NO URAIAN AGT SEPT OKT NOV DES JAN FEB
III IV I II III IV V I II III IV I II III IV I II III IV V I II III IV I II III IV
ENGINEERING PREPARATION
I I.i Topographie
I.ii Planning for Excavation & Embankment
MOBILIZATION
II.i Employee
II II.ii Equipment
II.iii Material
II.iv Labor
III OPERATIONAL
RC0 Layout
· Cut & Fill
RC1 Warehouse A & B Wall
· Beam
· Coulom
· Wall
RC2 Ground Water Tank
· Piling
· Stone Masonry
· Footing Beam
· Embankment
· Lean Concrete
· Wall
· Coulomb
RC3 Control Room for Blast Furnace
RC4 Primary Road
· Cut & Fill
· Base Course
· Rigid Pavement
RC5 Secondary Road
RC6 Primary Drainage
· Cut
· Stone Masonry
RC7 Laboratory
· Coulomb
· Wall
· Roofing
· Flooring
RC8 Air Blower to HRU Building