Kurva S
Kurva S
II PEKERJAAN KABEL FEDEER & GROUNDING 7.75 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77
III PEKERJAAN KABEL TRAY 4.88 0.70 0.70 0.70 0.70 0.70
0.70 0.70
IV PEKERJAAN INSTALASI PENERANGAN 11.91 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85
0.85 0.85 0.85 0.85
V PEKERJAAN ELEKTRONIC 41.66 2.60 2.60 2.60 2.60 2.60 2.60 2.60 2.60 2.60 2.60 2.60 2.60 2.60 2.60 2.60 2.60
RENCANA BOBOT MINGGUAN 100.00 0.85 0.85 0.85 1.63 1.63 2.32 4.93 5.92 6.88 6.88 8.07 8.07 7.37 6.60 5.75 5.75 5.75 4.76 3.79 3.79 3.79 3.79
AKUMULATIF RENCANA BOBOT MINGGUAN 0.85 1.70 2.55 4.18 5.80 8.12 13.05 18.97 25.85 32.73 40.80 48.87 56.24 62.84 68.59 74.33 80.08 84.84 88.63 92.42 96.21 100.00
RENCANA REALISASI MINGGUAN 1.38 1.38 1.38 1.38 1.38 1.38 1.38
AKUMULATIF REALISASI MINGUAN 1.38 2.76 4.15 5.53 6.91 8.29 9.67