Professional Documents
Culture Documents
POWER PLANT
CANDIDATE’S DECLARATION
I hereby declare that the work which is being presented in this dissertation report
entitled “MODELING AND SIMULATION OF HYDRO POWER PLANT”
submitted in partial fulfillment of the requirements for the award of the degree of
Master of Technology in Alternate Hydro Energy Systems, submitted in Alternate
Hydro Energy Centre, Indian Institute of Technology Roorkee is an authentic record
of my own work carried out during July 2014 to May 2018 under the supervision of Dr.
…………, Asst. Professor, EC KIET.
I have not submitted the matter embodied in this report for the award of any
other degree or diploma.
This is to certify that the above statement made by the candidate is correct to the best of
my knowledge.
(Dr.)
Assistant Professor
EC
KIET
i
ACKNOWLEDGEMENT
ii
ABSTRACT
This dissertation presents the modeling and simulation of large hydropower plant
under different operating conditions. The considered large hydropower plant consists of
a hydro turbine with PID governor and synchronous generator with DC1A excitation
system and is connected to the grid. The large hydropower plant simulation model is
developed under MATLAB/Simulink environment. The Matlab/Simulink model of a
large hydropower plant is also transformed to RT-LAB environment for the real-time
(OPAL-RT) simulation.
With the help of this developed simulation model of large hydropower plant, the
study of dynamic behavior of large hydropower plant have been analyzed when
subjected to disturbances like load addition, load removal, and three phase short circuit
fault conditions at the terminal of synchronous generator of plant. The hydraulic
transient analysis of hydropower plant at different parameters of PID governor gain
(Proportional gain, Integral gain and Derivative gain) is also carried out. Finally, the
comparison of results of the real-time simulation in RT-LAB and offline simulation in
Matlab/Simulink are presented and discussed.
iii
TABLE OF CONTENTS
CANDIDATE’S DECLARATION i
ACKNOWLEDGEMENT ii
ABSTRACT iii
TABLE OF CONTENTS iv
NOMENCLATURE x
CHAPTER 1 : INTRODUCTION 1
1.1 General 1
1.3.1 Run-of-River 2
iv
1.4.2.3 Deterministic and Stochastic Simulations 6
v
4.3.3 Case -III: Short Circuit Fault 38
4.4 Hydraulic Transient Analysis of Hydropower Plant for Different Values of PID
Governor Gain 43
5.1 Conclusions 56
REFERENCES 58
vi
LIST OF FIGURES
vii
Fig. 4.17: Gate opening Vs time, Case-I 32
Fig. 4.18: MATLAB/Simulink model of hydro power plant for load reduction 33
Fig. 4.19: Single line diagram for load reduction at SG terminal 33
Fig. 4.20: Generator voltage Vs time, Cae-II 34
Fig. 4.21: Generator current Vs time, Case-II 34
Fig. 4.22: Load current Vs time, Case-II 34
Fig. 4.23: Electrical power Vs time, Case-II 35
Fig. 4.24: Rotor speed Vs time, Case-II 35
Fig. 4.25: Excitation voltage Vs time, Case-II 35
Fig. 4.26: Generator load angle (degree) Vs time, Case-II 35
Fig. 4.27: Mechanical power Vs time, Case-II 36
Fig. 4.28: Grid voltage Vs time, Case-II 36
Fig. 4.29: Grid current Vs time, Case-II 36
Fig. 4.30: Gate opening Vs time, Case-II 36
Fig. 4.31: MATLAB/Simulink model of hydropower plant for short circuit fault 38
Fig. 4.32: Single line diagram for three phase short circuit fault at SG terminal 38
Fig. 4.33: Generator voltage Vs time, Case-III 39
Fig. 4.34: Generator current Vs time, Case-III 39
Fig. 4.35: Load current Vs time, Case-III 39
Fig. 4.36: Electrical power Vs time, Case-III 40
Fig. 4.37: Rotor speed Vs time, Case-III 40
Fig. 4.38: Excitation voltage Vs time, Case-III 40
Fig. 4.39: Generator load angle (degree) Vs time, Case-III 40
Fig. 4.40: Mechanical power Vs time, Case-III 41
Fig. 4.41: Grid voltage Vs time, Case-III 41
Fig. 4.42: Grid current Vs time, Case-III 41
Fig. 4.43: Gate opening Vs time, Case-III 41
Fig. 4.44: Electrical power Vs time at constant Ki & Kd 43
Fig. 4.45: Mechanical power Vs time at constant Ki & Kd 43
Fig. 4.46: Rotor speed Vs time at constant Ki & Kd 44
Fig. 4.47: Gate opening Vs time at constant Ki & Kd 44
Fig. 4.48: Electrical power Vs time at constant Kp & Kd 45
Fig. 4.49: Mechanical power Vs time at constant Kp & Kd 45
Fig. 4.50: Rotor speed Vs time at constant Kp & Kd 45
Fig. 4.51: Gate opening Vs time at constant Kp & Kd 46
viii
Fig. 4.52: Electrical power Vs time at constant Kp & Ki 46
Fig. 4.53: Mechanical power Vs time at constant Kp & Ki 47
Fig. 4.54: Rotor speed Vs time at constant Kp & Ki 47
Fig. 4.55: Gate opening Vs time at constant Kp & Ki 47
Fig. 4.56: Separated RT-LAB model 48
Fig. 4.57: Console subsystem 49
Fig. 4.58: Master subsystem 49
Fig. 4.59: Electrical power Vs time, Case-I 50
Fig. 4.60: Rotor speed Vs time, Case-I 50
Fig. 4.61: Excitation voltage Vs time, Case-I 50
Fig. 4.62: Generator load angle (degree) Vs time, Case-I 51
Fig. 4.63: Mechanical power Vs time, Case-I 51
Fig. 4.64: Gate opening Vs time, Case-I 51
Fig. 4.65: Electrical power Vs time, Case-II 52
Fig. 4.66: Rotor speed Vs time, Case-II 52
Fig. 4.67: Excitation voltage Vs time, Case-II 52
Fig. 4.68: Generator load angle (degree) Vs time, Case-II 53
Fig. 4.69: Mechanical power Vs time, Case-II 53
Fig. 4.70: Gate opening Vs time, Case-II 53
Fig. 4.71: Electrical power Vs time, Case-III 54
Fig. 4.72: Rotor speed Vs time, Case-III 54
Fig. 4.73: Excitation voltage Vs time, Case-III 54
Fig. 4.74: Generator load angle (degree) Vs time, Case-III 55
Fig. 4.75: Mechanical power Vs time, Case-III 55
Fig. 4.76: Gate opening Vs time, Case-III 55
ix
NOMENCLATURE
x
At Turbine gain -
g
FL Full load gate opening m
g
NL No load gate opening m
Subscripts:
d, q: d and q axis quantity
R, s: Rotor and stator quantity
l, m: Leakage and magnetizing inductance
f, k: Field and damper winding quantity
xii
CHAPTER 1
INTRODUCTION
1.1 General
Hydropower is a renewable energy source, which converts the energy of
flowing water from the higher elevation to lower elevation into electricity.
Hydropower is a proven, mature, predictable, cost competitive and highest efficient
convertible renewable energy source. Hydropower plays an important role in the
management of water resources by preventing flooding in downstream, solving
irrigation problems, creating recreational areas and making the river navigable.
Hydropower provides the alternate sources of energy thereby conserving the fossil
fuels which reduces the environmental impact produced by the use of fossil fuels. The
total installed global hydropower capacity is 1,036 GW [1]. The power generated by a
hydropower plant depends on the volume of water flowing and the net head available
at the site. The power generated from hydropower is given by the following equation:
P g Q H (1.1)
Where,
P = Power generated in kW
η = Overall efficiency of the plant
2
g = Acceleration due to gravity in m/s
3
Q = Discharge in m /s
H = Head in metre
1
1.2.2 Classification Based on Capacity Rating
The classification of hydropower plant on the basis of plant capacity rating [2]
Up to 5 kW - Pico Hydropower Plant
5 kW to 100 kW - Micro Hydropower Plant
100 kW to 2000 kW - Mini Hydropower Plant
2 MW to 25 MW - Small Hydropower Plant
25 MW to 100 MW - Medium Hydropower Plant
100 MW & above - Large Hydropower Plant
1.3.1 Run-of-River
In a Run-of-River (ROR) hydropower plant, water is diverted towards
powerhouse by a channel or pipeline (penstock) to convey water to a hydraulic
turbine which is connected to a generator. This type of plant does not store the water.
It uses the water as it comes directly from the river. Therefore, the plant’s output
depends on the seasonal variations and weather conditions. Generally, this type of
power plants is preferred for high head and low discharge schemes. The typical
arrangement of run-of-river hydropower station is shown in Fig. 1.1.
2
Fig. 1.1: Typical Arrangement of Run-of-River Hydropower Station [3]
6
1.7 Objectives of the Study/Work
The following are the objectives of the present study/work carried out in this
dissertation:
i. To developed the hydropower plant model in Matlab/Simulink Environment.
ii. To simulate and analyze the operation of the hydropower plant at various
operating conditions like addition of load, removal of load and fault
conditions.
iii. To simulate and analyze the operation of the hydropower plant at various
operating conditions in real-time under OPAL RT-LAB environment.
7
CHAPTER 2
LITERATURE REVIEW
This chapter presents the literature review on the modeling and simulation of
the hydropower plants and gaps identified.
Fang et al. [9] demonstrated the simulation of hydropower plant having high
head and long penstock with two surge tanks placed in upstream and downstream.
The simulation model of the hydropower plant with Francis turbine was developed in
Matlab/Simulink environment. For simulation and calculation of hydraulic transients,
the hydraulic turbine's nonlinear characteristics and inelastic water hammer effect
were considered. The simulation results of hydropower plant model carried out in
Matlab/Simulink was compared with the simulation result of an actual hydropower
plant which was performed at full load rejection.
Hannett et al. [11] described a dynamic simulation model of the pumped storage
hydropower plant to be interconnected to the power grid. The Simulation model was
developed to represents the plant on an electrical network for studies of electrical
disturbances to the power grid as well as evaluating the response of the plant
8
itself. The governor models and pump model was developed to analyze the
characteristics of plant operations.
Jaeger et al. [12] presented a nonlinear hydraulic turbine model for dynamic
studies of hydropower plants and investigated the modeling of a power plant
consisting of several turbines supplied from a common tunnel, taking into account of
hydraulic coupling effects. The proposed model was simulated for large transients as
load rejections and their effect, due to coupling in the common conduit.
Jadid & Salami [15] investigated the problem of load pickup in the power
system after the occurrence of faults for the restorations of the system to a normal
state which was caused by deviation of frequency response from allowable limits. For
the investigation, the study was carried out on hydropower plant. Based on the study
carried out, an accurate model of the plant was proposed and simulation was
performed on proposed model of the plant. A linearized model of a hydraulic turbine
was used in proposed model of the plant for simulation.
9
Hannett et al. [16] proposed hydropower plant model having multiple units
sharing a common conduit. The simulation model having multiple units with a
different size of units was derived. The simulation of the model was carried out to
determine the plant response and to find the physical parameter's relation. The setting
of governor parameter and hydraulic coupling effect relation were also discussed. The
stability effects of a plant by the parameter setting at islanded condition were
demonstrated by simulation.
Robert & Michaud [18] gave a model of the hydroelectric power plant which
was connected to a power grid for designing the power controller. The slow and fast
dynamics models of hydraulic plants considering the elasticity of penstock and effect
of surge tank were developed. Reduced order models for a multi-machine power
system were proposed and its validity was verified by making comparison of
simulation result performed in Matlab/Simulink and measurements carried out on a
252 MVA hydro unit.
Souza et al. [19] presented the analyses of a discrete hydraulic system to carry
out the study of hydraulic parameters. In this work, an analog mathematical model of
the hydraulic turbine was used for developing simulation model. The results were
obtained by using nonlinear analog-digital simulation method. The theoretical results
obtained by using characteristics method done in literature example was compared
with analog mathematical method result.
Lindenmeyer et al. [20] presented the model of hydro and nuclear power plant's
auxiliaries in Electromagnetic Transients Program (EMTP). The models of generator,
turbine, exciter, and induction motor were derived and validations of individual
model were carried out by field measurement. A modeled hydropower plant and a
nuclear power plant’s auxiliaries using EMTP were also investigated. To verify the
power system model, the simulation results was compared with the 10
measurement carried out in Engineered Safeguards Functions (ESF) test on the
emergency power system (i.e., Oconee nuclear power plant).
Choo et al. [22] gave a model of the hydraulic turbine with long penstock
considering water hammer effects and friction. For transient response analysis during
load disturbances, a detailed hydraulic turbine-penstock was used to study the
governor stability. Both frequency and transient response analyses were performed to
study the effect of detailed modeling of turbine-penstock to the stability studies and
dynamic performance of the system.
Gao & Wang [23] presented the nonlinear, linearized based on prototype,
linearized based on internal characteristics, and ideal model of the hydro turbine.
These four different types of hydro turbine model's effect and applicability on power
system analysis were performed and concluded that the effect of developed models of
the hydro turbine was more on electro mechanic and hydraulic oscillation mode than
on the excitation system oscillation mode.
Naik et al. [24] presented PID governor with internal model control (IMC) for
hydropower plant considering the presence of water hammer effect. In this work, the
simulation result of the proposed IMC tuning was compared with the single frequency
and Ziegler-Nichols closed loop tuning. It was found that the simulated result of IMC
tuning technique was feasible and versatile to use in the control of hydropower plant
having water hammer effect.
Vinatoru & Iancu [25] presented the mathematical model of cascade run-off-the-
river hydropower plant which considered the dynamic and static behavior of the plant
for implementing the digital control algorithm. To perform the simulation and analysis
of control structures and algorithm, a simplified mathematical model of the 11
hydropower plant was developed. The simulated result was compared with the result
obtained by an experiment performed on the actual system.
Nicolet et al. [28] developed SIMSEN, a numerical software package used for
simulation of electrical power systems and hydraulic components. The developed
software was useful for the stability analysis of hydroelectric power plant and could
be used for global design optimization. In this work, the hydraulic components of
hydropower plant were represented by an equivalent electrical circuit.
Cozorici et al. [32] carried out designing of wind-hydropower plant model for
the use in research work and demonstration to the students about the power generation
from wind and small hydropower plant. Simulation of designed wind-hydropower
plant model was also performed.
Chen et al. [33] developed nonlinear real-time simulation system for testing
hydroelectric generating unit's speed governing system. In this work, a nonlinear
feature of a hydro turbine was simulated by using the neural network which achieved
higher accuracy of the simulation.
Kishor et al. [35] presented the review of research work carried out in the
field of hydropower plant model development and control system used in a model for
studying the performance of hydropower plant. In this work, the research gaps on
modeling of the hydropower plant and its control were identified for further research
work to be carried out in the field of modeling and simulation of the hydropower
plant.
Rahi & Kumar [36] presented the studies on different types of excitation
system used for generator excitation in a small hydro power plant (SHP) to design the
excitation system at different operating conditions. In this work, three types of
excitation system were simulated and found out that the static excitation system has
faster response time than DC and AC excitation system.
Arun.s [37] presented the simulation studies of Bhikuriagad and Zhagdong rong mini-
hydropower plant having a capacity of 500 kW and 100 kW respectively. The
mathematical models of various components of mini-hydropower plant were 13
considered for simulation. The behaviors of mini-hydropower plant at different
operating condition were studied by simulating the developed model in ALICES
simulation environment.
14
CHAPTER 3
MATHEMATICAL MODELING OF VARIOUS COMPONENTS
OF HYDROPOWER PLANT
H pc H c K pc Qc Qc
(3.4)
2
2gAco
dH c
Ac z dt Qc
(3.5)
Lpc
Lc (3.6)
gA
co
Rc
K
Q
pc c
2gAco 2
Cc Ac z
The three components Rc, Lc, Cc are connected in series since equations (3.4),
(3.5) and (3.6) are related to incoming discharge Q c in the surge tank [38] as shown in
Fig. 3.2.
(a) (b)
Fig. 3.2: (a) Surge tank model (b) Electrical equivalent circuit model [38]
16
3.2 Hydraulic Turbine Model
The nonlinear hydraulic turbine model and penstock is given by equations
(3.7) - (3.22) considering non-elastic water column and incompressible water. Basic
hydro dynamic equations considering simple hydraulic systems with unrestricted head
and tail race, with a very large or without surge tank, assuming rigid conduit and
incompressible fluid [39] are as given in following equations.
G
P HU (3.11)
dU gH r H 0 H (3.12)
dt LU r
dU 1 H 0 H (3.13)
dt T
W
Where TW is the water starting time at rated load and it has a fixed value for a given
turbine-penstock unit and is given by
LU
T
W
gH r (3.14)
r
UH0 H (3.15)
STW
Power output from turbine: Pm P PNL
Pm K P U U NL H (3.16)
17
Normalizing the output power of turbine:
P m U U NL H (3.17)
Torque: T Pm (3.18)
m
VA
base
Rated torque: Tr (3.19)
rated
Tm Pm O
T VA
r base
Pm
Tm P r 1
T VA
r base
T m Pm Pr U U NL H P r
(3.20)
Fig.3.3 shows the relation between real gate opening and ideal gate opening.
The relationship between real gate opening and ideal gate opening is given by
equation (3.21).
Fig. 3.3: Relation between ideal gate opening and real gate opening [39]
G At g (3.21)
1
At (3.22)
g
FL g NL
18
By combining equations (3.7) - (3.22), the nonlinear hydro-turbine model is
obtained as shown in Fig.3.4.
19
3.4 Synchronous Generator Model
The model of synchronous machine is used to consider the electrical and
mechanical characteristics of machine and it consider the winding dynamics of stator,
field and damper. Rotor reference frame (dq frame) is used to represent the equivalent
circuit of synchronous machine model as shown in Fig. 3.6. The electrical quantities
and rotor parameters are viewed from stator side which is identified by primed
variables. In synchronous machine model, it assumes currents flowing into the stator
windings while the currents flowing out from the machine is a measured stator
currents returned by Synchronous Machine (Ia, Ib, Ic, Id, Iq) [42].
The electrical model of synchronous machine is given by following equations:
V R id
(3.23)
d s d dt d R q
(3.24)
d (3.25)
V fd' R'fd i 'fd dt 'fd
d (3.26)
Vkd' Rkd' ikd' dt kd'
d (3.27)
Vkq'1 Rkq'1ikq'1 dt kq'1
d
Vkq' 2 Rkq' 2ikq' 2 dt kq' 2 (3.28)
(3.30)
q Lq iq Lmq ikq'
'
L'kq1ikq'1 Lmq iq (3.33)
kq 1
' (3.34)
kq 2 L'kq 2ikq' 2 Lmq iq
20
(a) q-axis
(b) d-axis
Fig. 3.6: Synchronous Machine Model (a) q-axis equivalent model (b) d-axis
equivalent model [42]
21
The DC1A exciter model represents field-controlled dc commutator exciter
with voltage regulators acting continuously. It may be self-excited or separately
excited. For the self-excited excitation system, Ka is selected so that the value of
regulator voltage VR is zero initially. The DC excitation system model block diagram
used in this study is shown in Fig. 3.7 below.
dX 9 X 8 X 9 (3.36)
dt Tf
dX 9
V3 K f (3.37)
dt
V
V1 ref X 5V3 (3.38)
V X
dX 6 1 6 (3.39)
dt T
b
dX 6
V2 X 6 TC (3.40)
dt
dX 7 K aV2 X 7 (3.41)
dt T
a
22
dX 7
If dt 0 and X 7 Vmax
dX 7
dt 0 and X 7 Vmin (3.43)
dX 7
If dt 0 and X 7 Vmin
dX 8 X 7 Ae BX 8 Ke X 8 (3.44)
dt Te
The exciter output voltage, Efd is given by:
E fd X 8 (3.45)
23
The sending end voltage and sending end current of a transmission line can be
expressed as:
VS AVr BI r (3.46)
For nominal T:
YZ
A1 2
YZ
B Z 1
4
CY
YZ
D1 2
For nominal π:
YZ
A 1
2
BZ
YZ
C Y 1
4
YZ
D 1
2
24
CHAPTER 4
SIMULATIONS AND RESULTS
Fig. 4.3: MATLAB/Simulink model for subsystem of type IEEE DC1A excitation
system
1. General
Net Head : 820 m
3
Design Discharge : 142.5 m /s
2. Turbine
Type : Vertical Pelton
Number :6
Capacity : 170 MW
No. of jets :5
Nozzle level : 501.5 m
3
Rated discharge : 23.52 m /s
Speed : 375 rpm
3. Generator
Type : Vertical shaft, Synchronous
machine
Number :6
Capacity : 190 MVA
Voltage : 13.8 kV
4. Transformer
Type : Single phase
Number : 18+1 (spare)
Capacity : 70 MVA
Rated voltage : 13.8 kV/400 kV
5. Transmission Line
Type : Double circuit
Rated voltage : 400 kV
Length : 140 circuit km
27
6. PID Governor Parameter
Permanent droop RP = 0.05 Proportional gain Kp = 1.0
Integral gain Ki = 0.2 Derivative gain Kd = 0.1
Servo-motor gain Ka = 3.33 Servo-motor time Ta = 0.07 sec
Maximum gate opening = 0.975 pu Minimum gate opening = 0.01 pu
Fig. 4.5: MATLAB/Simulink model of hydro power plant for load addition 28
Initially, there is 20 MW load in the plant and the disturbance is created by
adding 20 MW load to the existing 20 MW load at SG terminal at time t = 5.0 seconds
and simulation is carried out for 10.0 seconds. All the quantities are in per units unless
it is stated.
Fig. 4.7 shows generator voltage variation with time, Fig. 4.8 shows a
variation of generator current with time, Fig. 4.9 shows the variation of load current
with time, Fig. 4.10 shows the variation of the electrical power of the generator with
time, Fig. 4.11 shows the variation of rotor speed with time, Fig. 4.12 shows the
variation of excitation voltage with time, Fig. 4.13 shows the variation of generator
load angle with time, Fig. 4.14 shows the variation of mechanical power with time,
Fig. 4.15 shows the variation of grid voltage with time, Fig. 4.16 shows the variation
of grid current with time and Fig. 4.17 shows the variation of gate opening with time.
30
Fig. 4.13: Generator load angle (degree) Vs time
Initially, the generator voltage, rotor speed, and grid voltage are at 1.0 pu,
while the generator current and grid current are at 0.65 pu and 0.35 pu, respectively.
The load current at 0.1 pu, the electrical power at 0.75 pu, the excitation voltage at
1.10 pu, generator load angle at 27 degree, mechanical power at 0.754 pu, and gate
opening at 0.726 pu.
From the Fig. 4.7 and 4.15, it is observed that there is no effect on the generator
voltage and grid voltage due to the addition of load while there is slight increase in the
generator current during the addition of load at t = 5.0 seconds and it reached to initial
steady state value after 6.0 seconds as shown in Fig. 4.8. The load current is doubled to
around 0.2 pu from the initial value of 0.1 pu due to the addition of load as illustrated in
Fig. 4.9. It is observed that the electrical power is increased to 0.8 pu from the initial
value of 0.75 pu during the addition of load and it reached to initial steady state value
after 7.0 seconds as shown in Fig. 4.10 while the rotor speed is decreased at the time of
load addition but it reached to initial steady state value after 7.0 seconds as illustrated in
Fig. 4.11. There is increase in excitation voltage to around
1.3 pu at the time of load addition and it oscillates for around 3.0 seconds and reached
to initial steady state value after 8.0 seconds as shown in Fig. 4.12. There is also
increase in generator load angle to 28 degree from 27 degree at the time of addition of
load and it oscillates for around 2.0 seconds and the initial steady state value is
reached after 7.0 seconds as illustrated in Fig. 4.13. The mechanical power developed
is also increased during the addition of load at t = 5.0 seconds and it oscillates for
around 3.0 seconds and it reached to initial steady state value after 8.0 seconds as
shown in Fig. 4.14. Due to the addition of load, the grid current is decreased to 0.29
pu from 0.3 pu as illustrated in Fig. 4.16. From Fig. 4.17, it is observed that the gate
opening is decreased when load is added to the system and it oscillates for around 2.0
seconds and reached back to initial steady state after 7.0 seconds.
32
4.3.2 Case -II: Load Reduction
For this case, the Matlab/Simulink model is shown in Fig. 4.18 and single line
diagram is shown in Fig. 4.19.
Fig. 4.18: MATLAB/Simulink model of hydro power plant for load reduction
Initially, 40 MW is the total load in the plant and the disturbance is introduced
by removing 20 MW load from the total load at SG terminal at time t = 5.0 seconds
and simulation is carried out for 10.0 seconds. All the quantities are in per units unless
it is stated.
33
Fig. 4.20 shows generator voltage variation with time, Fig. 4.21 shows a
variation of generator current with time, Fig. 4.22 shows the variation of load current
with time, Fig. 4.23 shows the variation of the electrical power of the generator with
time, Fig. 4.24 shows the variation of rotor speed with time, Fig. 4.25 shows the
variation of excitation voltage with time, Fig. 4.26 shows the variation of generator
load angle with time, Fig. 4.27 shows the variation of mechanical power with time,
Fig. 4.28 shows the variation of grid voltage with time, Fig. 4.29 shows the variation
of grid current with time and Fig. 4.30 shows the variation of gate opening with time.
34
Fig. 4.23: Electrical power Vs time
35
Fig. 4.27: Mechanical power Vs time
From the Fig. 4.20 and 4.28, it is observed that there is no effect on the
generator voltage and grid voltage due to the reduction of load while there is slight
decrease in the generator current during the addition of load at t = 5.0 seconds and
generator current reached to initial steady state value after 6.0 seconds as shown in
Fig. 4.21. The load current is decrease to around 0.1 pu from the initial value of 0.2 pu
due to the reduction of load as illustrated in Fig. 4.22. It is observed that the electrical
power is decreased to 0.7 pu from the initial value of 0.75 pu during the reduction of
load and it reached to initial steady state value after 7.0 seconds as shown in Fig. 4.23
while the rotor speed is increased at the time of load reduction but it reached to initial
steady state value after 7.0 seconds as illustrated in Fig. 4.24. There is decrease in
excitation voltage to around 1.0 pu at the time of load reduction and it oscillates for
about 3.0 seconds and reached to initial steady state value after 8.0 seconds as shown
in Fig. 4.25. There is also decrease in generator load angle to 26 degree from 27
degree at the time of reduction of load and it oscillates for about 2.0 seconds and the
initial steady state value is reached after 7.0 seconds as illustrated in Fig. 4.26. The
mechanical power developed is decreased during the reduction of load at t = 5.0
seconds and it oscillates for about 3.0 seconds and reached to initial steady state after
8.0 seconds as shown in Fig. 4.27. Due to the reduction of load, the grid current is
increased to 0.35 pu from 0.29 pu as illustrated in Fig. 4.29. From Fig. 4.30, it is
observed that the gate opening is increased when load is removed from the system and
it oscillates for about 2.0 seconds and reached back to initial steady state after 7.0
seconds.
37
4.3.3 Case -III: Short Circuit Fault
For this case, the Matlab/Simulink model is shown in Fig. 4.31 and single line
diagram is shown in Fig. 4.32.
Fig. 4.31: MATLAB/Simulink model of hydropower plant for short circuit fault
Fig. 4.32: Single line diagram for three phase short circuit fault at SG terminal 38
Fig. 4.33 shows generator voltage variation with time, Fig. 4.34 shows the
variation of generator current with time, Fig. 4.35 shows the variation of the load
current with time, Fig. 4.36 shows the variation of the electrical power of generator
with time, Fig. 4.37 shows the variation of rotor speed with time, Fig. 4.38 shows the
variation of excitation voltage with time, Fig. 4.39 shows the variation of generator
load angle with time, Fig. 4.40 shows the variation of mechanical power with time,
Fig. 4.41 shows the variation of grid voltage with time, Fig. 4.42 shows the variation
of grid current with time, and Fig. 4.43 shows the variation of gate opening with time.
41
Initially, the generator voltage, rotor speed, and grid voltage are at 1.0 pu,
while the generator current and grid current are at 0.65 pu and 0.29 pu, respectively.
The load current around 0.1 pu, the electrical power at 0.75 pu, the excitation voltage
at 1.10 pu, generator load angle at 27 degree, mechanical power at 0.751 pu, and gate
opening at 0.725 pu.
42
4.4 Hydraulic Transient Analysis of Hydropower Plant for Different Values
of PID Governor Gain
The transient analysis of hydropower plant is carried out by simulating the
hydropower plant model for different values of PID governor gain (Kp, Ki and Kd).
gain (Ki) keeping the proportional gain (K p=1.0) and derivative gain (K d=0.0) constant.
All the quantities are in per units unless it is stated. The transient analysis of the electrical
power, mechanical power, rotor speed, and gate opening are carried out for the different
values of integral gain (K i) 0.1, 0.2 and 0.3. Fig.4.48 shows electrical power with respect
to time, Fig.4.49 shows mechanical power with respect to time,
44
Fig.4.50 shows rotor speed with respect to time and Fig.4.51 shows gate opening with
respect to time.
proportional gain (Kp =1.0) and derivative gain (Kd=0.0). Thus, increases the settling
time of the electrical power, mechanical power, rotor speed and gate opening.
Therefore, a system is becoming unstable when the integral gain increased.
48
Fig. 4.57: Console subsystem
49
4.6 Simulation Results in RT-LAB Environment and Discussion
The real-time simulation results in RT-LAB environment for different cases
are presented and discussed below.
50
Fig. 4.62: Generator load angle (degree) Vs time
From the real-time simulation results obtained for the load addition on large
hydropower plant, the electrical power, rotor speed, excitation voltage, mechanical
power, generator load angle and gate opening characteristics of the plant are similar
with the simulation results obtained in Matlab/Simulink environment for load
addition. However, it is observed from the real-time simulation results that the
addition of load does not take place at the instant of the set time but the effect of load
addition is felt after few seconds from the set time.
51
4.6.2 Case -II: Load Reduction
With keeping the same conditions given in Matlab/Simulink model simulation,
the real-time simulation results of electrical power, rotor speed, excitation voltage,
generator load angle, mechanical power, and gate opening for load reduction on large
hydropower plant are obtained as shown in Fig. 4.65, 4.66, 4.67, 4.68, 4.69 and 4.70
respectively.
52
Fig. 4.68: Generator load angle (degree) Vs time
53
4.6.3 Case -III: Short Circuit Fault
With keeping the same conditions given in Matlab/Simulink model simulation,
the real-time simulation results of electrical power, rotor speed, excitation voltage,
generator load angle, mechanical power, and gate opening for three phase to ground
faults on large hydropower plant are obtained as shown in Fig. 4.71, 4.72, 4.73, 4.74,
4.75 and 4.76 respectively.
54
Fig. 4.74: Generator load angle (degree) Vs time
From the real-time simulation results obtained for three-phase to ground faults
on large hydropower plant, the electrical power, rotor speed, excitation voltage,
mechanical power, generator load angle and gate opening characteristics of the plant
are same with the simulation results obtained in Matlab/Simulink environment.
55
CHAPTER 5
CONCLUSIONS AND FUTURE SCOPE OF WORKS
In this chapter, conclusion of the work presented in this thesis and future scope
of work is presented.
5.1 Conclusions
In this dissertation work, mathematical modeling of various components of the
hydropower plant is carried out. The individual components of hydropower plant:
nonlinear hydraulic turbine, excitation system, Proportional, Integral and Derivative
(PID) governor, synchronous generator, three phase transmission line and three phase
grid are developed in MATLAB/Simulink environment. The individual components of
hydropower plant are integrated to form hydropower plant and simulated for various
operating conditions i.e., load addition, load reduction and three-phase to ground fault.
The Matlab/Simulink model of the hydropower plant is simulated in real-time
simulation environment (RT-LAB) for the same conditions carried out in
Matlab/Simulink environment after some modification of the Matlab/simulink model.
56
ii. PID governor is considered for the developed simulation model. The simulation
model may be developed considering artificial intelligence for control systems.
iii. The real-time simulation of the hydropower plant under RT-LAB environment is
carried out for software synchronization. The simulation can be extended to
hardware synchronization.
57
REFERENCES
[5] “Alternative energy sources: Energy generation and storage using water.”
[Online]. Available: http://www.hk-phy.org/energy/alternate/hydro_is02_e.
html. [Accessed: 13-Oct-2015].
[7] A. M. Law, "Simulation Modeling and Analysis.", MC. Graw Hill, 2008.
[10] Y. Wangdi and D. Richards, “Modelling and simulation of the Chukha hydro
power plant, Bhutan and the nearby Indian power system,” Power Symp.
1990., Proc. Twenty-Second Annu. North Am., pp. 398–404, October, 1990.
58
studies,” POWERCON ’98. 1998 Int. Conf. Power Syst. Technol. Proc. (Cat.
No.98EX151), vol. 2, pp. 1300–1304, August, 1998.
[15] S. Jadid and A. Salami, “Accurate model of hydroelectric power plant for load
pickup during power system restoration,” 2004 IEEE Reg. 10 Conf. TENCON
2004., vol. C, pp. 307–310, November, 2004.
[18] G. Robert and F. Michaud, “Hydro power plant modeling for generation control
applications,” Am. Control Conf., pp. 2289–2294, June, 2012.
59
375, June, 1995.
[23] H. Gao and C. Wang, “Effect of detailed hydro turbine models on power system
analysis,” 2006 IEEE PES Power Syst. Conf. Expo. PSCE 2006 - Proc., no.
50277034, pp. 1577–1581, October/November, 2006.
[24] K. A. Naik, P. Srikanth, and P. Negi, “Imc Tuned Pid Governor Controller for
Hydro Power Plant with Water Hammer Effect,” Procedia Technol., vol. 4, pp.
845–853, 2012.
[25] M. Vinatoru and E. Iancu, “The design of control systems for hydraulic
turbines,” 2006 IEEE Int. Conf. Autom. Qual. Testing, Robot. AQTR, no. 13,
pp. 32–36, May, 2006.
[26] H. Zhang, D. Chen, B. Xu, and F. Wang, “Nonlinear modeling and dynamic
analysis of hydro-turbine governing system in the process of load rejection
transient,” Energy Convers. Manag., vol. 90, pp. 128–137, November, 2014.
60
for Hydropower Plants,” 2005 IEEE/PES Transm. Distrib. Conf. Exhib. Asia
Pacific Dalian, China, pp. 1–4, 2005.
[36] O. P. Rahi and G. Kumar, “Simulation Studies for Refurbishment and Uprating
of Hydro Power Plants,” PES Gen. Meet. / Conf. Expo. 2014 IEEE, pp. 1–5,
July, 2014.
[38] C. Nicolet, P. F. Avellan, P. Allenbach, A. Sapin, and J.-J. Simond, “New Tool
for the Simulation of Transient Phenomena in Francis Turbine Power Plants,”
Proc. Hydraul. Mach. Syst. 21st IAHR Symp., vol. 1, no. September 2015, pp.
1–8, 2002.
[39] P. Kunder, “Power System Stability and Control,.” New Delhi: Tata McGraw
Hill Education Private Limited.
[40] K. Anil Naik, P. Srikanth, and A. K. Chandel, “A novel governor control for
stability enhancement of hydro power plant with water hammer effect,” Int.
Conf. Emerg. Trends Electr. Comput. Technol., pp. 40–45, March, 2011.
[41] IEEE Working Group Report, “Hydraulic Turbine and Turbine Control Models
for System Pynamic Studies,” 1992.
61
machine - Simulink - MathWorks India.” [Online]. Available: http://in.math
works.com/help/physmod/sps/powersys/ref/synchronousmachine.html;jsessioni
d=68c293295733897701bf1d106348. [Accessed: 06-Jan-2016].
62