TILEWORKS

FLOOR AREA

ATOTAL = 69 m2

UNIT COST TOTAL COST


QUANTITY UNIT DESCRIPTION MATERIALS LABOR MATERIALS LABOR COST
(40%) (40%)
211 PCS 0.6 M x 0.6 M POLISHED CERAMIC 150 60 31650 12660 44310
TILES
23 BG TILE ADHESIVE 400 160 9200 3680 12880
23 BG TILE GROUT 75 30 1725 690 2415
13 PCS TILE TRIM 100 40 1300 520 1820
TOTAL 61425
TILEWORKS

TOILET AND BATH

AFLOOR = 3 m2

ALATERAL = 12.35 m2

UNIT COST TOTAL COST


QUANTITY UNIT DESCRIPTION MATERIALS LABOR MATERIALS LABOR COST
(40%) (40%)
85 PCS 0.4 M x 0.4 M UNGLAZED TILES 60 24 5100 2040 7140
21 PCS 0.4 M x 0.4 M UNGLAZED TILES 60 24 1260 504 1764
6 BG TILE ADHESIVE 400 160 2400 960 3360
6 BG TILE GROUT 75 30 450 180 630
5 PCS TILE TRIM 100 40 500 200 700
TOTAL 13594