Province Government

Lumbini Province
Ministry of Physical Infrastructure Development
Transport Infrastructure Directorate
Road Infrastructure Devlopment office(RIDO)
Dang, Ghorahi
Bar Bending Schedule (BBS)
Single Cell: 2x1.5mm Span Road Width in (m) 10.00
Total Unit
Decsriptions Diameter Spacing M2 Length No. of Total Weight-
SN Bar Shape M1 (mm) Length Weight Remarks
of Items (D-mm) (mm) (mm) (mm) Bars kg
(TL)-m (Kg/m)
A RCC Box Culvert

1 M1 M1 Rebar-1 10 250 780 2,500 4,020 41 164.82 0.62 101.74


M2

M1

2 M2 Rebar-2 16 250 850 2,130 3,766 82 308.81 1.58 488.00


M1

M1
3 Rebar-3 - - 1,400 - 1,400 - - -

M2

4 M1 M1 Rebar-4 16 250 280 3,500 3,996 41 163.84 1.58 258.90

0.2m

5 M1 Rebar-5 16 250 2,130 700 3,134 82 256.99 1.58 406.10


0.2m

M2

M2
6 M1 M1 Rebar-6 16 250 300 2,500 3,036 41 124.48 1.58 196.70

M1
7 Rebar-7 - - 1,400 2,800 - - - -

M2
8 M1 M1
Rebar-8 10 250 750 2,500 3,960 41 162.36 0.62 100.22

M1
M2
9 Rebar-9 10 250 200 919 1,279 82 104.90 0.62 64.75
M1

M1

10 M2 Rebar-10 12 250 200 962 1,314 82 107.72 0.89 95.75


M1

M2
11 M1 M1 Rebar-11 10 250 175 9,900 10,210 16 163.36 0.62 100.84

M2
12 M1 M1 Rebar-12 10 250 190 9,900 10,240 16 163.84 0.62 101.14

Prepared By: Checked By: Approved By:


M2
13 M1 M1 Rebar-13 10 250 150 9,900 10,160 12 121.92 0.62 75.26

M2

14 M1 M1 Rebar-14 10 - 150 9,900 10,160 12 121.92 0.62 75.26

M2
M1 M1
15 Rebar-15 10 250 190 9,900 10,240 12 122.88 0.62 75.85

Approach
M1
16 Rebar-16 Not Used Rest part of
Box cell
M1
Approach
17 Rebar-17 Not Used Rest part of
M2
Box cell

M1 M1
18 Rebar-18 10 - 180 9,900 10,220 4 40.88 0.62 25.23
M2

19 M1 M1 Rebar-19 10 - 180 9,900 10,220 8 81.76 0.62 50.47


M2

M1

50mm
20 M2 Rebar-20 10 200 200 1,030 2,660 19 50.54 0.62 31.20 Cut off US
M2

M1

M1 M1 Cut off
21 Rebar-21 10 200 150 3,500 3,760 28 105.28 0.62 64.99
M2 Distribution

M2 Abutment
22 M1 M1 Rebar-22 10 250 150 9,900 10,160 12 121.92 0.62 75.26 wall
Distribution

M1

50mm
23 M2 Rebar-23 10 200 200 1,780 4,160 19 79.04 0.62 48.79 Cut off DS
M2

M1
e
d 50mm
24 a Rebar-24 10 200 - - 1,974 28 55.28 0.62 34.12 Kerb
c

Prepared By: Checked By: Approved By:


M2
Kerb
25 M1 M1 Rebar-25 10 - 200 2,600 3,000 8 24.00 0.62 14.81
Distribution

Total 2,485.40 Kg

Prepared By: Checked By: Approved By: