Professional Documents
Culture Documents
Recommendation
That the August 27, 2018, Integrated Infrastructure Services report CR_5846, be
received for information.
Executive Summary
The report provides information on negotiations with MacEwan University regarding
land requirements for the Valley Line West. Administration has consulted with
MacEwan University and together considered the impacts the LRT system design will
have on MacEwan University lands such as to trees, property, and the pedestrian
realm and on its long term plan. LRT operation requirements and infrastructure
capacity needs such as roadways, sidewalks, and utilities were also considered.
MacEwan University has reviewed this option and supports the design. Administration
will continue to work with MacEwan University to finalize design coordination and land
requirements along 104 Avenue.
Report
Background
The Valley Line is a 27 kilometre urban-style, low-floor LRT line that will operate
between Mill Woods in southeast Edmonton and Lewis Farms in west Edmonton. The
Valley Line was separated into two stages for project delivery: Valley Line Southeast
(between 102 Street downtown and Mill Woods Town Centre) and Valley Line West
(between 102 Street downtown and Lewis Farms Transit Centre).
In September 2016, the City of Edmonton received funding, through the Government
of Canada’s Public Transit Infrastructure Fund, to update the Valley Line West
preliminary design, determine the most appropriate project delivery method, develop a
business case for construction funding, and ensure that the project is ready for
construction procurement in 2018. Recently, the provincial government committed $1.5
billion for LRT projects in Edmonton and the federal government committed $878
million for transit projects in Edmonton.
Design Considerations
As part of the Valley Line West LRT preliminary design update, Administration
engaged with MacEwan University through meetings, workshops and site visits.
Based on the approved Valley Line West Concept Plan, 104 Avenue will have LRT
running down the centre of the roadway. The roadway will be reduced from the
existing six lanes to four lanes, with two lanes in each direction. This design will
require a strip of land from MacEwan University to accommodate LRT and roadway
infrastructure (trackway, roadway, sidewalk, boulevard and utilities).
Remove westbound left turn movement at 104 Avenue and 109 Street
Removing the westbound left-turn lane opens up space to shift the alignment of
westbound through lanes southward, thereby reducing impact to the north boulevard
and its southern sidewalk. West of 110 Street, the boulevard width will be reduced but
may still require some of the existing trees to be removed or relocated. East of 110
Street, the boulevard width reduction will accommodate the existing trees in this area,
but construction impacts will need to be reviewed as the project progresses.
Removing the westbound left turn bay at 109 Street will open up right-of-way space for
traffic lanes to be shifted south. Westbound left turn movement would no longer be
permitted at 109 Street. With the introduction of LRT on 104 Avenue, Administration
projects that less than 50 vehicles per hour during both the AM and PM peak hour
would make the westbound left turn. Westbound vehicular traffic looking to head south
on 109 Street are accommodated via 106 Avenue, 103 Avenue or Jasper Avenue; the
downtown roadway network has sufficient roadway capacity to accommodate the
re-routed traffic. Westbound through and right-turn movements would not change from
the approved concept plan.
MacEwan University has reviewed this option and supports the proposed design.
Administration will continue to work with MacEwan University to finalize design
Public Engagement
MacEwan University has been an active stakeholder on this project and was engaged
during the conceptual and preliminary design phases. In 2017, MacEwan University
was re-engaged as part of the Valley Line West preliminary design update work.
During 2017 to March 2018, Administration engaged MacEwan University through
email, by telephone, and in-person meetings and workshops (5 meetings and 1
workshop). MacEwan University was also present at the March 21 public hearing of
Valley Line West crossing assessments and concept plan amendments and addressed
its concerns regarding the impact to trees, property and pedestrian realm. Subsequent
to the council meeting on March 21, Administration continued to consult with MacEwan
University through emails and meetings to develop a mutually agreeable solution. A
meeting was held with MacEwan University to share the proposed design and support
for the design was received.
Design considerations and negotiation progress are presented via this report.
However, once design is confirmed, the final design will be presented to the public as
part of overall Valley Line West LRT project wrap-up.
Corporate Outcome(s): Edmontonians use public transit and active modes of transportation
Edmontonians use Transit ridership (rides per 91.6 (2017) 105.0 (2018)
public transit and active capita)
modes of transportation
Journey to work mode 26.1% (2016) 25.9% (2018)
(percent of survey
respondents who select
auto passenger, transit,
walk, cycle or other)
Corporate Outcome: The City of Edmonton has sustainable and accessible infrastructure
Outcome Measure Result Target
Attachment
1. 104 Avenue Design Preferred Option