MINGGU KE-1 MINGGU KE-2 MINGGU KE-3


NO. URAIAN PEKERJAAN BOBOT
15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct 1-Nov 2-Nov 3-Nov 4-Nov 5-Nov
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
PEKERJAAN ELEKTRIKAL LANTAI 1

I PEKERJAAN PANEL - PANEL DISTRIBUSI. 14.24


1.19 1.19 1.19 1.19 1.19 1.19 1.19 1.19 1.19 1.19 1.19 1.19

II PEKERJAAN KABEL FEDEER & GROUNDING 7.75 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77

III PEKERJAAN KABEL TRAY 4.88 0.70 0.70 0.70 0.70 0.70
0.70 0.70

IV PEKERJAAN INSTALASI PENERANGAN 11.91 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85
0.85 0.85 0.85 0.85

V PEKERJAAN ELEKTRONIC 41.66 2.60 2.60 2.60 2.60 2.60 2.60 2.60 2.60 2.60 2.60 2.60 2.60 2.60 2.60 2.60 2.60

VI PEKERJAAN AIR CONDITIONING ( AC ) 9.91 0.99 0.99 0.99


0.99 0.99 0.99 0.99 0.99 0.99 0.99

VII PEKERJAAN INSTALASI PEMADAM KEBAKARAN 9.66 0.97 0.97


0.97 0.97 0.97 0.97 0.97 0.97 0.97 0.97

RENCANA BOBOT MINGGUAN 100.00 0.85 0.85 0.85 1.63 1.63 2.32 4.93 5.92 6.88 6.88 8.07 8.07 7.37 6.60 5.75 5.75 5.75 4.76 3.79 3.79 3.79 3.79

AKUMULATIF RENCANA BOBOT MINGGUAN 0.85 1.70 2.55 4.18 5.80 8.12 13.05 18.97 25.85 32.73 40.80 48.87 56.24 62.84 68.59 74.33 80.08 84.84 88.63 92.42 96.21 100.00

RENCANA REALISASI MINGGUAN 1.38 1.38 1.38 1.38 1.38 1.38 1.38

AKUMULATIF REALISASI MINGUAN 1.38 2.76 4.15 5.53 6.91 8.29 9.67

DEVIASI 0.53 1.06 1.59 1.35 1.11 0.17 -3.38