You are on page 1of 19

FAKULTI KEJURUTERAAN AWAM DAN ALAM SEKITAR

BFC31602 CONTRACT AND ESTIMATION


SEKSYEN 2
TITTLE: Project Cadangan pembangunan 620 unit Perumahan Rakyat 1
Malaysia with 300 unit of terrace house type A, 192 unit type B and 128
unit type C, 1 unit Kindergarten, 1 unit Mosque and 1 unit Multi-Purpose
Hall located at Kg. Lumat Beaufort, Sabah.

GROUP 7
NAME MATRIX NO
JACKSMITH LDRECKSSON CLAUDIUS CF150117
MUHAMAD HAZIQ B SAIPOLBAHRI DF140034
MUHHAMAD SHAFIQ BIN ABDUL DF140072
JALIL
MUIZZUDDIN BIN HERMAN DF140001
SAMI MARESH ABDO SAIF AL- AF140189
SHARABI

LECTURER: ENCIK SYED BURHANUDDIN HILMI BIN SYED MOHAMAD


TABLE OF CONTENT

PAGE
`1.0 INTRODUCTION 1

2.0 BACKGROUND
2.1 CASE STUDY 2

3.0 OBJECTIVE 3

4.0 METHODOLOGY 4

5.0 CALCULATION
5.1 PRELIMINARY COST ESTIMATING 5
5.2 BUILD UP RATE 7
5.3 TAKING OFF 9

6.0 CONCLUSION 16

APENDIX
1.0 INTRODUCTION

Estimation knowledge is one of the crucial part in being a good engineer instead of
accountability and integrity. Estimation in developing a contract document consists three
major steps which are preliminary, build-up rate and taking off. So, upon the completion of
this estimation project where we need to estimate the total cost of a building, our group has
chosen a building which is multi-purpose hall for construction project of Pembangunan
PR1MA terrace house.

Preliminary means a description of a project that allows the contractor to assess costs.
Generally, the purpose of preliminaries is to describe the works as a whole, and to specify
general conditions and requirements for the project. The costs attached to preliminaries may
also be referred to as preliminaries or prelims or site overheads or general cost items or
expenses. The cost of administering a project and providing general plan, site staff, facilities,
and site based services and other items not included in the rate. By completing the task, we
could know the method to determine the early cost by using volume method and floor area
method.

While build-up rate means the method of formulating budgets or projections by


estimating the cost of performing or achieving predetermined tasks or objectives. By
completing the build-up rate task, we could gain the knowledge to calculate the cost of
excavation.

Last but not least, taking off which means a detailed measurement of materials and
labour needed to complete a construction project. By completing the taking-off task, we are
able to calculate the cost of every element in the drawing and the general cost.
2.0 BACKGROUND

2.1 CASE STUDY

The project title is Cadangan pembangunan 620 unit Perumahan Rakyat 1 Malaysia with 300
unit of terrace house type A, 192 unit type B and 128 unit type C, 1 unit Kindergarten, 1 unit
Mosque and 1 unit Multi-Purpose Hall located at Kg. Lumat Beaufort, Sabah. The main
contractor for this project is Stone EPC (Sabah) Sdn Bhd. With a lot of building type in this
housing project, our Project is only estimating the taking off, build up rate and method
estimating of Multi Purpose Hall. The Multi Purpose Hall is using IBS (interlocking brick
system) brick and has 2 level of building. The Foundation type that we are using is F8 shows
in drawing with size 2.5 x 2.5 x 0.45 and ground beam GB14 with size 150 x 500. The Multi
Purpose Hall drawing and detail were attached in appendix including beam detailing, footing
plan, ground beam and slab drawing.

Type C
Office
SEPC

Surau Type B

Dewan

Tadika

Type A
Site Plan PR1MA Woodford Estate, Beaufort
3.0 OBJECTIVE

1. To estimate project cost using preliminary estimating techniques (floor area and
building volume method).
2. To calculate build-up rate for specific work.
3. To perform the taking off quantities for specific work elements of the project.
4.0 METHODOLOGY

START

FIND A DRAWING OF PROJECT

TAKING OUT ALL OF INFORMATION OF STRUCTURE MEASUREMENT

MAKE A CALCULATION OF

1. PRELIMINARY (FLOOR AREA AND VOLUME


METHOD)

2. BUILD UP-RATE

3. TAKING OFF

END
5.0 CALCULATION

5.1 PRELIMINARY COST ESTIMATING

Information
1) This building we open in 3 parts A,B,Cand D the measurement of this 3 parts is :

(PART A AND B)
WIDTH 30125 MM or 30.125 M
HEIGHT 3600 MM or 3.6 M
LENGTH 28125 MM or 28.125 M

PART C
WIDTH 20000 MM or 20 M
HEIGHT 3000 MM or 3 M
LENGTH 20125 MM or 20.125 M

PART D
WIDTH 20000 MM or 20 M
HEIGHT 3000 MM or 3 M
LENGTH 20125 MM or 20.125 M

2) A building multipurpose hall with 250 mm thick block wall (measure centre to
centre)
3) A similar building multipurpose hall was built with a price rate of RM 250/m3 and
RM 150/m2

Calculation:
Building volume method (SUM ALL PART A, B, C AND D)
=lxwxh
= 2 ([28.125+ (0.250)] X [30.125 + (0.250)] X[3.600+ (0.250)] +[(20.125+
(0.250)] X [20.000+ (0.250)] X [3.000+(0.250)] + ([20.125+(0.250)] X
[20.000+(0.250)] X [3.000+(0.250)]
= 6636.56+1340.93+1340.93
= 9318.42 m3

Total cost
= 9318.42 m3X RM250/M3
= RM 2329605
Floor area method (SUM ALL PART A, B, C AND D)
=lXW
= 2[28.125-(0.250)]X [30.125-(0.250)] + [(20.125-(0.250)] X [20.000-(0.250)] +
[20.125-(0.250)]X [20.000-(0.250)]
=1665.53+392.53+392.53
=2450.59 m2

Total cost
= 2450.59 m2X RM 150/M2
=RM 367588.5
5.2 BUILD UP RATE

Item Rate
Worker salary (8 hours working/day) RM 50.00/day
Soil excavation not exceeding 1.5m depth 1.50 hour/m3
Soil excavation exceeding 1.50m but not 1.60 hour/m3
exceeding 3.00m depth

Spreading up soil in making up level (surface 0.12 hour/m2


to receive pad footing)

Filling in and ramming soil 0.60 hour/m3


Carting away remainder load 1.20 hour/m3
Typical soil expansion 25%
Profit 20%

1. Cost of excavation out


Total depth of excavation = 0.05 + 0.45 + 0.65 + 0.50
=1.65m

Volume of excavation (not exceed 1.50m):


V =lxwxd
= 2.5 x 2.5 x 1.5
= 9.375m3

Volume of excavation (exceed 1.50m)


V =lxwxd
= 2.5 x 2.5 x 0.15
= 0.938m3

Cost:
= 9.375m3 x 1.50 hour x (RM50.00/8 hour) + 0.938m3 x 1.60 hour x
(RM50.00/8 hour)
= 87.89 + 9.38
= RM97.27

2. Cost spread up in making up level (surface to receive pad footing)

= (2.5m x 2.5m) x 0.12 hour x (RM50.00/8hour)


= RM 04.70

3. Cost of filling and ramming

Cost:
= [10.313m3 - (2.5m x 2.5m x 0.45m ) (0.25m x 0.375m x 0.65m) (1.06 x
0.15 x 0.5) x 2 x 0.60 hour x (RM50.00/8hour)

= (10.313m3 2.810m3 0.061m3 0.160m3) x 0.60 hour x RM6.25

= RM27.31

4. Cost of carting away remainder load

= [10.313m3 (7.282m3 x 1.25)] x 1.20 hour x RM6.25/hour


= RM09.08

5. Profit

= 20% x [RM97.27 + RM04.70 + RM27.31 + RM09.08] / 10.313


= 20% x RM13.42
= RM02.68/m3
5.3 TAKING-OFF

TIMES DIM RESULT DESCRIPTION UNIT QTY


W.B.L.F.F.
Excvt. top soil
length
5.375
Add fdn. spr.
2.500
0.450 2.050
7.425

7.43
[ Excvt. top soil for preservn. avg. 100
7.43 55.20 M2 55.20
[ mm deep

[Dep. preserved top soil in temp. spoil heaps avg.


7.43 10.000 m dist.
7.43
0.10 5.52 M3 5.52

Surc. excvn.
9.00 Depth
14.50 conc. bed 0.125
0.10 13.05 Hardcore 0.150 m3 13.05

0.275

Less top soil


excvn. 0.100
0.175
7.23
7.23 [ Exvct. to red. lev. max. depth n.e. 250mm
0.18 9.409 [& Rem. excvt. mat. from site. m3 9.409
pitexcvn.
depth
lean 0.05
ftg. 0.450
stump 0.650
1.15
Less excvn.
top soil 0.100
red lev 0.175 0.275
1.425

[ Excvt. pit to rec. col. bases startg. from red. lev.


[ max. depth n.e. 1.00 m
[ (In No. 6)
[&
6/ 2.50 [ Fillg. to excvn. w. mat. arising from excvn.
2.50 6
1.425 53.44 m3 53.44

[ E.o pit excvn. for excvtg. in rock


[ (Prov.)

10 2.50
100 2.50
6/ 1.425 5.340 m3 5.340
EXCAVATION
W.B.LF.F
TR.excvn

Length
5.375
Less col. st.
2/0.450
0.490
4.4750

Depth
0.500

Add ln con
0.050
0.550

Less excvn
Top soil 0.100
Red.lev 0.175 0.275
0.275

Excvt. Tr.to rec.grd. bm. Starting from red. Lev depth


n.e 0.25m
& Rem excvtd. Mat from site
6/ 4.48
0.25
0.25 1.68 m3 1.68

10 4.48 E.otr.excvn.forexcvtg. In rock


100/ 0.25 (prov)
6 0.25 0.168 m3 0.168

BLINDING AND CONCRETE


6/ 2.5 col.bases
2.5
0.45 16.88 M3 16.88
(Conc. Gr 7 blinding n.e 10 mm thk. Laid on earth &
rem. Excvtd. Mat from site& (ddt. Filg to excvn .w.
mat. Arising from excvn.

(reinfdinsituconc gr 30 in soil fdn bases in no 6 & rem


excvtd mat from site &ddtfillg to excvn w. mat arising
6/ 2.5 from excvn M3 14.06
2.5
0.45 14.06

6/ 0.250 Reinfdinsituconc gr 30 in soil col stump


0.375 M3 0.370
0.650 0.37

W.B.L.F.F.
Vol. of stump in pit
Ht
0.650
Lessexcvn
Top soil 0.100
Red. Lev. 0.175 0.275
0.375

(rem. Excvtd. Mat from site &ddtfillg to excvn .w. mat


6/ 0.25 arising from excvn
0.375
0.38 0.214 m3 0.214

Stump
Gth
6/0.375 2.250
6/ 2.25 m2 8.78
0.65 8.78

Reinft bars in soil col stump


Stump
Length
Fdn. 0.450
Stump 0.650
Lap In col. 0.450
1.55

Less
Conc.cov 0.04
Fdn bars
2/0.012 0.0240.064
1.486

Add bend 0.250


1.736
(20 mm diah.t.steel reinft in strt& bent bars in iso. Col
6/4 1.74 41.76 stump m2 41.76

Links
gth.
Width 0.375
less
con. cov. 2/0.040 0.080
4/ 0.295
=1.18

Add
Hooks 24/0.010 0.24
1.42
W.B.L.F.F

6/
6/ 1.42 51.12 (8 mm diam.sreinf in links in soil . col. stump m 51.12

Blindg. To grd. Bm.


Length
5.325
6/ 4.48 Less 3 stump
3/0.300
0.25 0.900
0.05 0.34 4.475

10 10.55
100 0.13 Conc gr blindgn.e. 100 mm thk laid on earth
2/ 0.18 0.50 m3 0.34

Fwk to fdns& beds


fdn
6/2.515.00

(fwk to edges & faces of fdn exceeding 250 mm and


6/ 15 90.00 n.e. 500 mm high m 90.00

(fwk to edges & faces of fdn exceeding 250 mm and


6/2 4.48 53.76 n.e. 500 mm high m 53.76

Pad ftg
Length
2.500
LESS
Conc. Cover b/s
2/0.0400
0.080
2.420

Add
2 bends 0.300

Less m3
2 conc cov 0.080
2/0.295
0.590
6/ 3.010 0.13
6 3.010 108.36
(mm dia h.t reinft in strt& bent bars in fdn
Pad ftg m 108.36

W.B.L.F.F.
Grd beam
Length
5.375
Lessconc.cov
2/0.0400.080
5.295
Add 2 bends
2/0.300
0.600
6/ 5.895
6 5.895 212.22 (12 mm diaht steel reinft in strt& bent bars in fdn m 212.22

stirupss
Grdbm
Gth
Width
01.50

Less
Cov 2/0.040 0.080
0.070

Ht 0.500

Less
Cov 2/0.040 0.080
0.420
2/ 0.490
=0.980

Add
Hooks 24/0.008
0.192
1.172

6/ 8 mm diam.sreinft in stirups in fdn


28/ 1.18 198.24 (grdbms m 198.24

h/c &dpm

Length /width
5.375
Less
2 stumps 2/0.300
0.600
4.875

4.875 W.B.L.F.F.
4.875 23.77 M2 23.77
Fillg to make up levavg 150 mm thkw.h/c of clean hard
broken stones obtained off site &polyetlene not less
than 1000 gauge horizdpmlapdd 100 mm at jts laid on
h/c

4.875 Conc gr 30 ln bed 100mm 150 thk laid on h/c


4.875
0.13 3.08 M3 3.08
6.0 CONCLUSION

The conclusion from this project is that we are able to learn about contract and its relation to
estimation of such project. This knowledge can be use in the future upon stepping into carrier
environment. From this project, there three type of calculation that has been used which is
preliminary that consist floor area method and volume method. Next is build up-rate and the
last one is taking off method. All these three methods are very important in completing a
project and will benefit to the developer both before and after the project is done. Preliminary
calculation is done to predict the overall cost of the project and cost for resources required
before starting the project. This will help in forecasting the cost for the project upon
completion. From the build-up rate calculation, we are able to determine the cost for
excavation work, cost for filling and ramming the soil, cost to carting away remainder load
and cost for spreading up soil in making up level. The last method is taking off where the
calculation is done to produce bill of quantity for such project. Analysis
of drawings and specifications allows the cost consultant to prepare a taking off list, which
lists all of the individual elements that comprise the works. These elements can then be
measured in number, length, area, volume, weight or time then collated and structured to
produce an unpriced bill of quantities. Therefore all this method is very useful for civil
engineering students as one of the compulsory knowledge that will be used in the future.
GROUP OF MEMBER PICTURE

FROM LEFT:
1). MUHHAMAD SHAFIQ BIN ABDUL JALIL (DF140072)
2). SAMI MARESH ABDO SAIF AL- SHARABI (AF140189)
3). JACKSMITH LDRECKSSON CLAUDIUS (CF150117)
4). MUIZZUDDIN BIN HERMAN (DF140001)
5). MUHAMAD HAZIQ B SAIPOLBAHRI (DF140034)

You might also like