procedure Duration Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7

working
day
1-5 6-10 11-15 16-20 21-25 26-30
A 5
B 15
C 25
D 15
E 30
F 10
G 10
H 5
I 5