Professional Documents
Culture Documents
ABSTRACT
This paper covers the optimization of the investment of a large system / plant, as a balance between
reliability, life costs and incomes; it is the development at system level of a work presented at IX ICEC
World Congress.
The general topics are:
- Relationships amongst the service supply, life cost and incomes.
- Plant alternatives, and the relevant costs.
- System reliability assessment, i.e. the outages frequency and duration, and their economic
impact.
- Criteria for comparison of the alternatives, to reach a sound decision.
Some topics are also considered:
- Economic Impact of Common Cause Failures.
- Cost reduction with autodiagnostic.
- Impact of repair times
1. INTRODUCTION
The energy supply continuity has become one of the more relevant factors both in Industrialized and in
Developing Countries; therefore, a suitable analysis is recommended to reach a sound compromise
between service quality and cost.
The evaluation of industrial projects is usually carried out trying to reach an optimization / compromise
between performance and what are considered overall costs along the project life; conversely,
reliability aspects are often taken into account only once that the plant configuration and the budget
have been decided, and this rarely leads to a sound optimization.
In general, reliability and performance are considered as opposite to lower cost; the solution is to reach
an optimization that can be:
- Maximum reliability at a prefixed cost, or
- Minimum cost at a prefixed reliability level
Optimization of the Investment of a Large System / Plant, as a Balance between Reliability,
Costs and Incomes 2
2. METHODOLOGY
The following example will be used to clarify the application of the above proposed methodology.
This analysis covers the comparison of three Combined Cycle (the gas turbine exhaust is used to
produce steam) Power Plant Configuration Alternatives A, B and C, referred to the following
parameters:
- Power Plant probabilistic evaluation of the average power delivery,
- Quality of the power delivery, i.e., frequency and duration of the faulted conditions
4. CALCULATION METHOD
The Second Step is the identification of the several operating states, and of the operating condition
(power delivery) relevant to these states
ST
GT
λGT GT
GT
ST GT
ST
λCCF µGT
GT ST
10
GT
µCCF 5 GT
2
λGT 9
λST GT GT
2λGT ST µGT ST GT
µST
GT λCCF GT ST
µGT 11
GT 3
µCCF 6 GT
ST 10
λCCF
GT 8
µCCF GT
0
2λGT λGT
λST GT GT GT ST
ST µGT ST µGT ST GT
λCCF
µST GT 9 GT λCCF GT 11
12
µCCF
1 4
µCCF 7
GT
ST
Generating Sets Failures
GT
Common Cause Failures (CCF)
12
The Transition Matrix is leading to a linear system of equations, that can be solved by means of usual
can be solved by means of usual numerical methods.
- Average Power Delivery: It is the weighed mean of the products of the power delivery of each
generating state (Residence State), and the probability of the system to reside in this state,
referred to the overall power plant capacity:
(1)
where:
The Pi probabilities are those included in the asymptotic transition matrix; they represent the
asymptotic probabilities of the system to reside into the several states.
where:
- Frequency and Duration of System Residence into the “i” States: This index represent the quality
of the power delivery
The result of the above reliability evaluation is the power amount that can be generated and delivered
to the grid; the product “power x time = energy” leads to the further “energy x KWh tariff = project
economic income”.
However, for a sound project evaluation, it is advisable to consider also two different points of view:
- Utility Point of View: the Utility main interest is in energy selling, therefore the system
performance index is simply the Project Economic Income = Energy x KWh Tariff. However,
there are some constraints related with Industrialized/Developing Countries, Load Forecast and
Power Station size, as reported in the following chapters.
Optimization of the Investment of a Large System / Plant, as a Balance between Reliability,
Costs and Incomes 7
- Customer Point of View: for the Customers, the main concern is to avoid as far as possible
power outages; therefore, the several system “states” with less than the total possible power
delivery have to be penalized.
Moreover, two different points of view relevant to the Customers have to be considered, in order to
take into account the specific aspects of power delivery in Industrialized or Developing Countries, as
follows.
The project evaluation is usually carried out by means of the widely used DCF - Discounted Cash Flow
technique; in this case, the DCF “income” is the energy selling, that has to be adapted in accordance
with the above considerations.
Specifically:
- The system “states” with total or higher energy production have to be compared with the actual
Load Demand; otherwise the DCF income would be not realistic. This comparison leads to quite
negligible effects in Industrialized Countries, but relevant effects in Developing Countries.
- The system “states” with low or null production have to be “penalized”, due to the difficulties
arising from the total or partial power outage; the penalization is low or negligible in Industrialized
Countries, and it can be serious in Developing Countries.
The above mentioned penalization of every low production state of all the alternatives has to be
computed as an yearly “outcome” Q in the Discounted Cash Flow; it has to be considered as an
amount to be properly assessed on a case-by-case basis, taking into account the specific
characteristics of the project, as above discussed.
This fixed amount has to be adjusted with the following figures / coefficients:
- L: Loss of produced energy; this is coming from the identification of states and their power
production.
Optimization of the Investment of a Large System / Plant, as a Balance between Reliability,
Costs and Incomes 8
- C: Unit (KWh) Shadow Cost of the lost energy; this shadow cost (outcome) has to be assessed
on a case-by-case basis, and it can be quite different from the unit cost (income) of the produced
energy.
- K1: Coefficient that takes into account the difficulties for the power outage; this coefficient is much
greater for Developing Countries that for Industrialized Countries. and especially in case that the
power station in analysis is predominant.
- K2: Coefficient that takes into account the extension of a power outage; a general black-out is
much worse than a localized outage. This coefficient is much higher for Developing Countries,
Finally, the penalization (yearly outcome) is:
Q = L*C*K1*K2
The above criteria is originated by a general system reliability rule: If the overall system is poor, the
component reliability has to be strong.
6. FINAL ANALYSIS
The project evaluation can be properly carried out by means of DCF – Discounted Cash Flow
technique.
Incomes
- Energy selling, properly evaluated and adjusted as described in the previous chapters.
- Residual value of the Plant
Outcomes
- Capital cost of the several alternatives.
- Penalization of the low power states, as described in the previous chapters.
- Operational costs of the Life Cycle.
Other aspects related to both reliability and costs, and included in the life Cycle, are:
- Preventive Maintenance;
- Corrective Maintenance;
- Spare Parts.
They will be treated in future papers.
A typical solution to improve system reliability is the use of sub-system / component redundancy; in
fact, this is a good practice, but it is entailing additional costs.
A typical problem with the redundancies is the occurrence of CCFs (Common Cause Failures) wich
can decrease so much the impact of the redundancies.
In simple words, a CCF is such an additional component in series with the redundant ones; in most
cases, this fictitious additional component can become predominant and neutralise the impact of
component redundancies. In terms of economics, the benefit of the additional cost of the redundancies
is frustrated by the impact of the CCF.
Optimization of the Investment of a Large System / Plant, as a Balance between Reliability,
Costs and Incomes 9
Therefore, a comprehensive CCF analysis is highly recommended, in order to avoid frustrating the high
cost of the redundancies.
A suitable methodology has been developed by the Authors to properly include CCFs in the Transition
Diagram and Matrix; it has to be pointed out that CCFS:
- Add new Transitions;
- Do not add new Cumulative Residence States;
Therefore, it is possible to “superpose” the CCFs and their transitions to the previous transition
diagram without CCFs. The new CCFs and their transitions have to be “ordered” in such a way that
they will be with higher sequential codes; in this way they will appear only in a peripheral strip of the
transition matrix. In Fig. 3 it is possible to see that the internal (grey) part of the transition matrix is
“without” CCFs, and the external (light) strips are relevant to CCFs.
8. TOPIC – AUTODIAGNOSTIC
A reliability / cost optimization must take into account both the impact of the “heavy” faults and the long
outages (loss of energy delivery) due to their long repair times.
Auodiagnostic proved a very effective technique to reduce dramatically the probability of “heavy” faults
on main equipment; in fact, the degradation factors are permanently monitored, and it is possible to
detect and to decide when and how to repair the fault before it becomes the cause of a serious
equipment damage.
A specific study [9] has been carried out comparing the outage time of two EHV (Extra High Voltage)
Substation alternative configurations:
1. 1 ½ Circuit Breaker Scheme – Tot. 9 High Voltage Circuit Breakers
2. Single Circuit Breaker Scheme – Tot. 6 High Voltage Circuit Breakers
The comparison showed that with the adoption of autodiagnostic it is possible to adopt the simpler
(cheaper) 2) configuration with almost the same reliability. In fact, the adoption of autodiagnostic has a
relevant impact on the simpler configuration, and conversely a negligible impact on the more expensive
one, that is already very reliable.
It is possible to evaluate the impact of autodiagnostic, with the following sequence, in the frame of the
above described methodology.
The faults which can be detected in their early stage by autodiagnostic should be identified and
separated since the beginning in the FMEA (Failure Modes and Effects Analysis).
Two separated sets of faults should then be considered in the transition diagram, which will have the
same residence states. The problem is that if the new “heavy” faults would be included (added) in the
original frame, it is very likely that the transition matrix could became too large to be easily handled;
this is the biggest limit of the Markov Process. The solution is to carry out two separate Markov
analysis, considering the same transition and matrix diagram as follows (symbols and codes are same
as for (1)):
A. A Markov analysis with all the faults but the “heavy” ones; it has to be pointed out that in this case it
is necessary to evaluate the power NOT delivered in every residence state, instead of the delivered
power.
Optimization of the Investment of a Large System / Plant, as a Balance between Reliability,
Costs and Incomes 10
(2)
B. A further Markov analysis with the same residence states, but considering only the “Heavy” faults.
(3)
The Average Power Delivery, not taking into account the simultaneous probability of outages (REA –
Rare Events Approximation), is
(4)
Long repair times of the main equipment have of course to be avoided as far as possible, because
they correspond to long power outages. A recurrent situation is that, simply in order to maintain a
standard design, a more expensive High-Tech solution is adopted in cases where a non High-Tech
solution could be proposed, with approximately the same cost (sometimes cheaper); the problem is
that a High-Tech solution usually has a long repair time and requires very skilled (expensive) repair
team, conversely a standard solution is easily restored in service.
A typical case is the High-Voltage interconnection between the Main Step-Up Transformers of a Power
Station and the High Voltage Grid. Along many decades this interconnection has been provided by
means of a short aerial line, but in the last decades many interconnections have been done with High
Voltage cables buried in the soil; this latter solution was originated in order to avoid exposed aerial
cables in urban areas.
The HV cables then became almost a standard solution, and now it is common to find them also in
Power Stations installed in not industrialized areas. It has to be pointed out that a cable has a lower
unit (1/km) failure rate than an aerial line, which is subject to lightning strokes etc., but in the case of a
cable there is to add the failure rate of the cable terminations at the two extremities, which is not low
and fixed i.e. independent from the conductor length; eventually, the overall failure rate a short HV
cable is of the same order of that of a short aerial line; unfortunately, the repair of a HV termination is
quite expensive (it requires High Tech components and very skilled personnel) and the repair time is
much longer than for an aerial line. An interesting study covering the HV cables repair times is reported
in [18].
Of course, the long repair times play a more important role in non industrialized countries, and mainly
in case that the power station is predominant; conversely their role can be relevant but not dramatic in
countries with very developed and interconnected HV grid, where the same grid is providing a sort of
network redundancy.
Also the interconnections of the Wind generators, and the main HV interconnection between the Wind
generating park and the HV grid are usually provided with buried cables [19], with sometimes heavy
problems; an alternative with Medium Voltage aerial lines for the generators, and HV aerial line for the
main interconnection, should always be taken into account.
In order to limit the size of the transition diagram and matrix, the above mentioned interconnections
can be included in “macrostructures” as an extension of the equipment they are connected to; the
theory of the “macrostructures” is comprehensively treated in [3].
10. REFERENCES
[1] Billinton, Allan “Reliability Evaluation of Power Systems”, Plenum Press – Ch. 13 “Evaluation
of Reliability Worth”.
[2] Billinton, Allan, Salvaderi (Editors) “Applied Reliability Assessment in Electric Power Systems”,
IEEE Press, Ch. 4 “Reliability Cost/Worth”.
[3] Birolini, “Reliability Engineering”, Springer Ed.
[4] Guenzi, Impact of Equipment and System Reliability on Project Economic Optimization, ICEC
IX Congress, Milan 2014
[5] IEEE Std. 399 Recommended Practice for Industrial and Commercial Power Systems Analysis
[6] IEEE Std 438 Recommended Practice for the Design of Reliable Industrial and Commercial
Power Systems.
[7] Guenzi – Cannistrà, “Economic Evaluations in Reliability Analysis of Repairable Systems” Univ.
Bocconi - AICE Seminar, 1999.
[8] Guenzi – Cannistrà, “Technical and Managerial Risks, and their Relationship with Economic
and Financial Risks” - Univ. Bocconi – AICE Seminar, 2000.
[9] Guenzi – Politano, “EHV Substations Reliability Improvement by means of Circuit Breakers
Autodiagnostic” – IEEE Powertech, Bologna 2003, Paper 327.
Optimization of the Investment of a Large System / Plant, as a Balance between Reliability,
Costs and Incomes 12
Giancarlo Guenzi was born in Italy on 1946. He received a Master of Science equivalent degree in Electrical Eng. - Power
Plants from Politecnico di Milano, a Master of Science in Electrical Eng. - Power Systems Analysis from USP - São Paulo,
Master of Science and PhD – Doctor of Philosophy in Reliability Engineering from University of Maryland; furthermore, he is
Certified Cost Engineer and Fellow of AICE – ICEC A, Life Senior Member IEEE, and Professional Engineer in Novara – Italy.
He is Managing Director of Energoconsult, Novara – Italy, in charge of cost engineering studies, risk and reliability analysis,
power systems design and analysis.
He is author / co-author of more than 30 papers covering cost engineering, reliability and risk analysis, ground grids, protection
systems.
Giovanni Cannistrà was born in Italy on 1949. He received a Doctoral Degree in Electrical Engineering (Magna cum Laude) on
1973 from Università di Bologna; he was Certified Cost Engineer and Fellow of AICE – ICEC A. He has been Site General
Manager in foreign offices of consulting companies, General Manager and Vice-President of OCEM Group, and he is Chief of
Project Management of Energoconsult.
He holds many patents on airfield lighting systems, and he is author / co-author of more than 20 papers covering cost
engineering, reliability and risk analysis.