ITEM DESCRIPTION

100(1) CLEARING AND GRUBBING


103(56) STRUCTURE EXCAVATION (RCPC & DRAIN)
105(1) SUBGRADE PREPARATION (COMMON MATERIALS)
200 AGGREGATE SUBBASE COURSE
500(1) PIPE CULVERT, 910MM DIAMETER
505(5) GROUTED RIPRAP, CLASS "A"
SPL6 BILLBOARD

S-CURVE
100

90

80

70
PERCENT ACCOMPLISHMENT

60

50

40

30

20

10

0
0 16 32 48 64

CONSTRUCTION DURATION

0
16
32
48
64
0 5
QUANTITY UNIT UNIT COST TOTAL COST
3.9 ha 47113.64 183743.196
36.96 cu.m 539.59 19943.2464
39000 sq.m 9.39 366210
217.44 cu.m 995.75 216515.88
22 lm 7076.2 155676.4
3.29 cu.m 5883.95 19358.1955
3 units 4165.91 12497.73
TOTAL 973944.6479

0 5
`

A
3
``

B
64 QUARTERLY COST 229,
CUMULATIVE COST 229,
% CUMULATIVE COST 23
0
23.57
57.39
85.57
100

0 0 A
5 10 15 20 25 30 35

5 10 15 20 25 30 35

10 15

14 25

229,526.38 333,356.41 270


229,526.38 562,882.79 833,
23.57% 57.39% 85
10

25

0
14

3 3 14
B
3 14

5 10 15 20 25 30 35
40 45 50 55 60 65

40 45 50 55 60 65

10 0

25

270555.88 140,505.98
833,438.67 973,944.65
85.57% 100%
15 10

25

14 14 C
35 40 45 50 55 60 65
24 39 E
NODES ACTIVITY TIME (DAYS)
A-B BILL BOARD 3
A-C CLEARING AND GRUBBING 14
B-C DUMMY 0
C-D SUBGRADE PREPARATION 25
C-E STRUCTURE EXCAVATION 10
E-F PIPE CULVERT 15
F-G GROUTED RIPRAP 10
G-H DUMMY 0
D-H AGGREGATE SUBBASE COURSE 25
ES EF LS LF TOTAL FLOAT FREE FLOAT
0 3 0 3 0 0
0 14 0 14 0 0
3 3 14 14 11 0
14 39 14 39 0 0
14 24 29 39 15 0
24 39 39 54 15 0
39 49 54 64 15 0
49 49 64 64 15 15
39 64 39 64 0 0
REMARKS

CP

CP

CP
S-CURVE
100

90

80

70
PERCENT ACCOMPLISHMENT

60

50

40

30

20

10

0
0 16 32 48 64

CONSTRUCTION DURATION
0 0
23.57 16
57.39 32
85.57 48
100 64

64