Professional Documents
Culture Documents
Pushpa Chitrakar
TABLE OF CONTENTS
Page No.
TABLE OF CONTENTS I
NOTICE 1
1. INTRODUCTION 2
1.1 GENERAL 2
1.2 OBJECTIVES OF THE DESIGN AIDS 2
1.3 SOURCES OF THE DESIGN AIDS 3
1.4 DESIGN AIDS: TYPICAL DRAWINGS 3
1.5 DESIGN AIDS: SPREADSHEETS 5
1.5.1 Flow chart notations 6
1.5.2 Iterative Processes 6
1.5.3 Macro Security 7
1.5.4 Individual vs. linked spreadsheets 8
1.5.5 User specific inputs 8
1.5.6 Interpolated computations 8
1.5.7 Errors 8
1.5.8 Cell notes 8
1.5.9 Cell Text Conventions 9
1.5.10 Types of input values 11
1.5.11 Pull Down menus and data validation 12
2 DISCHARGE MEASUREMENT 13
3 HYDROLOGY 15
3.1 HYDROLOGY AND NEPALI MHP 15
3.2 HYDROLOGICAL DATA 15
3.3 MEDIUM IRRIGATION PROJECT (MIP) METHOD 16
3.4 WECS/DHM (HYDEST) METHOD 18
3.4.1 Flood Flows: 18
3.5 AEPC MGSP/ESAP GUIDELINES & STANDARDS 19
3.6 PROGRAM BRIEFING & EXAMPLES 20
4 HEADWORKS 24
4.1 INTRODUCTION AND DEFINITIONS 24
4.2 AEPC MGSP/ESAP GUIDELINES AND STANDARDS 24
4.1.1 Weir 25
4.1.2 Intake 25
4.1.3 Intake Trashrack 25
4.3 PROGRAM BRIEFINGS AND EXAMPLES 25
Page : i
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
5 HEADRACE/TAILRACE 34
5.1 INTRODUCTION AND DEFINITIONS 34
5.2 MGSP/ESAP GUIDELINES AND STANDARDS 34
5.2.1 Canal 34
5.2.2 Pipe 34
5.3 PROGRAM BRIEFING AND EXAMPLES 34
5.3.1 Canal 34
5.3.2 Pipe 39
6 SETTLING BASINS 42
6.1 INTRODUCTION AND DEFINITIONS 42
6.1.1 Sediment Settling Basins 42
6.2 SETTLING BASIN THEORY 43
6.3 MGSP/ESAP GUIDELINES AND STANDARDS 43
6.3.1 Gravel Trap 43
6.3.2 Settling Basin 44
6.3.3 Forebay 44
6.4 PROGRAM BRIEFING AND EXAMPLES 44
6.4.1 Features of the spreadsheet 44
6.4.2 Vertical flushing pipe 45
6.4.3 Spillway at intake 45
6.4.4 Gate 45
8 TURBINE SELECTION 54
8.1 INTRODUCTION AND DEFINITIONS 54
8.2 MGSP/ESAP GUIDELINES AND STANDARDS 54
8.3 PROGRAM BRIEFING AND EXAMPLE 55
Page : ii
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
13. UTILITIES 73
13.1. INTRODUCTION 73
13. REFERENCES 75
APPENDICES I
LIST OF FIGURES
Figure 1.1: A typical Gravel Trap Drawing............................................................................5
Figure 2.1: Discharge calculations by salt dilution method..............................................14
Figure 3.1: MIP Regions.......................................................................................................16
Figure 7.1: Flow diagram of penstock design....................................................................51
Figure 7.2: Input required for penstock and power calculations......................................52
LIST OF TABLES
Table 1.1: Summary of Drawings .........................................................................................4
Table 1.2: Summary of Spreadsheets...................................................................................5
Table 2.1: Input parameters for Salt Dilution Method........................................................13
Table 3.1: MIP regional monthly coefficients .....................................................................16
Page : iii
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
NOTICE
These micro-hydropower design aids have been prepared to provide a basis for consultants to undertake
calculations and prepare drawings as per the requirements set aside by Alternative Energy promotion
Centre (AEPC) of His Majesty’s Government of Nepal (HMG/N). It is expected that the use of these
design aids will result in a standard approach to carrying out calculations and drawing on Peltric feasibility
studies and preliminary and feasibility studies of micro-hydro projects.
This manual and any examples contained herein are provided “as is” and are subject to change without
notice. Small Hydropower Promotion Project (SHPP/GTZ) and Mini-Grid Support Programme
(MGSP/AEPC-ESAP) shall not be liable for any errors or for incidental or consequential damages in
connection with the furnishing, performance, or use of this manual or the examples herein.
© Small Hydropower Promotion Project (SHPP/GTZ) and Mini-Grid Support Programme (MGSP/AEPC-
ESAP). All rights reserved.
All rights are reserved to the programs and drawings that are included in the MHP Design Aids.
Reproduction, adaptation or translation of those programs and drawings without prior written permission of
SHPP/GTZ and MGSP/AEPC-ESAP is also prohibited.
Permission is granted to any individual or institution to use, copy, or redistribute the MHP Design Aids so
long as it is not sold for profit, provided this copyright notice is retained.
Page: 1
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
1. INTRODUCTION
1.1 GENERAL
This Micro Hydropower Design Aids Manual covers the procedural guidelines for using Micro Hydro
Design Aids prepared under the collaboration between Small Hydropower Promotion Project (SHPP/GTZ)
and Alternative Energy promotion Centre (AEPC) of His Majesty’s Government of Nepal (HMG/N). The
Micro hydro Design Aids, which consists of a set of spreadsheets and drawings, has been developed as a
tool to provide quick and reliable means of computing design parameters of different components of the
perspective micro hydropower plants in Nepal.
Small Hydropower Promotion Project is a joint project of His Majesty’s Government of Nepal (HMG/N),
Department of Energy Development (DoED) and German Technical Cooperation (GTZ). Since its
establishment in 2000, this project has been providing its services to sustainable development of small
hydropower projects in Nepal (100kW to 10MW) leading to public private participation and overall rural
development.
Since the nature of small hydropower and micro-hydropower projects are similar in many aspects,
SHPP/GTZ signed collaboration with the AEPC to help the sector. During the course of supporting and
backstopping micro-hydropower sector as per the scope defined in the collaboration, SHPP helped AEPC
upgrading the existing AEPC guidelines, developing a user-friendly micro-hydropower related
computational tools and typical drawings. These micro hydropower tools (MHP Design Aids) have been
prepared to provide a basis for consultants to undertake calculations and prepare drawings as per the
requirements set aside by AEPC. It is expected that the use of these design aids will result in a standard
approach to carry out calculations and represent the calculations with the help of standard drawings on
Peltric feasibility studies, preliminary feasibility and detailed feasibility studies of micro-hydro projects.
The Design Aids consist of a set of fifteen typical drawings and fourteen typical spreadsheet calculations
useful for Nepali micro hydropower projects up to feasibility study level. During the preparation of these
design aids, special efforts were made so that the skills and knowledge of the practicing stakeholders such
as consultants, manufacturers, inspectors, etc, are not replaced by this design aids. Constant efforts were
equally made to make the design aids simple and user friendly. Since most of the stakeholders are
familiar with Autodesk AutoCad 2000 and Microsoft Excel XP application software, the design aids were
made based on the software.
It is also expected that the stakeholders will be using the electronic version of the design aids. The design
aids are distributed in template/read-only forms so that the original copy is always preserved even when
the users modify them.
The design aids are specifically prepared for micro hydropower schemes up to 100kW. Although, there
are many common approaches and features in all hydropower projects, special care should be taken while
using these aids for bigger schemes if the circumstances are unavoidable.
Preparation and use of the design aids is a continuous process. Therefore, valuable suggestions and
feedbacks are expected from all the stakeholders/users so that the overall quality of the micro hydro
sector is enhanced.
Page: 2
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
1. It should be able to function as a “Time Saver Kit” for precision and speed (e.g. hydrological
calculations based on exact flow measurement date, Q flood off take, friction of penstock, etc.).
2. It should be able to function as references for stakeholders of the micro hydro sector for using and
upgrading their skill and creativity. Any external references that may require referring during
calculations are minimised by incorporating them in the cell notes, tables, pictures, etc.
3. The presented reports by different consultants are uniform and their data presentations are to the
required depth.
4. The design aids should be able to serve as templates and not a readymade design set so that
there are sufficient rooms for further creativity and improvement to tailor to incorporate specific
needs of particular projects.
5. In addition to the objectives stated above, the design aids should equally be handy and user
friendly. The user familiar AutoCad 2000 and MS Excel XP software platforms are used to
develop the design aids.
Page: 3
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
5. All drawings with standard layouts for a specific printer (may have to be changed as per the actual
available printer).
While editing the drawing based on the project needs, it should be noted that the dimensions should be
amended along with their geometries. This is especially important so that a 2m long structure is always
longer than a 20cm structure.
The presented drawings cover from intake to transmission line. A set of all the drawings are presented in
the appendix. For an example, a typical drawing of a gravel trap is presented in Figure 1.1. The drawings
that are presented are listed in Table 1.1.
Page: 4
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Since the design aids are aimed at enhancing the quality of micro hydro up to feasibility study level, the
financing, manufacturing, etc., part are not covered in greater details.
The spreadsheets not only speed up the computational processes with adequate level of precision but
also provide adequate information (printable as well as references such as cell notes, etc). The main
features of the presented spreadsheets are:
Input
Conditional branching
Flow direction
Is Yes
Assume Xo Y =f(X): X=f`(Y) e=<|Yn+1 –Yn| End
No
X=X+h
Figure 1.2: Iterative process
As shown in the figure, the assumed value of X0 is amended until an accepted error limit is reached. By
default, Excel does not activate this kind of iterative process and generates Circular Reference Error. The
Page: 6
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: 7
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
1.5.7 Errors
Mainly three types of errors are generally expected. One of them is NAME# error which is caused by not
functioning the custom functions and procedures present in the spreadsheets. In case such an error
occurs, close the workbook, activate the macro security level to medium and enable the macros when
opening the workbook again. A typical NAME# error occurs adjacent to the depth of water during flushing
yfi (m) and d50f during flushing (mm) in the settling basin spreadsheet.
VALUE# error is the other error that is generated by the malfunctioning of circular references. When such
an error occurs, select the error cell, press F2 and press Enter. Q intake Qf cumec in the side intake is
such an error.
REF# error in transmission line computation occurs due to the deletion of unnecessary rows in a branch.
In such an instance, copy the second cell from the second line of any branch.
A cell containing a cell formula for calculating the specific speed of a turbine is presented in Figure 1.5.
Similarly, Figure 1.6 presents a basic table for selecting Manning’s coefficient of roughness of a canal.
Page: 8
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Cell Formula
Blue cells: These cells represent the mandatory input cell. The user must input these cells with
the correct values of the scheme data for correct output. The mandatory input includes the name
of the project, head, discharge, etc.
Red cells: These cells are optional input cells. Standard values are presented in these cells. If a
user has sufficient ground to change these values, he or she is allowed to do so by changing these
values. It is worth noting that care should be taken while changing these values. The optional
values/ input include the density of sediment, sediment swelling factor, temperature of water, etc.
Black cells: The black cells represent the information and or output of the computations. For the
sake of protecting accidental and deliberate amendment or change leading to wrong output, these
cells are protected.
Page: 9
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Cell Notes
Figure 1.6: A cell note presenting typical values of Manning’s n for different surfaces
Colour
coding
of cell
texts
Page: 10
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Based on the nature of the input, the inputs are categorised in the following three groups:
1. User or project specific input: The inputs variables that totally depend on the user and or the
project are categorised as the user or project specific inputs. The programs do not restrict on or
validate the values of such inputs. The name of the project, gross head of the projects, etc., are
some of the examples that fall on this category. The length of the crest in the example presented in
Figure 1.8 can have any value hence it is a user specific input.
2. Prescribed Input: Some of the inputs have some standard values. The programs suggest using
such values and giving choices for the user to select. However, the programs do not restrict on or
validate such variables. These inputs are termed as prescribed inputs. With the help of a pull down
menu, the probable type of the surface is presented for deciding the Manning’s coefficient in Figure
1.8. The user does not have to remember the specific values of the type of the surface he is
considering. However, he is free to input any values if he has a very good reason to change them.
3. Mandatory Input: Some inputs can have some specific values and the programs need to validate
such values for proper computations. These values are termed as mandatory inputs. Since Nepal
is divided into seven MIP regions, the MIP region value can have an integer ranging from 1 to 7. In
the example presented in Figure 3.1, the MIP region can have values from 1 to 7, the month can
have a string from January to December and the date can have an inter ranging from 1 to 31. In
case the user enters different values, the program will generate error and prompt for the correct
inputs.
Page: 11
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: 12
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
2 DISCHARGE MEASUREMENT
Almost all potential micro hydropower project sites are located in remote areas where there is a complete
lack of hydrological information. Tools developed for estimating hydrological parameters are mainly based
on regional correlations. The outputs of these tools are close to the actual parameters for rivers having
bigger (100km2 or more) catchment areas. Since most of the potential micro hydropower plants have
relatively smaller catchment areas, use of these regional regression methods based on at least one set
actual site measurement is recommended in the AEPC guidelines for estimating flow parameters. Bucket
method for flow up to 10 l/s, weir method for a flow from 10 to 30 l/s and for flows larger than 30l/s salt
dilution method (conductivity meter) are recommended.
Since the salt dilution method is quick (less than 10minutes per set of measurement), easier to accomplish
and reliable, its accuracy level is relatively higher (less than 7%) and suitable for smaller fast flowing
streams (up to 2000 l/s), preference should be given to this method. The change of conductivity levels of
the stream due to the pouring of known quantity of predefined diluted salt (50-300gm per 100l/s) are
measured with a standardised (conductivity meter with known salt constant, k) conductivity meter at a
regular interval (e.g., 5 seconds). For more information, please refer to MGSP Flow Verification
Guidelines or Micro Hydro Design Manual (A Harvey).
As per the MGSP guidelines, at least one set of discharge measurement at the proposed intake site
should be carried out between November and May. The discharge calculation spreadsheet presented in
the Design Aids can handle up to four sets of data and the individual as well as the average discharges
are presented as outputs.
The input parameters required for discharge measurement calculation are presented in Table 2.1. The
typical input parameters considered in the example are presented in the adjacent column. The first set
field readings are presented in Table 2.2.
Table 2.2: First set conductivity reading for Salt Dilution Method Example
Time(sec)
5 10 15 20 25 30 35 40 45 50 55 60 Sum
25 26 27 28 29 30 31 32 32 33 34 34 361
34 35 35 35 35 34 34 34 33 33 33 32 407
Water
32 32 32 31 31 31 31 31 31 30 30 30 372
Conductivity in
mS 30 29 29 29 29 29 29 28 28 28 28 28 344
28 28 27 27 27 27 27 26 26 26 26 26 321
26 26 26 26 26 26 26 25 25 25 257
Total (mS) 2062
Total readings 70
With the input parameters, the discharge at the stream is calculated by the following procedures:
Page: 13
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Weighted averages of the individual flows thus calculated are computed. The outputs of the spreadsheet
are presented in Figure 2.1. The estimated average discharge will further be used by Medium Irrigation
Project Method (MIP) to calculate long term average monthly flows. The calculations procedures for the
first set (Set 1) are:
50
40
30
20
10
0
0 50 100 150 200 250 300
Time(sec) 350 400 450 500 550 600
Date= 2004/1/12, 11deg C, , HANNA Instrum ents (HI 933000), Iyoo Noon, k=1.8,
Ave. Discharge = 453.89 l/s
3 HYDROLOGY
Streamflow
Streamflow Records
Records
Precipitation
Precipitation and
and Climatological
Climatological Data
Data MHP
MHP
Hydrological
Hydrological Data
Data
Topographic
Topographic Maps
Maps
Groundwater
Groundwater Data
Data
Evaporation
Evaporation and
and Transpiration
Transpiration Data
Data
Soil
Soil Maps
Maps
Geologic
Geologic Maps
Maps
Hydrological
Hydrological Data
Data
Page: 15
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
The seven regions are graphically shown in Figure 3.3 and the seven sets of monthly coefficients are
presented in Table 3.1. It is worth noting that these monthly coefficients have to be interpolated to get the
actual monthly coefficients if the flow measurement date is not on the 15th of the month.
Page: 16
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
INPUT
INPUT
Low
Low flow
flow measurement
measurement OUTPUT
OUTPUT
MIP
MIP
Measurement
Measurement date
date Mean
Mean monthly
monthly flows
flows
MIP
MIP region
region number
number
Figure 3.4: MIP model
Figure 3.4 represents the flow chart of the MIP model. As shown in the figure, this model takes low flow
measurement, its date and MIP region number as inputs and process them for estimating mean monthly
flows for that region. As stated earlier, the actual measurement date plays an important role in computing
more realistic mean monthly flows. These mean monthly flows are calculated as:
Mean Coeff. for this month by interpolation if the date is not on 15th
April coef = 1/coeff this month
April flow = April coeff * Q
Monthly flows = April flow * coeffs (Qi = QApril * Ci)
The importance of considering the actual date of measurement and the need of calculating actual mean
monthly flow of that month are further explained in Figure 3.5. The measured flow is 54 l/s. The corrected
flows for April are 45.38 l/s, 54 l/s and 37.5l /s if they are measured on April 1, 15 and 30 respectively. If
interpolation was not carried out, a feasible project may fail to prove its viability according to the ACPC
criteria or vice-a-versa.
This fact that the mean monthly coefficient calculation plays major role in AEPC acceptance criteria is
illustrated by a following example.
Measured flow for MIP method m3/s: 1
MIP region (1 -7): 3
Page: 17
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Figure 3.6 is the graphical representation of the outcome of the MIP method. The measurement date
namely on April 1, 15 and 30 are considered and the errors generated by using different dates are
presented. The design flow exceeds 11 months and fulfills the AEPC criteria if it is measured on either
April 1st or April 15th. However, the design flow exceeds only 10 months and does not meet AEPC criteria
if it is measured on either 1st or 30th of April.
1 -A pr
25
1 5 -A p r
3 0 -A p r
Q dive rted
20
Discharge (m 3/s)
15
10
0
1 2 3 4 5 6 7 8 9 10 11 12
M ONTH
Since the instantaneous and daily floods of 20-year return period are recommended to use while
designing Nepali micro hydro structures, the flood calculations methods recommended by this method are
used in the presented spreadsheet.
Page: 18
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Flood peak discharge, QF, for any other return periods can be calculated using:
QF = e
(lnQ 2 + S×s
lnQF
)
Where, S is the standard normal variant for the chosen return period, from Table 3.2, and
æ Q100 ö
ln çç ÷÷
slnQF = è Q2 ø
2.326
INPUT
INPUT OUTPUT
OUTPUT
Total
Total catchment
catchment area
area (MMF
(MMF &
& FDC)
FDC) *Mean
*Mean monthly
monthly flows
flows
Hydest
Hydest Flood
Area
Area below
below 5000m
5000m (LF)
(LF) Flood flows
flows (2-100
(2-100 yrs)
yrs)
Area
Area below
below 3000m
3000m (FF)
(FF) Low
Low flows(1,7,30
flows(1,7,30 &
& monthly)
monthly)
*Monsoon
*Monsoon wetness
wetness index
index (MMF
(MMF &
& FDC)
FDC) Flow
Flow duration
duration (0-100%)
(0-100%)
Monsoon
Monsoon wetness
wetness index=(Jun-Sept)
index=(Jun-Sept) mm
mm ** Area
Area =>100km
=>100km22
As shown in Figure 3.7, the Hydest method requires different catchment areas and monsoon wetness
index as inputs to estimate different hydrological parameters such as the mean monthly flows, floods, low
flows and flow duration curve. The hydrological parameters computed by this model are comparable to
the actual parameters for a total catchment area close to or more than 100km2.
1. Discharge measurement at the proposed intake site should be between November and May.
2. The recommended discharge measurement methods for different discharges are:
1. Bucket collection < Weir >Salt dilution
Page: 19
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Start
Yes Monthly
Hydrograph Q
Hydest
A 3000 Flood flows
End
A typical example of the spreadsheet including inputs and outputs are presented in Figure 3.9. The
information required for computations such as the MIP regions, etc., are included in the spreadsheet. The
MIP region map shows that this project lies in MIP region 3. The measured discharge of 80 l/s in March
23 shows that the project is proposed to utilize a small stream. Although the floods are not critical to the
project, they are calculated for sizing the floodwall and other structures. Although the estimated design
discharge is only 80 l/s, the probability of exceedance for this design discharge is only 10 months and
hence does not qualify AEPC acceptance criteria. For AEPC to qualify this project, the turbine design
discharge should not exceed 73.389 l/s. The procedures for the calculations are:
K March = 1.38
K April = 1.00
= 1.2787
Other mid monthly discharges are calculated similar to the discharge calculation for
the month of May.
Peak discharges for other return periods are calculated by using these formulas:
æ Q100 ö
ln çç
è Q2 ø
÷÷
QF = e
(lnQ 2 + S×s
lnQF
)
slnQF =
2.326
Different discharge calculations (as per AEPC criteria are presented for examples):
Qturbine = 85% of the 11 month flow exceedance from the MIP flow if the designed
flow is higher or the design flow.
= 73.389 l/s (since the design flow is higher and 10 month exceedance only)
= 77.252 l/s
A hydrograph including the design flow, exceedance of the proposed design flow and the flow acceptable
for AEPC is presented in Figure 3.9.
Page: 22
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
OUTPUT
Long Term Average Annual Hydrograph of Chhyota Khola river, Chhyota MHP
1800
1200
Discharge (l/s)
1000
800
600
400
200
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
MONTH
Page: 23
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
4 HEADWORKS
Headworks
A headworks consists of all structural components required for safe withdrawal of desired water from the
river into a canal/conduit. Intake, weir, protection works, etc., are the main structural components.
Indicators of an ideal headworks can be summarized as:
1. Withdrawal of the desired flow (i.e., Qdiverted and spilling in case of flood).
2. Sediment bypass of diversion structure (Continued sediment transportation along the river).
3. Debris bypass (Continued debris bypass without any accumulation).
4. Hazard flood bypass with minimum detrimental effects.
5. Sediment control at the intake by blocking/reducing sediment intake into the system).
6. Settling basin control (settling and flushing of finer sediments entered into the system through
intakes or open canals).
Intake
An intake can be defined as a structure that diverts water from river or other water course to a conveyance
system downstream of the intake. Side intake and bottom intake are the common types of river intakes
that are used in Nepali micro hydropower schemes.
Conveyance Intake is an intake which supplies water to a conveyance other than the pressure conduit to
the turbine. Power Intake is an intake which supplies water to the pressure conduit to the turbine.
Side Intake
A structure built along a river bank and in front of a canal / conduit end for diverting the required water
safely. Side intakes are simple, less expensive, easy to build and maintain.
Bottom/Drop/Tyrolean/Trench Intake
A structure built across and beneath a river for capturing water from the bed of the river and drops it
directly in to headrace. These are mainly useful for areas having less sediment movement, steeper
gradient, and surplus flow for continual flushing. Inaccessibility of trashrack throughout the monsoon
season and exposure of the system to all the bed load even though only a small part of the water is drawn
are the common problems/drawbacks of drop intakes.
Weir
A weir is a structure built across a river to raise the river water and store it for diverting a required flow
towards the intake.
Protection Works
Protection works are the river protection and river training works to safeguard the headworks against
floods, debris and sediments.
Trashrack
A structure placed at an intake mouth to prevent floating logs and boulders entering into headrace.
Coarse trashrack and fine trashrack are provided at the river intake and penstock intake respectively.
Page: 24
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
4.1.1 Weir
· Type: A weir can be either temporary or permanent in nature. A dry stone or gabion or mud stone
masonry can be termed as temporary weir whereas a cement masonry or concrete weir can be
termed as a permanent weir.
· Location: It is recommended that the weir should be 5m to 20m d/s of intake. This will assure that
water is always available and there is no sediment deposit in front of the intake. A narrow river
width with boulders is preferable for weir location.
· Height: The weir should be sufficiently high to create enough submergence and driving head.
· Stability: Permanent weir should be stable against sinking, overturning and sliding even during the
designed floods.
4.1.2 Intake
· Type: Side intake is suitable for all types of river categories whereas the drop intake is
recommended for rivers having longitudinal slopes more than 10%, less sediment and excess
flushing discharge. The side intake is generally is of rectangular orifice type with a minimum of
50mm submergence. The side intake should be at:
o Straight river u/s & d/s of the intake.
o Alternatively, on the outer side of the bend to minimize sediment problems and maximise
the assured supply of desired water.
o Relatively permanent river course.
o By the side of rock outcrops or large boulders for stability and strength.
· Capacity: According to the flushing requirement and tentative losses the intake has to be oversized
than the design flow by about 10% to 20% (or Qdiverted).
· A course trashrack should be provided to prevent big boulders and floating logs from entering into
the headrace canal.
· A gate/stop log should be provided to regulate flow (adjust/ close) during operation and
maintenance.
· To optimize the downstream canal and other structures, a spillway should be provided close to the
intake.
Since most of the program flow chart in this section is self explanatory or the calculation procedures are
familiar to most of the practicing stakeholders, only important points are explained.
Page: 25
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Figures 4.1 to 4.7 presents the assumptions, flow charts and typical examples for calculating trashrack
parameters, side intake and drop intake dimensioning.
Start
K = (hf + hb)/(Vo^2/2g)
Project name, location,
river, Trashrack coefficient kt
Bar thickness t mm Is Yes
Clear spacing of bars b mm cleaning K1=0.3
Approach velocity Vo m/s manual
The trashrack coefficients for different cross section of the bars are presented in the pull down menu.
Typical bar thickness, clear spacing and approach velocity are suggested in the respective cell notes.
It can be seen from the flow chart that the trashrack losses constitute of frictional and bend losses. The
frictional losses depend on the geometry of trashrack such as the trashrack coefficient, thickness and
clear spacing of bars, inclination of the trashrack and the approach velocity. The bend loss depends on
the hydraulics of the approaching flow such as the approach velocity and its deviated direction with
respect to the normal of the trashrack surface.
Page: 26
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
The trashrack surface area coefficient K1 for automatic racking is 0.8 whereas it is 0.3 for manual racking
suggesting that the racking area for manual operation to recommended surface area is 3.33 times more
than the theoretical area. Manual racking is recommended for Nepali MHPs. Since the consequence of
temporary reduced trashrack area in micro hydro is not severe and the trashrack sites are generally
accessible to operators all the year, the average of automatic and manual racking coefficient is taken for
practical and economic reason.
Flood
ht
A typical side intake parameters considered in the spreadsheet are presented in Figure 4.3. The design of
side intake parameters are presented in the flow chart in Figure 4.4. An example is presented in Figure
4.6. The design processes for the calculations of a typical side intake are also presented.
Trashrack Design:
Head losses,
h friction = kt * (t/b) (4/3) * (Vo 2/2g)* sin f
= 2.4*(4/25) (4/3) * (0. 5 2/2/9.81)* sin 60o
= 0.0023m
Page: 27
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Normal condition:
Depth @ canal (hc) = h submergence + height of orifice + height of orifice sill from bottom of
the canal
= 0.05+0.2+0.2
= 0.45m
Page: 28
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
h rf hr h sub h cf
River bed Gravel Flushing Gate hc Canal
hbot
Gravel trap (if needed)
1:30
Trashrack calculations
Input Output
Trashrack coeffieient kt 2.4 2.4
Bar thickness t mm 4.00 Headloss due to friction hf m 0.0023
Clear spacing of bars b mm 25.00 Headloss due to bends hb m 0.0044
Approach velocity Vo m/s 0.50 Headloss coeff K 0.5226
Angle of inclination from horizontal f deg 60.00 Total headloss ht m 0.0067
Flow deviation b deg 20.00 Surface area A surface m2 0.3750
Design Discharge Qd cumec 0.077 Vertical height h m 0.3647
Height of trashrack bottom from river bed ht 0.20 Trashrack width B m 0.89
Output
Normal Condition Flood
Canal witdth d/s of orifice 0.500 Critical depth of water at crest yc m 0.742
1/Slope of canal immediately d/s of orifice 1865 Flood head at river hf r = hw+yc m 1.406
Depth of water in canal hc m 0.450 Head difference dhf 0.916
Free board in canal h fb m 0.300 Velocity through orifice Vof m/s 2.544
Area of orifice A m2 0.064 Q intake Qf cumec 0.218
Width of orifice B m 0.321 Depth of water at canal (hc f) m 0.490
Actual velocity through orifice Vo act m/s 1.200
Canal width Wc m 0.500 Spillway
Water level difference dh m 0.115 Ls for Qf m (d/s Obs & 100% hot -50) 1.521
Water depth in the river hr = hc + dh m 0.565 Length of spillway Ls1 for Qf m (d/s Obs) 3.078
Height of weir (hw = hr+0.1) m 0.665 Length of spillway Ls2 for Qf-Qd m 3.978
Spillway overtopping height h overtop m 0.125 Designed spillway length Ls m 3.978
Figure 4.5: An example of side intake calculations
Page: 29
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Flood:
Critical depth at crest (yc)= (Qf2/L2/g)1/3
= (102/52/9.81)1/3
= 0.742 m
Water depth at canal during flood (by equating and iterating flow coming from orifice to that of
canal flow) (hcf) = 0.490m
The cell containing the depth of water at canal hcf (m) sometimes can generate VALUE# error. Should
such an error occur, select the cell, press F2 key and Enter respectively.
Care should be taken while designing spillway lengths. Ls for Gfm (d/s Obs & 100% hot -50) is only
applicable when full downstream obstruction for flood off-take is provided with the help of stop logs or
gates. Otherwise, the gradually varying water profile at the spillway has to be considered.
The example presented in Figure 4.7 follows the procedures presented in Figure 4.6. Although the
calculation procedures for the drop intake are relatively straight forward and simple, it has more
restrictions and limitations regarding the stream geometry and operational conditions.
Based on the flow conditions and the slope of rack the flow immediately upstream of the rack may be
either critical or sub-critical. Critical depth at the entrance of the rack has to be considered if the rack is
steeper (more than 15o). For more details, please refer to EWI UNIDO Standard.
The main differences for considering critical flow and normal flow condition are presented in the Table 4.1.
In the presented spreadsheet, the critical depth of the flow upstream of the intake is calculated and
presented if normal flow (sub-critical) is considered.
Page: 30
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
River Trashrack
Start
River W idth (Br) Aspect ratio (L across river/B along river)
Head of u/s water (ho) Design Discharge (Q)
U/s water velocity (vo) Gradient (b) deg, Contraction coeff (m)
River gradient (i) degrees W itdth/diameter (t), Clearance (a)
hof, vof
d = t + a, he = ho = vo^2/2g
X = =0.00008*b^2 - 0.0097*b + 0.9992
c =0.6*a/d*(COSb)^1.5
Yes h = ¾*Yc
Yc Considered?
Qo u/s = v (9.81 * ho 3 * Br 2 )
No Qof u/s = v (9.81 * hof 3 * Br 2 )
h =2/3*c*he
Qo u/s = Br * ho * vo
Qof u/s = Br * hof * vof
L =SQRT(3*Q/(2*c*m*L/B ratio*SQRT(2*9.81*h)))
L' = 120% of L, b = L/B ratio * L”, A=L'*b
Qu u/s = Qo u/s – Qdesign
h f = 2/3*c*(ho + vo f^2/2g)
End Q in f= 2/3*c*m*b*L'*SQRT(2*9.81*h f)
Quf d/s = Qof u/s of intake -Q in f
The calculations presented in Figure 4.7 are varified in the following section. In this example the flow
upstream of the intake is considered to be of critical.
Normal condition:
c/c distance of trashrack bars d (mm)
=t+a
= 60+30
= 90mm
Page: 31
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Bottom/Drop Intake
Gothi MHP
Output
c/c distance of trash rack bars d mm = 90 Area of intake (A=L' *b) m2 = 21.522
Total head (he) m = 0.340 Qo u/s of intake (m3/s) normal = 2.700
kappa (c) = 0.749 Qu d/s of intake (m3/s) normal = 0.000
velocity head (h) m = 0.170 h flood = 1.906
Correction factor ( c) = 0.146 Qof u/s of intake = Br * hof * vof (m3/s) = 325.497
Length of intake (L) m = 2.249 Q in flood m3/s = 10.855
Factored length (L' = 120% of L) m = 2.699 Quf d/s of intake (m 3/s) = 314.641
Intake length across the river (b) m = 7.975
Figure 4.7: An example of drop intake
Page: 32
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Flood:
h flood (hf) m = 2/3*c*(ho flood+vo flood^2/2g)
= 2/3*0.749*(3+4^2/2/9.81)
= 1.906 m
Page: 33
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
5 HEADRACE/TAILRACE
For computing head losses, Manning’s equation is used for canal whereas Darcy-Weisbach equation is
used for pipe.
5.2.1 Canal
a) Capacity: The canal should be able to carry the design flow with adequate freeboard, escapes to
discharge excess flow. A canal should generally be able to carry 110 to 120 % the design
discharge.
b) Velocity: Self cleaning but non erosive (≥ 0.3m/s).
c) Unlined canal: In stable ground and Q ≤ 30 l/s
d) Lined canal: 1:4 Stone masonry / Concrete (short: crossings or unstable ground). It is
recommended to minimize seepage loss and hence minimize the subsequent landslides.
e) Sufficient spillways and escapes as required.
f) Freeboard: Minimum of 300mm or half of water depth.
g) Stability and Safety against rock fall, landslide & storm runoff.
h) Optimum Canal Geometry: Rectangular or trapezoidal section for lined canal and trapezoidal
section for unlined canal are recommended.
5.2.2 Pipe
5.3.1 Canal
a) Permissible erosion free velocities for different soil conditions:
Fine sand =0.3-0.4
Sandy loam =0.4-0.6
Clayey loam=0.6-0.8
Clay =0.8-2.0
Stone masonry =0.8-2.0
Page: 34
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Concrete = 1.0-3.0
b) Sectional profiles:
Semicircular
Rectangular
Triangular
Trapezoidal
The calculations presented in Figure 5.4 are briefly described in the following section. The rectangular
intake canal is considered for the illustration.
Present Canal:
2
Area A m = D*B
= 0.3*0.5
= 0.15 m2
Page: 35
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Start
W etted perimeter (P)
Project name, Reach name, Semicircular = PI()* D/2
Design discharge (Qd) Trapezoidal = B+2*D*sqrt(1+N^2)
Roughness coefficient (n) Rectangular =2* D+B
Side slope (N) Triangular = 2*D*sqrt(1+N^2)
Sectional profile
Ao = Qd/Vo,
T=B+2*D*N (trapezoidal) or =B
Vcrit = sqrt(9.81*Ao/T)
V desired=80% of Vcrit,
Ho = Do + FBo
Channel width Bo
Semicircular = 2*Do hl =S*L+di
Rectangular = 4*ro Hl =hl previous + hl End
Traingular = 5.7*ro d crit =11000*r*S
Trapezoidal = 4*ro/Sin(N)
Optimum Canal:
2
Area A m = Q/v desired
= 0.185/1
= 0.185 m2
Page: 36
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Input
Type and Name Intake Canal Tailrace Main2 Main3
Flow (m3/s) 0.185 0.145 0.145 0.145
Roughness coefficient (n) 0.02
0.02 0.017
0.017 0.02
0.02 0.02
0.02
Sectional Profile Rectangular Trapezoidal Semicircular Triangular
Side slope N (1V:NHorizontal) 00 0.5
0.5 00 0.5
0.5
Length of the canal (m) 20 40 150 120
1/Canal slope (s) 77 200 30 72
Channel Depth/diameter D (m) 0.300 0.525 0.300 0.300
Freeboard FB (m) 0.300 0.250 0.150 0.150
Channel Width (B) m 0.500 1.000 0.400 0.400
Channel Drops di m 0.000 0.000 0.000 0.000
Channel Drops Horizontal length hi m 0.000 0.000 0.000 0.000
Desired velocity Vo (m/s) 1.000 1.500 1.500 1.500
Output
Side slope d (degrees) 0.000 63.435 0.000 63.435
Canal slope S 0.01299 0.00500 0.03333 0.01389
Total depth H (m) 0.600 0.775 0.450 0.450
Chainage L (m) 20.000 60.000 210.000 330.000
Page: 37
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Present canal
Area A m2 0.150 0.663 0.035 0.060
Top Width T (m) 0.500 1.525 0.400 0.400
Wetted Perimeter P (m) 1.100 2.174 0.471 0.671
Hydraulic Radius r (m) 0.136 0.305 0.075 0.089
3
Calculated flow (m /s) 0.226 1.249 low 0.057 low 0.071
Comment on freeboard ok low ok ok
Velocity V m/s 1.233 0.219 4.103 2.417
Critical Velocity Vc m/s & Remarks 1.72 Ok 2.06 Ok 0.93 Not Ok 1.21 Not Ok
Headloss hl (m) 0.260 0.200 5.000 1.667
Total headloss Hl(m) 0.260 0.460 5.460 7.126
Critical dia of sediment d crit (mm) 19.481 16.769 27.500 13.665
Optimum canal
Area Ao m2 0.1850 0.0967 0.0967 0.0967
Top Width T (m) 0.6022 0.7636 0.9949 0.4867
Critical Velocity Vc m/s & Remarks 1.74 Ok 1.11 Not Ok 0.98 Not Ok 1.4 Not Ok
Hydraulic Radius ro (m) 0.1505 0.1180 0.1244 0.1088
Channel Depth/diameter Do (m) 0.301 0.236 0.497 0.218
Freeboard Fbo (m) 0.150 0.263 0.150 0.150
Total depth Ho (m) 0.451 0.498 0.647 0.368
Channel Width Bo (m) 0.602 0.528 0.995 0.487
Canal Slope 0.0050 0.0112 0.0145 0.0173
Headloss hlo (m) 0.100 0.449 2.175 2.079
Total headloss Hlo(m) 0.100 0.549 2.724 4.803
Critical dia of sediment d crito (mm) 8.271 14.584 19.834 20.736
Figure 5.2: An example of canal design.
B = 1& 0.764
Page: 38
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
5.3.2 Pipe
The headrace pipe calculations presented in Figure 5.7 are briefly described in the following section. The
trashrack calculations are similar to the trashrack calculations presented earlier in the intake design,
hence it is not presented in this section. In this example, one HDPE pipe is considered for a design flow of
160 l/s each.
k 0.06 mm
= = 0.000231
d 260 mm
1.2Q 1.2 x0.160
= = 0.73846
d 0.260
From Moody chart (Appendix), f=0.0153. In the spreadsheet program, this friction factor is
calculated by the method described in Layman’s Guidebook on how to develop a small
hydro site, ESHA. In this method f is calculated by iterating following equations:
l V2
Friction loss = f
d 2g
fl 0.08Q 2 0.0153 x140 x0.08 x0.160 2
hwall loss = = = 3.82 m
d5 0.260 5
Turbulent losses considering, Kentrance= 0.8, Kexit=1.0 and Kbends based on the bending angles (see
Table in the Appendix)
æ 1.5V 2 ö 3.012
\ hturbulentlosses = (K entrance + K bends + K valve + K others + K exit )çç ÷÷ = 1.5 * = 0.69m
è 2g ø 2 x9.81
Design water level in Gravel trap is 4.53 m (i.e. 22.66% of the available head) below low river level at
intake. This is a headrace pipe conveying water from intake to the break pressure tank, therefore
headloss more than this may be acceptable if the pipe material is mild steel. The HDPE pipe does not
need expansion joints and therefore not calculated.
Page: 39
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Start
End
Figure 5.4: Flow chart for pipe design
INPUT
General:
Project: Chhyota MHP
Location: Dolakha Economic life (years) 15
Hydraulics:
Diversion flow Qd (m3/s) 0.110 U/S Invert Level (m) 1200.00
Flow in each pipe Qi (m3/s) 0.110 % head available or headloss hlt (m) 5.00%
Gross headHg (m) 5.000 Entrance Type Slightly rounded 0.2
Bending radius (r/d) 5 0.3
Headrace pipe
Pipe Material PVC Exit (Yes/No) Yes
Welded / Flat rolled if steel Welded No of pipes 1.00
Rolled if steel Rolled Bending angle 01 20.00
Type if steel IS Bending angle 02 4.00
Burried or exposed Burried Bending angle 03 6.00
Type of valve Gate 0.1 Bending angle 04 20.00
Non standard ultimate tensile strength (UTS) N/mm2 0 Bending angle 05 0
Estimated pipe diameter d(mm) 245 Bending angle 06 0.00
Provided pipe diameter d(mm) 400 Bending angle 07
Min pipe thickness t (mm) NA Bending angle 08
Provided pipe thickness t (mm) 3.0 Bending angle 09
Pipe Length L (m) 100.000 Bending angle 10
Trashrack
Flat k t b Vo f b Q H
2.40 6.00 20.00 1.00 60.00 0.00 0.110 3.00
Expansion Joints
Tmax (deg) T installation Tmin 1st Pipe length(m) 2nd Pipe L (m) 3rd Pipe L (m) 4th Pipe L (m) 5th Pipe L (m)
40 20 4 50.00 100.00 150.00 200.00 250.00
Page: 40
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
OUTPUT
Trashrack
hf hb H coeff H S B Min Submergence CGL=1.5v^2/2g
0.0213 0.0000 0.4174 0.0213 0.5504 0.16 0.81 0.06
Hydraulics
Pipe Area A (m2) 0.126 U/S Invert Level (mAOD) 1200.000
Hydraulic Radius R (m) 0.10 D/S Invert Level (mAOD) 1195.000
Velocity V (m/s) 0.88 Is HL tot < HL available OKAY
Relative Roughness ks/d 2.500E-05 Friction Losses hf (m) 0.14
Reynolds Number Re = d V /Vk 307018 Fitting Losses hfit (m) 0.07
Type of Flow Turbulent Trashracks and intake loss (m) 0.02
Friction Factor f 0.0147 Total Head Loss htot individual (m) 0.23
% of H.Loss of individual pipe 4.62% Ok
Expansion Joints (mm) Coeff of linear expansion /deg C 5.4E-05
EJ number 1 2 2 4 5
dL theoretical 97 194 292 389 486
dL recommended 194 389 583 778 972
dL for expansion 108 216 324 432 540
dL for contraction 86 173 259 346 432
Page: 41
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
6 SETTLING BASINS
According to the location and function the settling basin can be of following types:
1. Gravel Trap for settling particles of 2mm diameter or bigger.
2. Settling Basin for settling particles of 0.2mm diameter or bigger.
3. Forebay for settling similar to settling basin (optional) and smooth flow transition from open to
closed flow.
Micro hydro settling basins are generally made of stone masonry or concrete with necessary accessories
such as spillways, flushing gates, trashracks, etc., as and where necessary. However, functionally, all the
settling basins should have following components:
1. Inlet Zone: Gradual expansion.
2. Settling Zone: Settling, deposition, spilling and flushing (and trashrack removal).
3. Outlet Zone: Gradual contraction.
A typical section of a settling basin with all the components (inlet, transition, storage and outlet zones) and
accessories (spillway, gate) is presented in Figure 6.1.
Page: 42
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
a) H/W = L/V => Q/W = L*B = Surface area (i.e., the surface area is directly proportional to
the discharge and inversely proportional to the settling velocity/sediment
diameter/temperature).
As stated earlier a real basin is never ideal and the efficiency of an ideal basin is generally 2 times higher
than that of a real basin. This is mainly because of the following factors:
1. Presence of water turbulence in basin.
2. Imperfect flow distribution at entrance.
3. Flow convergence towards exit.
Vetter’s Equation takes care of the factors stated above and hence recommended for use in settling basin
design.
Page: 43
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
6.3.3 Forebay
While designing forebay, AEPC has outlined following points:
1. Dimensions and functions: Similar to SB if u/s is open canal or combined SB+FB.
2. Submergence: Sufficient to prevent vortex (ie 1.5 * v2/2g).
3. Active Storage: 15 sec * Qd.
4. Freeboard: 300mm or half the water depth whichever is less.
5. Drawdown: A drain pipe/Gate.
6. Spilling capacity: Minimum of spilling Qd (load rejection)
7. Fine Trashrack:
a. At the entrance of the penstock
b. Inclination: 3V:1H
c. Bars: Placed along vertical direction (ease of racking).
d. Clearance: 0.5 * nozzle diameter (Pelton) or half the distance between runner blade
(Crossflow)
e. Velocity: 0.6 to 1m/s
f. Weight: =< 60kg (porter load)
Page: 44
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
b. Vetter’s equation
3. Flushing of deposited sediment during:
a. Normal operational hour
b. Drawn-down condition
4. Sediment flushing with:
a. Vertical flushing pipe
b. Gate
c. Combination of both
5. Spilling of excess flow due to:
a. Incoming flood
b. Load rejection
6. Spilling of excess flow with
a. Spillway
b. Vertical flushing pipe
c. Combination of both
7. Drawdown / Dewatering with:
a. Vertical flushing pipe
b. Gate
8. Rating curve for the gate: The rating curve computation is based on Norwegian Rules and
Regulations of Dam Construction. According to this manual, the flow is of free flow until the gate
opening is two third of the water depth behind the gate. Beyond this level (i.e., the gate opening
hither than 2/3 of the water depth behind the gate), the flow is a pressure flow.
9. Multiple basins
10. Combination of approach canal / pipe options
2. Drawdown / Dewatering
1.5*Qd =C*A*(hb+fflush) 0.5: A=p*d212/4: C=2.76 for L=<6m
d21=(6*Qd/( p *C *( hb+fflush)0.5 )0.5 @ full
d22=(4*Qd/( p *C *( fflush)0.5 )0.5 @ empty
6.4.4 Gate
Lifting force F(kg)=W buoyant + 1000*m*Asub*hcg
Gate opening dh=h1-h2
Page: 45
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Discharge per basin Qbasin (m3/s) = 0.455 Water depth of inlet canal hc1 (m) = 0.50
Max section width for hydraulic flushing B (m) = 3.258 Outlet canal width /canal diameter Bc2 (m) = 0.50
Width used B (m) = 2.500 Water depth of outlet canal hc2 (m) = 0.30
Inlet canal width /canal diameter Bc1 (m) = 1.000 Provided Length of the basin Lact (m)= 0.00
Page: 46
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Length of basin L (m) = 10.000 Pipe does not need a straight approach! ***
Aspect ratio (4<=AR<=15) 4.000 Head over outlet weir h overtop (m) = 0.23
Min. water depth Hi (m) = 0.755 Approach inlet velocity vi1 (m/s) = 0.91
X-sectional area / basin Ai (m2) = 1.888 Approach outlet velocity vi2 (m/s) = 3.03
Wetted perimeter / basin Pi (m) = 4.010 1/Energy gradient during operation So = 15763.86
Hydraulic radius Ri (m) = 0.471 d 50 during operation (mm) = 0.33
Normal WL @ basin h b m = 1.360 Depth of water during flushing yfi (m) = 0.12
Straight inlet transition length at 1:5 (m) = 3.750 d 50f during flushing (mm) = 49.32
Straight approach canal length (m) = 10.000 Length of an Ideal Basin (m) = 10.00
Spillway
Freeboard m 0.300 Spillway length for Qd (under operation) 6.43
Spillway overtopping height h overtop m 0.125 Spillway length for Qd (load rejection & u/s flood bypass) 6.43
Spillway length for Qf (flood and non operational) 0.000 Spillway length for Qd (d/s obstruction & full hovertop-50) 3.18
Combination of vertical flushing pipe and spillway Flood and non operational (Qf)
Vertical flushing pipe diameter d1 m 0.30 Flood discharge passing through vertical pipe 0.000
No of vertical flushing pipe 1.00 Spillway length for the remaining discharge m 1.00
Spillway length used (m) 1.00
Figure 6.5: Typical example of a settling basin (Settling basin, spilling and flushing).
Figure 6.6: Typical example of a settling basin (Gate and rating curve).
Page: 47
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
The headrace pipe calculations presented in Figure 6.6 are briefly described in the following section.
a. Vetter’s equation
Surface area of basin = -(Qtotal)/w*LN(1-neff)
Asi = -(0.455)/.035* LN(1-neff)
2
= 25 m
Page: 48
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
2. Spilling of excess flow due to load rejection: A combination of a 0.3m diameter vertical pipe and
spillway of 1.0m length is used.
H overtopping = h ot =(Q1/(1.9*PI()*n1*d1+Cd*Ls))^(2/3)
= (0.455/(1.9*pi()*1*.3+1.6*1))^(2/3)
= 0.262 m
3. Flushing of deposited sediment through the flushing pipe: The pipe diameter will be the biggest of :
In the second case the depth of water during flushing yfi may be added to h flush for higher precision.
This is not considered here. The recommended minimum diameter of the flushing pipe diameter is 0.4 m.
The gate curve in the example presented in Figure 6.6 includes the gate dimensions, forces and the rating
curve. The rating curve of the gate versus different gate opening can be computed by entering the
allowable gate opening at the lowest input cell and clicking “Calculate Gate Rating Curve” button.
The last part the spreadsheet can be used if the considered basin is a settling basin cum forebay. The
basic penstock inlet geometry is computed in this section.
Page: 49
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
1. Material: Mild steel (exposed and buried) and HDPE (buried) pipes are widely used as penstocks for
micro hydro schemes in Nepal.
2. For exposed (i.e., above ground) mild steel penstock alignment, a minimum clearance of 300 mm
between the pipe and the ground should be provided for maintenance and to minimise corrosion
effects.
3. In case of buried HDPE pipes, they should be buried to a minimum depth of 1 m. Similarly, if mild steel
penstock pipes have to be buried, a minimum of 1 m burial depth should be maintained and corrosion
protection measures such as high quality bituminous/epoxy paints should be applied. Due to higher
risks of leakage, flange connected penstocks are not recommended to be buried.
4. The recommended initial trail internal diameter (D) can be calculated as:
D = 41 x Q 0.38 mm
Where, Q = Design flow in l/s
5. Total penstock headloss should be limited to 10% of the penstock gross head.
6. Anchor / Thrust block at every horizontal and vertical bends and for every 30m of straight pipe stretch.
7. Expansion joints should be placed immediately downstream of every anchor block for exposed mild
steel penstock.
8. Mechanical coupling of last penstock upstream of the turbine is recommended for ease of
maintenance and lesser force distribution to the turbine casing..
Power based on the AEPC criteria and actual power generation based on the actual cumulative efficiency
of the electro-mechanical are also presented.
Since a provision of maximum of ten bends is generally sufficient for a typical micro hydropower scheme,
ten bends are incorporated. However, users can add any cumulative values if there are more than ten
bends or other losses due to turbulence in the “K others” cells.
A fine trashrack is always recommended upstream of penstock inlet. A trashrack calculation is also
included with the minimum submergence criteria by Gordon and AEPC criteria. AEPC criterion of 150% of
the velocity head is enough for micro hydropower project up to 100kW.
User specific factor of safety and ultimate tensile strength are allowed in the spreadsheet.
Page: 50
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
The friction factor calculation is based on the iteration procedures described in the Layman’s Guidebook
on how to develop a small hydro site by European Small Hydropower Association.
Design and installation criteria of expansion joints are presented at the end of the spreadsheet.
Start
End
Figure 7.1: Flow diagram of penstock design
Pipe thickness:
It is worth noting that in reality the diameter of penstock pipe is optimized by calculating marginal
costs and benefit method. In this method, the incremental cost of annual energy by increasing the
pipe diameters and corresponding increase of costs are plotted. The intersecting point reflects the
cost of optimum diameter. Alternatively, net present values of these cash/cost flow can be
calculated and the net present value (NPV) of marginal benefit from energy gain should be higher
than that of the marginal cost of that diameter.
Let’s consider 4mm thick 300mm diameter pipe, the wave velocity
1440 1440
a= = = 1071.454 m / s
æ 2.1 x10 9 x d ö æ ö
1 + çç ÷÷ ç 2.1 x 10 9 x 0.300 ÷
è E xt ø 1+ ç ÷
ç 9 4 ÷
ç 200 x 10 x ÷
è 1000 ø
hsurge = a * V/(g*njet)
= 1071.454*2.12/(9.81*2)
= 115.84m
Page: 51
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
= 69+115.84
= 184.84 m
Based on the American Society of Mechanical Engineers (ASME) formula, the allowable thickness
is 4.00 mm. The static head for 3mm thick penstock of same diameter can be calculated by similar
procedures and found to be 57.91m. This can be found by decreasing the pipe thickness (and
diameter too) and noting the value corresponding to “H static capacity of the specified pipe (m)”.
The lower portion of the pipe corresponding to the static head of 69-57.91 = 11.09 m should be of
4mm thick 300 diameter pipe. The summary of the output is presented in Figure 7.3.
INPUT
General:
Project: Gothi MHP
Location: Gothi Village, Gothi VDC, Humla Economic life (years) 15
Hydraulics:
Diversion flow Qd (m3/s) 0.150 WL @ forebay or U/S Invert Level (m) 1920.00
Flow in each pipe Qi (m3/s) 0.150 % head headloss hlt (m) 16.00%
Gross head (from forebay) Hg (m) 69.00 Cumulative knowm efficiency (g,t,tr,others) 79.38%
Power:
Turbine type (CROSSFLOW/PELTON) Pelton Valves (Sperical/Gate/Butterfly) Butterfly 0.3
No of total jets (nj) 2 Taper (Yes/No) No
Direct Coupling (Yes/No) No Exit (Yes/No) No
Closure time T sec 30 Non standard ult. tensile strength (UTS) N/mm2 0
Number of units 1
Penstock pipe:
Pipe Material (STEEL/HDPE/PVC) Steel Safety factor for lower pipes (0 for default) 3
Welded / Flat rolled if steel Welded Entrance Type Slightly rounded0.2
Rolled if steel Rolled Entrance with gate and air-vent (Yes/No) No
Type if steel (UNGRAGED/IS) IS Bending radius (r/d) (1/2/3/5/1.5) 1.5 0.45
Burried or exposed Exposed Bending angle 05 22
No of pipes 1.00 Bending angle 06 14.00
Bending angle 01(degrees) 27.00 Bending angle 07 38.00
Bending angle 02 11.00 Bending angle 08 22.00
Bending angle 03 4.00 Bending angle 09 47.00
Bending angle 04 11.00 Bending angle 10 50.00
Penstock diameter d=>d estd, d act (mm) 275 300 Pipe thickness t=>t min, t act (mm) 3.0 4.0
Pipe Length L (m) 121.000 Roughness coefficient (ks) 0.060
Trashrack
k t b Vo f b Q H
0.00 6.00 20.00 1.00 71.56 0.00 0.150 0.70
Expansion Joints
Tmax (deg) T installation Tmin 1st Pipe length(m) 2nd Pipe L (m) 3rd Pipe L (m) 4th Pipe L (m) 5th Pipe L (m)
40 20 4 10.00 15.00 20.00 25.00 30.00
Page: 52
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
OUTPUT
Trashrack
hf hb H coeff H S B Min Subm ergence CGL=1.5v^2/2g
Hydraulics
Pipe Area A (m 2) 0.071 U/S Invert Level (mAOD) 1920.00
Hydraulic Radius R (m) 0.08 D/S Invert Level (mAOD) 1851.00
Velocity V (m/s) 2.12 Is HLtot < HL available OKAY
Pipe Roughness ks (mm) 0.060 Friction Losses hf (m) 1.41
Relative Roughness ks/d 2.000E-04 Fitting Losses hfit (m) 0.65
Reynolds Number Re = d V /Vk 558214 Trashracks and intake loss (m) 0.00
Type of Flow Turbulent Total Head Loss htot individual (m) 2.06
Friction Factor f 0.0153 % of H.Loss of individual pipe 2.99% Ok
Factor of Safety
Young's modulus of elasticity E N/mm 2 200000 Ultimate tensile strength (UTS) N/mm2 410
Thickness 4.000 H total for one jet closure of Pelton(m) 184.84
Diameter (mm) 300.000 t effective (mm) 2.03
Net Head (m) 66.940 Minimum t effictive for negative pressure (mm) 3.14
Wave Velocity a (m/s) 1071.454 Comment on thickness NA, No gate
Critical time Tc (sec) *2 = Closing time T 0.23 Ok Safety Factor (S) 3.00
K if crossflow turbine Kcf 0.00000 Check on Safety Factor Ok
Hsurge for one jet closure of Pelton(m) 115.840 Air vent diameter d vent (mm) 43.65
Hsurge for instanteneous closure of all unit closure of Pelton (m) 231.680 H total capacity of the specified pipe (m) 184.98
Lengths (max & actual) of the specified pipe (m) & Ok 155.120 121.000 H static capacity of the specified pipe (m) 88.46
Power
Turbine efficiency as per MGSP 75.00% Electrical Power as per MGSP GL (kW) 50.77
Available shaft power(kW) 70.18 Electrical Power based on Hnet (kW) 59.10
Reqd.'Turbine Capacity (+10%) (kW) 77.20 Power for known cumulative eff (kW) 78.19
Page: 53
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
8 TURBINE SELECTION
A turbine converts potential energy of water to rotational mechanical energy. Cross-flow and Pelton
turbines are the most commonly used turbines in Nepali micro hydropower plants. The size and type of
turbine for a particular site depends on the net head and the design flow. Pelton turbines are suitable
where the ratio of head to flow is high whereas Cross-flow turbines are suitable for high flow and low head
schemes. It should be noted that for certain head and flow ranges both Pelton (multi-jet) and Cross-flow
turbines may be appropriate. In such cases, the designer should consult with the manufacturer and make
a decision based on availability, efficiency and costs. On a horizontal shaft Pelton turbine the maximum
number of jets should be limited to 3 for ease of manufacturing. The number of jets can be higher for
vertical shaft Pelton turbines. However, these require higher precision work in mounting the generator
vertically on the turbine shaft and furthermore, in case of varying rotational speeds (RPM of the turbine
and the generator), the belt drive arrangements (including those for mechanically coupled end uses) will
be difficult.
The type of turbine can be determined by its specific speed given by the following equation:
The only unknown in the above equation is the turbine rotational speed (N). This depends on the RPM of
the generator and the drive system used (e.g., direct or belt drive). The specific speed of a multi-jet Pelton
turbine can be computed by multiplying the above ns by the square root of the number of jets. Because of
higher efficiency both in overall and part load, preference should be given to Pelton turbines. If ns exceeds
the range given in Table 8.2, multiple units should be used.
Page: 54
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Specific speed of multi-jet Pelton is computed by multiplying the specific speed of runner by the
square root of the number of the jets. The calculations show that for the given parameters in the
context of micro hydro plants in Nepal, either a gearless Crossflow turbine or a Pelton/Crossflow
with a gear ratio of 1:2 is recommended.
Turbine Selection
Chhota MHP
Input
Discharge (l/s) 150 Gear ratio at turbine 1
Gross head (m) 69 Gear ratio at generator 2
Hydraulic losses 15.94% No of turbines/generators 1
Max turbine output kW 67.89 Total number of jets if Pelton n 2
Turbine rpm 750
Output
Net head m 58.000 Generator with gearing rpm 1500
Page: 55
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Load controllers are generally used as the governing system in Nepali micro hydro schemes. An
Electronic Load Controller (ELC) is used for controlling the power output of a synchronous generator. To
control an induction generator an Induction Generator Controller (IGC) is used.
Synchronous Generator
Advantages of Synchronous Generator:
· High quality electrical output.
· Higher efficiency.
· Can start larger motors.
Based on the above assumptions, the general guidelines for selection of phase and type of generator are
prepared and summarized in Table 9.1.
Page: 56
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Factors affecting the size of the generator are temperature, altitude, electronic load controller correction
factor and power factor of the load. De-rating coefficients to allow for the above-mentioned factors are
presented in the Table 9.2.
Table 9.2: Generator rating factors
Max. Ambient
20 25 30 35 40 45 50 55
temperature in oC
A Temperature Factor 1.10 1.08 1.06 1.03 1.00 0.96 0.92 0.88
Where, A, B, C and D are correction factors from Table 9.2, and 1.3 is the overrating factor (up to
30% recommended) to allow for:
i) Unexpected higher power from turbine.
ii) Handling the starting current if large motors (> 10% of generator size) are supplied from the
generator.
iii) The generator running at full load when using an ELC.
3 The synchronous rotational speed:
120 f
Rotational speed ( N ) = RPM
P
Where, RPM is revolutions per minute
f is the frequency of the system in Hertz (Hz) (50 Hz in Asia and Europe)
P is the number of poles of the generator (2, 4, 6, etc., in pairs). P for Nepali MHP is
generally 4 so that the rotational speed is 1500 RPM.
Page: 57
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
120 f
Rotational speed ( Ni ) = (1 + s )RPM
P
Where,
Ns - Nr
P and f are as same as for synchronous generator and s =
Ns
Where,
s is the slip of the generator
120 f
Ns is the synchronous speed, i.e. Ns = RPM
P
Nr is the rated rotor speed of the induction motor and Ni always exceeds Ns
while acting as a generator.
Page: 58
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
V (V) = Rated Voltage of the motor (V) (phase to phase voltage 380/400/415)
Im (A) = Magnetizing Current = I rated at full load current (A) * sin (cos-1 (power factor))
I rated at full load current = Rated power (kW) * 1000/(V*pf)
hm = rated efficiency of motor at full load
For star connected capacitors, the excitation capacitance is three times that for the Delta
connection.
Where,
1.25 = overrating factor by 25%.
Pe (kW)= Installed capacity
V (V) = Rated phase to neutral Voltage (V) (V*√3 for 3-phase)
pf = power factor if induction generator is used
Where,
1.70 = overrating factor by 70%.
I (A) = Current = Generator size/(V *pf if induction generator is used)
V (V) = Rated phase to neutral Voltage (V) (V*√3 for 3-phase)
pf = power factor
INPUT
Discharge (m3/s) 0.204 Power factor 0.8
Gross head (m) 60.000 Safety factor of generator 1.3
Overall plant efficiency (%) 50% Phase 3-phase 3
Temperature (oC) 45 Type of Generator Synchrono 1
Altitude (m) 1500 Over rating factor of MCCB 1.25
ELC correction factor 0.83 Over rating factor of cable 1.5
Frequency of the system (Hz) 50 No. of poles 4
Capacity of used generator (kVA) 0 Rated rotor speed if induction generator N (rpm) 0
Delta 89%
OUTPUT
Pe Electrical output (active power) (kW) 60.04 Ok
Generator
Temp.factor 0.96 Altitude factor 0.96
Capacity (kVA) 127.70 Actual available capacity (kVA) 140.00
Synchronous rotational speed Ns (rpm) 1500
ELC capacity (kW) 60.04 Calculated Ballast capacity 1.2*Pe (kW) 72.04
Ballast capacity of ELC-Extention (kW) 67.24
Rated Voltage (V) 400 I rated for Cable & MCCB (A) at Generator side 202.08
Cable
Rating (A) 303.12 Size of 4-core cupper armoured cables 185
Figure 9.1: Electrical components of a 20kW 3-phase synchronous generator.
Page: 59
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
120 f
Rotational speed ( N ) = RPM
P
=120*50/4
= 1500 rpm
Since Pe > 50kW, the ballast capacity of ELC extension (kW) = 60% * 1.2 * Pe + 40% * Pe
= 0.6*1.2*60.04 + 0.4*60.04
= 67.24 kW
I rated for Cable & MCCB at Generator side = 1000/ V rated * Generator size /1.732
= 1000 / 400*140/1.732
= 202.08 Amp
For this current a 4-core copper armoured cable of ASCR 185mm2 is chosen.
Since the electrical output is more than 10kW, a reminder error is flagged in the adjacent cell.
= 1.3*20/(0.96*0.96)
= 28.25 kW
Page: 60
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
120 f
Rotational speed ( N ) = RPM
P
=120*50/4
= 1500 rpm
INPUT
Discharge (m3/s) 0.08 Power factor 0.8
Gross head (m) 50.968 Safety factor of generator 1.3
Overall plant efficiency (%) 50% Phase 1-phase 1
Temperature (oC) 45 Type of Generator Induction 2
Altitude (m) 1500 Over rating factor of MCCB 1.25
ELC correction factor 0.83 Over rating factor of cable 1.5
Frequency of the system (Hz) 50 No. of poles 4
Capacity of used generator (kW) 0 Rated rotor speed if induction generator N (rpm) 1450
Capacitor configuration Delta Efficiency of motor at full load 89%
OUTPUT
Pe Electrical output (active power) (kW) 20.00 Use of 3-phase generator is mandatory
Generator
Temp.factor 0.96 Altitude factor 0.96
Capacity (kW) 28.25 Actual available capacity (kW) 30.00
Synchronous rotational speed Ns (rpm) 1500 Rotational speed of the generator (rpm) 1550
IGC capacity (kW) 20.00 Calculated Ballast capacity 1.2*Pe (kW) 24.00
Excitation Capacitance (micro F) 123.16
Rated Voltage (V) 220 Irated for Cable & MCCB (A) at Generator side 170.45
Cable
Rating (A) 255.68 Size of 2-core cupper armoured cables 150
Figure 9.2: Electrical components of a 20kW 1-phase induction generator.
Excitation capacitance
1000*Pe* sin (cos-1 (power factor))
C (цF) = -----------------------------------------------------
3*V2*pf*2*pi()*f*hm
= 123.16 цF
Page: 61
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
I rated for Cable & MCCB at Generator side = 1000/ V rated * Generator size /pf
= 1000 / 220*30/0.8
= 170.45 Amp
For this current a 2-core copper armoured cable of ASCR 185mm2 is chosen.
Page: 62
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
7 ASCR Specifications:
Current
ACSR rating Equivalent Sp.
Code Type of Resistance max Cu area Impedance Weight Sp. Cost
2
number ACSR Ohm/km Amps mm Ohm/km (kg/km) (Rs/km)
1 Squirrel 1.374 76 13 0.3013 80 13000
2 Gopher 1.098 85 16 0.294 106 14500
3 Weasel 0.9116 95 20 0.288 128 15500
4 Rabbit 0.5449 135 30 0.2723 214 25750
5 Otter 0.3434 185 50 0.257
6 Dog 0.2745 205 65 0.25 394 52000
Start
Length Current
Length of cables of Voltage drop Resistance
Cost of cables neutral Voltage at node Reactance
cables Impedance
End
The grid and load presented in Figure 10.2 are used for the calculations presented in Figure 10.3.
Page: 64
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Node/Load (kW)
Transformer # 1
Figure 10.2: Transmission line and load used for the example.
Page: 65
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Pow er at
Vrated @
Reach next node &
Reach Length Phase node ACSR Current
Node name name (km) 1,3,11 (kW) type (A)
PH-A-B-C-D 3 400.00
PH A PHA 0.450 3 16 Dog 28.87
A B AB 0.660 1 5 Rabbit 27.64
C AC 0.090 1 5 Rabbit 30.65
D AD 0.090 1 6 Rabbit 33.68
PH-T1 3 400.00
PH T1 PHT1 0.050 3 20 Otter 36.08
T1-T2 11 11000.00
T1 T2 T1 T2 1.500 11 20 Squirrel 1.31
T2-E 3 400.00
T2 E T2 E 0.300 3 20 Dog 36.08
E-J ( r ) 1 226.90
T2 J T2 J 0.300 1 20 Dog 110.18
E-M ( r) 1 226.90
E F EF 0.300 1 1 Squirrel 5.51
F M FM 0.600 1 1 Squirrel 5.62
F-L(b) 1 212.80
F L FL 0.180 1 1 Squirrel 5.87
Page: 66
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Total length of cables (km) 7.02 0.00 10.00 2.68 1.55 2.85
Length of neutral cables (km) 10
Cost of cables(Rs.) 517720.00
Reach
Voltage Volt at node % voltag
drop (V) branch (V) drop Squirrel Gopher Weasel Rabbiit Otter Dog
400.00
8.40 391.60 2.10 1.35
22.20 203.89 13.45 1.32
3.40 222.69 3.18 0.18
3.70 222.39 3.31 0.18
400.00
1.30 398.70 0.32 0.15
11000.00
4.70 10995.30 0.04 4.50
400.00
7.00 393.00 1.75 0.90
226.90
24.50 202.40 12.00 0.60
226.90
8.50 218.40 5.04 0.60
9.80 208.60 14.35 0.80
226.90
14.10 212.80 7.48 0.60
7.20 205.60 18.09 0.40
226.90
4.60 222.30 3.35 0.60
9.30 213.00 10.74 1.20
218.40
5.70 212.70 7.52 0.36
212.80
2.90 209.90 8.74 0.36
Figure 10. 3: Typical example of a low voltage transmission line.
Page: 67
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Start
Annual energy
24 hr load
Yearly loads
Load duration
EU factors
Graph (decision making)
Yearly income
End
Figure 11.1: Flow chart of the load and benefits calculation spreadsheet.
Page: 68
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
INPUT
General
Power Output (kW) 96.1 Domestic lighting
Name of the Source Gadi Gad Khola Average subscription/household (W/HH) 80
Location Ladagada VDC, Doti System loss 10%
Beneficiary HH (nos.) 1035 time 0 5 8 18 20
Plant's operating days330 load 91.08 0 0 91.1 0
Summary
Annual Available kWh 761112
First 3 years After 3 years
Yearly load (kWh) 117060 147680
Productive end use load factor (%) 15.38 19.40
Annual total (domestic + end uses) Income (Rs) 1,429,230 1,612,950
90
120
80
100
70
60
80
50
60
40
30
40
20
20
10
0 0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
T i me (hr s)
Domestic Agro-processing Bakery Saw Mill Herbs Processing load 5 load 6 Installed Capacity
It can be seen from the load duration curve presented in Figure 11.3 that the project is mainly dominated
by domestic load. Other end uses can be incorporated within 05 to 16 hours. If the project has to share
water with other existing water utilities such as irrigation system, etc. This can be arranged during the non-
operating hours or during partial load period. This load duration curve can also be used to maximize
benefits even at lower tariff during such hours.
Page: 70
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Table 12.1: Per kilowatt subsidy and cost ceiling as per AEPC
Walking distance Subsidy Ceiling
less than 2 days walking distance 70000 150000
2-5 days walking distance 78750 158750
more than 5 days walking distance 91500 171500
Start
Sources of investment
Project Payback of loan
Name, Discount factor
Location, Breakdown of investment cost
Annual operating cost
End
Figure 12.1: Flow chart for Project costing and financial analyses.
Page: 71
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Summary
Without With
probable probable
business load business
Project cost (Rs) 8,516,715 NPV on ====>>> (Rs) load (Rs)
Annual Operation, Maintenance and other Costs (Rs) 305,004 Total cost (4,367,625) (4,135,377)
Annual Income without probable business loads (Rs) 826230 Total Cost -Subsidy 31,413 263,662
Annual Income with probable business loads (Rs) 855180 Equity 2,667,678 2,899,926
Annual installment for Bank loan 303364 After Loan Repayment 3,509,282 3,704,195
Cash Flows
Ye ar =>> 0 1 2 3
A nnua l inc o m e wit ho ut pro ba ble bus ine s s lo a ds 826230 826230 826230
A nnua l inc o m e wit h pro ba ble bus ine s s lo a ds 826230 826230 826230
T o t a l E quit y 1200000
A nnua l O & M c o s t s 305,004 305,004 305,004
Lo a n re pa ym e nt 303364 303364 303364
C a s h f lo w wit ho u t pro ba ble bus ine s s lo a d -1200000 217862 217862 217862
C a s h f lo w wit h pro ba ble bus ine s s lo a d -1200000 217862 217862 217862
4 5 6 7 8 9 10 11 12 13 14 15
826230 826230 826230 826230 826230 826230 826230 826230 826230 826230 826230 826230
855180 855180 855180 855180 855180 855180 855180 855180 855180 855180 855180 855180
305,004 305,004 305,004 305,004 305,004 305,004 305,004 305,004 305,004 305,004 305,004 305,004
303364 303364 303364 303364 0 0 0 0 0 0 0 0
217862 217862 217862 217862 521226 521226 521226 521226 521226 521226 521226 521226
246812 246812 246812 246812 550176 550176 550176 550176 550176 550176 550176 550176
Page: 72
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
13. UTILITIES
13.1. INTRODUCTION
In this spreadsheet small tools for independent calculations are presented. These calculations are similar
to the calculations presented in other spreadsheet for individual components. The main aim of these
small calculations is to provide quick and handy computation of:
2. Payment of loan for different periods such as monthly, quarterly and yearly.
Payment of a loan
Loan amount: 1,800,000
Interest rate (APR): 6.00%
Monthly payments and No 12
3. Power calculations
4. Spillway sizing.
Page: 73
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Voltage Drop
Reach length (km) 7.000
Voltage at 1st node (V) 11,000
Power (kW) 190
ASCR type Squirrel 1.00
Phase at 1st node (1/2/11(for 11kV or above) 11
Phase at 2nd node (1/2/11(for 11kV or above) 11
Current (A) 12.47
Impedence Ohm/km 1.3803
Voltage at 2nd node (kV) 208.6V ,1.9% 10,791.40
Page: 74
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
13. REFERENCES
1. Mini-Grid Support Programme, Alternative Energy Promotion Centre, Kathmandu, Nepal (2002),
Peltric Standards
2. Mini-Grid Support Programme, Alternative Energy Promotion Centre, Kathmandu, Nepal (2003),
Preliminary Feasibility Studies of Prospective Micro-hydro Projects
5. European Small Hydropower Association (1998), Layman's Guidebook on How to Develop a Small
Hydro Site
8. GTZ/Department of Energy Development, Energy Division, Papua New Guinea, Micro Hydropower
Training Modules (1994), Modules 1-7, 10, 13, 14 & 18B.
10. KB Raina & SK Bhattacharya, New Age International (P) Ltd (1999), Electrical Design Estimating
and Costing.
11. Badri Ram & DN Vishwakarma, Tata McGraw-Hill Publishing Company Limited, New Delhi 1995,
Power System Protection and Switchgear, 1995.
12. Adam Harvey et.al. (1993), Micro-Hydro Design Manual, A guide to small-scale water power
schemes, Intermediate Technology Publications, ISBN 1 85339 103 4.
13. Allen R. Inversin (1986), Micro-Hydropower Sourcebook, A Practical Guide to Design and
Implementation in Developing Countries, NRECA International Foundation, 1800 Massachusetts
Avenue N. W., Washington, DC 20036.
14. Helmut Lauterjung/Gangolf Schmidt (1989), Planning of Intake Structures, GATE/GTZ, Vieweg.
15. HMG of Nepal, Ministry of Water Resources, Water and Energy Commission Secretariat,
Department of Hydrology and Meteorology, Methodologies for estimating hydrologic characteristics
of ungauged locations in Nepal (1990).
17. His Majesty's Government of Nepal, Ministry of Water Resources, Department of Irrigation,
Planning and Design Strengthening Project (PDSP), United Nations Development Programme
(NEP/85/013) / World Bank, Design Manuals for Irrigation Projects in Nepal, 1990.
18. ITECO, DEH/SATA Salleri Chialsa Small Hydel Project (1983), Technical Report.
Page: 75
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
19. P.N. Khanna (1996), Indian Practical Civil Engineer's Handbook, 15th Edition, Engineer's
Publishers, Post Box 725, New Delhi - 110001.
22. ITDG, IT Nepal Publications, Financial Guidelines for Micro-hydro Projects, 1997
23. IT Nepal Publications, Management Guidelines For Isolated MH Plant In Nepal, 1999.
24. ITDG, prepared for ESAP, Guidelines relating to quality improvement of MH plants, 1999
25. ICIMOD, Manual for Survey and Layout Design of Private Micro Hydropower Plants.
26. Norwegian Water Resources and Energy Administration, The Norwegian Regulations for Planning,
Construction and Operation of Dams, Norwegian University Press, Oslo, Norway, 1994.
Page: 76
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
APPENDICES
Page: i
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: ii
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: iii
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: iv
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: v
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: vi
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: vii
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: viii
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: ix
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: x
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: xi
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: xii
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: xiii
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: xiv
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: xv
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: xvi
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: xvii
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: xviii
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: xix
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: xx
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: xxi
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: xxii
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: xxiii
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: xxiv
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: xxv
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: xxvi
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: xxvii
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: xxviii
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: xxix
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: xxx
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: xxxi
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: xxxii
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: xxxiii
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: xxxiv
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: xxxv
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: xxxvi
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Month Regions
1 2 3 4 5 6 7
January 2.40 2.24 2.71 2.59 2.42 2.03 3.30
February 1.80 1.70 1.88 1.88 1.82 1.62 2.20
March 1.30 1.33 1.38 1.38 1.36 1.27 1.40
April 1.00 1.00 1.00 1.00 1.00 1.00 1.00
May 2.60 1.21 1.88 2.19 0.91 2.57 3.50
June 6.00 7.27 3.13 3.75 2.73 6.08 6.00
July 14.50 18.18 13.54 6.89 11.21 24.32 14.00
August 25.00 27.27 25.00 27.27 13.94 33.78 35.00
September 16.50 20.91 20.83 20.91 10.00 27.03 24.00
October 8.00 9.09 10.42 6.89 6.52 6.08 12.00
November 4.10 3.94 5.00 5.00 4.55 3.38 7.50
December 3.10 3.03 3.75 3.44 3.33 2.57 5.00
Page: xxxvii
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: xxxviii
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC
Page: xxxix
Micro-hydropower Design Aids Manual SHPP/GTZ-MGSP/AEPC