You are on page 1of 9

PT.

Sigma Kreasi Instrument (SKIns)


Training & Consulting – Procurement – Engineering Services

Project : Upgrading Fuel & Detonation Control System


Client : Petrochina International Jabung Ltd
No.Contract : PCJ-2733-CA

WORK PROCEDURE METHOD

FOR

UPGRADING FUEL & DETONATION CONTROL SYSTEM

AT CP-5100 & K-600


PT. Sigma Kreasi Instrument (SKIns)
Training & Consulting – Procurement – Engineering Services

Contents

1. Introduction
1.1 Purpose
1.2 Scope
1.3 Test Overview
1.4 General Procedures
1.5 Succes Criteria
1.6 Constraints and Limitations
1.7 Coverage Matrix
1.8 Definition,Acronyms, and Abbreviations
1.9 References
1.10 Refernces Documents

2. Functional Test
2.1 Introducton
2.2 Exacta 21 Logic Test as per Flow Chart & Control Philosophy
2.3 Exacta 21 Logic Test as per Cause & Effect
2.4 Graphic Test
2.5 Modbus Interface Simulations Test
2.6 Test Check List
PT. Sigma Kreasi Instrument (SKIns)
Training & Consulting – Procurement – Engineering Services

Section 1

Introduction

1.1 Purpose
1.2 Scope
1.3 Test Overview
1.4 General Procedures
1.5 Succes Criteria
1.6 Constraints and Limitations
1.7 Coverage Matrix
1.8 Definitions, Acronyms And Abbreviations
1.9 References
1.10 Reference Documents

1 Introduction

This Volume of document forms the Test Procedure for Upgrading fuel & Detonation Control System
at CP-5100 & K-600.

1.1 Purpose

1.1.1 Objective
PT. Sigma Kreasi Instrument (SKIns)
Training & Consulting – Procurement – Engineering Services

The Objective of this document are as follow : -

(a) to define the funtions to be provided


(b) to be used as the basis for Site Acceptance Test.

1.1.2 Intended Readers

The intended readers are listed below who will be involved in one way or another :

(a) Vendor
(b) Client's Representative
1.2 Scope

The scope of the document defines all Procedure Method of the system as provided in the following chapters.

1.3 Test Overview

This section describes the testing philosophy, objectives , general procedures and the success criteria for this
Acceptance test.

1.3.1 Testing Philosophy

1.3.2 The Procedures test shall take place at Client's premises. It shall be conducted by Vendor and witnessed
By Client's personnel,all of those understand the background and objectives of each test.

1.3.3 Ther be shall be at least one test case covering a specific functional area. The actual number of test cases
needed would be agreed upon client and Vendor.
PT. Sigma Kreasi Instrument (SKIns)
Training & Consulting – Procurement – Engineering Services

1.3.4 Each test case's result shall be recorded for reference if further testing is required or it will be signed off
by Client if the result satisfies the acceptance criteria defined for the test.

1.3.5 The original Test Procedure shall be signed by Client and Vendor with Vendor keeping the original and
Client the copy.

1.4 General Procedures

1.4.1 Vendor's personnel will carry out the test with the client's observation according to the step-by-step test
Procedures or steps prepared each test.

1.4.2 All test cases are described in section 1.7 of this document.

1.4.3 Vendor's Test Supervisor shall record the data or result of the test procedure or steps for each test case.

1.4.4 Vendor's Test Supervisor shall record any comments on the tests being carried out

1.4.5 Client, the test Approver will observe the result of the test cases.If the test case satisfies its succes criteria,
The test Approver will sign on the test case certificate and record down the date completion.

1.4.6 Vendor's Project Manager shall collect all test cases that are not signed, determined the effort required to
Get ready for a retest and arrange the time with Client.

1.4.7 When all the test case certificates have been sign off, the Test Supervisor or Vendor Project Manager shall
Sign on the Acceptance Test Certificate. The date of acceptance shall also be recorded.
PT. Sigma Kreasi Instrument (SKIns)
Training & Consulting – Procurement – Engineering Services

1.5 Succes Criteria

The Acceptance Criteria of the system delivered by Vendor are translated into test cases whre each test further
defines the individual succes criteria. When all test cases have been signed off, Client shall sign the ANNEX A
of this document to declare acceptance of the system.

1.6 Constraints and Limitations

1.6.1 All simulation of valves opening and closing and motor starters are provided by forcing the Exacta I/Os.

1.6.2 Only those on the Exacta that are provided in this contract would be simulated.

1.7 Coverage Matrix

The following chart shows the areas of the systems to be tested and the test case number covering each area.
Those "H" test cases would cover the hardware area while "F" cases cover the functionality.

Part Requirements / Functions Test Case #


H001
1.0 Controller Panel Loop Check

( Digital Input,Digital Ouput,Analog


Input,Analog Output Check ,and Thermocouple
Input Check )
PT. Sigma Kreasi Instrument (SKIns)
Training & Consulting – Procurement – Engineering Services

( As per Internal Wiring Diagram )

H002
Bill of Material Check
2.0
( Hardware & Accesories )

F101
Exacta21 Logic Test As per Flow Chart &
3.0 Control Philosophy

Exacta21 Logic Test As per Cause & Effect


4.0 F102

Graphic Test
5.0 F103
( As Per P&ID or submitted graphic
screen s )

1.8 Definitions, Acronyms And Abbrevations

1.8.1 Glossary

1.8.1.1 Database : a group of blocks that connects software to the hardware and defines the control strategy
1.8.1.2 Node : a station within a network e.g. SCADA Node.
PT. Sigma Kreasi Instrument (SKIns)
Training & Consulting – Procurement – Engineering Services

1.8.1.3 Tag : a user's define name,particularly for a block in the database or instrument. Tag is
synonymous with tag name.

1.8.2 Acronyms

1.8.2.1 Midas : Monitored Information Devices And Systems

1.8.3 Abbrevations

1.8.3.1 I/O : Input and Ouput

1.8.3.2 PID : Proportional ,Integral and Derivative

1.8.3.3 DI : Digital Input

1.8.3.4 DO : Digital Output

1.8.3.5 AI : Analog Input

1.8.3.6 AO : Analog Output

1.8.3.7 TC : Thermocouple Input

1.9 References

1.9.1 CPU Exacta21 data sheet


PT. Sigma Kreasi Instrument (SKIns)
Training & Consulting – Procurement – Engineering Services

1.9.2 Exacta21 Discrete Board data sheet

1.9.3 Exacta21 Smart Analog data sheet

1.10 References Documents

1.10.1 Vendor generated document

A. I/O Instrument List ( Rev )

B. Bill of Material

C. Midas HMI Graphic Screens ( Add)

D. Internal Wiring Diagram ( Rev)

You might also like