• Deck is new construction and has never been installed. • New Jacket can be quickly fabricated • Platform designed as a normally unmanned wellhead platform • Drilling to be performed by Jackup Drilling Rig • 16 well slots designed to accommodate “dual trees” • 45’ x 45’ deck leg spacing • Main Deck 85’ x 89’, (plated) designed for coiled tubing • Cellar Deck 85’ x 96’, (grated) • Sub-cellar Deck 45’ x 28’ (grated) • Design Rates: • 40,000 BOPD • 30,000 BWPD • 25 MMSCFD Produced Gas • 7 MMSCFD Gas Lift OKWOK WELLHEAD PLATFORM EQUIPMENT LIST
• Wellhead Control Panel
• Production Manifold Skid No. 1 • Gas Lift Manifold Skid • Water Injection Manifold Skid • Gas Injection Manifold Skid • Chemical Injection Skid No. 1/No.2 • Instrument Air Skid • Platform Crane 25 ton • Diesel Transfer Pump Skid • Tool Storage Building • MCC Building • Pipeline Pig Launcher • Sump Tank OKWOK WELLHEAD PLATFORM MAIN DECK EQUIPMENT LAYOUT OKWOK WELLHEAD PLATFORM CELLAR DECK EQUIPMENT LAYOUT OKWOK WELLHEAD PLATFORM SUB-CELLAR DECK EQUIPMENT LAYOUT