20M MID HINGED MAST

OPTION 1 NO BARRIER OPTION 2 - WITH

SI ITEM UNIT QTY SI

1 EXCAVATION M3 18 1

2 DISPOSAL M3 5 2

3 BACKFILLING M3 13 3

4 FORMWORK M2 8.5 4

5 CONCRETE M25 M3 3 5

6 REINFORCEMENT KG 150 6
ED MAST

OPTION 2 - WITH BARRIER

ITEM QTY

EXCAVATION M3 20

DISPOSAL M3 15

BACKFILLING M3 5

FORMWORK M2 30

CONCRETE M25 M3 5.6

REINFORCEMENT KG 610