydrolysis reactor outlet to the decomposition
reactor where it is decomposed into copper(I) chloride and oxygen (Figure 4.4). Before entering
the reactor, the Cu2 OCl2 is heated to 823 K, the temperature at which the decomposition
reaction occurs. Similarly to the hydrolysis step, the oxygen leaves the reactor as gas (at the
top) whereas the molten CuCl spills over a weir in order to be collected and send for recycling
afterwards. The energy requirements of the oxychloride decomposition unit are reported in
Table 4.4.
Table 4.4: Heat grade and quantity required for the decomposition reaction [21, 20]
Parameter Value
Heat required ∆H [kJ/kmol H2 ] 129.2
Heat grade T [◦ C] 550
21
4 H2 PRODUCTION PLANT DESIGN
O2
Weir
CuCl
Cu2 OCl2
sea purified
water water H2 (g) H2 (l)
Desalination Cu-Cl cycle Liquefaction
E˙+ Q˙+
CSP plant
Finally, a concentration solar power plant is designed next to the production facility in order
to satisfy the electrical and thermal energy requirements of the system. It is important to note
that both the desalination and the liquefaction utilities are not described as precisely as the
major production unit (Section 4.2) since only the related costs are relevant for this study.
Water preparation unit Desalination methods have been heavily studied and are well-known
technologies which are commercially available. However, the state of development and the
respective costs of each existing process are not similar. Indeed, Wade [19] presents and describes
the energy requirements of three major water preparation methods: multi-stage flash distillation,
multiple effect distillation and reverse osmosis. Since the reverse osmosis (with brine booster) has
the lowest energy consumption of all three processes, it is selected for this study and incorporated
22
4 H2 PRODUCTION PLANT DESIGN
into the overall production plant design. The additional energy requirements are presented in
Table 4.5
Table 4.5: Energy requirements for the water preparation unit
Parameter Value
Conversion energy [MJ/m3 ] [19] 24.2
Plant operation [h/day] 24
Daily requirements [m3 /day] 1072.5
Electric power required [kWe ] 300.4
Liquefaction unit In order to achieve proper hydrogen storage for large scale applications,
two major methods are considered; high compressed gas, generally up to 350-700 bar, or liquid
hydrogen (LH2). Both technologies have their respective benefits and drawbacks which have
been widely defined and described in [12]. Hence, following the selection made during this
previous study, a liquefaction utility is chosen.
Although the minimum theoretical energy needed for hydrogen liquefaction from almost
ambient conditions (300 K, 1 atm) is 3.3-3.9 kWh/kg LH2, the real conversion requirements
are much higher [17]. Indeed, actual liquefaction plants required about 10 to 13 kWh/kg LH2
depending on the system size. Nevertheless, recent technologies such as active magnetic regen-
erative liquefier are predicted to consume much less (Table 4.6) and are thus, highly interesting
for large scale applications. Since this paper evaluates hydrogen production for the long term,
this novel conversion method is selected, despite the fact that it is not commercially mature yet.
Table 4.6: Energy requirements for liquefaction unit
Parameter Value
Conversion energy [kWhe /kg LH2] [17] 7
Plant operation [h/day] 24
Production rate [mt/day] 120
Electric power required [MWe ] 35
Thermal requirements In order to assess the MER, a flowsheet is first elaborated which
models the main process steps occurring in the considered thermodynamical cycle. Due to lack
of information and time, following assumptions have been made:
• The Cu2 OCl2 has been modeled as two single compounds, copper oxide CuO and cop-
per(II) chloride CuCl2 . Obviously, this assumption is disputable. However, since no mul-
tiple objective optimization is performed in this study, all energy balances related to this
compound can be defined by an external code. As the mass balance is not altered, this
hypothesis can be hence validated regarding the precision level of the model required for
this study.
23
4 H2 PRODUCTION PLANT DESIGN
The corresponding composite curves (energy) and Carnot composite curves (exergy) are
presented in Figure 4.6 and 4.7 respectively. The resulting minimum energy requirements (MER)
are reported in Table 4.7.
24
4 H2 PRODUCTION PLANT DESIGN
25
4
26
H2 PRODUCTION PLANT DESIGN
Parameter Value
High graded heat at 565 ◦C
[MWh ] 153.397
◦
Low graded heat at 100 C [MWh ] 86.576
Cooling water at 10 ◦ C [m3 /s] 0.157
Electrical requirements The electrical requirements of the hydrogen production plant and
the complementary utilities are summarized in Table 4.8. It is important to note that the
electrolyzers consumption is not yet reported here since it is defined in the following chapter
(Section 4.4.1).
Parameter Value
Net cycle consumption [kWh ] 17’2324
Water preparation unit [kWe ] 300.4
Liquefaction unit [kWe ] 35’000
Subtotal [MWe ] 52.53
∆G = ∆H − T ∆S [kJ/mol] (4.3)
Finally, by adding the sum of all overpotentials required to overcome the different losses through-
out the system, the cell operating voltage can be determined (4.4).
X
Ucell = Uoc + Uloss,i [V ] (4.4)
i
Regarding first experimental results generated by [27] (Figure 4.9), the operating voltage
decreases linearly with increasing temperature. Moreover, the slope increases with HCl concen-
tration, leading to even lower operating voltages at higher temperatures. The extrapolated data
shows that in order to achieve a high current density of 0.5 A/cm2 and a low cell voltage of 0.7
V, operating conditions over 90◦ C are required.
4
Pumps, compressors and turbines power consumption/generation
27
4 H2 PRODUCTION PLANT DESIGN
Figure 4.9: Effect of temperature and HCl concentration on cell voltage [27]
Consequently, given the operating values of 0.7 V at 0.5 A/cm2 proposed by [22], the min-
imum power required to drive this first production step reaches 93.07 MWe for a total active
cell area of 26’600 m2 . It is important to note that this result does not include the power re-
quired by the different auxiliary units necessary to drive the electrolyzers (pumps, control, etc.).
The following table (Table 4.9) summarizes the total electrical requirements of the hydrogen
production plant.
Parameter Value
Electrolyzer requirements [MWe ] 93.07
Total cell area [m2 ] 26’600
HCl concentration M [mol/l] 11
Total plant requirements [MWe ] 145.6
4.4.2 Efficiency
In order to evaluate the performance of the hydrogen production plant, the efficiency must be
defined. Hence, based on the first thermodynamic law, the efficiency compares the produced
amount of energy in form of hydrogen (based on the LHV) to the energy input of the system
(Table 4.7 and 4.9). The following equation describes the efficiency used in this study
ṁH LHVH2
= 1 P 2 P (4.5)
η Ėe + Q̇h
where η=0.36 is the heat-to-electricity efficiency of the power block (Section 5.3.2).
28
4 H2 PRODUCTION PLANT DESIGN
A γ It
Cp = Cp,ref [$] (4.6)
Aref It,ref
It 2
Cp = Cp,ref 10k1 +k2 logA+k3 (logA) [$] (4.7)
It,ref
Due to the corrosive environment generated by the Cu-Cl process, the carbon steel equipment
is coated with a porcelain lining and hence, capital costs are assumed to be increased by 20%
[15].
Heat exchanger network Since the heat exchanger network (HEN) is not exactly deter-
mined, the related costs are computed by using a different relation than the one presented
above. Indeed, in order to assess the HEN capital expenses, the composite curves are split into
multiple vertical sections for which the corresponding heat capacity cp is constant. After deter-
mining the heat exchanger area for each section, the mean heat exchanger area can be defined
by summing up all computed areas and dividing them by the number of units. By assuming
an equal separation of the area, an overestimation of the HEN investment costs can be finally
generated.
Electrolyzers The capital expenses related to the electrolyzer modules can be approached by
assuming a specific cost factor cel which is multiplied by total active cell area Ael .
Regarding the investment cost projections proposed by [15], a specific cost factor cel = 1140 $/m2
is considered in this study.
Complementary utilities Similarly to the HEN cost assessment method, the liquefaction
and water preparation plant investment expenses are defined by using a different approach than
presented above. Indeed, given the results presented by [19] and [2], the capital cost of each
utility is defined by only considering their respective output capacity cout . Consequently, the
related plant costs are solely multiplied by a multiplication factor Fmulti in order to meet the
desired utility size required for the hydrogen production. The different parameter values are
presented in Table 4.10.
Annualized capital cost After defining the capital expenses Cp for each plant unit, the
investment is annualized. Considering a given interest rate i and plant lifetime n the annual
expenses I ? related to the plant equipment cost can be defined. Finally, in order to include
29
4 H2 PRODUCTION PLANT DESIGN
Parameter Value
Liquefaction plant output cout [LH2 kg/d] 30’000
Liquefaction plant output cout,cost [M$] 40
Liquefaction plant factor F [-] 4
Preparation plant output cout [m3 /d] 31’822
Preparation plant output cout,cost [M$] 37.7
Preparation plant factor F [-] 0.034
all additional installation expenditure, the equipment cost is multiplied by a bar module factor
FBM .
? i(1 + i)n
Idirect = FBM Cp [$/yr] (4.10)
(1 + i)n − 1
? i(1 + i)n
Iindirect = Cf ixed [$/yr] (4.12)
(1 + i)n − 1
Parameter Value
Project contingency [-] 0.18
Upfront Permit cost [-] 0.03
Total cf ixedcap.,total [-] 0.21
• Labor expenses are determined by multiplying the plant personnel number by the average
labor rate cl,plant . The required staff size can be approached by using [15]
30
4 H2 PRODUCTION PLANT DESIGN
where P represents the number of steps involving solid particles handling whereas N de-
nominates the remaining process step number (Table 4.12). Since no specific process
diagram was generated for the water preparation unit, the labor cost is assumed to be
0.126$ per cubic meter of water desalinated [19].
• Property tax, insurance and replacement cost are expressed as a function of the direct
capital expenses [15]
where cf ixedop.,total is the sum of all contributing cost factors (Table 4.12).
Considering the high annual output of gaseous oxygen co-generated with the hydrogen pro-
duction, a storage system can be designed in order to sell it as a byproduct and hence strongly
decrease the operating expenses . Indeed, regarding the selling price of gaseous oxygen cO2 in
2002 of 0.109 $/kg O2 5 and the annual plant production of 346’896 mt O2 /yr, a $37.8 millions
income can be included during the operating cost assessment. It is nevertheless important to
mention that the equipment required for pressuring and preparing the oxygen for delivery was
not included in either the energy bill or the direct investment cost evaluation.
Parameter Value
Labor rate cl,plant [$/hr] 50
Property tax [-] 0.02
Insurance [-] 0.06
Total cf ixedop.,total [-] 0.08
Cu-Cl Cycle Liquefaction unit
Solids handling P [-] 3 0
Remaining steps N [-] 12 8
5
http://ed.icheme.org/costchem.html
31
4 H2 PRODUCTION PLANT DESIGN
4.6 Conclusion
This chapter presented the different steps and assumptions used to make a preliminary design of
a hydrogen production plant based on a four-step hybrid copper-chloride themochemical cycle.
Table 4.13 summarizes the different results generated throughout this section.
Table 4.13: MER and investment costs of the overall production plant
It is interesting to note that, as presented above, the computed cycle efficiency is much lower
than the value stated in the previous chapter (Section 3.2.2). However, Lewis et al. [16] first
assumed an idealized process for the efficiency computation and hence, by increasing the model
complexity, his efficiency evaluation decreases to 30% which corresponds to the generated result.
Kromer et al. [15] confirmed this value during his assessment.
32
5 POWER SUPPLY PLANT DESIGN
5.1 Localization
Regarding the low direct normal irradiation and high weather factor related to Switzerland, the
solar power plant and the respective conversion plant are assumed to be located elsewhere in
order to achieve a higher efficiency. Therefore, the coastal region near Ben Gardane in Tunisia
is chosen. Indeed, the benefits of outsourcing the production to this location are:
• The average yearly solar irradiation is higher than any other location in Europe and hence
capital costs are slightly lower
• The coastal land is very cheap in this region compared to South European coasts which
are well developed and extremely expensive
• The coastal location enables a free access to the plant raw material, sea water. After
desalination and deionisation, the water is used for hydrogen generation or solar panel
cleaning and hence, the operating costs are much lower.
Obviously, the major drawback of selecting this location are the delivery costs which are
substantially higher considering the means of transport necessary in this case. It is important
to note that due to lack of time and information, the trade-off between capital and shipping
expenses has not been optimized in this study.
leading to
r 2
ED = 10.45 sin(δ) sin(φ)[HD − tan(HD )] [kW h/m2 ] (5.3)
r
where φ is the latitude at which the power plant is located, D the day of the year and HD the
half day of sunlight expressed as an angle
33
5 POWER SUPPLY PLANT DESIGN
Figure 5.1: Daily extraterrestrial irradiation ED (red), irradiation including reflection losses ηa (yellow),
the weather factor ηw (green) and ground albedo ηg (blue) over the year
Nevertheless, since ED represents the daily extraterrestrial irradiation, correction factors must
be added in order to take in account the different losses engendered by the atmosphere. Hence,
effects due to the atmosphere albedo ηa , the ground albedo ηg > 1 and the weather ηw < 1 are
included
EDcorrected = ED · ηa · ηg · ηw [kW h/m2 ] (5.5)
The previous graph (Figure 5.1) represents the daily irradiation (DI) and the corresponding
losses over an entire year. The different values used during the evaluation are presented in Table
5.1.
Table 5.1: Solar correction factors and parameters
Parameter Value
Latitude of Ben Gardane [◦ ] 33.171
Atmosphere albedo factor [-] 0.69
Weather factor [-] 0.9
Ground albedo factor [-] 1.1
Finally, in order to assess the mean yearly irradiation at Ben Gardane, the corrected daily
irradiations are summed for each day
365
X
EDcorrected = EYcorrected (5.6)
D=1
34
5 POWER SUPPLY PLANT DESIGN
Superheater
Heliostat field 565◦ C
Turbine &
Evaporator II Generator
390◦ C
Evaporator I Condenser
In the second part, the tower system generates the heat required by the second evaporator, the
superheater and the reheater. Hence, by increasing the inlet temperature of the steam turbine,
the cycle efficiency is highly improved. Moreover, in this case, the heliostat field satisfies the high
graded heat requirements of the hydrogen production facility designed in the previous chapter.
Figure 5.2 illustrates the power plant layout presented above.
35
5 POWER SUPPLY PLANT DESIGN
Ėe−
= (5.7)
Q̇+
high
where Q̇+ high is the required heat input delivered by the solar concentration field. Regarding
(5.7), the integration of a low pressure extraction (LPE) system obviously decreases the electrical
efficiency of the cycle. Nevertheless, since the low graded heat can be satisfied by a heat source
at lower temperature than the available solar high level heat, the exergetic efficiency is strongly
affected. Indeed, considering the same electrical and thermal output for both cases (5.8 and 5.9),
the overall exergetic heat input is higher when a cycle without LPE is used since the thermal
output is directly satisfied by the available high graded heat source. Consequently, the exergetic
efficiency of the power cycle is higher when a LPE system is included.
Ėe− + Ėq−low,required
ηwith LP E = (5.8)
Ėq+with LP E
Ėe− + Ėq−low,required
ηwithout LP E = (5.9)
Ėq+without LP E + Ėq+low,required
36
5 POWER SUPPLY PLANT DESIGN
Parameter Value
Electrical output Ėe+[MWe ] 145.6
Thermal output at 100◦ C [MWth ] 86.58
Turbine inlet conditions 500 [◦ C] at 175 [bar]
Condensation conditions 25 [◦ C] at 0.25 [bar]
with LPE without LPE
Cycle heat input Q̇+ high [MWth ] 409.79 373.67
Thermal output [MWth ] 86.58 -
Electrical efficiency [-] 0.36 0.39
Exergetic efficiency [-] 0.62 0.55
drive the Rankine cycle, the overall heat amount is defined. Table 5.3 summarizes the thermal
energy requirements of the power cycle.
Parameter Value
Preheater [MWth ] 180.98
Evaporator [MWth ] 85.07
Superheater [MWth ] 93.69
Reheater [MWth ] 50.05
High graded heat (production plant) [MWth ] 153.397
Figure 5.4: Temperature-enthalpy flow diagram of the molten salt streams (red) and vapor/water
streams (blue)
37
5 POWER SUPPLY PLANT DESIGN
By using energy integration, the composite curves of the molten salt streams and the wa-
ter/steam streams are plotted (Figure 5.4) and hence, the size of each solar concentration field
can be defined. Considering a yearly solar operation time of 2500 hr/yr, the thermal storage
size which enables ”around-the-clock” operation and the respective active mirror area of each
CSP plant are finally determined. The following table presents the different energy demands for
both the trough and tower plants (Table 5.4).
38
5 POWER SUPPLY PLANT DESIGN
Parameter Value
0
Reference improvement cost Iimprov [M$] 1.1
0 2
Reference field area Aland [km ] 2.8
Reference land specific cost cpurchase [$/m2 ] 0.5
Scaling factor sland [-] 0.3687
Heliostats Similarly to the land cost assessment, the heliostat expenses are computed by
using the correlation defined by Ausburger [7]. Therefore, the heliostat cost can be broken down
into direct purchasing cost Ipurchase , overhead costs Ioverhead which take in account contingency
and corporate oversight expenses and finally indirect costs Iindirect which include engineering
and manufacturing facilities.
Iheliostat = Ipurchase + Ioverhead + Iindirect [$] (5.13)
Regarding the purchasing cost for a single heliostat unit cheliostat , the direct investment expenses
can be expressed as
Ipurchase = cheliostat · Nheliostat [$] (5.14)
where Nheliostat represents the number of heliostat units required for the power plant. Based on
reference case values, the purchasing costs can be evaluated as follows
V
Ahelio shelio,i log2 helio
V0
X
0
cpurchase = cdirect,i · 0 · pri helio
· pii [$] (5.15)
i
A helio
39
5 POWER SUPPLY PLANT DESIGN
Parameter Value
Reference heliostat area A0helio [m2 ] 148
0
Reference volume Vhelio [u] 1625
Heliostat area Ahelio [m2 ] 120
Heliostat Volume Vhelio [u] 23436
The second specific heliostat expenses, the overhead costs Ioverhead , are determined as a
function of the direct investment costs Ipurchase , a progress ration prover and an overhead ratio
or. The different reference and ratio values used during the overhead expense assessment are
reported in Table 5.7.
Vhelio
log2
V0
Ioverhead = Ipurchase · or · (prover ) helio [$] (5.16)
Parameter Value
Progress ratio prover [-] 0.96
Overhead ratio or [-] 0.2
Similarly to the direct investment definition (5.15), the last sub-cost related to the heliostats,
the indirect expenses Iindirect , are expressed as follows
shelio,i Vhelio
log2
X
0 Ahelio V0
Iindirect = Iindirect,i · · pri helio
· pii [$] (5.17)
i
A0helio
0
where Iindirect,i represents the different indirect cost reference values which are presented in
Appendix B.1.1 with their corresponding scaling ratios.
Trough modules The parabolic trough modules expenses are assessed by using the same
correlations determined during the heliostats cost evaluation. The corresponding reference case
values required for the direct investment estimation are stated in Table 5.8 and Appendix B.1.2.
The remaining sub-cost are computed with the same baseline parameter values as for the he-
liostats assessment.
Tower/receiver The capital cost related to the tower/receiver of the heliostat field can be
approached by assuming a scaling factor stower which is multiplied by the field thermal output.
Regarding the investment projections proposed by Turchi et al. [28], a specific cost factor stower =
200 $/kWth is considered in this study.
40
5 POWER SUPPLY PLANT DESIGN
Table 5.8: Direct trough module cost reference values [7] and design parameters
Parameter Value
Reference Trough module area A0trough [m2 ] 3270
0
Reference volume Vtrough [u] 156
Trough module area Atrough [m2 ] 3270
Trough Volume Vtrough [u] 567
Thermal storage Similarly to the tower and receiver cost assessment, the storage facility
expenses can be determined by expressing the capital cost as a function of the overall storage
capacity Estorage and a specific cost factor sstorage .
Istorage = sstorage · Estorage [$] (5.19)
Regarding the investment projections proposed by Turchi et al. [28], a specific cost factor
sstorage = 20 $/kWhth is considered in this study.
Power block The last direct investment expense, the power block, can be evaluated by using
the following relation
Ipower = spower · Pel [$] (5.20)
where spower is the power block specific cost factor. Regarding the investment projections
proposed by Turchi et al. [28], a specific cost factor spower = 1140 $/kWel is considered in this
study.
41
5 POWER SUPPLY PLANT DESIGN
Parameter Value
Replacement cost [-] 0.005
Insurance and property tax [-] 0.01
Total cf ixedop.,total [-] 0.015
Labor rate cl,power [$/hr] 31
Total field area Af ield [km2 ] 20.36
Staff size [-] 326
5.5 Conclusion
This chapter presented the different steps and assumption used to design a hybrid CSP plant
based on the minimum energy requirements defined in the previous chapter. Table 5.10 sum-
marizes the different results generated throughout this section.
Table 5.10: Investment costs and characteristics of the hybrid CSP plant
42
6 DELIVERY COSTS
6 Delivery costs
The production and power plants being designed, the shipping methods and related costs must
finally be evaluated in order to assess the overall cost of hydrogen production for the given
scenario. Since the fleet hub is located in Geneva - Switzerland, three different transportation
means are analyzed in order to select the less expensive solution afterwards. The following
chapter describes the different steps and assumptions made during the selection and assessment
process.
Parameter Value
Installation cost - rural [$/km] 300’000
Installation cost - urban [$/km] 600’000
Pipeline capital cost [$/km] 1869 (d6 pipe )2
Fixed operating costs 5% of total capital
6.1.2 Trucking
A second hydrogen transportation type considered in this study is truck transport. The cryogenic
fuel is filled into a large cylindrical vessel which is fixed on an undercarriage of a standard size
semi-truck. The capital and operating costs related to liquid hydrogen trucks are defined by
Yang et al. [31] and presented in Table 6.2.
6
Diameter in inches
43
6 DELIVERY COSTS
6.1.3 Shipping
Since LH2 shipping has not being commercialized yet and hence, no information about its
costs are currently available, analogies with LNG carriers have been made. Similarly to truck
transport, shipping expenses can be split into two parts; capital and operating costs.
Capital costs During the last years, LNG tanker prices have highly fluctuated, especially due
to the financial crisis which lead to a decreased demand for new vessels. Indeed, while 170,000
m3 vessel prices reached a peak value of $250 millions in 2008, mainly caused by high steel prices
and shipyard’s undercapacity, new vessel costs have sharply fallen to $203 millions by the end
of 20107 (Table 6.3).
Operating costs Since LNG tankers are very sophisticated ships, operating costs (Table 6.3)
which include manning, insurances and maintenance are much higher than traditional tanker
expenses, reaching $14 millions per year in 20107 . In addition to these fixed operating expenses,
travel costs which take in account the marine fuel and harbor fees must be added. Nevertheless,
in the case of LH2 carriers, the boil-off losses generated during the trip may directly be used to
power the vessel engines and hence, strongly decrease the fuel costs.
• The liquefaction plant does not need to be move to Geneva since the pipeline operates
which gaseous hydrogen. Hence, the objective regarding the production from renewable
energy sources is not altered as the plant is not connected to the national grid.
• Undersea pipelines create additional construction costs which are extremely difficult to
assess and therefore, investment costs might be inaccurate.
In light of these results, a combination of truck transport and shipping is selected as delivery
method. Hence, the produced liquid hydrogen is assumed to be loaded on a LH2 tanker and
shipped across the Mediterranean Sea to a European harbor in North Italy, Genoa. Once
arrived, the cryogenic fuel is filled into specific trucks and routed to its final destination at the
International airport of Geneva.
7
http://www.petroleum-economist.com/Article/2801286/LNG-shipping-economics-on-the-rebound.
html
44
6 DELIVERY COSTS
Parameter Value
Sea distance (Ben Gardane - Genoa) [km] 1300
Mean sea travel speed [km/hr] 30
Land distance (Genoa - Geneva) [km] 400
Mean land travel speed [km/hr] 80
Parameter Value
Vessel Capital expenses [M$] 41
Storage capital expenses [M$] 25.36
Operating expense [M$/yr] 26
Parameter Value
Capital expenses [M$] 24
Operating expense [$/yr] 4’348’125
45
6 DELIVERY COSTS
6.4 Conclusion
The total investment and operation costs for the hydrogen delivery are summarized in the
following table (Table 6.7). As presented, the transportation expenses account for almost 0.89
$/ LH2 kg of the overall hydrogen cost.
Table 6.7: Overall capital and operating expenses for hydrogen delivery
46
7 CONCLUSION
7 Conclusion
This study highlighted the different processes and their respective state of development able
to produce hydrogen at large scale, solely by using renewable energy sources. Their analysis
led to the conclusion that a hybrid copper-chloride thermochemical cycle is the best tradeoff
between high efficiency, long system lifetime and technological constraints - especially related
to high temperature thermal storage - and hence, it was selected for a preliminary design.
After determining the MER of the production plant and its auxiliary facilities, a hybrid solar
concentration power plant was designed in order to satisfy the energy demand.
Figure 7.1: Hydrogen price (left) and investment cost (right) breakdown
Indeed, the European Jet-A selling price reached $988.88 per metric ton in December 2013
which corresponds to an energetic cost of $82.4 per MWh. Thus, the equivalent hydrogen price
presented previously is 152% higher than the standard aviation fuel. Moreover, since no profit
margin has been assumed during the hydrogen cost assessment, the real price gap between both
fuels should be even stronger. Indeed, if an additional rate of return of 20% is considered, the
LH2 price drives up to $8.29 per kg ($7.22 per kg when excluding the transportation expenses)
increasing hence the cost difference up to 202%.
In light of these results, LH2 produced from renewable energy sources remains an unattrac-
tive fuel replacement for the airline industry in the near term. With growing oil prices and
decreasing specific costs of solar power plants, alternative fuel generation could become increas-
ingly interesting in the long term. However, this study gave a first approach of the different
challenges and impediments related to clean hydrogen production for a small aircraft fleet. Re-
garding the total infrastructure and area required to satisfy the daily fuel consumption of solely
five Clip-Air planes, it is obvious that the current air traffic density is highly unsustainable. In
8
http://www.iata.org/publications/economics/fuel-monitor/Pages/price-analysis.aspx
47
7 CONCLUSION
order to achieve environmental friendly air travel in the long term, both mobility and alternative
fuels generation cost must decrease.
• Regarding the high level heat required for the selected conversion process, a single CSP
plant has been designed to satisfy the different energy requirements of the production
facility. Nevertheless, depending on the plant location, other renewable energy sources
can be considered during the power plant assessment in order to minimize the total annual
expenses. Indeed, as presented previously, the power generation represents the major cost
factor and hence, additional technologies such as photovoltaic systems, wind and/or sea
turbines could be analyzed with regard to find the most attractive solutions.
• As mentioned in the previous chapter, the cost tradeoff resulting from outsourcing the
LH2 production has not been minimized in this study. A detailed expense analysis should
indeed be performed in order to define the most attractive location leading to low delivery
cost and has high annual solar irradiation.
• A strong limiting factor during the process selection was the high level heat required by
most thermochemical cycles which exceeds the working temperature of current thermal
storage units. Hence, with the introduction of novel storage methods allowing higher heat
grades, a wider range of conversion processes could be considered for continuous LH2
production. Further studies related to high temperature storage medium research and
development could then be analyzed.
48
8 REFERENCES
8 References
[1] Birelaire M Leonardi C Atasoy B, Salani M. Impact analysis of a flexible air transportation
system. EJTIR, 13:123–146, 2013.
[3] Olson N. K Bartels J. R, Pate M. B. An economic survey of hydrogen production from con-
ventional and alternative energy sources. International journal of hydrogen energy, 35:8371–
8384, 2010.
[4] Zahid M Brisse A, Schefold J. High temperature water electrolysis in solid oxide cells.
International journal of hydrogen energy, 33:5375–5382, 2008.
[5] Mergel J Stolten D Carmo M, Fritz D. L. A comprehensive review on pem water electrolysis.
International journal of hydrogen energy, 38:4901–4934, 2013.
[7] Augsburger G. Thermo-economic optimisation of large solar tower power plants. PhD
thesis, EPFL, 2013.
[8] Sargent & Lundy LLC Consulting Group. Assessment of parabolic trough and power tower
solar technology cost and performance forecasts. National Renewable energy laboratory
NREL, October 2003.
[9] Dr. Berster P Bischoff G Prof. Dr. Ehmer H Dr. Gelhausen M ... Dr. Scheelhaase J
Grunewald E, Ayazkhani A. Annual analyses of the European air transport market.
Deutsches Zentrum für Luft- und Raumfahrt (DLR), December 2008.
[10] Werner H. The flexible solution - i.m. skaugen’s fleet of small scale lng carriers. IMS -
Innovative Maritime Solutions, June 2007.
[11] Curtin B Wonhas A Boyd R Grima C Tadros A Hall R Naicker K Hinkley T. J, Hayward
A. J. An analysis of the costs and opportunities for concentrating solar power in australia.
Renewable energy, 57:653–661, 2013.
[12] Amouyal Y Stadler P Ingram J, Nahon J. Cryogenic fuel tanks for the clip-air plane.
Bachelor project, EPFL, June 2012.
[14] Siegel N Kolb G. J, Diver R. B. Central-station solar hydrogen power plant. American
society of mechanical engineering, 129:179–183, 2007.
[15] Takata R Chin P Kromer M, Roth K. Support for cost analyses on solar-driven high
temperature thermochemical water-splitting cycles. Final report to the DOE, prepared by
TIAX LLC, February 2011.
[16] Masin G. J Lewis M. A. The evaluation of alternative thermochemical cycles - part ii: The
down-selection. International journal of hydrogen energy, 34:4125–4135, 2009.
49
8 REFERENCES
[17] Gardiner M. Energy requirements for hydrogen gas compression and liquefaction as related
to vehicle storage needs. Technical report, Department of energy (DOE), October 2009.
[18] Rutkowski M. Current (2005) hydrogen from coal with CO2 capture and sequestration.
National Renewable Energy Laboratory, Jun 2005.
[19] Wade N. M. Distillation plant development and cost update. Desalination, 136:3–12, July
2000.
[22] Stolberg L Lewis M Wangd Z Dincer I Rosen M.A Gabriel K Secnik E Easton E.B Pioro I
Lvov S Jiang J Mostaghimi J Ikeda B.M Rizvi G Luf L Odukoya A Spekkens P Fowler M
Avsec J Naterer G.F, Suppiah S. Progress of international hydrogen production network
for the thermochemical cuecl cycle. International journal of hydrogen energy, 38:740 –759,
2013.
[23] United Nations. Review of maritime transport 2011. United Nations conference on trade
and development, pages 64–84, 2011.
[24] BINE projecktinfo. Power plant with coal gasification. RWE project description, 2006.
[25] Vie P. J. S Ulleberg O Riis T, Hagen E. F. Hydrogen production and storage. International
energy agency IEA, Paris, 2006.
[26] Penner S. Steps toward the hydrogen economy. Energy, 31:33–43, 2006.
[28] Clifford K. H Kolb J. G Turchi C, Mehos M. Current and future costs for parabolic trough
and power tower dystems in the us market. National Renewable energy laboratory NREL,
October 2010.
[29] Beuret V. Evolution des marchés en énergies fossiles 2/2013. Office fédérale de l’énergie
(OFEN), Juin 2013.
[30] Gabriel K.S Gravelsins R Daggupati V.N Wang Z.L, Naterer G.F. Comparison of different
copperchlorine thermochemical cycles for hydrogen production. International journal of
hydrogen energy, 34:3267 – 3276, 2009.
[31] Ogden J Yang C. Determining the lowest-cost hydrogen delivery mode. International
journal of hydrogen energy, (32):268–286, 2007.
50
LIST OF FIGURES
List of Figures
1.1 The Clip-Air aircraft . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
2.1 A320-100/200 fuel consumption (FC) graph fitting for the respective flight dis-
tance (FD) assuming a landing weight of 57 [mt] . . . . . . . . . . . . . . . . . . 5
2.2 Short-haul and medium-haul flight ranges from LSGG . . . . . . . . . . . . . . . 6
3.1 Gasification processes for coal [24] . . . . . . . . . . . . . . . . . . . . . . . . . . 9
3.2 Operating principle of an alkaline electrolyzer . . . . . . . . . . . . . . . . . . . . 10
3.3 Operating principle of a PEM electrolyzer . . . . . . . . . . . . . . . . . . . . . . 12
3.4 Energy of reaction (∆ H, red) and Gibbs energy of reaction (∆ G, gray) in function
of the steam inlet temperature . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
3.5 Operating principle of a SOEC . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
3.6 Operating principle of a sulfur-iodine cycle . . . . . . . . . . . . . . . . . . . . . 14
4.1 Operating principle of a four-step copper chloride cycle . . . . . . . . . . . . . . . 19
4.2 Operating principle of the CuCl/HCl electrolysis . . . . . . . . . . . . . . . . . . 20
4.3 Hydrolysis spray reactor [20] . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
4.4 Oxychloride decomposition reactor [20] . . . . . . . . . . . . . . . . . . . . . . . . 22
4.5 Plant functional sheet . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
4.6 Composite curves . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
4.7 Carnot composite curves . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
4.8 Four step Cu-Cl cycle . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26
4.9 Effect of temperature and HCl concentration on cell voltage [27] . . . . . . . . . 28
5.1 Daily extraterrestrial irradiation ED (red), irradiation including reflection losses
ηa (yellow), the weather factor ηw (green) and ground albedo ηg (blue) over the
year . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34
5.2 Hybrid tower/through CSP plant . . . . . . . . . . . . . . . . . . . . . . . . . . . 35
5.3 Rankine cycle with LPE flowsheet . . . . . . . . . . . . . . . . . . . . . . . . . . 36
5.4 Temperature-enthalpy flow diagram of the molten salt streams (red) and va-
por/water streams (blue) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37
7.1 Hydrogen price (left) and investment cost (right) breakdown . . . . . . . . . . . . 47
A1 Fuel consumption sheet of a A320 100/200 powered by two CFM56-5C4 . . . . . i
51
LIST OF TABLES
List of Tables
2.1 Clip-Air and A320 specific weight [1] . . . . . . . . . . . . . . . . . . . . . . . . . 4
2.2 Fitted function properties . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
2.3 Fuel consumption of Clip-Air and A320-100/200 . . . . . . . . . . . . . . . . . . 5
2.4 Scenario characteristics . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
2.5 Hydrogen assessment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
3.1 State of the art for specifications of Alkaline and PEM electrolysis [5] . . . . . . 11
3.2 Major characteristics for each hydrogen production process . . . . . . . . . . . . 16
4.1 Chemical reactions in a four-step Cu-Cl cycle . . . . . . . . . . . . . . . . . . . . 18
4.2 Heat grade and quantity required for precipitate drying [30] . . . . . . . . . . . . 20
4.3 Heat grade and quantity required for the hydrolysis reaction [21, 20] . . . . . . . 21
4.4 Heat grade and quantity required for the decomposition reaction [21, 20] . . . . . 21
4.5 Energy requirements for the water preparation unit . . . . . . . . . . . . . . . . . 23
4.6 Energy requirements for liquefaction unit . . . . . . . . . . . . . . . . . . . . . . 23
4.7 Minimum thermal energy requirements of the production cycle . . . . . . . . . . 27
4.8 Minimum electrical energy requirements of the production cycle . . . . . . . . . . 27
4.9 Minimum electrical energy requirements of the production plant . . . . . . . . . 28
4.10 Complementary utility investment costs . . . . . . . . . . . . . . . . . . . . . . . 30
4.11 Indirect capital cost factors [15] . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
4.12 Operating cost factors [15] . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
4.13 MER and investment costs of the overall production plant . . . . . . . . . . . . . 32
5.1 Solar correction factors and parameters . . . . . . . . . . . . . . . . . . . . . . . 34
5.2 Power cycle performance and characteristics . . . . . . . . . . . . . . . . . . . . 37
5.3 Power cycle requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37
5.4 Hybrid CSP plant size . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38
5.5 Land cost reference values [7] . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39
5.6 Direct heliostat cost reference values [7] and design parameters . . . . . . . . . . 40
5.7 Overhead cost reference values [7] . . . . . . . . . . . . . . . . . . . . . . . . . . . 40
5.8 Direct trough module cost reference values [7] and design parameters . . . . . . . 41
5.9 Operating cost factors [15] . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42
5.10 Investment costs and characteristics of the hybrid CSP plant . . . . . . . . . . . 42
6.1 Pipeline operating and capital expenses [31] . . . . . . . . . . . . . . . . . . . . . 43
6.2 LH2 Truck operating and capital expenses [31] . . . . . . . . . . . . . . . . . . . 43
6.3 LH2 carrier operating and capital expenses . . . . . . . . . . . . . . . . . . . . . 44
6.4 Transportation data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
6.5 Ship capital and operating expenses . . . . . . . . . . . . . . . . . . . . . . . . . 45
6.6 Truck capital and operating expenses . . . . . . . . . . . . . . . . . . . . . . . . . 45
6.7 Overall capital and operating expenses for hydrogen delivery . . . . . . . . . . . 46
B1 Direct heliostat cost reference values [7] . . . . . . . . . . . . . . . . . . . . . . . ii
B2 Indirect heliostat cost reference values [7] . . . . . . . . . . . . . . . . . . . . . . ii
B3 Direct trough module cost reference values [7] . . . . . . . . . . . . . . . . . . . . ii
52
A FUEL ASSESSMENT
Appendices
A Fuel assessment
A.1 A320 fuel consumption sheet
Figure A1: Fuel consumption sheet of a A320 100/200 powered by two CFM56-5C4
i
B POWER PLANT DESIGN
ii