Professional Documents
Culture Documents
Chapter-6 Directional Drilling: Inaccessible Locations
Chapter-6 Directional Drilling: Inaccessible Locations
Chapter-6 Directional Drilling: Inaccessible Locations
DIRECTIONAL DRILLING
Directional drilling is much more than simply selecting a well path and
may alter or affect the casing and cement program, hydraulics, centralization
from the vertical. This definition is the basis for all controlled directional
Inaccessible Locations
Quite often, a target pay zone lies vertically beneath the surface
locations, riverbeds, mountains, harbors, and roads. In these cases, a rig site
is selected and the well is drilled directionally into the target zone.
110
Multiple Wells Drilling from A Single Site
build individual platforms from vertical well. Some North Sea platforms have
Wilson)
111
Figure 6-2 Relief well drilling (Courtesy Wilson Directional Drilling)
structure. Multiple wells from a single site are not uncommon in land
multiple sites, pipelines, and production facilities. Most of the western Siberia
Sidetracks
primary purpose is to deviate the well bore around and away from an
obstruction in the original well bore, such as stuck drill string. Generally
112
Relief Well Drilling
relief well to intersect a blowout well near the bottom so that mud and water
can be pumped into the blowout well. Directional control in this type of drilling
is stringent due to the extreme accuracy required to locate and intersect the
blowout well. Quite often, special logging tools are required in locating the
blowout well.
Multiple Targets
drilled with a vertical well. It may be necessary to drill through one target and
alter the direction of the well to reach the next target. The targets may be in
two-dimensional plane such that the drift angle must be altered. Other cases
may involve three-dimensional planning such that the inclination and azimuth
must be changed.
Design Considerations
Assuming that a target and rig site have been selected, the directional
113
Figure 6-3 Directional planning considerations(Courtesy Wilson
Directional Drilling)
114
Figure 6-5 S-type kick (Courtesy Wilson Directional Drilling)
If an S curve is selected as the plan type the engineer must also select
a drop angle rate and a depth at which the hole must return to vertical (Figure
6-3).
115
The drift, or inclination, of the well bore is the angle, measured in
degrees, between the actual well path, or some depth and a vertical line below
heading. Typically this value will range from 15o to 35o. The minimum
personnel. Drift angles less than this range are slightly more difficult to
control. In other words, it is usually easier to control a 20o well than a 10o well.
Although wells have been drilled in the 70o – 80o range, common upper
restraints are 45o – 48o. Hole angles greater than 45o – 48o begin to encounter
requirements for some logging operations. Many operators establish 35o as the
The Kick off point (KOP) is the depth at which the well bore path will be
intentionally diverted from the vertical position. The KOP is usually selected in
KOP is often selected so the final angle build-up can be achieved prior to
setting surface casing. This approach minimises key-seat problems in the hole
section. The KOP affects the final inclination angle. Assume that a target
116
exists at 10000 ft TVD, 2000 ft north and 2800 ft east. If a build angle of
3o/100 ft is used, the following maximum inclination angles must be used for
various KOP's.
Plan Type
Two plan types are used in directional drilling. The straight kick builds
angle and drills directionally through the target. The S curve will drop angle
prior to drilling into the target so entry is vertical. Perhaps the most
consideration prior to its implementation. Since the angle change will occur
deeper in the well where the formation are harder, directional contact may be
more difficult. In addition, the S curve will usually require 10-20 % more
drilling time than a straight kick. The S curve is selected primarily because it
allows vertical entry into the target zone. Many operator believe that vertical
117
Build (and Drop) Angle Rates
The build angle rate describes the rate of angle decrease, prior to
wellbore path. Typical ranges for build and drop angle rates are 1-4o/100 ft
with 3o/100 ft being perhaps the most common. Values above 4o/100 ft can
Graphical Presentation
illustrates the heading of the well path from the KOP and is usually
Calculation Methods
and survey analysis calculations. Although the calculations are not extremely
difficult to make manually, the computer eases the difficulty and minimises
118
Survey Techniques
-single shot instruments that take only one reading on a single photographic
of film during one run. The compass unit in both single and multi-shot
steel drill pipe and collars, they are generally run inside a non-magnetic drill
collar. The collar is often termed monel collar because of its composition of K-
earth’s magnetic poles, thus giving a true magnetic compass reading of the
direction and angle of the borehole at a depth at which the compass reading
was taken. A sufficient length for the monel collar should be used for the hole
instrument using this principle can be used for determining the direction in
both cased and uncased holes and adjacent to magnetic bodies. The single shot
It records the inclination and direction of the borehole on a film disc. This is
119
accomplished by photographing the position of the angle indicator, referenced
to a compass card with a calibrated angle unit. A timing mechanism allows the
Calculation Techniques
trajectory as it is being drilled. The three most widely used methods are the
The tangential method uses only the inclination and direction angles
measured at a lower end of the course length. The wellbore path is assumed to
be tangent to those angles throughout the section length. The wellbore path is
Although this method has probably been the most widely used approach, it is
The angle averaging is the simple average of the angles at the top and
these two average angles over the course length. The wellbore is calculated
120
tangentially using these two average angles over the course length. The
end of the course length to generate a space curve representing the wellbore
path. It has a shape of spherical arc passing through the measured angles at
both ends of the course. Although this approach is perhaps the most accurate
Example 6-1
Use the following survey data to compare the three survey calculation
techniques.
121
o
Measured Depth, Hole Angle, Azimuth
ft
3000 2 N28E
3300 4 N10E
3600 8 N35E
3700 12 N25E
5000 15 N30E
6000 16 N28E
7000 17 N50E
8000 17 N20E
9000 17 N30E
10000 17 N25E
Solution
Depth TVD North East/ TVD North East/ TVD North East/
/ West / West / West
South South South
3000 3000 0 0 3000 0 0 3000 0 0
3300 3299 20.6N 3.6E 3299 14.8N 5.1E 3299 14.8N 5.1E
3600 3596 54.8N 27.6E 3597 43.8N 17.1E 3597 43.5N 17.0E
3900 3889 113.3N 53.9E 3893 88.9N 43.2E 3893 88.6N 43.0E
5000 4952 357.9 196.3E 4963 316.7 161.3E 4962 316.2 161.5E
N N N
6000 5913 601.3 325.7 5926 550.4 291.7E 5926 550.0 291.1E
N E N N
7000 6869 789.2 549.7 6885 771.2 476.7 6885 769.3 468.7
N E N E N E
8000 7826 1063.9 649.7 7841 1010.7 673.7 7841 1006.1 634.7
N E N E N E
9000 8782 1317.1 795.8 8798 1275.6 761.8E 8797 1270.7 757.8
N E N N E
10000 9738 1582.1 919.4E 9754 1535.0 896.4 9754 1530.0 892.4
N N E N E
122
Dogleg Severity
Large angle changes occurring over short course length can place high
change allowable over a 100 ft segment. Generally the limit is 4o-6o per 100 ft.
Doglegs that occur at shallow and deep intervals are concerns for different
reasons. Although shallow doglegs tend to wash out and enlarge in softer
formations, they can cause increasing problems due to high string weights
hanging at the doglegs as the well deepens. Dogleg calculation technique based
DL = 100 / {(L) [(sinI1 . sinI2) (sinA1 . sinA2 + cosA1 . cosA2) + (cosI1 . cosI2)]
DL = dogleg, o/100 ft
L = course length, ft
o
I1 . I2 = inclination at upper and lower surveys,
o
A1 . A2 = direction at upper and lower surveys,
123
Example 6-2
Calculate the dogleg severity for the two successive surveys as follows:
Solution:
DL = 100 / {(L) [(sinI1 . sinI2) (sinA1 . sinA2 + cosA1 . cosA2) + (cosI1 . cosI2)]
cos14.7)]
DL = 3.229o / 100 ft
124