Professional Documents
Culture Documents
PARTICIPANTS
Architect/Main
M/s Gul & Thariani Gul Ahmed,Kamran,Fiza GA,KAM,FZ
consultant
M/s Maam Associates Zaheer Mirza ZM HVAC Consultant
M/s Ayub Associates Naseer uddin NUD Electrical Consultant
M/s Technocon Arif khan,Noman ali NA Project Manager
Haroon Kalam, Abdul rauf,
M/s Gulf Constructors HK, SA,AS Civil Contractor
,Arshad Siddique
M/s National M.Kamran ,M.Yameen,Hassan
MK,MY,HH HVAC Contractor
Engineering Services Hameed
A meeting 85 was held at Shield Corporation. There was a review of the construction
progress.
The following items were discussed and observations made.
Target
S.No Matters Review & Discussed Action By Status
Date
CIVIL WORKS
Complete remaining coat of color in .
1
mixing and crushing
NIK suggested doing the plastering of
2 ceiling in gym and recreational area
as there is no false ceiling.
Prepared by NA
Page 1 of 3
NIK suggested doing porcelain tiles
3. flooring in gym and recreational area Target
S.No Matters Review & Discussed Action By Status
and GA agreed to the suggestion Date
ELECTRICAL WORKS
MECHANICAL WORKS
Prepared by NA
Page 2 of 3
NOTE: The overall project has been categorized into 4 different phases which are:
PHASE I: New Production Unit.
PHASE II: Pigeon Project.
PHASE III: Refurbishment of Existing Building.
PHASE IV: Gate Office, Shield Shop, External Works & Elevation.
Note:
The preceding is assumed to be a complete and correct account of the items discussed,
directions given, and Conclusions drawn, unless any participant notified to the contrary
immediately.
Prepared by NA
Page 3 of 3