Professional Documents
Culture Documents
Procedure For Composite Gider Constructionconstruction
Procedure For Composite Gider Constructionconstruction
G.Radhakrishnan
Composite girders are coming up mostly for Road Over Bridges for which detailed
guidelines are yet to be issued by RDSO. A trial has been made for quality control in
fabrication of steel portion of composite girders with reference to the following codes,
manuals & guidelines so as to have confidence in fabrication with required quality.
IS 2062 – 2006
IS 1852-1985 (Re-affirmed 1998).
IRBM-1998
IRS B-1-2001
IRS Steel Bridge Code
IRS Welded Bridge Code
Schedule of Technical Requirements (STR) issued by RDSO
Stages
Suitability of Workshop
• Spaceavailability for
Raw material receipt & storage
Cutting & storing the steel members during various stages of fabrication
Inspection of fabricated members
Painting or metalizing (Better to do metalising @ site after splicing so as to
get uniformity otherwise discontinuity will occur which is prone to develop
corrosion)
Stacking of finished members till dispatch
• Required machineries
Crane with minimum 10t capacity for handling the components
Steel measuring tape duly calibrated
Plate & structural sections straightening machine
Profile cutting equipment
Self-propelled straight cutting equipment (Oxy-acetylene gas)
Edge planning machine for edge preparation before welding
Automatic SAW equipment
Welding transformer/rectifier for MMAW
Inert gas CO2 welding machine
Radial drilling machine with adequate capacity
Weld gauge for checking size & throat thickness
Leveling instrument for measuring camber
ELCO meter for measuring the paint or metalising thickness
DP test kid for checking the welds (NDT)
Adequate power supply with alternate arrangements like generator
In-house jig manufacturing capabilities
System for periodical maintenance of M&P
1. Inspection of welds
2. Inspection of Rivets
3. Structural and dimensional inspection
4. Trial Assembly (First Girder)
1. Raw material:
Steel confirms to IS: 2062 – 1992 - Grade B (Revised code 2006, Amended 2009)
Rolling & Cutting Tolerances w.r.to IS 1852-1985 (Re-affirmed 1998).
Sampling & testing in approved lab or IIT/NIT/Government Engineering colleges or
as per conditions of contract
Mill TCs with cast number / heat number (10 & 12mm plates with less than
2.0m width are coming as coils which are having cast number and other
plates are having heat number
Physical Properties like tensile, bend & impact tests as per IS 2062 Grade B
Chemical Composition for IS 2062 Grade B
2. Consumables:
Rivets
Material (IS: 1148)
Finished Rivet (IS: 1929)
Electrode
Flux coated manual welding electrode (IRS: M-28)
Copper coated wire for CO2 Welding (IRS: M-46)
Copper coated wire for SAW (IRS: M-39)
Welding flux agglomerated/ granulated for SAW (IRS: M-39)
3. FABRICATION PROCESS:
Straightening.
Cutting of Plates/Sections.
Welding for Welded Girder.
Drilling of Holes with Approved Jig.
Initial Assembly.
End Profile cutting.
End Milling.
End Finishing.
Quality Control:
• INSPECTION:
Pre Fabrication Stage.
During Fabrication Stage.
After Fabrication Stage.
• PRE-FABRICATION STAGE:
Approved Drawing.
Infrastructure for Fabrication.
Approval of QAP.
Preparation of WPSS
Procedure Qualification and Approval of Welders.
Raw Material Inspection & Testing.
Jig & Fixtures
DURING FABRICATION:
Use of Tested Raw Material
Stage Inspection.
Use of Approved Set of Jigs.
Deployment of Qualified Welders.
Preparation of Joint Details and Parameters as per WPSS.
Radiographic Evaluation of Butt Joints.
Application of Primer on Permanent Contact Surfaces.
• AFTER FABRICATION:
Dimensional Inspection.
Sections Used,
Overall Length,
Bearing Centres,
Distance between Group
of Holes,
Number of Holes,
Pitches/ Gauges,
Weld Inspection:
Visual Inspection,
Dye Penetrant Test,
Magnetic Particle Test,
Macro Etching,
Throat Thickness,
Leg Length,
Root Penetration,
Weld Profile.
Painting:
The entire steel portion except shear connectors of composite girders to be metalised at
bridge site after assembling/splicing, riveting/HSFG bolting
• Higher level of surface preparation with sand blasting (material in accordance with
Clause 3 of IS: 6586 & surface produced in accordance with appendix A of IS: 5905)
Washed salt free angular silica sand of mesh size 12 to 30 with a minimum of 40%
retained on a 20 mesh screen and shall provide an adequate key for the
subsequently sprayed metal coating)
• Nozzle dia: Not exceeding 12mm & nozzle position @ right angles to and
approximately 225mm from the surface with pressure not less than 2.109 kg/cm2
• Aluminium wire 3mm dia conforming to BS: 1475/IS: 739
• Spraying pressure not less than 4.218 kg/cm2
• Multiple layers within specified time intervals
• Painting scheme
Primer: ETCH primer (IS: 5666) or wash primer (SSPCPT-3537) - one coat,
Paint Zinc Chromate primer (IS: 104) – one coat,
Finishing coat: Paint Aluminum (IS: 2339) – 2 coats.
DO’S AND DON'TS in the fabrication of composite girder:
Use only the weldable quality steel conforming to IS: 2062 Gr ‘B’ fully killed
and fully normalized.
Obtain the steel test certificate (material testing certificate) and check carefully the
chemical composition and mechanical properties of steel to ensure that it conforms
to IS: 2062 Gr ‘B’ fully killed and fully normalized. In addition, Railways having the
rights to take samples to ensure that it conforms to IS:2062 Gr ‘B’ fully killed and
fully normalized
Steel received from the rolling mills has generally punch heat mark numbers. These
numbers should be legibly marked again with paint for easy identification. Heat mark
numbers should be transferred to cut members with paints. For plates less than
16mm, cast number instead of heat marks to be ensured
The welding electrodes must conform to IRS/M-28 for manual metal are welding,
wire-flux combination must conform to IRS/M-39 and for CO2 welding the RDSO
approved procedure must be followed.
Before taking up the fabrication of each type of welding joint the welding procedure
specification sheet (WPSS) should be prepared and approved by nominated person
by the competent authority.
After the WPSSs are approved by the competent authority, the qualified welders as
per IS: 7310 (Pt-I)-74, shall only be deployed for the welding works. For this, test
pieces should be made by the welders according to the approved WPSSs in presence
of nominated person by the competent authority. If the test pieces are found
satisfactory the welding procedure qualification record (WPQR) is approved and the
welder is qualified. After the welder is qualified, the fabrication of the girder can be
taken up.
While fabricating the welded bridge girder follow the guidelines and fabrication
tolerance as laid down in “Code of practice for metal are welding in Mild Steel
Bridges carrying Rail, Rail-Cum-Road or Pedestrian Traffic (Welded Bridge Code)”
and “Fabrication and Erection of Steel Girder Bridge, IRS B1-2001”.
Maintain the same welding parameters like welding current, voltage, polarity of the
electrode, speed and travel of welding heads etc. as approved in the WPSS for
particulars type of welding work.
While welding in cold weather pre-heat the material before welding and apply post
heating to prevent the weld joint from rapid cooling and develop stress raiser due to
sudden contraction.
Welding must be done in proper welding position as already approved in WPSSs and
WPQRs.
Channel shear connectors shall be welded on top flange plate prior to assembly of ‘I’
section. This facilitates correction of any distortion of flange plate developed during
the welding of channel shear connectors and also it will restrict the magnitude of
warping of top flange during SAW
The orientation of shear connectors should have symmetricity with respect to the
centre of girder
Tack welds shall be not less than the throat thickness or leg length of the root run to
be used in the joint. The length of the tack weld shall not be less than four times the
thickness of the thicker part or 50 mm whichever is the smaller and tack welds shall
not be made at extreme ends of joints. The electrode for tack welding shall be the
same as that of normal MMAW.
Do not keep the welding consumables in open or in damp place, as these will absorb
moisture. Welding with damp electrodes will result in porosity and cracks in the
welded joint and impair the quality and strength of the joint.
Do not allow the un-qualified welder to make the welding joint, as the proper quality
welding is not guaranteed.
Do not weld with un-controlled welding parameters, these will affect the quality of
welding and make the joints weak and may yield in dynamic loading on the
structure.
Do not weld the joint haphazardly with out following the proper welding sequence.
Otherwise, this will lead to uncontrolled and irreparable distortion of the proper
geometry of the joint.
Do not hammer the distorted joints for rectification. It may lead to the development
of cracks and failure of the joints.
Do not do the welding without proper protection like welding goggles,
welding gloves, welding masks, etc.