Professional Documents
Culture Documents
Cost Estimates
Detailed Cost
Estimates
Equipment Cost =
(Quantity of Work / Production Rate) * All-in Plant rate, or
(Quantity of Work * Unit Rate) * All-in Plant rate
4/19/2016 7:15 PM Dr. Hany Abd Elshakour ٧
Detailed Cost Estimates
2) Operational Estimating
Used extensively in civil engineering works because this
method links well with Time Planning and is effective in
allowing for Idle Time which is common in most plant
dominated works.
Operational estimating would base the costs of the plant
on the time that the plant was on site (elapsed time),
not on an assumed output rate.
The time the plant was on site would be derived from the
construction program.
In building construction works the operational estimating
can be used in estimating the cost of pumps, tower
cranes…
4/19/2016 7:15 PM Dr. Hany Abd Elshakour ٨
Example
A bid for a hospital project was advertised in the newspaper. The
hospital consists of three buildings. After reviewing the bidding
documents, the quantity of excavation for the three buildings
according to the B.O.Q were as follow:
Building (1): 1000 m3
Building (2): 2000 m3
Building (3): 2600 m3
According to the construction method selected, the equipment
used for the excavation activities consists of one excavator and
three trucks with a production rate of the crew equals 200 m3
/day.
The rental rate of the excavator = L.E. 1000/ day
The rental rate of one truck = L.E. 300/day/truck
Estimate the equipment cost of excavation per cubic meter using
unit rate estimating method.
4/19/2016 7:15 PM Dr. Hany Abd Elshakour ٩
Example
If you know that, the program utilized by the contractor for excavation
activities is illustrated in the bar chart below. The equipment crew will
stay in the project and can not be transported outside the project
during the excavation time. Estimate the equipment cost of excavation
per cubic meter using operational cost estimating method.
Activity Duration 1 2 3 4 5 6 7 8 9 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 3 3 3 3
(Day) 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3
Excavation build. 1 5
Excavation build. 2 10
Excavation build. 3 13
……………………………..
4/19/2016 7:15 PM Dr. Hany Abd Elshakour ١٠
Example: Unit Rate Estimating
Equipment Cost =
(Quantity of Work / Production Rate) * Daily Equipment Costs
Estimate the direct cost for each item and the site
overheads of the project
Calculate thePM
4/19/2016 7:15 tender price and the unit price of each item Dr. Hany Abd Elshakour ١٤
Plan and Schedule Cost Estimate Process
The careful reading of the bidding documents by the
estimator will enable him to:
Obtain an overall concept of the project
Establish the level of assistance required from other
departments, e.g. planning, purchasing and equipment
departments
Identify the required time to accomplish the cost
estimate process
Determine key dates for sending out of inquires and
receipt of quotations, for visiting site, for submitting the
tender, etc.
Estimate the direct cost for each item and the site
overheads of the project
Calculate thePM
4/19/2016 7:15 tender price and the unit price of each item Dr. Hany Abd Elshakour ١٧
Review the Project Scope, and Analyze Bidding Documents
Estimate the direct cost for each item and the site
overheads of the project
Calculate thePM
4/19/2016 7:15 tender price and the unit price of each item Dr. Hany Abd Elshakour ٢٠
Visit the Site, and Attend Meetings
The characteristics of the particular site where the
building is to be constructed play an important role in
estimating project costs.
As result of the site visit, the estimator prepares a report
or set of notes, which includes at least the following:
Description of the site and access to it,
Available space for storage of materials,
Positions of existing services/ underground utilities,
Description of ground conditions,
Assessment of the availability of labor,
Any problems related to the security of the site,
Topographical details of the site,
Description of the facilities available for the disposal of
spoil, and
Description of any demolition works or temporary works to
adjoining
4/19/2016 7:15 PM buildings. Dr. Hany Abd Elshakour ٢١
Visit the Site, and Attend Meetings
Estimate the direct cost for each item and the site
overheads of the project
Calculate thePM
4/19/2016 7:15 tender price and the unit price of each item Dr. Hany Abd Elshakour ٢٤
Perform Work Breakdown
A work breakdown structure (WBS), is a deliverable-oriented
decomposition of a project into smaller components.
Estimate the direct cost for each item and the site
overheads of the project
Calculate thePM
4/19/2016 7:15 tender price and the unit price of each item Dr. Hany Abd Elshakour ٢٨
Quantity Survey
Reasons for quantity takeoff
for lump-sum bidding, the bidding documents may not
include quantities of work.
for unit-price bidding, most bid items cannot be priced
without breaking the work down into smaller
subdivisions.
the A/E’s quantity estimates are specifically stated to
be approximations only.
making the quantity survey provides the estimator
with the close familiarity of job requirements so vital to
realistic project pricing.
Estimate the direct cost for each item and the site
overheads of the project
Calculate thePM
4/19/2016 7:15 tender price and the unit price of each item Dr. Hany Abd Elshakour ٣٠
Select Method of Construction
Many activities have alternative methods of accomplishment.
They include using various levels of resource capability or
skills, different size or type of machines, different tools (hand
versus automated), and make-rent-or-buy decisions regarding
the resource.
Estimate the direct cost for each item and the site
overheads of the project
Calculate thePM
4/19/2016 7:15 tender price and the unit price of each item Dr. Hany Abd Elshakour ٣٢
Develop a General Time Schedule
When a new project is being estimated, it is necessary
that a general time schedule be devised.