TIME SCHEDULE CIVIL WORK

2018 2019
NO URAIAN AGT SEPT OKT NOV DES JAN FEB
III IV I II III IV V I II III IV I II III IV I II III IV V I II III IV I II III IV
ENGINEERING PREPARATION
I I.i Topographie
I.ii Planning for Excavation & Embankment
MOBILIZATION
II.i Employee
II II.ii Equipment
II.iii Material
II.iv Labor
III OPERATIONAL
RC0 Layout
·         Cut & Fill
RC1 Warehouse A & B Wall
·         Beam
·         Coulom
·         Wall
RC2 Ground Water Tank
·         Piling
·         Stone Masonry
·         Footing Beam
·         Embankment
·         Lean Concrete
·         Wall
·         Coulomb
RC3 Control Room for Blast Furnace
RC4 Primary Road
·         Cut & Fill
·         Base Course
·         Rigid Pavement
RC5 Secondary Road
RC6 Primary Drainage
·         Cut
·         Stone Masonry
RC7 Laboratory
·         Coulomb
·         Wall
·         Roofing
·         Flooring
RC8 Air Blower to HRU Building