You are on page 1of 51

As published in the February and March 2007 issues of Chemical Engineering Magazine

Piping Design
Part 1: The Basics
With regard to material of construction, the ongoing
evolution of technology has raised expectations
throughout industry…
William M. (Bill) Huitt
W. M. Huitt Co.

This is the first in a series of three articles that will ASME-BPE much of the 3-A piping Standards were
cover a wide range of piping topics. Topics that will cross plagiarized to facilitate design of pharmaceutical facilities.
industry lines to include chemical, petroleum refining,
pharmaceutical, and other industries as well. It will be the While some of the above Standards Committees, and
intent of these articles to address questions and their resulting Codes and Standards, are specific to a
misunderstandings as they relate to industry on a general particular industry others are more generalized in their use
basis. and are utilized across the various industries.

“Pipe is pipe”. This is a euphemism (jargon if you will) As an example, Not only does the design and
quite often used among piping designers and engineers. construction of a large pharmaceutical facility require the
Taken at face value, this is a true statement…pipe is need for pharmaceutical based Standards, Codes, Guidelines
certainly pipe. However, taken in context, it means that no and Industry Practices such as those generated by ISPE and
matter which industry you work in when designing piping ASME-BPE, it also requires those Standards created for
systems it‟s all the same. And in that context it could not be other industries as well. Meaning that, when designing and
further from the truth. constructing a bulk pharmaceutical finishing facility, or a
bulk Active Pharmaceutical Ingredient (API) facility the
The pharmaceutical industry, in its current state of engineers and constructors will also be working under some
growth, is a relative new comer to design, engineering and of the same standards and guidelines as they would when
construction compared to the oil refining, bulk chemical, designing and building in other industries such as a
pulp & paper and nuclear industries. As a frame of reference petroleum refinery or bulk chemical facility.
the American Society of Mechanical Engineers (ASME) was
established in 1880; the American Petroleum Institute (API) It is not that the pharmaceutical industry itself is young,
was established in 1919; 3-A Standards (for food & dairy) but the necessary engineering standards and practices are.
were first developed in the 1920‟s; the ASME committee for Within the past fifteen or so years, industry practice,
BPVC (Boiler Pressure Vessel Code) Section III for nuclear including dimensional standards for high purity fittings,
power was proposed in 1963; Semiconductor Equipment and were left to the resources of the pharmaceutical Owner or
Materials Institute (SEMI) was established in 1973; the their engineering firm (engineer of record). The same applies
International Society of Pharmaceutical Engineers (ISPE) to construction methods and procedures, including materials
was established in 1980; and ASME Biopharmaceutical of construction. These requirements were basically
Equipment (BPE) issued its first Standard in 1997. Prior to established for each project and were very dependent upon
what the Owner‟s personnel and the engineering firm 1. ASME flange ratings, is it 150 and 300 pound
brought to the table. Industry standards did not exist. flange or is it Class 150 and Class 300 flange?
2. Does the 150, 300, etc. actually mean anything
With regard to material of construction, the ongoing or is it simply an identifier?
evolution of technology has raised expectations throughout 3. In forged fittings, is it 2000 pound and 3000
industry, but even more so in the pharmaceutical, pound, or is it Class 2000 and Class 3000?
biopharmaceutical and semiconductor industries. 4. How do you determine which Class of forged
fitting to select for your specification?
For instance, out of the research and development that 5. Corrosion allowance in piping; how do you
went into the Hubble Space Telescope came new determine and then assign corrosion
methodology and technology to better measure and define allowance?
the all too tangible limits of surface roughness required in 6. How do you select the proper bolts and gaskets
material used in hygienic fluid service contact piping. This is for a service?
of particular interest to the pharmaceutical, 7. How is pipe wall thickness determined?
biopharmaceutical and semiconductor industries, where 8. What is MAWP?
cross-contamination at the molecular level cannot be 9. What is Operating and Design Pressure?
tolerated in many cases. This requires surfaces to be very 10. What is Operating and Design Temperature?
cleanable. 11. How do Design Pressure and Temperature
relate to a PSV set point and leak testing?
Surface roughness used to be expressed as polish 12. What Code should you be designing under?
numbers (ie, #4 or #7) then grit numbers such as 150, 180 or 13. What kind of problems can you expect with
240). The problem with either of these two methods lay in sanitary clamp fittings?
their subjectivity and their generality. These indicators were 14. How do you alleviate those problems with
not specific enough and the accept/reject result relied too sanitary clamp fittings?
much on a subjective visual verification. There will be more 15. What is ASME-BPE?
on surface finish requirements in Part II. 16. How does ASME B31.3 and ASME-BPE work
in concert with one another?
With acute awareness of the ongoing problems currently 17. What is ASME BPE doing to bring
faced in the pharmaceutical industry and, for altogether accreditation to the pharmaceutical Industry?
different reasons, the semiconductor industry, various 18. Design is the culmination and application of
Standards organizations have taken steps to alleviate the industry standards and industry requirements
consistent problems that have plagued the industry in the that take into account constructability along
past with high purity welding issues, standardization of with maintenance and operational needs. These
fittings, and guidelines for industry practice. We will discuss points will be covered as well.
some of the finer points of these issues and in some cases
what these Standards organizations, are doing to promote We will first of all lay some groundwork by beginning
and consolidate some of the better thinking in this industry with the basics of general piping. By understanding the basic
and in this field. elements of piping the designer and engineer can improve
their decision making in the material selection process and
In these early paragraphs it seems as though I am system design effort. These articles will also make clear a
singling out the pharmaceutical industry as the focal point of number of misconceptions with regard to terminology and
these discussions. As you will see this is not true. And in general practices.
saying pharmaceutical I do mean to include
biopharmaceutical (biopharm) as well. What we will try to avoid is a lot of in-depth discussion
and elaborate analysis on specific points. What I would like
In making an example of the pharmaceutical industry it to achieve is a general discussion on many topics rather than
is simply an attempt on my part to utilize its relative finite rhetoric on only a few.
newness in the development of its own particular brand of
standards to give the reader a sense of standards With that said, this first article is entitled:
development and how these standards evolve.
Piping Design Part I – The Basics
This article and the two that follow will address metallic
piping topics including a discussion on hygienic piping. This article will not attempt to cover all of the various
While non-metallic piping is worthy of discussion it is too types of piping components and joints that are available in
broad a topic to try and capture here and will not be a part of industry today. To keep the discussion focused we will
these articles. Some of the points that will be covered in this discuss only that segment of joints, fittings and components
and the following articles are topics such as: most frequently used in general piping design.

2
Neither will we duplicate the dialog of previous articles
that have provided excellent commentary on segments of
this same topic. Articles such as the one written by John C.
Cox and published by Chemical Engineering for their
January 2005 edition titled “Avoid Leakage in Pipe
Systems”. John provides a concise and descriptive narrative
on threaded and compression type connections. And the
article by Trinath Sahoo published by Chemical Engineering
for their June 2005 edition titled “Gaskets: The Weakest
Link”. In his article Trinath gives the reader some excellent Figure 1
insight into the mechanics of gasket selection and design.
The Threaded flange, through Class 400, is connected to
PIPE FLANGES threaded pipe in which the pipe thread conforms to ASME
B1.20.1. For threaded flanges in Class 600 and higher the
Pipe flanges are used to mechanically connect pipe length through the hub of the flange exceeds the limitations
sections to other pipe sections, inline components, and of ASME B1.20.1. ASME B16.5 requires that when using
equipment. Flanges also allow pipe to be assembled and threaded flanges in Class 600 or higher Schedule 80 or
disassembled without cutting or welding, eliminating the heavier pipe wall thickness be used, and that the end of the
need to issue a burn card for cutting and welding when pipe be reasonably close to the mating surface of the flange.
dismantling is required. In providing a breakable joint, Note that the term “reasonably close” is taken, in context,
flanges unfortunately provide a potential leak path for the from Annex A of ASME B16.5, it is not quantified.
service fluid contained in the pipe. Because of this, as in all
other joints, they need to be minimized where possible. In order to achieve this “reasonably close” requirement
the length of the thread has to be longer and the diameters of
The most prevalent flange standards to be used in the smaller threads become smaller than that indicated in
industry are based on requirements of the American Society ASME B1.20.1. When installing Threaded flanges Class 600
of Mechanical Engineers (ASME) Standards. These include: and higher, ASME B16.5 recommends using power
equipment to obtain the proper engagement. Simply using
B16.1 – Cast Iron Pipe Flanges and Flanged Fittings, arm strength with a hand wrench is not recommended.
B16.5 - Pipe Flanges and Flanged Fittings (NPS 1/2 through
NPS 24), The primary benefit of threaded flanges is in eliminating
B16.24 – Cast Copper Alloy Pipe Flanges and Flanged the need for welding. In this regard Threaded flanges are
Fittings, sometimes used in high-pressure service in which the
B16.36 – Orifice Flanges, operating temperature is ambient. They are not suitable
B16.42 – Ductile Iron Pipe Flanges and Flanged Fittings, where high temperatures, cyclic conditions or bending
Large Diameter Steel Flanges (NPS 26 through NPS 60) stresses can be potential problems.
B16.47 – Large Diameter steel flanges (NPS 26 through
NPS 60)
NPS, indicated above, is an acronym for Nominal Pipe Size.
Socketweld Flange

Flanges are available with various contact facings (the


flange-to-flange contact surface) and methods of connecting
to the pipe itself. The flanges under B16.5 are available in a
variety of styles and pressure classifications. The different
styles, or types, are denoted by the way each connects to the
pipe itself and/or the type of face. The type of pipe-to-flange
connections consist of Threaded, Socket Welding (or Socket
Weld), Slip-On Welding (or Slip-On), Lapped (or Lap
Joint), Welding Neck (or Weld Neck), and Blind.
Figure 2
Threaded Flange
The Socketweld flange is made so that the pipe is
inserted into the socket of the flange until it hits the shoulder
of the socket. The Pipe is then backed away from the
shoulder approximately 1/16” before being welded to the
flange hub.

If the pipe were resting against the shoulder (This is the


flat shelf area depicted in Fig. 2 as the difference between

3
diameters B and B2) of the socket joint during welding, heat fatigue rate is about 66% less than that of a Weld Neck
from the weld would expand the pipe longitudinally into the flange. The Slip-On flange is not approved above Class
shoulder of the socket forcing the pipe-to-flange weld area to 1500.
move. This could cause the weld to crack.
Lap Joint Flange
The Socketweld flange was initially developed for use
on small size, high-pressure piping in which both a back-
side hub weld and an internal shoulder weld was made. This
provided a static strength equal to the Slip-On flange with a
fatigue strength 1.5 times that of the Slip-On flange.

Because the two-welds were labor intensive it became


the practice to weld only at the hub of the flange. In doing
this it relegated the socketweld flange to be more frequently
used for small pipe sizes (NPS 2” and below) in non-high-
pressure, utility type service piping. The Socketweld flange
is not approved above Class 1500. Figure 4

The Lap Joint flange requires a companion lap joint, or


Slip-On Flange Type A stub-end (ref. Fig. 5) to complete the joint. The
installer is then able to rotate the flange. This allows for
quick bolthole alignment of the mating flange during
installation without taking the extra precautions required
during prefabrication of a welded flange.

Their pressure holding ability is about the same as a


Slip-On flange. The fatigue life of a Lap Joint/stub-end
combination is about 10% that of a Weld Neck flange, with
an initial cost that is a little higher than that of a Weld Neck
flange.
Figure 3
The real cost benefit in using a Lap Joint flange
Unlike the Socketweld flange, the Slip-On flange allows assembly is realized when installing a stainless steel or other
the pipe to be inserted completely through its hub opening. costly alloy piping system. In many cases the designer can
Two welds are made to secure the flange to the pipe. One elect to use a stub-end specified with the same material as
fillet (pronounced “fill-it”) weld is made at the hub of the the pipe, but use a less costly, e.g. carbon steel, Lap Joint
flange and a second weld is made at the inside diameter of Flange. This prevents the need of having to weld a more
the flange near the flange face. costly compatible alloy flange to the end of the pipe.

The end of the pipe is offset from the face of the flange Just a quick word about stub-ends; they are actually
by a distance equal to the lesser of the pipe wall thickness or prefabricated or cast pipe flares that are welded directly to
1/4” plus approximately 1/16”. This is to allow for enough the pipe. They are available in three different types: Type A,
room to make the internal fillet weld without damaging the (which is the lap-joint stub-end), Type B and Type C (ref.
flange face. Fig. 5).

The Slip-On flange is a preferred flange for many Type A (Fig 5) is forged or cast with an outside radius
applications because of its initial lower cost, the reduced where the flare begins. This radius conforms to the radius on
need for cut length accuracy and the reduction in end prep the inside of the Lap-Joint flange. The mating side of the
time. However, the final installed cost is probably not much flare has a serrated surface.
less than that of a Weld Neck flange.
Type B (Fig. 5) is forged or cast without the radius
The strength of a Slip-On flange under internal pressure where the flare begins. It is used to accommodate the Slip-
is about 40% less than that of a Weld Neck flange. The On flange or Plate flange as a back-up flange.

4
Type C (Fig 5) is fabricated from pipe using five
suggested methods indicated in ASME B31.3. The most
prevalent of these is the machine flare. This is done by
placing a section of pipe into a flaring machine, flaring the
end of the pipe and then cutting it to length.

As you can see in the assembly detail of Fig. 5, stub-end


types B & C have no radius at the flare while Type A does.
This allows it to conform to the Lap-Joint flange. Due to the Figure 7
radius of the type A stub-end, a slip-on flange would have a
poor fit, creating non-uniform loading of the flare face as While the Blind flange is used to cap off the end of a
well as an undesirable point load at the radius of the flare. pipeline or a future branch connection it is also used for
other purposes. It can be drilled and tapped for a threaded
Weld Neck Flange
reducing flange or machined out for a Slip-On reducing
flange. The reduced opening can be either on-center or
eccentric.
Flange Pressure Ratings

ASME B16.5 flange pressure ratings have been


categorized into material groupings. These groupings are
formulated based on both the material composition and the
process by which the flange is manufactured.

The available pressure Classifications under ASME


Figure 6 B16.5 are: 150, 300, 400, 600, 900, 1500 and 2500. The
correct terminology for this designation is Class 150, Class
The reinforcement area of the Weld Neck flange 300, etc. The term 150 pound, 300 pound, etc. is a carry over
distinguishes it from other flanges. This reinforcement area from the old ASA (American Standards Association)
is formed by the added metal thickness, which tapers from Classification. ASA is the precursor to the American
the hub of the flange to the weld end. The bore of the flange National Standards Institute (ANSI).
needs to be specified in order to obtain the same wall
thickness at the weld end as the pipe it will be welded to. Taking a quick step back, ANSI was founded as a
This will give it the same ID bore as the pipe. committee whose responsibility was to coordinate the
development of standards and to act as a standards
The Weld Neck flange is actually the most versatile traffic cop for the various organizations that develop
flange in the ASME stable of flanges. Much of its use is for standards. Its basic function is not to develop standards,
fitting-to-fitting fabrication in which the flange can be but rather to provide accreditation of those standards
welded directly to a fitting, such as an elbow, without the
need for a short piece of pipe, as would be required with a Originating as the American Engineering
Slip-On flange. It can be used in low-pressure, non- Standards Committee (AESC) in 1918, ANSI had, over
hazardous fluid services as well as high-pressure, high- its first ten years, outgrown its Committee status and in
cyclic and hazardous fluid services. 1928 was reorganized and renamed as the American
While the initial cost of the Weld Neck flange may be Standards Association (ASA). In 1966 the ASA was
higher than that of a Slip-On flange the installed cost reorganized again under the name of the United States
reduces that differential. And for conditions of possible high of America Standards Institute (USASI). In 1969 ANSI
thermal loading, either cryogenic or elevated temperatures, adopted its present name.
the Weld Neck flange would be essential.
While the B16 and B31 Standards have previously
Blind Flange carried the ASA and ANSI prefix with its various
Standards titles ASME has always been the
administrative sponsor in the development of those
standards. In the 1970’s the prefix designation changed
to ANSI/ASME and finally to ASME.

Referring to ANSI B16.* or ANSI B31.* is no


longer correct. Instead it is correct to refer to a
standard as ANSI/ASME B16.* in that it indicates an

5
ANSI accredited ASME standard. Or you can simply ASME these pressure ratings are a sub-group of the various
refer to the standard as ASME B16.* or ASME B31.*. material groups designated in B16.5.

Development of ASME B16.5 began in 1920. In 1927 Figure 8 represents one of the Tables from the Table 2
the American Tentative Standard B16e was approved. This series in ASME B16.5. This is a series of Tables that lists
eventually became what we know today as ASME B16.5. the Working Pressures of flanges based on material
Until the 1960‟s the pressure Classifications, as addressed groupings, temperature and Classification.
earlier, were referred to as 150 pound, 300 pound, etc. It
was at this point the pressure Classification was changed to There are 34 Tables segregated into three material
the Class designation. These designations have no direct Categories of Carbon and low alloy steels, austenitic
correlation with pounds of pressure. Rather, they are a factor stainless steels, and nickel alloys. These are further
in the pressure rating calculation found in B16.5. In Part II segregated into more defined material sub-groups. Figure 8
of this series, we will discuss how these designations are shows Table 2-1.1, which indicates, in reverse sequence,
factored into the design of the flange. sub-category 1 of material group 1 (carbon and low alloy
steels).
Flange Pressure Ratings
If you had an ASME B16.5, Class 150, ASTM A105
Flanges, whether manufactured to ASME (American flange this is the table you would use to determine the
Society of Mechanical Engineers), API (American Working Pressure limit of the flange. To find the Working
Petroleum Institute), MSS (Manufacturers Standardization Pressure of the above mentioned flange enter the column of
Society), AWWA (American Water Works Association) or this table designated as 150 then move down the column to
any other Standard, are grouped into pressure ratings. In the operating temperature. For intermediate temperatures,

6
linear interpolation is permitted. that every service should have an operating
pressure/temperature and a design pressure/temperature. A
In the previous paragraph you will notice that I design condition is the maximum coincidental pressure and
indicated “operating temperature” when looking to temperature condition that the system is expected or allowed
determine the Working Pressure of a flange. „Operating‟ and to see. This then becomes the condition to which you should
„working‟ are synonymous. The indication of a working design for, and to which the leak test is based on, not the
pressure and temperature of a fluid service is the same as operating condition.
indicating the operating pressure and temperature.
Tables 2, as it indicates, represents the working or
There exists some confusion in this area. That confusion operating pressures of the flange at an indicated temperature
becomes apparent when the engineer is determining design for a specific Class. The maximum hydrostatic leak test
pressure and temperature and applying that to the flange pressure for a Class 150 flange in Table 2-1.1 is 1.5 times
rating. On the surface there appears to be a conflict between the rated working pressure at 100°F, or 285 x 1.5 = 427.5
rating a flange for design conditions when Table 2 only rounded off to the next higher 25 psi, or 450 psig.
indicates working pressures.
We can extrapolate that piece of information to say that
Operating and design pressures and temperatures will be since hydrostatic leak test pressure is based on 1.5 x design
explained in more detail in Article 2. For now I will explain

7
pressure the working pressure limit given in the Table 2 Sealing the flange joint, and as you will see further in
matrix ostensibly becomes the design pressure limit. this article, the hygienic clamp joint, is paramount in
providing integrity to the overall piping system. This is
When working with ASME B31.3 Category D fluid achieved with the use of bolts, nuts and gaskets. Making the
services, and initial service leak testing is performed, the right selection for the application can mean the difference
working pressure limit then remains the working pressure between a joint with integrity and one without.
limit because testing is performed at operating or working
pressures. In saying that however, there are caveats that ASME B16.5 provides a list of appropriate bolting
address the fact that not all Category D fluid services should material for ASME flanges. The bolting material is grouped
waive the hydrostatic leak test for an initial service leak test. into three strength categories; high, intermediate and low,
These conditions, such as steam service, will also be which are based on the minimum yield strength of the
discussed in a subsequent article. specified bolt material.

Category D fluid services are those fluid services that The High Strength category includes bolt material with
are nonflammable, nontoxic and not damaging to human a minimum yield strength of not less than 105 ksi. The
tissue. Category D fluids additionally do not exceed 150 psig Intermediate Strength category includes bolt material with a
and 366º F. minimum yield strength of between 30 ksi and 105 ksi. The
Low Strength category includes bolt material with a
In initial service leak testing the test fluid is the service minimum yield strength no greater than 30 ksi.
fluid. Leak testing occurs during or prior to initial operation
of the system. As the service fluid is introduced to the piping As defined in ASME B16.5, the High Strength bolting
system and brought to operating pressure, in pressure materials "…may be used with all listed materials and all
increments, all joints are observed for possible leaks. If no gaskets". The Intermediate Strength bolting materials
leaks are detected the pipeline simply remains in service. "…may be used with all listed materials and all gaskets,
provided it has been verified that a sealed joint can be
Other ASME B31.3 fluid services may be expected to maintained under rated working pressure and temperature”.
operate at one set of conditions, but are designed for another The Low Strength bolting materials "…may be used with all
set. For those systems, which might include periodic steam- listed materials but are limited to Class 150 and Class 300
out (cleaning, sterilization, sanitization) or passivation, you joints", and can only be used with selected gaskets as
therefore want to base your flange rating selection on those defined in ASME B16.5.
more extreme, periodic design conditions. To clarify
periodic in this context, the sanitization process can be done ASME B31.3 further clarifies in para. 309.2.1, "Bolting
as frequently as once per week and last for one to one and having not more than 30 ksi specified minimum yield
half shifts in duration. strength shall not be used for flanged joints rated ASME
B16.5 Class 400 and higher, nor for flanged joints using
Flange Facing & Surface Finishes metallic gaskets, unless calculations have been made
showing adequate strength to maintain joint tightness".
Standard flange facing designations (ref. Fig. 9) are as B31.3 additionally states in para. 309.2.3, “…If either flange
follows: Flat Face, Raised Face, Ring Joint, Tongue and is to the ASME B16.1 (cast iron), ASME B16.24 (cast
Groove, Large and Small Male and Female, Small Male and copper alloy), MSS SP-42 (valves with flanged and buttweld
Female (on end of pipe), Large and Small Tongue and ends), or MSS SP-51 (cast flanges and fittings)
Groove. The height of the raised face for Class 150 and 300 specifications, the bolting material shall be no stronger than
flanges is 0.06”. The height of the raised face for Class 400 low yield strength bolting unless: (a) both flanges have flat
and above is 0.25”. faces and a full face gasket is used: or, (b) sequence and
torque limits for bolt-up are specified, with consideration of
Across industry, not discounting the lap-joint flange and sustained loads, displacement strains, and occasional loads
stub-end combination, the two most widely used flange (see paras. 302.3.5 and 302.3.6), and strength of the flanges.
facings are the flat face and the raised face.
In specifying flange bolts, as well as the gasket, it is
The surface finish of standard raised face and flat face necessary, not only to consider design pressure and
flanges has a serrated concentric or serrated spiral surface temperature, but fluid service compatibility, the critical
finish with an average roughness of 125 μin to 250 μin. The nature of the fluid service and environmental conditions all
cutting tool used for the serrations will have a 0.06 in. or in conjunction with one another.
larger radius and there should be from 45 to 55 grooves per
inch. To better understand the relationship of these criteria I
will list and provide some clarification for each:
BOLTS, NUTS & GASKETS

8
1. The coincident of design pressure and temperature not need to specify the nut since it is already defined in
is what determines the pressure Class of a flange A307.
set. That, in turn, along with flange size, will
determine the number and size of the flange bolts. However, ASTM A193, alloy and stainless steel bolts,
The flange Class will also determine the goes only so far when it states that nuts shall conform to
compressibility range of the gasket material. ASTM A194, but there are several grades of A194 nuts to
2. Fluid service compatibility will help determine the select from. This is an example of where the matching nut is
gasket material. not always explicitly called out in the ASTM Standard.
3. The critical nature of the fluid will determine the Because the ASTM Standards are inconsistent in that regard
degree of integrity required in the joint. This will the spec-writer must make sure it is covered in a
help determine bolt strength and material as well as specification.
gasket type.
4. Environmental conditions will also help determine You can see from this bit of information that all four
bolt material (Corrosive atmosphere, wash-down components, flanges, bolts, nuts and gaskets have to be
chemicals, etc.). selected in conjunction with one another in order for the
joint assembly to perform in a way that it is expected to for a
What this ultimately means is that all of the variables given application.
that come together in making up a flange joint have to do so
in a complementary fashion. Simply selecting a gasket based Pipe, Tube & Fittings
on material selection and not taking into account the
pressure rating requirement could provide a gasket that One of the big differences between pharmaceutical and
would get crushed under necessary torque requirements semi-conductor piping and other industrial piping, is the
rather than withstand the bolt load and create a seal. requirements of high purity, or hygienic fluid services.
These requirements, as dictated by current Good
Selecting a low strength bolt to be used with a Class 600 Manufacturing Practices (cGMP) and defined and quantified
flange joint with proper gasketing will require the bolts to be by the ISPE and ASME-BPE, are stringent with regard to the
torqued beyond their yield point, or at the very least beyond manufacture, documentation, fabrication, installation,
their elastic range. To explain this briefly; bolts act as qualification, validation and quality control of hygienic
springs when they are installed and loaded properly. In order piping systems and components.
for the flange joint to maintain a gasket seal it requires
dynamic loading. Dynamic loading of flange bolts allows The man-hours required in generating, maintaining and
expansion and contraction movement in and around the joint controlling the added documentation required for hygienic
while maintaining a seal. This is achieved by applying fabrication and installation is in the range of 30% to 40% of
sufficient stress to the bolt to take it into the material‟s the overall cost of fabrication and installation. Part II in this
elastic range. series will get more into the requirements of hygienic
fabrication and where that added cost comes from.
If the bolts are not stressed sufficiently into their elastic
range any relaxation in the gasket could reduce the sealing For now we will stay with general pipe and fittings. In
ability of the joint. To the other extreme, if the bolts were an attempt at keeping this article concise we will only cover
stressed beyond their elastic range and into the plastic range those fittings that are predominantly used throughout
of their material of construction the same issue applies, they industry, both in process and in utility services.
will lose their dynamic load on the gasket. In this case, if
they do not shear they will take a set. Any relaxation in the Pipe fittings are manufactured by the following
gasket will then result in the reduction or elimination of the processes: cast, forged and wrought.
joints sealing ability.
Cast Fittings
With regard to the nut, it should be selected to Cast fittings are provided in cast iron, malleable iron,
compliment the bolt. Actually the bolt material specification steel, stainless steel, brass, bronze, and other alloy material
will steer you, either partially or completely, into the proper as follows:
nut selection.
Cast Iron: Cast iron threaded fittings, under ASME
ASTM A307, a material standard for bolts in the low- B16.4, are available in Class 125 and Class 250 for sizes
strength category, states that the proper grade for bolts to be NPS 1/4” through 12”. Cast iron flanged fittings, under
used for pipe flange applications is Grade B. A307 goes ASME B16.1, are available in Class 25, 125 and 250 in sizes
further to state that when used for pipe flanges Grade B bolts NPS 1” through 48”.
require a Heavy Hex Grade A nut under ASTM A563. In
writing a pipe spec that includes the A307 bolt you would Malleable Iron: Malleable iron fittings, under ASME
B16.3, are available in Class 150 and Class 300 in sizes NPS

9
1/8” though 6” for Class 150 and 1/4” through 3” for Class which is where the process gets its name. The slag and
300. impurities were then mechanically removed from the molten
mass by twisting and hammering which is where the term
It needs to be noted here that Classifications such wrought originates.
as 150 and 300 are not universal throughout the ASME
Standards. They are specific to the Standard that they Today forged and wrought are almost synonymous. If
are associated with. You cannot automatically transfer we look in ASTM A234 - Standard Specification for Piping
the pressure/temperature limits of a flange joint in Fittings of Wrought Carbon Steel and Alloy Steel for
ASME B16.5 to that of a fitting in B16.3. Moderate and High Temperature Service we can see in Para
4.1 and in Para 5.1 that wrought fittings made under A234
Cast Steel: Cast steel, stainless steel and alloy steel are actually manufactured or fabricated from material pre-
flanged fittings, under ASME B16.5, are available in Class formed by one of the methods listed previously, which
150, 300, 400, 600, 900, 1500 & 2500 in sizes 1/2” though includes forging. In ASTM A961 - Standard Specification
24”. for Common Requirements for Steel Flanges, Forged
Fittings, Valves and Parts for Piping Applications the
Cast Brass: Cast Brass and bronze threaded fittings, definition for the term Forged is, “the product of a
under ASME B16.15, are available in Class 125 and 250, in substantially compressive hot or cold plastic working
sizes NPS 1/8” through 4” for Class 125 and 1/4” through 4” operation that consolidates the material and produces the
for Class 250. required shape. The plastic working must be performed by a
forging machine, such as a hammer, press, or ring rolling
Cast Copper: Cast copper solder joints, under ASME machine, and must deform the material to produce a
B16.18, are available in sizes 1/4” through 6”. wrought structure throughout the material cross section.”

Forged Fittings The difference therefore between forged and wrought


Before getting into forged fittings I would like to fittings is that forged fittings, simply put, are manufactured
explain the difference between forged and wrought fittings. from bar, which while in its plastic state is formed into a
There seems to be some vague misconception of what the fitting with the use of a hammer, press or rolling machine.
term forged means and what the term wrought means and Wrought fittings, on the other hand, are manufactured from
how it applies to pipe fittings. killed steel, forgings, bars, plates and seamless or fusion
welded tubular products that are shaped by hammering,
The term forging actually comes from the times when pressing, piercing, extruding, upsetting, rolling, bending,
metal was worked by hand. A bar of steel would be placed fusion welding, machining, or by a combination of two or
into a forge and heated until it reached its plastic state, at more of these operations. In simpler terms wrought signifies
which time the metal would be pulled out of the forge and “worked”. There are exceptions in the manufacture of both,
hammered into some desired shape. Today forging metal but that is the general difference.
basically means working the metal by means of hydraulic
hammers to achieve the desired shape. Something worth noting at this point concerns the
ASTM specifications. In quoting from ASTM A961 I was
As a small bit of trivia, up until the late 1960‟s, when quoting from what ASTM refers to as a General
mills stopped producing it, wrought iron was the choice of Requirement Specification, which is what A961 is. A
ornamental iron workers. It is still produced in Europe, but General Requirement Specification is a specification
most of what we see manufactured as wrought iron in the that covers requirements that are typical for multiple
U.S. is actually various forms of steel made to look like individual Product Specifications. In this case the
wrought iron. individual Product Specifications covered by A961 are
A105, A181, A182, A360, A694, A707, A727 and A836.
True wrought iron is corrosion resistant, has excellent
tensile strength, welds easily and in its plastic range is said The reason I point this out is that many designers
to be like working taffy candy. What gives wrought iron and engineers are not aware that when reviewing an
these attributes is the iron silicate fibers, or “slag” added to A105 or any of the other ASTM individual Product
the molten iron with a small percentage of carbon, whereas Specifications you may need to include the associated
cast iron, with a high carbon content, is more brittle and not General Requirement Specification in that review.
as easily worked. Reference to a General Requirement Specification can
be found in the respective Product Specification.
The smelters, where the iron ore was melted to produce
wrought iron, were called bloomeries. In a bloomery the Forged steel and alloy steel socketweld and threaded
process does not completely melt the iron ore, rather the fittings, under ASME B16.11, are available in sizes NPS
semi-finished product was a spongy molten mass called a 1/8” through 4”. Forged socketweld fittings are available in
bloom, derived from the red glow of the molten metal, pressure rating Classes 3000, 6000 and 9000. Forged

10
threaded fittings are available in pressure rating Classes under B16.28 (short radius 1D elbows), are available in sizes
2000, 3000 and 6000. 1/2” through 24”. There is no pressure/temperature rating
classification for these fittings. In lieu of fitting pressure
What I see quite often, and this includes all of the classifications both B16.9 and B16.28 require that the fitting
industries I have been associated with, is a misapplication of material be the same as or comparable to the pipe material
pressure rating in these fittings. This leads me to believe that specification and wall thickness. Under ASME B16.9, given
the person specifying components does not fully understand the same material composition, the fittings will have the
the relationship between the pressure Class of these fittings same allowable pressure/temperature as the pipe. ASME
and the pipe they are to be used with. requires that the fittings under B16.28, short radius elbows,
be rated at 80% of that calculated for straight seamless pipe
In ASME B16.11 is a table that associates, as a of the same material and wall thickness.
recommendation, fitting pressure Class with pipe wall
thickness, as follows: These fittings can be manufactured from seamless or
welded pipe or tubing, plate or forgings. Laterals, because of
Table 1 – Correlation of Pipe Wall Thickness & Pressure Rating the elongated opening cut from the run pipe section are rated
Pipe Wall Thk. Threaded Socketweld at 40% of that calculated for straight seamless pipe of the
80 or XS 2000 3000 same material and wall thickness. If a full strength lateral is
160 3000 6000 required either the wall thickness of the lateral itself can be
XXS 6000 9000 increased or a reinforcement pad can be added at the branch
to compensate for the loss of material at the branch opening.
The ASME recommendation is based on matching the
I.D. of the barrel of the fitting with the I.D. of the pipe. The Wrought copper solder joint fittings, under ASTM B88
shoulder of the fitting (the area of the fitting that the end of and ASME B16.22, are available in sizes 1/4” through 6”.
the pipe butts against), either socketweld, as shown in Fig. These fittings can be used for brazing as well as soldering.
10, or threaded, is approximately, allowing for fabrication
tolerances, the same width as the specified mating pipe wall The pressure/temperature rating for copper fittings are
thickness. based on the type of solder or brazing material and the
tubing size. It will vary too, depending on whether the fitting
is a standard fitting or a DWV (Drain, Waste, Vent) fitting,
which has a reduced pressure rating.

As an example, using alloy Sn50, 50-50 Tin-Lead


Solder, at 100ºF, fittings 1/2” through 1” have a pressure
rating of 200 psig and fittings 1½” through 2” have a
pressure rating of 175 psig. DWV fittings 1½” through 2”
have a pressure rating of 95 psig.

Using alloy HB, which is a Tin-Antimony-Silver-


Figure 10 – Socket Weld Fitting Joint from ASME B16.11 Copper-Nickel (Sn-Sb-Ag-Cu-Ni) solder, having 0.10%
maximum Lead (Pb) content, at 100ºF, fittings 1/2” through
As an example, referring to Table 1, if you had a 1” have a pressure rating of 1035 psig and fittings 1½”
specified pipe wall thickness of Sch. 160 the matching through 2” have a pressure rating of 805 psig. DWV fittings
threaded forged fitting would be a Class 3000, for 1½” through 2” would have a pressure rating of 370 psig.
socketweld it would be a Class 6000. The fitting pressure
Class is selected based on the pipe wall thickness. Referring As you can see, within the same type of fitting, there is
to Fig. 10, you can readily see that by not matching the a significant difference in the pressure ratings of soldered
fitting Class to the pipe wall thickness it will create either a joints depending on the type of filler metal composition.
recessed area or a protruding area the length of the barrel of Much of the difference is in the temperature at which the
the fitting, depending on which side you error on. For forged solder or brazing filler metal fully melts. This is referred to
reinforced branch fittings refer to MSS Standard SP-97 – as its liquidus state. The temperature at which it starts to
Integrally Reinforced Forged Branch Outlet Fittings - melt is referred to as its solidus temperature, the higher the
Socket Welding, Threaded and Buttwelding Ends. liquidus temperature the higher the pressure rating of the
joint.
Wrought Fittings
Pipe and Tubing
Wrought Steel Butt Weld Fittings under ASME B16.9
(standard radius 1.5D elbows and other fittings) are available The catch-all terminology for pipe and tubing is tubular
in sizes 1/2” through 48”. Wrought Steel Butt Weld Fittings products. This includes pipe, tube and their respective

11
fittings. Piping itself refers to a system of pipe, fittings, give it a high compressive strength and a hardness that
flanges, valves, bolts, gaskets and other in-line components provides added resistance to wear, but leave it very brittle.
that make up an entire system used to convey a fluid. The
simple distinction between pipe and tubing is that tubing is Malleable iron is white cast iron that has been heat
thin-walled pipe with a different size for size diameter. treated for added ductility. By reheating white cast iron in
the presence of oxygen containing materials such as iron
Tubular products can basically be grouped into three oxide, and allowing it to cool very slowly, the free carbon
broad classifications: pipe, pressure tube and mechanical forms small graphite particles. This gives malleable iron
tube. excellent machinability and ductile properties along with
good shock resistant properties.
Based on user requirements the above classifications
come in various types such as Standard Pipe, Pressure Pipe, Gray iron is the oldest form of cast iron pipe and is
Line Pipe, Water Well Pipe, Oil Country Tubular Goods, synonymous with the name cast iron. It contains carbon in
Conduit, Piles, Nipple Pipe and Sprinkler Pipe. The two the form of flake graphite, which gives it its gray identifying
types that we are mainly interested in are Standard and color. Gray cast iron has virtually no elastic or plastic
Pressure Pipe. Distinguishable only from the standpoint of properties, but has excellent machining and self-lubricating
use, Standard Pipe is intended for low pressure, non-volatile properties due to the graphite content
use, whereas Pressure Pipe is intended for use in higher
integrity services. These are services in which the pipe is Ductile iron is arguably the most versatile of the cast
required to convey high pressure volatile or non-volatile irons. It has excellent ductile and machinable properties
liquids and gases at sub-zero or elevated temperatures. while also having high strength characteristics.

The following represents a combined description of Welded Steel Pipe and Tubing: Referring to pipe in
Standard and Pressure Pipe. the following also includes tubing.

Pipe: Pipe is manufactured to a NPS in which the OD Welded steel pipe is manufactured by Furnace Welding
of a given nominal size remains constant while any change or by Fusion Welding. Furnace Welding is achieved by
in wall thickness is reflected in the pipe ID. Pipe wall heating strip steel, also referred as skelp, to welding
thicknesses are specified by Schedule (Sch.) numbers 5, 10, temperature then forming it into pipe. The continuous weld,
20, 30, 40, 60, 80, 100, 120, 140 and 160. Add the suffix „s‟ or buttweld, is forged at the time the strip is formed into
when specifying stainless steel or other alloys. Wall pipe. This is a process generally used to manufacture low
thickness is also specified by the symbols Std. (Standard), cost pipe 3 ½” and below.
XS (Extra Strong) and XX (Double Extra Strong).
Fusion Welded pipe is formed from skelp that is cold
Pipe NPS 12” and smaller has an OD that is nominally rolled into pipe and the edges welded together by resistance
larger than that specified. Pipe with a NPS 14” and larger welding, induction welding or arc welding. Electric
has an OD equal to the size specified. resistance welding (ERW) can be accomplished by flash
welding, high-frequency or low-frequency resistance
Tubing: Steel and alloy tubing is manufactured to an welding. A scarfing tool is used to remove upset material
OD equal to that specified. Meaning that 1/4” tubing will along the seam of flash-welded pipe.
have a 1/4” OD, 2” tubing will have a 2” OD. Copper
tubing, accept for ACR (Air-Conditioning & Refrigeration) Flash welding produces a high strength steel pipe in
tubing, which has an OD equal to that specified, has an OD NPS 4” through 36”. Low-frequency resistance welding can
that is always 1/8” larger than the diameter specified. As an be used to manufacture pipe through NPS 22”. High-
example, 1/2” tubing will have a 5/8” OD, 1” tubing will frequency resistance welding can be used to manufacture
have a 1 1/8” OD. pipe through NPS 42”.

Wall thickness for tubing is specified in the actual High-frequency induction welding can be used for high
decimal equivalent of its thickness. rate production of small NPS pipe. This is a cleaner form of
welding in which scarfing, or the cleaning of upset material
Pipe is manufactured in three basic forms: cast, welded along the seam, is normally not required.
and seamless. Tubing is manufactured in two basic forms:
welded and seamless. Arc welding the longitudinal seam of production pipe is
accomplished with submerged arc welding (SAW), inert gas
Cast Pipe: Cast pipe is available in four basic types: tungsten arc welding (GTAW) also called tungsten inert gas
white iron, malleable iron, gray iron and ductile iron. White welding (TIG), or gas shielded consumable metal arc
iron has a high carbon content in the carbide form. The lack welding (MIG).
of graphite gives it its light colored appearance. Carbides

12
As you will see in Part II, the type of weld seam used in were no standard fitting dimensions and the availability of
the manufacture of pipe is a factor when calculating the size and type of fittings would vary from one company to
Pressure Design Thickness (t) of the pipe wall. It reduces the another, and still, to a much lesser degree, does to this day.
overall integrity of the pipe wall by a percentage given in
ASME B31.3 based on the type of longitudinal seam weld. Due to the autonomous nature of lined pipe
manufacturing during its initial stages the pipe designer
Seamless Steel Pipe and Tubing: Referring to pipe in would have to know early in the design process which
the following also includes tubing. manufacturer they were going to use. Particularly in fitting
make-up situations, you needed to know in advance what
Seamless steel pipe, using various extrusion and those make-up dimensions were going to be, and thus the
mandrel mill methods, is manufactured by first creating a fitting manufacturer.
tube hollow from a steel billet, which is a solid steel round.
The billet is heated to its hot metal forming temperature then While not having industry standard dimensions was a
pierced by a rotary piercer or by a press piercer creating the design problem other operational type problems existed as
tube hollow, which will have a larger diameter and thicker well. Some of the fluid services these line pipe systems were
wall than its final pipe form. The tube hollow is then hot- specified for, and still are, would normally be expected to
worked by the Mandrel Mill Process, Mannesmann Plug- operate under a positive pressure, but at times would phase
Mill Process, or Ugine Sejournet Extrusion Process. into a negative pressure. The liners in these early systems
were not necessarily vacuum rated and at times would
Upon completion of these processes the pipe is referred collapse under the negative internal pressure, plugging the
to as hot-finished. If further work is required to achieve pipeline.
more accuracy in the diameter, wall thickness or improve its
finish the pipe can be cold-finished, or cold-worked. When There was an added problem when gaskets were thrown
the pipe is cold-finished it will require heat treating to into the mix. Gaskets were not normally required unless
remove stress in the pipe wall created when worked in its frequent dismantling was planned, and many firms, both
cold state. engineers and manufacturers, felt more secure in specifying
gaskets at every joint. When required, the gasket of choice,
There are also two forging processes used in the in many cases, was an envelope type gasket made of PTFE
manufacture of large diameter (10 to 30 inch) pipe with (polytetrafluoroethylene) with an inner core of various filler
heavy wall thickness (1.5 to 4 inch). The two forging material,Viton (a DuPont trade name) or EPDM.
methods are called Forged and Bored, and Hollow Forged.
These gaskets had a tendency to creep under required
Other Material and Systems bolt torque pressure at ambient conditions. From the time a
system was installed to the time it was ready to hydrotest the
We have touched on just some of the key points of steel gaskets would, on many occasion, creep, or relax to the point
pipe and fittings. What I have not touched on are plastic of reducing the compressive bolt load of the joint enough to
lined pipe systems and non-metallic piping including where it would not stand up to the hydrotest pressure. Quite
proprietary piping systems. The area of non-metallic piping often leaks would become apparent during the fill cycle prior
is certainly worth including in the context of piping. to testing.
However, we will keep these articles focused on metallic
piping material. Non-metallic piping merits a discussion on There also exists the problem of permeation with regard
its own, and should not be relegated to a paragraph or two to PTFE liner material and of Internal and External
here. Triboelectric Charge Generation and Accumulation (static
electricity). But, due to the diligent efforts of the line pipe
However, since plastic lined pipe is steel pipe with a and gasket industries these types of problems have either
liner and is so widely used in the various industries I will been eliminated or controlled, and some are still being
touch on some of its key points. pursued.

Lined Pipe Systems: Lined flex hoses were first Fitting dimensions have been standardized through
developed in 1936 by Resistoflex followed by lined pipe, ASTM F1545 in referencing ASME B16.1 (cast iron
which did not come to the industry until 1956 by way of the fittings), B16.5 (steel fittings) and B16.42 (ductile iron
same company. When first introduced, plastic line pipe filled fittings). You will need to read Note 3 under Sub-Para. 4.2.4,
a large fluid handling gap in industry, but brought with it which states, “Center-to-face dimensions include the plastic
some technical issues. lining.” Meaning, the dimensions given in the referenced
ASME standards are to the bare metal face of the fittings.
As other manufacturers such as Dow and Peabody However, when lined fittings are manufactured the metal
Dore‟ began producing lined pipe and fittings industry casting is modified to accommodate the liner thickness being
standards for lined pipe did not exist. Consequently, there included in that same specified center-to-face dimension.

13
does not. It pertains strictly to the health aspects of a clean
With regard to vacuum rating, liner specifications are and cleanable system for the pharmaceutical industry. The
greatly improved, but you will need to check the vacuum semi-conductor industry requires a high, or in some cases
ratings of available pipe and fittings with each tentative higher, degree of cleanliness and cleanability than hygienic
manufacturer. This provision will vary from manufacturer to systems in the pharmaceutical industry, for altogether
manufacturer depending on size, fitting, liner type, pressure different reasons.
and temperature.
A term that can more appropriately be interchanged
Gasket materials such as Garlock‟s Gylon gasket, which between these two industries is high-purity. This implies a
is a PTFE/Silicate composite, and W. L. Gore‟s Universal high degree of cleanliness and cleanability without being
Pipe Gasket, which is a 100% expanded PTFE, have been implicitly connected with one industry or the other.
developed to reduce the creep rate in a gasket material that is
compatible with virtually the same fluid services that lined For what is referred to as product contact material, the
pipe systems are usually selected for. surface roughness, dead-leg minimums and an easily
cleanable system are all imperative. Because of this the
Permeation issues with PTFE liners (it also exists, to a pharmaceutical industry had to make a departure from the 3-
lesser extent, with other liner material) have been A standards it plagiarized early on in order to develop a set
accommodated more than resolved with the use of vents in of guidelines and standards that better suit its industry. Enter
the steel pipe casing, the application of vent components at ASME-BPE.
the flange joint, and increased liner thickness.
ASME-BPE has taken on the task of providing a forum
Internal and external charge accumulation, known as for engineers, pharmaceutical manufacturers, component and
static electricity, or triboelectric charge accumulation, is the equipment manufacturers, and inspectors in an effort to
result of an electrical charge generation unable to dissipate. develop consensus standards for the industry where none
If the electrical charge generation is allowed to continually existed before. I won‟t go further with this except to say that,
dissipate to ground then there is no charge build-up and no to the handful of engineers undaunted by the task ahead of
problem. This is what occurs with steel pipe in contact with them, in approaching ASME about the need to create
a flowing fluid. Charge generation has a path to ground and another standards committee, and the perseverance to see it
does not have an opportunity to build up. through; my hat goes off to you.

With regard to thermoplastic lined pipe there are two Hygienic piping was, up until just recently, referred to
issues to be considered: external charge accumulation and as sanitary piping. Because this term has been so closely
internal charge accumulation. associated with the plumbing industry and sanitary drain
piping it is felt by the pharmaceutical industry that the
This is an issue that requires experience and expertise in change in terminology to hygienic is more appropriate.
order to analyze a particular situation. What we will do in
Part II of this series is provide you with basic information In both the pharmaceutical and semiconductor industries
that will at least allow you to be familiar with the subject, the need for crevice free, drainable systems is a necessity.
and help you to understand the issues. This translates into weld joint quality, mechanical joint
design requirements, interior pipe surface roughness limits,
Standard sizes of plastic lined pipe and fittings range system drainability and dead-leg limitations.
from NPS 1” through 12”. Edlon, a lined pipe manufacturer,
also manufactures larger diameter pipe and fittings from Slope, welding, dead-legs and surface roughness will be
NPS 14” through 24”, and when requested can manufacture discussed in Part II. This article will concentrate on the basic
spools to 144” diameter. aspects of the fittings.

Hygienic Piping Fittings


There are two basic types of fitting joints in hygienic
Hygienic is a term defined in ASME-BPE as: “of or piping: welded and clamp. Welded fittings, unlike standard
pertaining to equipment and piping systems that by design, buttweld pipe fittings, have an added tangent length to
materials of construction, and operation provide for the accommodate the orbital welding machine. The orbital
maintenance of cleanliness so that products produced by welding machine allows the welding operator to make
these systems will not adversely affect animal or human consistent high quality autogenous welds. Autogenous welds
health.” are welds made without filler metal. Fusion is made between
the parent metals of the two components being welded by
While system components such as tube, fittings, valves means of tungsten inert gas welding; more on welding in
and the design itself, with regard to hygienic conditions, can Part II.
translate to the Semi-Conductor industry the term hygienic

14
hold-up. This can result in the loss of residual product, cause
potential cross-contamination of product, and promote
microbial growth.

The reason I mention this here, and I won‟t go into it


any further until Part II, is because there are manufacturers
that are attempting to overcome these issues by improving
on the concept of the clamp joint.

Two manufactures, Swagelok and The Neumo


Ehrenberg Group, represented in the US by VNE, have,
what I would consider, well developed re-designs of the
Figure 11 - Fittings Ready To Be Orbital Welded standard hygienic clamp assembly.
Compliments of ARC Machines, Inc.

Figure 11 is an example of an orbital, or automatic,


welding machine mounted on its work-piece. In this example
it happens to be a 90° elbow being welded to a cross. You
can see by this example why the additional straight tangent
section of automatic weld fittings is needed. That extra
length provides a mounting surface for attaching the
automatic welding machine.

The clamp connection is a mechanical connection


whose design originated in the food and dairy industry, but
whose standardization has been under development by
ASME-BPE. Due to a lack of definitive standardization most
companies that use this type connection require in their
specifications that both the ferrule, the component that the Figure 12 – Swagelok TS Series Profile
clamp fits on, and the clamp itself come from the same Compliments Swagelok Company
manufacturer. This is to ensure a competent fit.
Swagelok has developed what they call their TS series
There are no specific dimensions and tolerances for the fittings. These ferrules (Fig. 12) have a design that provides
clamp assembly, except for that which is being developed by compression control of the gasket while also controlling the
ASME-BPE. Currently it is possible to take a set of ferrules creep tendency inherent in, arguably, the most prevalent
from one manufacturer, mate them together with a gasket, gasket material used in high purity piping, Teflon.
attach a clamp from a different manufacturer and tighten up
on the clamp nut. In some cases you can literally rotate the
clamp by hand about the ferrules. Meaning, there is no force
being applied on the joint seal.

For those of you unfamiliar with the clamp joint, it is


the clamp that applies the force that holds the ferrules
together. The fact that this can occur begs the need for
standardization to a greater degree than what currently
exists.

We‟ll get into this in greater detail in Part II, but another
issue that currently exists with the clamp joint is gasket
intrusion into the pipe ID due to inadequate compression Figure 13 – Maxpure Connect S
control of the gasket. Compliments Neumo Ehrenberg Group

Gasket intrusion is a problem in pharmaceutical service The Neumo Ehrenberg Group manufactures a clamp
for two reasons: 1. Depending on the hygienic fluid service joint (also provided as a bolted connection) that does not
and the gasket material the gasket protruding into the fluid require a gasket (Fig. 13). This type of joint, called the
stream can break down and slough off into the fluid flow, Connect-S under their newly formed MaxPure label of
contaminating the hygienic fluid. 2. The intrusion of the fittings, is currently in use in Europe. While this connection
gasket into pipe ID on a horizontal line can also cause fluid alleviates the issues that are present with a gasketed joint

15
added care would need to be applied in its handling. Any About the author:
scratch or ding to the faced part of the sealing surface could W. M. (Bill) Huitt has been
compromise its sealing integrity. Nevertheless this is a involved in industrial piping
connection design worth consideration. design, engineering and
construction since 1965.
In this first article we have covered a few of the basics, Positions have included
which will provide us with a little more insight when we design engineer, piping design
discuss the more in-depth topics of piping Codes, piping instructor, project engineer,
design, and fabrication of pipe in Part II. project supervisor, piping
department supervisor,
Future Articles engineering manager and
president of W. M. Huitt Co. a
What we have discussed so far is just some of the basics piping consulting firm
of general piping. While there is a great deal left unsaid we founded in 1987. His
will provide further clarification as we move through the experience covers both the engineering and construction
next two articles. fields and crosses industrial lines to include petroleum
refining, chemical, petrochemical, pharmaceutical, pulp &
The next article, titled “Piping Design Part II – Code, paper, nuclear power, biofuel, and coal gasification. He has
Design and Fabrication”, will cover the more specific written numerous specifications, guidelines, papers, and
aspects of Code governance, engineering in pipe design and magazine articles on the topic of pipe design and
fabrication as it relates to welding, assembly and installation. engineering. Bill is a member of ISPE (International Society
of Pharmaceutical Engineers), CSI (Construction
The third article in this series, titled “Piping Design Part Specifications Institute) and ASME (American Society of
III – Installation, Cleaning, Testing and Verification”, will Mechanical Engineers). He is a member of three ASME-
wrap up the series by discussing the four title points. BPE subcommittees, several Task Groups, an API Task
Group, and sets on two corporate specification review
Acknowledgement: boards. He can be reached at:
I wish to thank Earl Lamson, senior Project Manager with W. M. Huitt Co.
Eli Lilly and Company, for taking time out of a busy P O Box 31154
schedule to read through the draft of this article. He obliged St. Louis, MO 63131-0154
me by reviewing this article with the same skill, intelligence (314)966-8919
and insight he brings to everything he does. His comments wmhuitt@aol.com
kept me concise and on target. www.wmhuitt.com

16
As published in the June and July 2007 issues of Chemical Engineering Magazine

Piping Design
Part 2: Code, Design and
Fabrication
There is not a reason sufficiently good enough not to
comply with appropriate industry Standards and
Codes.
W. M. (Bill) Huitt
W. M. Huitt Co.
A request was put to me a few years back asking if I Standard and a Code, but before I do, here‟s the written
would respond in writing to the question, “Why do we, as a response I gave to the above question:
company, need to comply with a piping Code?” The
question was in regard to the building of industrial facilities, Consensus Standards such as those published by ASME,
and was in preparation for a meeting that was about to take ANSI, API, NFPA, ASTM, International Plumbing Code and
place for which the main topic was going to be the issue of others are not mandatory in and of themselves. However,
Code compliance. federal, state, city and other local Codes are mandatory. In
these municipal Codes you will find regulations that
If you considered the question while reading it you may establish various requirements taken in whole, or in part
have noticed that there is, although unintentional, a trick to from the Standards published by the above listed
it. Code, by definition is law with statutory force. Therefore organizations, and others, as legally binding requirements.
the reason for complying with a Code is because you These Standards, as adopted, then become Code, which is
literally have to, or be penalized for non-compliance. enforceable by law.

The question actually intended was, “why comply with When not addressed on a municipal level, but included
or adopt a piping consensus standard?” When a question like in corporate specifications, the Standard becomes a legal
the one above is phrased as it is it supports my contention Code on a contractual basis.
that many people, referring to engineers and designers in our
case, do not fully understand the difference between a Code To comply with these Codes, irrespective of government
and a Standard. And it doesn‟t help matters when some regulations or corporate requirements, doesn't cost the
Standards are published as a Code, and some Codes are builder any more than if they didn't comply. It does,
published as a Standard. This is certainly nothing to get however, cost more to fabricate and install piping systems
excited about, but it is something worth pointing out. that have a high degree of integrity as opposed to a system
that doesn't.
My take on the reason for the misunderstanding of these
two closely related terms, Standard and Code, is that they By hiring non-certified welders and plumbers, by-
get bounced around so often in the same context that passing inspections, examinations and testing, using
designers and engineers simply begin interchanging the two material that may potentially not withstand service pressures
terms without much consideration for their different and temperatures, and supporting this type of system with
meanings. I‟m going to explain the difference between a potentially inadequate supports is less costly but there's too
much at risk. I don't think anyone in good conscience would
intentionally attempt to do something like that in order to
save money, but then again the world is full of unscrupulous Like the seatbelt law Code compliance is not just the
individuals and corporations. law, it makes good sense. A professional Consensus
Standard is, very simply put, a Code waiting to be adopted.
If anyone intending on fabricating and installing a Take the ASME Boiler and Pressure Vessel Code (BPVC),
piping system plans to: since its first publication in 1915 it has been adopted by 49
states, all the provinces of Canada, and accepted by
1. Use listed material, regulatory authorities in over 80 countries.
2. Specify material that meets the requirements for fluid
service, pressure and temperature, On May 18, 2005 it was finally adopted by the 50 th
3. Inspect the material for MOC, size and rating, state, South Carolina. And this doesn‟t mean the BPVC is
4. Use certified welders and plumbers, adopted in its entirety. A state, or corporation for that matter,
5. Inspect welds and brazing, can adopt a single section or multiple Sections of the BPVC,
6. Adequately support the pipe, or they can adopt it in its entirety. Until South Carolina
7. Test the pipe for tightness; adopted the BPVC it was actually no more than a Standard
in that state and only required compliance when stipulated in
Then they are essentially complying with Code. The Code a specification. However, in all honesty you would not get a
simply explains how to do this in a formal, well thought-out US boiler or pressure vessel manufacturer to by-pass Code
manner. compliance. That is, unless you wanted to pay their potential
attorneys fees.
There is not a reason sufficiently good enough not to
comply with appropriate industry Standards and Codes. If With regard to Code compliance, the question I get
there was a fee involved for compliance this might be a quite often is, “How do I determine which piping Code, or
stimulus for debate. But there is no fee, and there is usually Standard, I should comply with for my particular project?”
just too much at stake. Even with utility systems in an admin
building or an institutional facility, the potential damage Determining proper Code application is relatively
from a ruptured pipeline, or a slow leak at an untested joint straightforward while at the same time providing a certain
could easily overshadow any savings gained in non- degree of latitude to the Owner in making the final
compliance. That's without considering the safety risk to determination. In some cases that determination is made for
personnel. the Engineer or Contractor at the state level, the local level
or by an Owner company itself. Providing guidelines for
The first thing that someone should do, if they are Code adoption on a project basis is direction that should be
considering to do otherwise, is check local and state Code. included in any company‟s set of specifications, but quite
They may find regulations that require adherence to ASME, often is not. This can cause a number of disconnects through
the International Plumbing Code or some of the other design and construction.
consensus Standards. If not already included, this should be
a requirement within any company’s specifications. In order to answer the question about Code assignment
some history has to be told. In keeping this brief I will just
Just a bit of trivia: touch on the high points. In 1942, ASA B31.1 – American
ASME published the first edition of the Boiler and Standard Code for Pressure Piping was published by the
Pressure Vessel Code in 1914-15. Prior to creation of the American Standards Association. This would later change to
Code, and what played a large part in instigating its B31.1 - Power Piping. In the early 1950‟s the decision was
creation, was that between 1870 and 1910 approximately made to create additional B31 Codes in order to better define
14,000 boilers had exploded. Some were devastating to both the requirements for more specific needs. The first of those
people and property. Those numbers fell off drastically as Standards was ASA B31.8 – Gas Transmission and
the Code was adopted. Distribution Piping Systems, which was published in 1955.
In 1959 the first ASA B31.3 – Petroleum Refinery Piping
Uniformity and regulation does have its place. Standard was published.

PIPING CODE After some reorganization and organizational name


changes the ASA became ANSI, American National
In a piping facility, defined here as an industrial facility Standards Institute. Subsequent Code revisions were
requiring a significant amount (apply your own order of designated as ANSI Codes. In 1978, ASME was granted
magnitude here) of pipe, the three key factors in its accreditation by ANSI to organize the B31 Committee as the
development are the governing Code, the design (includes ASME Code for Pressure Piping. This changed the Code
specifications and engineering), and pipe fabrication designation to ANSI/ASME B31.
(includes installation). These are the three topics we will
discuss on a broad, but limited basis in this article.

2
Since 1955 the B31 Committee has continued to research facility could possibly require fluid services beyond
categorize, create and better define Code requirements for the fluid service limits of B31.9. In that case, B31.3 would
specific segments of the industry. Through the years since be adopted for those services.
then they have created, not necessarily in this order, B31.4 –
Liquid Transportation Piping, B31.5 – Refrigeration Piping, In the case of a process manufacturing facility, B31.3
B31.9 – Building Services Piping, and B31.11 – Slurry would be the governing Code. Since B31.3 covers all piping,
Transportation Piping. Each of these Standards is considered B31.5 or B31.9 would not need to be included, not even
a stand-alone Section of the ASME Code for Pressure necessarily with associated lab, office and research facilities.
Piping, B31. The only time B31.5 or B31.9 would become governing
Codes, in association with a manufacturing facility, is if a
What the B31 committee has accomplished, and is refrigeration unit, or an office, lab and/or research facility
continuing to improve upon, are Standards that are better were under a separate design/construct contract from the
focused on specific segments of industry. This alleviates the process manufacturing facility. Or they were a substantial
need for a designer or constructor building an institutional part of the overall project.
type facility from having to familiarize themselves with the
more voluminous B31.3 or even a B31.1. They can work As an example, project XYZ consists of a process
within the much less stringent and extensive requirements of manufacturing facility, related office building and lab
B31.9, a Standard created for and much more suitable for facilities. If the utility service piping for the office and lab
that type of design and construction. facilities is a small percentage of the overall project, and/or
the design and construction contracts for those facilities are a
As mentioned above, ASME B31.1 – Power Piping, was part of the overall process manufacturing facility, all piping,
first published in 1942. Its general scope reads: “Rules for with Code exclusions, could be governed by B31.3.
this Code Section have been developed considering the
needs for applications which include piping typically found If, however, the office and lab facilities were a
in electric power generating stations, in industrial and substantial part of the overall project, or they were to go to a
institutional plants, geothermal heating systems, and central separate constructor it may be more beneficial to determine
and district heating and cooling systems.” battery limits for those facilities and designate anything
inside those battery limits as B31.1 or B31.9 and/or B31.5.
The general scope of ASME B31.3 – Process Piping, In such a case, separate pipe specifications may have to be
reads: “Rules for the Process Piping Code have been issued for those portions of the project designated as being
developed considering piping typically found in petroleum governed by B31.9. This is due to the range of fluid services
refineries, chemical, pharmaceutical, textile, paper, and the corresponding pressure and temperature limits of
semiconductor and cryogenic plants; and related processing B31.9 compared to those of B31.3. These differences in
plants and terminals.” Code assignment and battery limits may be a driver for the
project‟s contracting strategy.
ASME B31.5 – Refrigeration Piping, applies to
refrigerant and secondary coolant piping systems. Many piping service requirements such as steam, air,
chilled water, etc. can come under the auspices of multiple
Closely related to B31.1, but not having the size, Codes. These fluid services, which fall within the definition
pressure or temperature range, B31.9 was first published in of B31.3 Category D fluid services, can just as easily fall
1982. It was created to fill the need for piping in limited within the requirements of B31.1 or B31.9 as well. In an
service requirements. Its scope is narrowly focused on only effort at maintaining a high degree of continuity in the
those service conditions that may be required to service the process of making the determination of which Code to apply
utility needs of operating a commercial, institutional or to a project, company guidelines should be well defined.
residential building.
The final determination as to what constitutes a
From its shear scope of responsibility, B31.3 governing Code, within the purview of the above mentioned
encompasses virtually all piping, including those also Codes, is left to the Owner and/or to the local governing
covered by B31.1 (except for boiler external piping), B31.5 jurisdiction. Engineering specs should clarify and reflect the
and B31.9. The difference, and distinction, as to which Code intent of the Owner and the respective Codes in an attempt
should apply to a particular project, lies with the definition to provide consistency and direction across all projects
and scope of the project itself. within a company.

If a project includes only the installation of perhaps a PIPING DESIGN


refrigeration system, B31.5 would apply. If a project's scope
of work consists of an office, laboratory, research facility, Piping design is the job of configuring the physical
institutional facility or any combination thereof, B31.1 or aspects of pipe and components in an effort to conform with
B31.9 and possibly B31.5 would apply. A laboratory or P&ID‟s, fluid service requirements, associated material

3
specifications, equipment data sheets, and current Good and technical material selection for sulfuric acid service
Manufacturing Practice while meeting Owner expectations. would not be economically feasible for chilled water service.
All of this has to be done within a pre-determined three-
dimensional assigned space while coordinating that activity Procurement too, will need detailed specifications to
with that of the architecture, structural steel, HVAC, limit the assumptions they will have to make or the
electrical, video, data & security conduit and trays, and questions they will have to ask in preparing purchase orders.
operational requirements. The piping specification should make clear exactly what the
material of construction is for each component, and what
Pulling together and coordinating the above mentioned standard that component is manufactured to. Also included
discipline activities to achieve such a compilation of design in the component description should be pressure rating, end
requires a systematic methodology, planning, technical connection type and surface finish where required.
ability, coordination, foresight, and above all experience.
There are a few rather consistent mistakes that
A note of omission here: CAD (Computer Aided Design) companies make in developing or maintaining specs: 1.
is such an integral part of piping design that it’s difficult, if within the spec itself they are either not definitive enough or
not impossible, to discuss design without including CAD in they are too definitive; 2. they are not updated in a timely
the discussion. It plays such a large part that, rather than manner; and/or 3. The specs are too broad in their content.
enter into it here, I will dedicate an entire article to it at a
later date. That article will discuss the integration of CAD In defining the above issues we‟ll begin with:
into the industry including its merits, and how, in many
respects, its method of implementation and integration has Point #1: When defining pipe and components in a
inversely diminished the quality of design with respect to specification you should provide enough information to
industrial piping. The article will also discuss industry’s identify each component without hamstringing yourself or
reaction to this unexpected result, and the issues we are still procurement in the process. What I mean by that is, do not
dealing with today in the use of CAD. get so specific or proprietary with the specification that only
one manufacturer is qualified to provide the component,
PIPING SPECIFICATIONS unless you intend to do just that. With standard pipe and
fittings it‟s difficult to provide too much information.
One of the first activities the piping engineer will be However, with valves and other inline equipment it can
involved with is development of piping specifications, happen quite easily.
design guidelines and construction guidelines. Piping
specifications, as an overview, should provide essential A common practice of spec writers is to write a
material detail for design, procurement and fabrication. specification for a generic type valve, one that can be bid on
Guidelines, both design and construction, should provide by multiple potential suppliers, by using the description of
sufficient definition in a well organized manner to allow the one particular valve as a template. What happens is that
designer and constructor the insight and direction they need proprietary manufacturer trade names, such as some of the
in order to provide a facility that will meet the expectation of trim materials, are carried over to the generic valve spec.
the Owner with minimal in-process direction from the When the procurement person for the mechanical contractor,
Owner or Construction Manager. or whoever is buying the valves for the project, gets ready to
buy this valve the only manufacturer that can supply it with
Piping Specifications the specified proprietary trim is the one from which the spec
was copied.
A Piping Specification is the document that will
describe the physical characteristics and specific material You would think that, in doing this, it would eliminate
attributes of pipe, fittings and manual valves necessary to the multiple bids for the valve based on the unintentional
needs of both design and procurement. These documents proprietary requirements in the spec. In actuality it creates
also become contractual to the project and those contractors confusion and propagates questions. The valve bidders, other
that work under them. than the one the spec was based on, will bid the valve with
an exception to the proprietary material, or they will contact
Design will require a sufficient degree of information in the purchasing agent for clarification. Since the purchasing
a specification that will allow for determining the service agent won‟t have the answer, the question, or actually the
limitations of the specification and what fluid services the clarification, then goes back to the engineer and/or the
specification‟s material is compatible with. That is, a project Owner. The time necessary in responding to these types of
may have, among other fluid services, sulfuric acid and issues is better spent on more pressing matters.
chilled water. The economic and technical feasibility of the
material selection for chilled water service would not be When developing a spec be specific, but try not to
technically feasible for sulfuric acid. Inversely, the economic include proprietary data unless you intend to. As an example
when specifying Viton you are specifying a generic DuPont

4
product. Generic in that there are several different types of 6. Gasket type, rating and material
Viton such as Viton A, Viton B, Viton GF, Viton GFLT, etc. 7. Bolt & nut type and material
Each of these has specific formulations, which gives them 8. Manual valves grouped by type
different fluid service compatibility and pressure/ 9. Notes
temperature ranges. Viton is a type of fluorocarbon. 10. Branch chart matrix with corrosion allowance
Fluorocarbons are designated FKM under ASTM D-1418.
So when specifying “Viton” you are identifying a specific The ten line items above provide the primary
product from a specific manufacturer…almost. component information and notations required for a typical
piping system. Some specifications are written to include
If, in developing a specification, you wish to establish such components as steam traps, sight glasses, 3-way or 4-
minimum requirements for a component or a material it is way valves, strainers, and other miscellaneous type items.
certainly acceptable to identify a specific proprietary item as Those miscellaneous items are better referred to as specialty
a benchmark. In doing this, and we‟ll stay with the items (or some other similar descriptive name) and are sized
fluorocarbon gasket or seal material example, you could and specified for each particular application. This does not
identify Viton GF or equal, which would indicate that a make them a good candidate for inclusion into a basic pipe
comparable material from one of the other fluorocarbon specification.
manufacturers would be acceptable so long as the fluid
service compatibility and pressure/temperature ranges were To explain the above we can use, as an example, a
equal to or greater than the Viton GF material. carbon steel piping system that is specified to be used in a
150 psig steam service. The pipe, flanges, fittings, bolts,
In saying “almost” above what I meant by that is, if you gaskets and valves can all be used at any point in the system
write the spec as Viton you would most likely get the as specified. The specification for a steam trap, however,
original formulation, which is Viton A. The fluid service will vary depending on its intended application. And
may be more suited for an FKM with depending on its application the load requirements for each
polytetrafluoroethylene in it. That would be a Viton GF. Or trap may vary.
an FKM suitable for colder temperatures may be a better
choice. That would be a Viton GFLT. Be specific for those As an example, a steam trap application at a drip leg
that have to use the specs to design from and those that have will have a light steady load, whereas a steam trap
to purchase the material. application at a shell & tube heat exchanger may have a
heavier modulating load. And that doesn‟t take into account
Point #2: All too often after a specification is developed the need for the different types of traps, e.g. F&T, inverted
it will reside in the company‟s database without being bucket, thermodynamic, etc.
periodically reviewed and updated. Industry standards
change, part numbers change, manufacturers are bought and You could, depending on the size of the project, have
sold; manufacturers improve their products, etc. All of these multiple variations of the four basic types of steam traps
things constitute the need and necessity to review and revise with anywhere from 30 to 300 or more traps in multiple
specifications on a timely basis. sizes and various load requirements. I think you can see why
this type of requirement needs to be its own specification
A company that houses their own set of specifications and not a part of the piping specification.
should review those specifications at least every two years.
This timing works out for a couple reasons: 1. industry A piping specification should be concise, definitive and
standards, on average, publish every two years, and 2. repeatable. Adding specialty type items to the specification
capital projects, from design through close-out, will arguably makes it convoluted and difficult to control and interpret.
have an average duration of two years. Lessons-learned from Users of these specifications are designers, bidders,
projects can then be considered for adoption into company procurement personnel, fabricators, receipt verification
specs, prompting a new revision. clerks, validation and maintenance personnel.

Point #3: Specs being too broad in their content refers to With that in mind you can better understand, or at least
an attempt at making the specs all-inclusive. A piping value the fact, that these documents have to be interpreted
specification should contain only those components and and used by a wide range of personnel. Those personnel are
information that would typically be used from job to job. looking for particular information, written in a concise
That would include the following (as an example): manner that will allow them to design and order or verify
components within that specification. In attempting to
1. Pressure/Temperature limit of the spec include the specialty type items it will, at the very least,
2. Limiting factor for Pressure/Temperature complicate and exacerbate the process.
3. Pipe material
4. Fitting type, rating and material DESIGN AND CONSTRUCTION GUIDELINES
5. Flange type, rating and material

5
Design and construction guidelines, working in petroleum refining and chemical companies you
conjunction with the piping specifications, should convey to will see entire departments whose mission is to
the designer and constructor point by point requirements as create, maintain and refine all of the
to how a facility is to be designed and constructed. The specifications and guidelines necessary to
guidelines should not be a rhetorical essay, but instead execute a project. When a project is approved to
should follow an industry standard format, preferably a CSI go out for bid to an Engineer the necessary
(Construction Specifications Institute) format. specifications and guidelines, along with the
requisite drawings, are assembled, packaged and
Look at it this way, the material specifications tell the provided to the Engineer as bid documents, and
designer and constructor what material to use; the guidelines beyond that as working documents in the design,
should tell them how to assimilate and use the material engineering and construction efforts.
specifications in applying them to Good Design Practice. 2. In scenario 2 the Owner, or Customer, has some
Without these guidelines as part of any bid package or specifications and guidelines that have possibly
Request For Proposal package, the Owner is essentially not been updated for several years. These are
leaving it up to the Engineer and/or Constructor to bring provided to the Engineer with the understanding
their own set of guidelines to the table. And this may or may and stipulation that any errors or omissions in
not be a good thing. Leaving the full facilities delivery to the the documents should be addressed and
Engineer and Constructor depends a great deal on the corrected by the Engineer. These too would be
qualifications of the Engineer and the Constructor, and used in the bid process as well as on the project
whether or not consistency from plant to plant and project to itself.
project is an issue. 3. In scenario 3 the Owner, or Customer, brings no
specifications or guidelines to the project table.
If the Owner approaches a project with expectations as Specification development becomes part of the
to how they would like their plant or facility designed and overall project engineering effort.
built then some preparation, on the Owner‟s part, is in order.
Preparation should include, not only material specifications Scenarios 1 and 3 are at opposite ends of the spectrum,
as described earlier, but also the guidelines and narratives but afford the best situation for both the Owner and
(yes, narratives) necessary to define the design and Engineer/Constructor. By providing the Engineer and
construction requirements. Constructor, as in scenario 1, with a full set of current
specifications and well articulated guidelines, making the
I mention the use of narratives here because it helps assumption that both the engineer and constructor are
facilitate the understanding and convey the magnitude of the, qualified for the level of work required, they can very
in most cases, reams of specifications and guidelines effectively execute the design, engineering and construction
necessary to build an industrial facility of any appreciable for the project.
size.
Scenario 3 allows the Engineer and Constructor to bring
A narrative, in general, should explain in simple, their own game-plan to the project. This too is effective, due
straight-forward language, for each discipline, the only to the fact that the learning curve is minimal. Most
numbering scheme used for the specifications and engineering firms will be prepared to execute a project with
guidelines; association between the material specifications their own set of specifications and guidelines. This applies to
and the guidelines; an explanation as to why the project is qualified Constructors as well. The down-side of this is the
governed by a particular Code or Codes; and a brief project to project inconsistency in specifications and
description of expectation. methodology when using different engineers and
constructors.
The narrative allows you to be more explanatory and
descriptive than a formal point-by-point specification. It Scenario 2 is a worse case situation. Ineffective and
gives the bidder/Engineer a Readers Digest version of the outdated Owner specifications create confusion and
stacks of specifications and guidelines they are expected to inefficient iterations in both the bid process and the
read through and assimilate within a matter of a few weeks execution of a project. It additionally creates the greatest
opportunity for conflicts between Owner documents and the
How piping specifications are delivered to a project can Engineer‟s documents. For Project Management, this
have a significant impact on the project itself. There are, translates into change orders at some point in a project.
generally speaking, three scenarios in which project
specifications and guidelines are delivered to a project: A guideline should explain to the engineering firm or
1. In scenario 1 the Owner, or Customer, has constructor, in a concise, definitive manner, just what it is
developed, throughout their existence, a the Owner expects of them in executing the design and
complete arsenal of specifications and construction of a facility. By actively and methodically
guidelines. In the older, more established developing a set of guidelines an Owner/Customer does not

6
have to rely on an outside resource, such as an engineering wall thickness, MAWP/MADP, design pressure/temperature,
firm or constructor, to hopefully provide them with the and charge accumulation.
facility they require and hope to get.
Flanges
Developing guidelines to convey your company‟s
requirements and expectations can be accomplished using In the learning process, some designers (I include
one or both of the following two basic methods: engineers as well) will gloss over some of the primary basics
of design and go directly to the bottom line information they
1. A formal point-by-point format that covers need. Case in point: In Part I, of this series of articles, we
all necessary criteria that you, as the Owner, discussed ASME flanges and their Classifications. Most
require on a proprietary basis, plus a listing designers are familiar with ASME flange Classifications
and description of the necessary Code and such as 150, 300, 400, etc. And even though verbally stating
cGMP requirements. 150 pound flange (we discussed the origin of this term in
2. A narrative, for each discipline, that allows Part I) rolls off the tongue much easier and is still an
the writer to expand and define, in a much industry accepted term; Class 150 is the proper terminology
more descriptive manner, the points that and designation.
aren‟t made clear enough, or readily
apparent in the more formal format. What you may not know is that the Class designation is
a factor in the calculation for determining the rated working
The guideline itself can be structured based on one of pressure of a flange. That calculation is:
the CSI formats. The format examples provided by CSI give
a company sufficient flexibility in writing guidelines, or PT Pr S1 / 8750 Pc (eq. 1)
specifications for that matter, to allow the document to
conform to their own particular brand of requirements and
nuances. It also lends a degree of intra-industry conformity Where:
to the guidelines and specifications, providing a degree of Pc = ceiling pressure, psig, as specified in
familiarity to the engineers and constructors that will have to ASME B16.5, para. D3 at temperature T
adhere to them. PT = Rated working pressure, psig,for the
specified material at temperature T
Design Elements Pr = Pressure rating class index, psi1 (e.g., Pr =
300 psi for Class 300)
In the first paragraph of this segment of the article, S1 = Selected stress, psi, for the specified
“Piping Design”, I described the act of designing piping material at temperature T. See ASME
systems for a facility as bringing a number of technical B16.5, paras. D2.2, D2.3 and D2.4.
1
components together to make the pipe conform to a specific This definition of Pr does not apply to Class 150. See ASME
B16.5, paras. D2.2, D2.3 and D2.4.
set of requirements, within a prescribed area.

That‟s pretty simplistic, and does not really convey the Pipe Internal Surface Finish
magnitude of the experience, technical background or the
imagination required to execute such a task. Experience is Internal surface roughness is a topic that is specific to
the essential component here. And that is simply because, the pharmaceutical, bio-pharmaceutical and semiconductor
aside from whatever innate ability a good designer might industries, but can also be an issue in the chemical industry.
possess, the knowledge required is not taught through formal
education, but is instead learned by being involved in the Quantifying and specifying a maximum surface
process of hands-on design over a period of time roughness for internal pipe wall for use in, what is referred
accompanied by ongoing learning. to as direct impact fluid services, is a necessity in the above
mentioned industries.
Ongoing learning can be in the form of organized
classes, a mentor and/or any other means available to help Direct impact piping systems are those systems that
learn and understand the physical requirements and restraints carry product or carry a fluid service that ultimately comes
of the various systems you will be designing and industries in contact with product.
you will be serving.
The need for a relatively smooth internal pipe wall is
Since we do not have enough space here to cover all of predicated on three primary issues as it relates to the
the design elements I would like to, I will key in on a few industries mentioned above. Those issues are: 1.
topics that generally find their way to me for clarification. Cleanability/Drainability, 2. The ability to hinder the growth
And this doesn‟t even scratch the surface. We will discuss (we don‟t yet have the ability to control it) of biofilm and to
flanges, pipe internal surface finish, weld seam factor, pipe enhance the ability to remove it once it does appear, and 3.
To reduce, to a microscopic level, crevices in which

7
microscopic particles can reside and at some point dislodge
and get carried along in the fluid stream to damage product. The accepted max surface finish in the pharmaceutical
and bio-pharmaceutical industries is 25Ra µin (0.6 µm). In
Regarding the first point, cleanability and drainability the semiconductor industry you might typically see surface
are associative in this context. Meaning that, in order for a finishes in the 7Ra µin to 15Ra µin, particularly in gas
system to be fully cleanable it has to be designed and laid delivery systems. While the pharmaceutical industry is
out in a manner that will eliminate any pockets and provide concerned with bacterial growth and cross contamination,
enough slope to eliminate any residual liquid (drainable). the semiconductor industry is concerned more with
Not only is this residual liquid, or hold-up, a contaminant, particulate damage to product, on the microscopic level.
from both a bacterial standpoint and as a cross batch This pertains to point three above.
contaminant, it can also be costly due to the high cost of
some drug products. Along those lines, the ASME-BPE
Standard provides criteria for minimum slope, maximum
deadleg, gasket intrusion, gasket concavity, and many other
criteria for design of cleanable and drainable hygienic piping
systems.

Regarding the second point, biofilm (Fig. 1) is defined


as a bacterial population composed of cells which are firmly
attached as microcolonies to a solid surface.

A paper titled, “Microbial Biofilms – are they a problem


in the Pharmaceutical Industry?”, was delivered at an
ASME-BPE symposium in Cork, Ireland, June 2004 by
Frank Riedewald, a Senior Process Engineer with Fig. 2 – Biofilm Attachment vs Surface Roughness
Lockwood-Greene IDC Ltd. In it he explains the results of (Courtesy of Mr. Riedewald)
testing that was performed to determine the relative
association between the formation of biofilm, pipe wall Pipe Weld Seam Factor
surface finish and pipe wall surface cleanability.
Part I, of this series of articles, mentioned the fact that
the weld seam in longitudinally welded pipe is a factor in the
pipe wall pressure design thickness calculation.

In ASME B31.3 there are two pipe wall thicknesses to


calculate for. One is pressure design thickness (t) and the
other is minimum required thickness (tm).

There are two equations for finding pressure design


thickness (t) for straight pipe under internal pressure. One is
where t < D/6. This calculation (eq. 2) is based on internal
pressure, actual (not nominal) OD of the pipe, stress value of
the material at design temperature, joint efficiency factor,
Fig. 1 – Biofilm magnified ≈2000X and the coefficient Y [a factor used to adjust internal
(Courtesy of Mr. Riedewald) pressure (P) for a nominal material at temperature].

One of the many interesting factors that came from the The other calculation used is that in which t ≥ D/6. This
studies mentioned in this paper is the fact that the internal calculation (eq. 3) is based on the above listed criteria except
surface of the pipe wall can actually be too smooth. for the OD and uses instead ID of the pipe, and the sum of
Referring to the graph in Fig. 2, results of the studies in the all mechanical allowances.
above mentioned paper indicate that the surface finish range
best suited to reduce biofilm adherence to the internal pipe The two equations look like this:
wall surface is from 0.4Ra µm to 1.Ra µm (15.7Ra µin to Where t < D/6:
58.8Ra µin). What this implies is that while we currently do
not have the means to prevent the onset of biofilm on the PD (eq. 2)
internal walls of hygienic or semiconductor piping systems t
2( SE PY )
we can facilitate its removal in the cleaning process by
specifying the proper surface finish of the internal pipe
walls. Where t ≥ D/6:

8
Throughout design the vessel‟s intended maximum
P(d 2c) (eq. 3) pressure is referred to as its design pressure. All calculations
t
2[ SE P(1 Y )] are based on specified material and component tolerances
along with fabrication specifics, meaning types and sizes of
welds, reinforcement, etc. Not until after the vessel is
Where: fabricated can the engineer know what the actual material
t = Pressure design thickness thickness is, the type and size of each weld, thickness of
tm = Minimum required thickness, including each nozzle neck, etc. Only when all of the factual data of
mechanical, corrosion, and erosion construction is accumulated and entered into vessel
allowances engineering programs can the MAWP be determined. This
c = Sum of the mechanical allowances (thread value, once determined, then replaces the design pressure,
or groove depth) plus corrosion and and is calculated based on the installed configuration of the
erosion allowances. For threaded vessel. That is, mounted vertically or horizontally; mounted
components, the nominal thread depth on legs; or mounted on lugs.
(dimension h of ASME B1.20.1, or
equivalent) shall apply. For machined The difference between the design pressure and the
surfaces or grooves where the tolerance is MAWP is that the engineer will design to the design
not specified, the tolerance shall be pressure, but the final MAWP is the limiting pressure of the
assumed to be 0.02 in. (0.5 mm) in vessel, which may exceed the design pressure; it can never
addition to the specified depth of the cut. be less than the design pressure.
D = Actual pipe OD
d = Pipe ID In applying this to piping we will first calculate the
P = Internal design gage pressure burst pressure of the pipe and then determine the MAWP, or,
S = Stress value for material from ASME as was mentioned earlier, a term more closely related to
B31.3 Table A-1, at design temperature piping, the Maximum Allowable Design Pressure (MADP).
E = Quality factor, or joint efficiency factor
Y = Coefficient from ASME B31.3 Table There are three equations generally used in calculating
304.1.1, valid for t < D/6. burst pressure for pipe. They are:

The minimum required thickness (tm) is simple enough: The Barlow formula;

(eq. 4) 2 TF S T
tm t c
PBA (eq. 5)
D
To determine wall thickness for pipe under external
pressure conditions refer to the Boiler and Pressure Vessel The Boardman formula:
Code (BPVC) Section VIII, Division 1, UG-28 through UG-
30 and ASME B31.3, Para. 304.1.3.
2 TF S T (eq. 6)
PBO
Keep in mind that for seamless pipe E will be removed D (0.8 T )
from equations eq. 2 & eq. 3.

Taking a page from the BPVC we will go through a few The Lame` formula:
brief steps to determine Maximum Allowable Working
Pressure (MAWP) for straight pipe. But let me begin by
saying that MAWP is not a B31.3 expression, it comes from
ST (D 2 d 2 )
the BPVC. We will instead transpose this term to MADP PL (eq. 7)
(Maximum Allowable Design Pressure), which is also not a (D 2 d 2 )
B31.3 term, but more closely relates to piping.
Where:
When a vessel goes into design it is assigned a PBA = Burst Pressure, psig (Barlow Formula)
coincidental design pressure and temperature. These are the PBO = Burst Pressure, psig (Boardman Formula)
maximum conditions the vessel is expected to experience PL = Burst Pressure, psig (Lame` Formula)
while in service, and what the vessel engineers will design D = Actual pipe OD, inches
to. The material, material thickness, welds, nozzles, flanges, d = Pipe ID, inches
etc. are all designed predicated on this predetermined design TF = Wall thickness, inches, minus factory
criteria. tolerance
ST = Minimum tensile strength, psi, from

9
B31.3 Table A-1 System Operating Temperature: The temperature at
Sf = Safety factor, a factor of 3 or 4 is applied which a fluid service is expected to normally operate at.
to burst pressure to determine MADP
M = Maximum Allowable Design Pressure System Design Temperature: Unless extenuating
(MADP) process conditions dictate otherwise, the design
temperature, for operating temperatures between 32°F and
Using the results from any one of the above equations 750°F, shall be equal to the maximum anticipated operating
we can then solve for MADP as follows: temperature, plus 25°F rounded off to the next higher 5°.

Applying a sort of philosophy created by the above


P** (eq. 8) definitions is somewhat straight forward for utility services
M
Sf such as steam, water, non-reactive chemicals, etc. However,
that part of the above definitions for design conditions that
** = BA, BO, or L subscript provide the caveat, “…extenuating process conditions…”
implies a slightly different set of rules for process systems.
Design Pressure and Temperature
Extenuating process conditions can mean increased
The ASME B31.3 definition for Design Pressure and pressure and temperature, beyond that defined above, due to
Design Temperature is stated as two separate definitions. I chemical reaction, loss of temperature control in heat
will integrate them into one by stating: The design pressure transfer, etc.
and temperature of each component in a piping system shall
be not less than the most severe condition of coincident Charge Accumulation of Lined Pipe
internal or external pressure and temperature (minimum or
maximum) expected during service. Clarification
Internal and external charge accumulation, known as
It goes on to state: The most severe condition is that static electricity, or more technically known, as triboelectric
which results in the greatest required component thickness charge accumulation, is the result of charge generation
and the highest component rating. unable to dissipate. If a charge generated in a flowing fluid
is allowed to dissipate to ground, as it does in grounded
How do you determine these values and where do you metallic pipe, then there is no problem. However, if a charge
apply them? We‟ll cover the where first. What we did earlier cannot dissipate and is allowed to accumulate, it now
in determining pipe wall thickness was based on design becomes a problem by potentially becoming strong enough
conditions, in which P = Internal Design Gage pressure and to create an Electrostatic Discharge (ESD). With regard to
S = Stress value at design temperature. Design conditions are thermoplastic lined pipe there are two forms of this to be
also used to determine component rating and as a basis for considered: External Charge Accumulation (ECA) and
determining leak test pressure, which we will get into in the Internal Charge Accumulation (ICA).
final article of this series.
External Charge Accumulation
There is no published standard, or real industry ECA is a concern with lined pipe due to the possibility
consensus on how to determine design conditions. It of not achieving spool-to-spool continuity during installation
basically comes down to an Owner‟s or engineer‟s due, in large part, to improved paint primer on flanges.
experience. What I will provide here is a resultant
philosophy developed from many sources along with my To explain the loss of spool-to-spool continuity: this
own experiences. lack of integral continuity is, as mentioned above, the result
of the prime paint coat that is applied by the manufacture.
In understanding what constitutes design conditions we When pipe spools, lined or un-lined, are joined by flanges
first of all need to define them. Following is some accepted using non-metallic gaskets the only thing that completes the
terminology and their definitions: Spool-to-spool continuity is the bolting. The improved paint
primer on lined pipe flanges makes this more difficult to
System Operating Pressure: The pressure at which a achieve because normal bolt tightening doesn‟t guarantee
fluid service is expected to normally operate at. metal-to-metal contact between the nut and the flange.

System Design Pressure: Unless extenuating process Pipe generally does not come with a prime coat of paint,
conditions dictate otherwise, the design pressure is the however lined pipe does. Since flange bolts are used to
pressure at the most severe coincident of internal or external complete continuity from spool to spool the installer has to
pressure and temperature (minimum or maximum) expected make certain, when installing lined pipe, that the bolts, at
during service, plus the greater of 30 psi or 10%. least one of the bolts, has penetrated the primer and made
contact with bare metal. This was achieved in the past by

10
using star washers on at least one flange bolt while assuming ready-made solution to the external continuity problem is the
possible bare metal contact with the other bolts allowing the addition of stud bolts located in close proximity to flanges
washers, as they were tightened, to scrape away the prime on both pipe spools and fittings (see Fig. 3). These studs can
coat so that contact was made with the bare metal of the be applied at the factory or in the field. At each flange joint a
flange. With improved prime coat material this is no longer a grounding strap (jumper) is then affixed to a stud on one
guarantee. spool with a nut, extended over the flange joint and attached
to a stud on the connecting spool completing continuity
If continuity from spool to spool is not achieved any throughout the chain of connecting spools and fittings.
charge generation resulting from an internal or an external
source cannot readily dissipate to ground. The voltage in
triboelectric charge generation will build until it is strong
enough to jump to the closest grounded object creating an
undesired spark of electricity in doing this (Electrostatic
Discharge).

Internal Charge Accumulation


ICA, with regard to pipe, is unique to thermoplastic
Figure 3 – Grounding Lug Location
lined pipe and solid thermoplastic pipe. Without being
impregnated with a conductive material, thermoplastics are
Another method of creating continuity at flange joints,
not good conductors of electricity. PTFE
while being less obtrusive and more integral, is described as
(Polytetrafluoroethylene), as an example, used as a pipe
follows and represented in Fig. 4:
liner, has a high (>1016 Ohms/Square), resistivity factor. This
is a relatively high resistance to conductivity. This means
Referring to Fig. 4, flanges would be purchased pre-
that any charge created internally to the pipe cannot readily
drilled and tapped in the center of the outer edge of the
be conducted away to ground by way of the PTFE liner.
flange between the backside of the flange and the face side
Instead the charge will be allowed to build until it exceeds
of the flange. The drilled and tapped hole in each flange will
its total dielectric strength and burns a pinhole in the liner to
need to be centered between boltholes so that they line up
the internal metal wall of the casement pipe. It isn‟t charge
after the flange bolts are installed. The tapped hole is 1/4”
generation itself that is the problem, it‟s the charge
dia. x 1/2” deep.
accumulation. When the rate of charge generation is greater
than the rate of charge relaxation (the ability of material to
After a flange set is installed and fully bolted the
conduct away the generated charge), charge accumulation
Continuity Plate (Fig. 4) can be installed using two 1/4”
occurs.
x1/2” long hex head screws and two lock washers. The
Continuity Plate has two 0.312” slotted boltholes allowing
The dielectric strength of PTFE is 450 to 500 volts/mil.
for misalignment and movement.
This indicates that for every 0.001” of PTFE liner 450 volts
of triboelectric charge will be required to penetrate the liner.
The entire continuity plate assembly is relatively simple
For a 2” pipeline with a 0.130” thick liner this translates into
to install, unobtrusive and establishes integral contact with
58500 volts of triboelectric charge to burn through the liner
the pipeline.
thickness.

When the liner is penetrated by an accumulated charge


two additional problems (time bombs) are created: 1.
Corrosive fluid (a major user of lined pipe) is now in contact
with and corroding the metal pipe wall and at some point,
depending on rate of corrosion, will fail locally causing fluid
to leak to the environment, and 2. The initial charge that
burned through the liner is now charging the outer metal
pipe, which, if continuity has not been achieved for the outer
pipe, a spark of triboelectric charge is, at some point, going
to jump to ground causing a spark.

Corrective Action
External Charge Generation
The simplest method to ensure continuity is to sand
away any primer on the back side of each flange to ensure
good metal-to-metal contact between nut and flange. Aside
from that or the use of a conductive prime paint, the current

11
Figure 4 – Continuity Flange Plate

Internal Charge Generation Figure 5 – Conductive Orifice Plate Assembly


One of the first options in preventing Internal Charge
Accumulation is by minimizing charge generation. This can
be done by adjusting the flow velocity relative to the liquid‟s
conductivity. To minimize design impact, cost and even
schedule impact on a project this needs to be evaluated early
in the project due to the possibility of a change in line size.
To retard charge generation by reducing flow velocities
British Standard (BS) suggests the following as represented
in Table 1 per BS 5958:

TABLE 1 - RECOMMENDED VELOCITIES


BS 5958 Recommended Flow
Liquid Conductivity
Velocity
>1000 pS/m No restriction
50 – 1000 pS/m Less than 7 m/s
Less than 50 pS/m Less than 1 m/s Figure 6 – Conductivity Orifice Plate Assembly Section
pS/m (picosiemens/meter)
Conclusion and Recommendations
If velocity reduction is not an option, or if further It is difficult to pre-determine what fluid services and
safeguards against charge accumulation are warranted then a systems will be candidates for charge accumulation
mechanical solution to provide a path to ground for Internal prevention and Electrostatic Discharge protection. The
Charge Generation might be called for. simplest and most conservative answer to that is to assume
that all fluid services in lined pipe systems are susceptible.
One method for conducting charge accumulation from In saying that, we then have to declare that a company‟s pipe
the interior of the pipe to ground is indicated in Figures 5 & specifications need to reflect a global resolution that will
6. What is shown is an orifice plate made of conductive affect all installations.
(static dissipative) material that is compatible with the fluid
service. The orifice itself is off center to the OD of the plate With regard to External Charge Accumulation, the
and the pipeline itself. With the shallow portion of the ID at recommendation for future installations with the least impact
the invert of the pipe it allows the piping to drain in would be to specify pipe with no prime coat or at least no
horizontal runs. primer on the flanges, or a prime coat using a conductive
paint. The un-primed pipe would be primed prior to
The tab portion of the plate extends beyond the flange installation with care given to primer touchup on flanges
OD. On the tab is a bolthole for attaching the modified after installation by the installing contractor or their sub.
Continuity Flange Plate. The plate is designed to come in This would better ensure spool-to-spool external continuity.
contact with the interior surface of the liner wall as well as
protrude into the flowing fluid providing a conduit for For existing installations either the studs or the
internally generated charge. Continuity is achieved by continuity plate installation would work. It can also be
attaching the plate to the flange OD that is in contact with suggested that the continuity plates can be tacked on to one
the piping, which is, in turn, grounded through equipment. flange rather than drilling and tapping both flanges.

For dissipating internal charge generation the orifice


plate, as shown in Figures 5 & 6, is the only
recommendation.

PIPE FABRICATION

Entering this part of the article on fabrication does not


mean that we leave engineering behind. Indeed, the majority,
if not all, fabricators (referring to the fabricators that are
qualified for heavy industrial work) will have an engineering
staff.

12
Hygienic Clamp Joint
As a project moves from the design phase into the
construction phase anyone with a modicum of project The clamped joint, as mentioned in Article I, refers to
experience can acknowledge the fact that there will most the sanitary or hygienic clamp. As you can see in Fig. 7
certainly be conflicts, errors and omissions, no matter how there are issues with this type clamp.
diligent one thinks they are during design. This is inherent in
the methodology of today‟s design/engineering process.
There are methods and approaches to design in which this
expected result can be minimized. It‟s actually a
retrospective concept, but we will save that for a future
article.

The preparation for such errors and omissions is always


prudent. If, on the other hand, the assumption is made that
the Issued for Construction design drawings will facilitate
fabrication and installation with minimal problems, then you
can expect to compound whatever problems do occur
because you weren‟t prepared to handle them. The greatest
asset a project manager can have is the ability to learn from
past experience and the talent to put into practice what they Figure 7 – Hygienic Clamp Joint
have learned. (Courtesy Rubber Fab Technologies Group)

Fabrication Represented in Fig. 7 are three installed conditions of


the hygienic joint, minus the clamp. Joint „A‟ represents a
Pipe fabrication, in this context, is the construction of clamp connection that has been over tightened causing the
piping systems by forming and assembling pipe and gasket to intrude into the ID of the tubing. This creates a
components with the use of flanged, threaded, clamped, damming effect, preventing the system from completely
grooved, crimped and welded joints. draining.

In Article I we discussed the flange joint, we will In joint „B‟ the clamp wasn‟t tightened enough and left
discuss the others here. There are various factors, or a recess at the gasket area. This creates a pocket where
considerations, that prompt the decision as to which type of residue can accumulate and cleanability becomes an issue.
connection to use in the assembly of a piping system. To
start with, any mechanical joint is considered a potential leak Joint „C‟ represents a joint in which the proper torque
point and should be minimized. Also, the decision as to was applied to the clamp leaving the ID of the gasket flush
which type of joint should be specified comes down to with the ID of the tubing.
accessibility requirements, installation requirements and
joint integrity. Using that as our premise we can continue to The clamp „C‟ representation is the result that we want
discuss the various joining methods. to achieve with the hygienic clamp. The problem is that this
is very difficult to control on a repeatable basis. Even when
Threaded Joints the gasket and ferrules are initially lined up with proper
assembly and torque on the joint, some gasket materials
Pipe thread, designated as NPT (National Pipe Taper) have a tendency to creep (creep relaxation), or cold flow.
under ASME B1.20.1, is the type of thread used in joining
pipe. This is a tapered thread that, with sealant, allows the Creep relaxation is defined as: A transient stress-strain
threads to form a leak-tight seal by jamming them together condition in which strain increases concurrently with the
as the joint is tightened. decay of stress. More simply put, it is the loss of tightness in
a gasket, measurable by torque loss.
I described the threaded flange joint in Article I. Those
same criteria apply also to threaded fittings, in which the Cold Flow is defined as: Permanent and continual
benefits of the threaded joint is both in cost savings and in deformation of a material that occurs as a result of
eliminating the need for welding. In this regard, to prolonged compression or extension at or near room
paraphrase Article I, threaded components are sometimes temperature.
used in high-pressure service in which the operating
temperature is ambient. They are not suitable where high There have been a number of both gasket and fitting
temperatures, cyclic conditions or bending stresses can be manufacturers that have been investing a great deal of
potential concerns. research in attempting to resolve this issue with the clamp
joint. Some of the solutions regarding fittings were

13
addressed in Article I. Additionally, gasket manufacturers, The pressed joint is actually a system that uses thin wall
and others have been working on acceptable gasket materials pipe, up through 2” NPT, to enable the joining of pipe and
that have reduced creep relaxation factors, as well as fittings with the use of a compression tool. Welding is not
compression controlled gasket designs. required and threading is only necessary when required for
instrument or equipment connection.
When mentioning acceptable gasket material in the
previous paragraph, what I am referring to is a gasket that is
not only compatible with the hygienic fluid service, but also
meets certain FDA requirements. Those requirements
include Gasket material that complies with USP Biological
Reactivity Test #87 & 88 Class VI for Plastics and FDA
CFR Title 21 Part 177.

Grooved Joint

The grooved joint (Fig. 8), from simply a static internal


pressure containment standpoint, is as good as or, in some Figure 9 – Pressed Joint
cases superior to the ASME Class 150 flange joint. In the (Courtesy Victaulic)
smaller sizes, 1” through 4” the working pressure limit will
be equal to that of a Class 300, carbon steel, ASTM A105, These types of systems are available from various
ASME B16.5 flange. manufacturers in carbon steel, 316 and 304 stainless steel
and copper. Because of the thin wall pipe corrosion
Its main weakness is in its allowable bending and allowance becomes a big consideration with carbon steel.
torsional stress at the coupling. This can be alleviated with
proper support. Because of this design characteristic the While the static internal pressure rating of these systems
manufacturers of grooved joint systems have focused their is comparable to an ASME Class 150 flange joint there are
efforts and created a niche in the fire protection and utility additional fluid service and installation characteristics that
fluid service requirements, with the exception of steam and need to be considered. With axial and torsional loading
steam condensate. being the weak spot in these systems they are not practical
where water hammer is a potential, such as in steam
This type of joint is comparatively easy to install and condensate. The axial load consideration carries over to
enhances that fact in areas that would require a fire card for supporting the pipe as well. Ensure that vertical runs of this
welding. Since no welding is required modifications can be pipe are supported properly from beneath. Do not allow
made while operation continues. Some contractors choose to joints in vertical runs to be under tension. They must be
couple at every joint and fitting, while others choose to supported properly from the base of the vertical run.
selectively locate couplings, much as you would selective
locate a flange joint in a system. It‟s a decision that should Welded Joint
be made based on the particular requirements or preference
of a project or facility. The welded joint is by far the most integrated and
secure joint you can have. When done properly it is as strong
as the pipe itself. The key to a weld‟s integrity lies in the
craftsmanship of the welder or welding operator, the
performance qualification of the welder or welding operator,
and the weld procedure specification.

Before I go further I want to explain the difference


between the terms welder and welding operator. A welder is,
as you might have guessed, someone who welds. To be more
precise, it is someone who welds by hand, or manually. A
welding operator is someone who operates an automatic
welding machine. The ends of the pipe still have to be
prepared and aligned, and the automatic welding machine
has to be programmed.
Figure 8 – Grooved Pipe & Coupling
(Courtesy Victaulic) The advantage of machine welding is apparent in doing
production welds. This is shop welding in which there is a
Pressed Joint quantity of welds to be made on the same material type, wall
thickness and nominal pipe size. Once the machine is set up

14
for a run of typical pipe like this it is very efficient and material it is welding it will provide excellent welds on a
consistent in its weld quality. consistent basis. Provided, that is, that the chemistry of the
base material is within allowable ranges.
This is another topic that could easily stand alone as an
article, but we won‟t do that here. Instead we will focus on
some of the primary types of welding used with pipe. Those
types include:

1. GMAW (Gas Metal Arc Welding) or MIG


2. GTAW (Gas Tungsten Arc Welding) or TIG
3. SMAW (Shielded Metal Arc Welding) or MMA or
Stick Welding
4. FCAW (Flux Cored Automatic welding)

GMAW: Most often referred to as MIG, Metal Inert


Gas welding, GMAW (Gas Metal Arc Welding) can be an Figure 11 – GTAW (TIG) Welding
automatic or semi-automatic welding process. It is a process (Courtesy The Welding Institute)
by which a shielding gas and a continuous, consumable wire
electrode is fed through the same gun (Fig. 10). The A wide differential in sulfur content between the two
shielding gas is an inert or semi-inert gas such as argon or components being joined can cause the weld to drift into the
CO2 that protects the weld area from atmospheric gases, high sulfur side. This can cause welds to be rejected due to
which can detrimentally affect the weld area. lack of full penetration.

There are four commonly used methods of metal SMAW: Also referred to as MMA, Manual Metal Arc
transfer used in GMAW. They are: welding, or just simply Stick welding, SMAW (Shielded
1. globular, Metal Arc Welding) is the most common form of welding
2. short-circuiting, used. It is a manual form of welding that uses a consumable
3. spray, and electrode, which is coated with a flux (Fig. 12). As the weld
4. pulsed-spray is being made the flux breaks down to form a shielding gas
that protects the weld from the atmosphere.
With the use of a shielding gas the GMAW process is
better used indoors or in an area protected from the wind. If The SMAW welding process is versatile and simple,
the shielding gas is disturbed the weld area can be affected. which allows it to be the most common weld done today.

Figure 10 – GMAW (MIG) Welding


(Courtesy The Welding Institute) Figure 12 – SMAW (Stick) Welding
(Courtesy The Welding Institute)
GTAW: Most often referred to as TIG, Tungsten Inert
Gas welding, GTAW (Gas Tungsten Arc Welding) can be FCAW: Flux Cored Arc Welding is a semiautomatic or
automatic or manual. It uses a nonconsumable tungsten automatic welding process. It is similar to MIG welding, but
electrode to make the weld (Fig. 11), which can be done the continuously fed consumable wire has a flux core. The
with filler metal or without filler metal (autogenous). The flux provides the shielding gas that protects the weld area
TIG process is more exacting, but is more complex and from the atmosphere during welding.
slower than MIG welding.
Welding Pipe
In Article 1 I mentioned the use of orbital welding for
hygienic tube welding. Orbital welding uses the GTAW The majority of welds you will see in pipe fabrication
method. Once the orbital welder is programmed for the will be full penetration circumferential buttwelds, fillet

15
welds or a combination of the two. The circumferential 11. Gage Calibration certifications
buttwelds are the welds used to weld two pipe ends together 12. Weld Continuity Report
or other components with buttweld ends. Fillet welds are 13. WPS‟s (Weld Procedure Specifications)
used at socketweld joints and at slip-on flanges. Welds in 14. PQR‟s (Procedure qualification Record)
which a combination of the buttweld and fillet weld would 15. Weld Coupon log
be used would be at a stub-in joint or a joint similar to that. 16. Weld Maps
17. Slope Maps
A stub-in joint (not to be confused with a stub-end) is a 18. Weld Logs
connection in which the end of a pipe is welded to the 19. Leak Test Reports
longitudinal run of another pipe (Fig. 13). Depending on 20. Inspection reports
what the design conditions are this can be a reinforced 21. Passivation Records
connection or an unreinforced connection. The branch 22. Detail mechanical layouts
connection can be at 90º or less from the longitudinal pipe 23. technical specifications for components
run. 24. As-Built Isometrics
25. Original IFC isometrics
26. Documentation recording any changes from IFC to
As-Build isometrics

The above listed documentation, which closely parallels


the list in ASME-BPE, is that which is generally required to
move an installed hygienic system through validation,
commissioning and qualification (C & Q). And this isn‟t all
Figure 13 – Sample Stub-In Connections that‟s required. There is additional supporting
(Courtesy ASME B31.3) documentation such as P&ID‟s, procedural documents, etc.
that are also required. Depending on the size and type of a
Hygienic Fabrication and Documentation project it can be a massive undertaking. If not properly set
up and orchestrated it can become a logistical nightmare.
Hygienic and semiconductor pipe fabrication uses
automatic autogenous welding in the form of orbital What you do not want to do is discover during C&Q
welding. This, as explained in Article I, is a weld without the that you are missing a portion of the required
use of filler metal. It uses the orbital welding TIG process. In documentation. Resurrecting this information is labor
some cases hand welding is required, but this is kept to a intensive and can delay a project‟s turn-over significantly. I
minimum, and will generally require pre-approval. cannot stress it strongly enough just how imperative it is that
all necessary documentation be identified up front. It needs
When fabricating pipe for hygienic services it will be to be procured throughout the process and assimilated in a
necessary to comply with, not only a specific method of turnover package in a manner that makes it relatively easy to
welding, but also an extensive amount of documentation. As locate needed information while also allowing the
mentioned in Article I, developing and maintaining the information to be cross indexed and traceable within the TO
required documentation for hygienic pipe fabrication and package.
installation can add an additional 30% to 40% to the piping
cost of a project. The term validation is a broad, generalized, self-
defining term that includes the act of commissioning and
The documentation needed, from the fabrication effort qualification. Commissioning and qualification, while they
for validation, may include, but is not limited to: go hand in hand, are two activities that are essentially
distinct within themselves.
1. Incoming Material Examination Reports
2. Material Certification For this article I will go no further with the topic of
a. MTR‟s Validation, Commissioning and Qualification. This is a topic
b. Certification of Compliance that I will touch on again in Article III.
3. Weld Gas Certification
4. Signature Logs Future Articles
5. WPQ‟s (Welder & Welding Operator Performance
Qualification) The third and final article in this series, titled “Piping
6. Welder & Welding Operator Inspection Summary Design Part III – Installation, Cleaning, Testing and
7. Mechanical and electropolishing procedures Verification”, will wrap up the series by discussing the four
8. Examiner Qualification title points.
9. Inspector Qualification
10. Welder Qualification Summary Acknowledgement:

16
I wish to thank Earl Lamson, Senior Project Manager
with Eli Lilly and Company, for being kind enough in taking
time out of a busy schedule to read through the draft of this
second article. Earl has a remarkable set of project and
engineering skills that set him apart from many I have
worked with. That and the fact that I value his opinion are
the reasons I asked him to review this article.

About the author:


W. M. (Bill) Huitt has
been involved in industrial
piping design, engineering
and construction since 1965.
Positions have included
design engineer, piping design
instructor, project engineer,
project supervisor, piping
department supervisor,
engineering manager and
president of W. M. Huitt Co. a
piping consulting firm
founded in 1987. His experience covers both the engineering
and construction fields and crosses industrial lines to include
petroleum refining, chemical, petrochemical,
pharmaceutical, pulp & paper, nuclear power, biofuel, and
coal gasification. He has written numerous specifications,
guidelines, papers, and magazine articles on the topic of pipe
design and engineering. Bill is a member of ISPE
(International Society of Pharmaceutical Engineers), CSI
(Construction Specifications Institute) and ASME
(American Society of Mechanical Engineers). He is a
member of three ASME-BPE subcommittees, several Task
Groups, an API Task Group, and sets on two corporate
specification review boards. He can be reached at:
W. M. Huitt Co.
P O Box 31154
St. Louis, MO 63131-0154
(314)966-8919
wmhuitt@aol.com
www.wmhuitt.com

17
As published in the September and October 2007 issues of Chemical Engineering Magazine

Piping Design Part 3:


Installation, Cleaning,
Testing & Verifification
Efficiency, quality and safety are the imperatives that
are factored in when considering field fabrication, but
don’t forget cost.
W. M. (Bill) Huitt
W. M. Huitt Co.
As the title implies this article will discuss the at an on-site field fabrication area and then erected. A
Installation, Cleaning, Testing and, to a lesser degree, number of factors will dictate whether or not it is feasible to
Validation of piping systems. I say to a lesser degree with field fabricate: The size and type of the project, pipe size and
Validation because Validation is a very complex, often material, the facility itself, weather conditions, availability
proprietary and exceedingly difficult-to-define topic. Rather of qualified personnel, existing building operations,
than delve into it in great detail as part of a multi-topic cleanliness requirements, time available to do the work, etc.
article I will attempt to simply provide some understanding
as to its function and need. Efficiency, quality and safety are the imperatives that
are factored in when considering field fabrication. And
PIPE INSTALLATION before you think I missed it, cost is the fallout of those
factors. Logistically speaking, if all pipe could be fabricated
But first things first, the installation of pipe follows its on-site in a safe and efficient manner, maintaining quality
fabrication and is very frequently a part of it. The installation while doing so, it would make sense to do it in that manner.
of pipe can be accomplished in the following four primary However, before making that final decision, let’s look at
ways, or combinations thereof: some of the pros and cons of field fabrication:

1. Field fabricate and install, Pros:


2. Shop fabricate and field erected, 1. Only raw material (pipe, fittings, valves, etc.)
3. Skid fabrication, assembly & installation, and need to be shipped to the site location. This is
4. Modular construction much easier to handle and store than multi-plane
configurations of pre-fabricated pipe.
I would like to assure you that I am not going to diverge 2. No time-consuming need to carefully crib, tie-
off into fabrication again since we discussed it, although down and chock pre-fabricated *spool pieces for
somewhat briefly, in Article II. I am including fabrication in transport to the job site.
this article simply because fabrication is such an integral part 3. Reduced risk of damage to spool pieces.
of pipe installation. 4. More efficient opportunity to fab around
unexpected obstacles (structural steel, duct,
FIELD FABRICATE AND INSTALL cable tray, etc.)
5. Fabricate-as-you-install reduces the rework risk
Field fabrication and installation is just what it implies. assumed when pre-fabricating spools, or the cost
The pipe is fabricated on site either in place or in segments
related to field verification prior to shop One is a Field Weld (FW) and the other is a Field
fabrication. Closure Weld (FCW). The FW indicates a joint in which the
6. The field routing installation of pipe through an end of a pipe segment is prepared for the installer to set in
array of insufficiently documented locations of place and weld to its connecting joint without additional
existing pipe and equipment, on a retrofit modification in the field. This means that the length of pipe
project, is quite frequently more effective than that is joined to another in the field is cut precisely to length
attempting to pre-fabricate pipe based on and the end prepared in the shop for welding.
dimensional assumptions.
*Spool pieces are the pre-fabricated sections of pipe that are The FCW provides the installer with an additional
fabricated and numbered in the fab shop then shipped to the job site
length of pipe, usually 4” to 6” longer than what is indicated
for installation.
on the design drawings, to allow for field adjustment.
Cons:
1. Weather is arguably the biggest deterrent. If the What has to be considered, and what prompts the need
facility under construction is not enclosed then for a FCW, is the actual, as-installed, location of both the
protection from the elements will have to be fixed equipment that the pipe assemblies may connect to and
provided. the actual installed location of the pipe assembly itself. Odds
2. When welding has to be done in conditions that are that all equipment and piping will not be installed
are not environmentally controlled then pre- exactly where indicated on design drawings.
heating will be required if the ambient
temperature (not the metal surface temperature) The dimensional location of the equipment items given
is 0° F or below. on design drawings is not a finite location, they are merely
3. In a new facility, as opposed to having to route intended locations, as are drawings for building steel, pipe
piping through an array of poorly located supports and others. What factors into the installation of
existing pipe and equipment, field fabrication of shop fabricated pipe is the actual location of the equipment
buttwelded pipe is not as efficient and cost nozzle it will be connecting to in relation to the pipe’s
effective as shop fabrication. installed location.
4. Concerns about safety and efficiency when
working in a facility while it is in operation in In connecting to equipment there is a build-up, or stack-
advance of a turnaround or to begin advance up, of tolerances that will effectively place the actual, or
work on a plant expansion. final, location of the nozzle at some point in the xyz
geometry of three-dimensional space, other than where the
Generally speaking, threaded, socketweld, grooved, and design drawing indicates. The tolerance stack-up comes
other proprietary type joints that do not require buttwelding from the following:
are field fabricated and installed. Buttwelding of small, 1
1/2” NPS and less, are very often field fabricated and 1. Manufacturing tolerances in material forming,
installed because of the added risk of damage during nozzle location, and vessel support location.
transport, in pre-fabricated form, from the shop to the site. 2. The actual set-in-place location of the vessel.
3. Load cell installation (when applicable).
SHOP FABRICATE AND INSTALL 4. The actual set-in-place pipe run-up location.

Shop fabrication is, generally speaking, any pipe, In order to allow for these inevitable deviations between
fittings and components that are assembled by welding into the drawing dimensions used to fabricate the vessel, set the
spool assemblies at the fabricator’s facility. The spools are vessel, and install the pipe assembly, and the actual installed
then labeled with an identifier and transported to the job site location of the connecting points, a field closure piece, or
for installation. two, will be required for that final adjustment.

Each spool piece needs its own identifier marked on the The field closure piece is a designated section of the
piece itself in some fashion that will make it easy to know pipe assembly in which a field weld has been indicated. The
where its destination is in the facility and/or where it belongs section with the field closure weld would be the length
in a multi-spool system of pipe. This will allow the installer required to agree with that indicated on the design drawing,
to efficiently stage the piece and ready it for installation. plus an additional 4” to 6” (more or less depending on
fabricator’s comfort level with the equipment locations).
As part of the process of developing spool sections What this does is allow the field to make the final
field-welded joints need to be designated. These are welded determination in the adjustments when connecting to fixed
joints that connect the pre-fabricated spools. In doing this equipment.
the designer or fabricator will identify two different types of
field-welded joints. SKID (SUPER SKID) FABRICATION

2
A skid is a pre-packaged assembly that may contain all approach. There are no hard and fast rules for determining a
or some of the following that make up an operating system: best approach at job execution. It requires experienced
vessels, rotating equipment, piping, automation components, personnel assigning values to the various aspects of project
operator interfaces, instrumentation, gages, electrical panels, execution, overlaying a timeline, and then assessing
wiring and connectors, framework, supports, in-line piping logistics. Sounds simple, but is in actuality can be a very
components, and insulation. A single process or utility complex process.
system may fit onto one skid or, depending on size
restraints, may comprise multiple skids. What I am attempting to say here is, that the following
is a guideline and not hard and fast rules. There are simply
After fabrication of a skid is complete it will typically too many project variables and complexities to allow it.
go through Factory Acceptance Testing (FAT) at the
fabricator’s facility. The skid is then shipped to the job site In approaching this decision keep in mind that the
where it is installed in its final location. After installation it method of installation needs to be weighed against a
would typically go through a follow-up Site Acceptance Test contractor’s preferred methodology. In saying that I am not
(SAT), including additional hydro-testing. This is basically a implying that the contractor’s preferred methodology should
system shake-down to determine that everything is intact, drive your decision on how to execute a job. On the
and that those things that did not remain intact during contrary, once you determine how the job needs to be
transport are discovered and repaired. executed you then look to only those contractors whose
preferred methodology agrees with your project execution
Logistics and the necessary skill-set required for the plans.
installation, connection and start-up of a particular skid
package will dictate to what extent the skid fabricator will be Some contractors prefer to do most, if not all fabrication
involved after it is shipped to the job site. in the shop, others prefer to set up at the job-site, while
others are flexible enough to utilize the best of both
MODULAR CONSTRUCTION methods.

The term module or modular construction is quite often, The three main criteria, efficiency, quality and safety
in this context, interchanged with the term skid fabrication. indicated earlier under “Field Fabricate and Install”, would
A module can refer to pre-fabricated units that actually form apply here as well. Using those three elements as a basis for
the structure of a facility as each is installed. Or, the units making our determination let us look at some common
may be smaller sub-assemblies that, when combined, make variables:
up a complete process or utility system.
1. Environment
Modules too consist of all or some of the following: a. Controlled environment
vessels, rotating equipment, piping, automation components, b. Open to the elements
HVAC, instrumentation, electrical wiring and connectors, 2. Industry
framework, walls, architectural components, lighting, a. Pharmaceutical
supports, in-line piping components, and insulation. This, as b. Biopharmaceutical
an example, allows a complete locker room module to be c. Semiconductor
placed and connected to a complete water treatment module. d. Food & Dairy
e. Petroleum refining
The smaller sub-assembly modules, in many cases, are f. Bulk chemical
interchanged with the term skid. It saves on misperception g. Pulp & paper
when a company defines these terms, both for internal h. Off-Shore
discussion and for the purpose of making it clear to outside i. Pipeline
contractors, as to what is meant when using the term j. Power generation
module. 3. Type of project
a. Retrofit
INSTALL APPROACH b. Fast track approach
c. New (Grassroots/Greenfield) project
Now that we have a general idea of the four primary d. Clean-build
approaches to piping installations how do we decide which e. Single level
is the best method, or combination of methods, to use for a f. Multi-level
particular project? But there is one major caveat I would like g. Room repetition
to address before launching into this subject. 4. Range of pipe material and sizes
a. Small percentage of alloy pipe
Each project is individualized with its own particular set b. Large percentage of alloy pipe
of decision drivers with regard to a selected execution c. Large % of large pipe sizes

3
d. Large % of small pipe sizes of a facility, to be microbial and particulate free, as
e. Mix of small and large pipe sizes stipulated by the design.
5. Location
a. Close to metropolitan area There can be no debris, organic or inorganic, remaining
b. Remote location after construction in accessible or inaccessible spaces of the
c. Country with limited resources facility. Of particular concern with the pharmaceutical,
biopharm and food 7 dairy is food waste and hidden
Environment moisture. Food waste can entice and support rodents and
The environment is only a factor when work has to be insects, and hidden moisture can propagate mold, which can
done in an open-air structure or other outdoor installation eventually become airborne. If not discovered until the
(tank farm, pipeline, pipe rack or yard piping, etc.). Working facility is in operation the impact, upon discovery, can
in an open air structure will require protection from the potentially be devastating to production.
elements (rain, snow, wind, cold, etc.). There may
additionally be a requirement to work in elevated areas on Such contamination can be discovered in one of two
scaffolding and otherwise. All of this can have a potential ways. Discovery at the source, possibly behind a wall or
impact on safety and efficiency. some other out-of-the-way place, means that not only does
current production have to cease, but product will have to be
Pipe rack installation consists mainly of straight runs of analyzed for possible contamination. Once found it hen has
pipe, and will not necessarily have a requirement or need for to be remediated.
pre-fabrication. That is, unless it is pre-fabricated as modular
skid units. Depending on the project it could be cost The other method of discovery comes from the
effective on an overall strategic basis to modularize the pipe continuous testing and validation of the product stream. If a
rack, steel and all. contaminant is discovered in the product the production line
is stopped and the problem then becomes an investigation in
The big advantage to shop fabrication is the controlled to finding the source of the contamination.
environment in which it’s done. This includes the Quality
Control aspect, better equipment (generally speaking), a The clean-build philosophy therefore dictates more
routine methodology of how a piece of work progresses stringent and strict requirements for controlling and
through the shop, and better control, through a developed inspecting for debris on an ongoing basis throughout
routine, of required documentation. construction and start-up.

Industry It will be necessary, on a clean-build site, to follow


I know this is generalizing, but we can group the some rather simple rules:
various industries into clean/indoor build and non- 1. Smoking or smokeless tobacco products of any
clean/outdoor build. There are exceptions to this, but under kind are not allowed on the site property,
clean/indoor build we can list the following; 2. Off site break and lunch areas, no food or drink,
other than water, allowed on the site premises,
Clean/Indoor build 3. Do not begin installing pipe, duct or equipment
a. Pharmaceutical until, at the very least, a roof is installed,
b. Biopharmaceutical 4. After roof and walls are installed ensure that
c. Semiconductor there is no standing water remaining in the
d. Food & Dairy facility,
5. Prior to and during the construction of hollow
Under non-clean/outdoor build we can list the walls, such as those framed and dry-walled,
following; ensure on a daily basis that there is no moisture
or debris in the wall cavity,
Non-Clean/Outdoor Build 6. Duct work delivered to the job site shall have the
a. Petroleum refining ends covered with a plastic sheet material, which
b. Bulk chemical shall remain on the ends until connected in place,
c. Pulp & paper 7. Fabricated pipe delivered to the job site shall
d. Off-Shore have the ends covered in a suitable fashion with
e. Pipeline suitable material, and shall remain on the ends
f. Power generation until connected in place,
8. During and after flushing and testing of pipelines
The clean build philosophy comes from the need to all water spills shall be controlled to the extent
construct certain facilities with a more stringent control on possible and shall be cleaned up after flushing
construction debris. Those industries listed above under and testing or at the end of the work day,
Clean/Indoor Build often require a facility, at least a portion

4
Type of Project Keeping personnel and equipment to a minimum at the
job site is not an absolute, but is one of the key
While the type of project is not the main influence in considerations to the efficiency of pipe installation.
determining how you approach the execution of a project it Following that logic most of the buttwelded pipe should be
does play a key role. It will help drive the decision as to how shop fabricated. A couple of things to consider, when
the piping should be fabricated and installed. determining which buttwelded pipe to shop fabricate, is size
and material.
As an example, if the project is a retrofit it will require
much of the pipe, regardless of size and joint connection, to Range of Pipe Material and Sizes
be field fabricated and installed. This is due simply to the
fact that the effort and cost necessary to verify the location Shop fabricated spools need to be transported to the job
of all existing pipe, equipment, walls, columns, duct, etc. in site. This requires handling. Handling and transporting small
a somewhat precise manner, would not be very practical. diameter pipe and/or thin-wall tubing spools creates the
You would be better served by field verifying the potential for damage to those spools.
approximate location of the above items with existing
drawings, for planning and logistic purposes, then shop or If you are shop fabricating everything and the distance
field fabricate, verify and install as you go. from shop to site is simply across town the risk to damaging
small diameter pipe spools is a great deal less than if they
A fast track project, one that has a compressed schedule, have to be shipped half way across the US, Europe or Asia.
will require parallel activities where possible. Whereas shop Or even across an ocean.
and skid fabrication would be utilized as much as possible
simply to expend more man-hours over a shorter time period In transporting spools over long distances, unless there
while attempting to maintain efficiency. Even though there is a great deal of thought and care given to cribbing the load
may be added cost to this approach. This approach is time of spools, it may not be beneficial to transport buttwelded
driven and not budgetary driven. pipe spools NPS 1 ½” and less. It may be more practical to
fabricate these sizes on site, unless you are fabricating
A new grassroots facility still requires routing hygienic or semi-conductor piping. These types of systems
verification as you go, but certainly not the much more require a great deal more control and a cleaner fabrication.
involved need to locate previously installed obstructions as Meaning that pipe fabrication will require a clean shop area
needs to be done when working with an existing facility. on-site, or the pipe will need to be fabricated at an off-site,
better controlled shop facility.
If the project is a clean-build project (typical for the
pharmaceutical, biopharmaceutical, semiconductor and food A practical rule of thumb in determining what to shop
& dairy industries) inside an environmentally controlled area fab and what to field fab follows in Table 3-1:
it will be more practical to shop fabricate or utilize skid or
modular fabrication for most, if not all of the piping. This Table 3-1 Shop and Field Fabrication
will reduce the number of personnel and the amount of Size (in) Material Joint Shop/Field
fabrication debris in the facility, and provide better control ≤1½ Pipe 1, 2, 3, 6 Field
for keeping it out of the pipe itself. With personnel you ≤1½ Pipe 4&5 Shop
could have food wrappers, drink cans and bottles, food ≥2 Pipe 3&6 Field
waste, and clothing items. Fabrication debris could include ≥2 Pipe 4&5 Shop
metal filings, cutting oil, pieces of pipe, weld rod and weld ≤1 Tubing 5 Field
wire remnants, etc. ≤1 Tubing 5 Shop (a, b)
≥1½ Tubing 5 Shop
If the project is not a clean-build, but is still inside an Joint Type:
environmentally controlled facility the same logic does not 1 = Socketweld
necessarily apply. The decision to shop fab and install or to 2 = Threaded
field fab and install becomes one based on efficiency rather 3 = Grooved – Fully (Grooved fittings and pipe ends.)
4 = Grooved – Partially (Shop-welded spools with grooved ends.)
than how best to maintain a clean area. And that’s not to say 5 = Buttweld
that if it doesn’t qualify as a clean-build project then the 6 = Flanged – Lined or unlined Pipe
construction debris can just be allowed to pile up. Notes:
a. Hygienic tubing
b. Special cribbing and support for transport
There is still safety and efficiency to be concerned with
on any project and a clean job site is a major part of that.
The above Table 3-1 is a general methodology. Dictates
Maintaining a clean job site is an integral component of
of the project and a contractors SOP will determine how best
good project execution.
to define what gets shop fabricated and what gets field
fabricated.

5
Petroleum refining and bulk chemical projects are remote areas. And this doesn’t even touch on the security
generally open air projects in which field fabrication and aspect.
installation of pipe is exposed to the elements. While a clean
build is not a requirement on these types of projects Nowadays, when constructing in any number of remote
efficiency and, above all, safety is, as it is on any type areas, security is a real concern that requires real
project. Because of this, it would make sense to utilize shop consideration and real resolution. Reduced on-site staffing is
fabrication as much as possible. a good counter-measure in reducing risk to personnel when
building in remote or even non-remote third-world areas.
Fabricating pipe spools under better controlled shop
conditions will provide improved efficiency and safer per PIPE SYSTEM CLEANING
hour working conditions over what you will generally find in
the field. This translates into fewer accidents. While there are requirements in ASME for leak testing
cleaning requirements do not exist. In ASTM A 380 & 967
Referring back to Table 3-1, with respect to the you will find Standards on cleaning, descaling and
potential for damage during transport, pipe sizes NPS 2” to passivation, but nothing in ASTM on simply flushing and
3” and larger ship much better than smaller pipe sizes. general cleaning. Defining the requirements for the internal
Particularly when working with thin-wall tubing. This is a cleaning of piping systems falls within the responsibilities of
consideration when determining what to shop fab and what the Owner.
to field fab.
The term “cleaning”, in this context, is a catch-all term
Location that also includes flushing, chemical cleaning, and
passivation. So before we go further let me provide some
Job site location is one of the key markers in definition for these terms as they apply in this context. I say,
determining shop or field fabrication. In many cases building “as they apply in this context”, because these terms are
a facility in a remote location will be a driver for utilizing a somewhat flexible in their meaning, depending on source
disproportionate amount of skid or module fabrication. and context, and could be used to describe activities other
Disproportionate in the sense that project management may than what is intended in this dialog.
look at modularizing the entire job, rather than mobilize the
staffing and facilities needed to fab and install on or near the Definitions
job site. This would constitute a larger amount of
modularization over what might normally be expected for Cleaning: A process by which water, solvents, acids or
the same type project in a more metropolitan region, or an proprietary cleaning solutions are flushed through a piping
area with reasonable access to needed resources. system to remove contaminants such as cutting oils, metal
filings, weld spatter, dirt, and other unwanted debris.
To expand on that thought; it was pointed out to me by
Earl Lamson, Senior Project Manager with Eli Lilly and Flushing: A process by which water, air or an inert gas
Company, an observation I fully agree with, that project is forced through a piping system either in preparation for
resources, even in metropolitan areas, are quite frequently chemical cleaning or as the only cleaning process. Flushing
siloed around a specific industry. In certain regions of the can be accomplished by using dynamic pressure head or
US for example, you may discover that there are an released static pressure head, as in a fill-and-dump
abundance of craftsman available when building a refinery, procedure. Blow-down can be considered as flushing with a
but that same region may have difficulty, from a trained and gas.
experienced personnel perspective, in supporting the
construction of a semiconductor facility. Passivation: A process by which a chemical solution,
usually with a base of nitric, phosphoric, citric acid or other
Consequently when building a pharmaceutical facility in mild oxidant, is used to promote or accelerate the formation
another region you may find a sufficient population of of a thin (25 to 50 Angstroms) protective oxide layer (a
trained and experienced craftsman for that industry, but may passive layer) on the internal surface of pipe, fittings and
not find that resource adequate when building a chemical equipment. In stainless steels, the most commonly used alloy
plant. at present, it removes any free iron from the pipe surface to
form a chromium-rich oxide layer to protect the metal
Building a project in a remote location requires the surface from aggressive liquids such as high purity waters.
project team to rethink the job-as-usual methodology. From
a logistics standpoint mobilization of personnel and material Note: Cleaning and Flushing can be interchanged when the process
only requires water, air or an inert gas to meet the required level of
become a major factor in determining the overall execution
cleanliness. When the term “cleaning” is used in this context it may
of such a project. Project planning is a big component in infer what is defined as flushing.
project execution, but is more so when attempting to build in
Cleaning and Testing

6
One other thing I would like to mention before we go
With regard to cleaning and leak testing, and which to on. Since we are discussing new pipe installation we will not
do first, there are drivers for both and different schools of include steam-out cleaning or pipeline pigging. These are
thought on the overall process. Each contractor will have cleaning procedures that are used on in-service piping to
their preference. It is in the Owner’s best interest to clean the fluid service residue build-up from interior pipe
determine their preference or be at risk in just leaving it to walls after a period of use.
the contractor. In either case you should have a line of
thought on the process, if for no other reason than to be able Before subjecting the system to an internal test pressure
to understand what it is the contractor is proposing to do. the piping should first be walked down to make certain, as
mentioned earlier, that there are no missing or loose
At the very least, in advance of leak testing, perform components. The system is then flushed with water or air to
either a basic flush of a *test circuit, or perform an internal make sure that there are no obstacles in the piping. Over the
visual examination as the pipe is installed. A walk-down of years we have discovered in installed piping systems
the test circuit should be done just prior to filling the system everything from soda cans to shop towels, work gloves, nuts
with any liquid. The last thing you want to happen is to & bolts, weld rod, Styrofoam cups, candy wrappers, and
discover too late that a joint wasn’t fully connected or an in- other miscellaneous debris including dirt and rocks.
line component was taken out of the pipeline. In a facility
that is not a clean-build it can simply be a mess that has to After this initial flush, which could also be the only
be cleaned up. In a clean-build facility an incident such as flush and cleaning required, the system is ready for chemical
this can potentially be costly and time-consuming to cleaning or to leak test. In large systems it may be beneficial
remediate. to leak test smaller test circuits and then perform a final
cleaning once the entire system is installed and tested. This
Note: *refer to the following section on “Leak Testing” would include a final completed system leak test that would
test all of the joints that connect the test circuits. That is,
Before getting into further specifics of this discussion unless these joints were tested as the assembly progressed.
we need to define some general cleaning and testing
procedures and assign them some easy to use indicators. In If it is decided, on large systems, to leak test smaller
this way it will be much easier to discuss the various segments, or test circuits as they are installed, prior to
processes. We can then work through some general flushing the entire system, the piping needs to be examined
scenarios and see which sequencing works best. internally as it is installed. This is to prevent any large debris
items, as listed above, from remaining in the piping during
Following is a list of cleaning requirements: the test.

Table 3-2 – General Cleaning Scenarios Now that we have touched on those generalities let’s
Category Description take a look at each of the cleaning Categories listed in Table
C-1 Flush only (water, air or inert gas) 3-2 and see how to apply them.
C-2 Flush, clean with cleaning solution, flush Cleaning Category C-1 is simply a flush with water, air
C-3 Clean with cleaning solution, flush or inert gas. The one non-manual assist that water requires in
C-4 Flush, clean, passivate, flush order for it to clean the inside of a piping system is velocity.
But what velocity is necessary?
Following is a list of leak testing requirements:
The main concept behind flushing a pipeline is to
Table 3-3 – General Leak Testing Scenarios dislodge and remove suspected debris. In order to dislodge,
suspend and remove this unwanted material in the piping
Category Description
system it is necessary that water or air be forced through the
T-1 Initial service leak test piping system at a velocity sufficient to suspend the heaviest
T-2 Hydrostatic leak test suspected particles and move them along the pipeline.
T-3 Pneumatic leak test
T-4 Sensitive leak test The velocity required to suspend the particles and move
them along the pipeline for removal is dependent upon their
T-5 Alternative leak test
size and weight, and the flush medium. Metal filings,
arguably the heaviest particles normally found in newly
While the cleaning descriptions are self explanatory the fabricated pipe, will have a terminal mid-range settling
leak testing descriptions may not be. Please refer to the velocity, in water, of approximately 10 feet per second.
following section on “Leak Testing” to find clarification of Therefore, a flushing velocity of approximately 10 feet per
the terms used in Table 3-3. second should be achieved during the flush. (This does not
apply to acid cleaning.)

7
circulation of a cleaning solution, which is then followed by
The following Table 3-4 indicates the rate of flow a final flush of water.
required to achieve approximately 10 feet per second of
velocity through various sizes and schedules of pipe. Cleaning solutions are, in many cases, proprietary
detergent or acid-based solutions each blended for specific
Table 3-4 – Rate of Flushing Liquid Needed to Maintain uses. Detergent-based solutions are generally used for
Approximately 10 FPS Velocity (GPM) removing dirt, cutting oils and grease. Acid-based solutions
Pipe Pipe Sizes (inches) are used to remove the same contaminants as the detergent-
Sch. ½ ¾ 1 1½ 2 3 4
base plus weld discoloration and residue. The acid based
solution also passivates the pipe wall.
5s 12 20 34 77 123 272 460
40 10 16 27 64 105 230 397 As defined earlier, passivation provides a protective
80 7 13 22 55 92 ─ ─ oxide barrier against corrosion. The acids used in some
cleaning solutions for ferrous and copper materials leave
Purging a piping system clear of debris with air requires behind a passivated interior pipe surface as a result of the
a velocity of approximately 25 feet per second. The cleaning process. In utility water services such as tower
following Table 3-5 indicates the rate of air flow required to water, chilled water, etc., this barrier against corrosion is
achieve approximately 25 feet per second of velocity through maintained with corrosion inhibitors that are injected into
various sizes and schedules of pipe. the fluid stream on an ongoing basis.

Table 3-5 – Rate of Air Flow to Maintain Approx 25 FPS Velocity And keep in mind that when I talk about passivated
(SCFS) surfaces this is a natural occurrence with metals in an
Pipe Pipe Sizes (inches) oxygen environment. The acid merely initiates and speeds
Sch ½ ¾ 1 1½ 2 3 4
up the process.
Press 5s 0.14 0.23 0.39 0.86 1.39 3.06 5.17
When using stainless alloys, usually 316L, in hygienic
15 40 0.11 0.19 0.30 0.71 1.18 2.59 4.47 water services such as Water For Injection (WFI), Purified
psig
80 0.08 0.15 0.25 0.62 1.04 2.32 4.03 Water, Deionized (DI) Water and in some cases Soft Water,
Press 5s 0.30 0.51 0.84 1.88 3.02 6.67 11.3 passivation is a final intended step in the preparation for
50 40 0.23 0.41 0.66 1.56 2.56 5.65 9.73 service of these pipelines.
psig
80 0.18 0.33 0.55 1.35 2.26 5.05 8.79
Passivation is also a periodic ongoing preventative
maintenance procedure. To explain: High purity water is
One thing you might notice is that the size range only
very corrosive and attacks any free iron found on the surface
extends to 4” NPS for both the liquid flush and for the air or
of stainless pipe. Free iron has a tendency to come out of
gas blow-down. The reason for that is the volume of liquid
solution when material is cold worked, as in bending or
or gas required to achieve the necessary velocity through the
forming pipe without the benefit of heat. It also occurs with
larger pipe sizes is quite significant.
the threading of alloy bolts, which are solution annealed
(heat treated) after threading. Passivation removes this free
As an example a 6” NPS pipeline would require
iron while also accelerating, in the presence of O 2, the
approximately 900 to 1000 GPM, depending on wall
oxidation rate of the stainless steel providing a chromium
thickness of the pipe, to achieve a velocity of 10 FPS. This
rich oxide corrosion barrier as defined above.
gets a little cumbersome and costly. That is unless you have
pumps or compressors in place that can achieve the
Over time (and this is one hypothetical thought on the
necessary flow rate.
subject), this very thin corrosion barrier tends to get depleted
or worn off, particularly at high impingement areas of the
The alternative for liquid flushing the larger pipe sizes
piping system (elbows, tees, pump casings, etc.). Once the
other than using source line pressure or a pump is to perform
passive layer wears through any free iron exposed to the
a fill-and-dump. In this process the pipe system is
high purity water will oxidize, or rust. This will show up as
completely filled with liquid and then drained through a full
surface rouge.
line size, quick opening valve.
Rouging is an unwanted surface discoloration which is
In doing this there has to be enough static head to
periodically removed by means of a derouging process. This
generate sufficient force and velocity to achieve essentially
is an operational, as-needed chemical cleaning process that
the same result as the pumped or line pressure liquid.
will remove all or most of the rouge and also re-passivate the
internal pipe surface.
Cleaning Category C-2 is a three-step process by which
the piping system is initially flushed out with a liquid to
remove most of the loose debris. This is followed by the

8
Discussions and research on the topic of rouging 2. A form to record components that were either
continues. This is a subject that has more questions than installed or removed prior to testing;
answers at the present time. Currently the ASME-BPE is 3. A checklist form for field supervision to ensure
looking into this issue. One of the questions to be answered that each step of the test process is
is whether or not rouge is actually detrimental to product accomplished; and
streams. 4. Leak test data forms

Cleaning Category C-3 is a two-step cleaning process The two sets of documents, from those listed above, that
that uses a detergent or acid based solution to clean the pipe need to be retained are the P&ID’s (#1) and the Leak Test
interior of any unwanted residue or debris. This is then Data Forms (#4). The other two sets of forms are procedural
followed by a final flush of water. checklists.

Cleaning Category C-4 is a three or four-step process The Leak Test Data forms should contain key data such
generally used in hygienic service piping. In most cases, as:
simply due to the clean fabrication approach used in 1. Test circuit number
hygienic pipe fabrication, only a water flush with Deionized 2. P&ID number(s)
(DI) quality water or better would be necessary for cleaning 3. Date of test
followed by passivation of the piping system, then a final 4. Project name and/or number
flush of water. 5. Location within facility
6. Line number(s)
There are variations to each of these primary cleaning 7. Design pressure
functions and it would be in an Owner’s best interest to 8. Test pressure
define these requirements, by fluid service, in advance of the 9. Test fluid
work to be done. 10. Test fluid temperature
11. Time (military) recorded test begins
LEAK TESTING 12. Pressure at start of test
13. Time (military) recorded test ends
Pressure testing is a misnomer that is quite often used 14. Pressure at end of test
when referring to leak testing of piping systems. And as long 15. Total elapsed time of test
as all parties understand what is meant by that, then that’s 16. Total pressure differential (plus or minus) from
fine. However, in a true sense a pressure test is a test you beginning to end of test period
perform on a relief valve to test its set point pressure. The 17. Comment section (indicate if leaks were found and
intent, when pressure testing a relief valve, is not to check system was repaired and retested or if system
for leaks, but to test the pressure set point of the valve by passed)
gradually adding pressure to the relief valve until it lifts the 18. Signatures & dates
valve off of the seat.
Also make certain that the testing contractor has current
A leak test, on the other hand, is performed to check the calibration logs of their test instruments, such as pressure
sealing integrity of a piping system by applying internal gages.
pressure to a pre-determined limit, based on design
conditions, then checking joints and component seals for To continue with the leak testing, ASME B31.3 defines
leaks. It is not intended that the MAWP of a piping system five primary leak tests as follows:
be verified or validated.
Initial Service Leak Test: This applies only to those
Before discussing the various types of leak tests and fluid services meeting the criteria as defined under ASME
leak test procedures I would like to briefly talk about B31.3 Category D fluid service. This includes fluids in
controlling and tracking this activity. which the following apply:
(1) the fluid handled is nonflammable, nontoxic,
Cleaning and testing, like many aspects of a project, and not damaging to human tissue;
should be a controlled process. Meaning, there should be a (2) the design gage pressure does not exceed 1035
formal method of documenting and tracking this activity as kPA (150 psi); and
the Contractor proceeds through the leak testing process.. (3) the design temperature is from -29°C (-20°F)
through 186°C (366°F).
In documenting the leak testing activity there are certain
forms that will be needed. They consist of the following: The Initial Service leak test is a process by which the
test fluid is the fluid that is to be used in the intended piping
1. A dedicated set of P&ID’s to identify the limits system at operating pressure and temperature. It is
and number the test circuits; accomplished by connecting to the fluid source with a

9
valved connection and then gradually opening the source energy in the pressurized gas. And for that reason alone it
valve and filling the system. In liquid systems air is purged should be used very selectively.
during the fill cycle through high point vents. A rolling
examination of all joints is continually performed during the When pneumatic testing is performed it must be done
fill cycle and for a period of time after the system is under a strictly controlled procedure with on-site supervision
completely filled and is under line pressure. in addition to coordination with all other crafts and
personnel in the test area.
In a situation in which the distribution of the pipeline
that is being tested has distribution on multiple floors of a PT 1.1P (eq. 3)
facility there will be pressure differentials between the floors
due to static head differences. This will occur in operation
and is acceptable under initial service test conditions. PT 1.4 P (eq. 4)

The test pressure achieved for initial service testing


pressure is what it is. Meaning that what you achieve in the PT 1.2Pto1.5P (eq. 5)
test is what it will be in operation. The only difference is that
the flowing fluid during operation will incur an amount of The test pressure for pneumatic leak testing under B31.3
pressure drop that will not be present during the static test. is calculated using eq. 3, for B31.9 it is calculated using eq.
4, and for B31.1 it is calculated using eq. 5.
Hydrostatic leak test: This is the most commonly used
leak test and is performed by using a liquid, normally water, One misconception I need to address here with
and in some cases with additives to prevent freezing, under a pneumatic leak testing is in its procedure, as described in
calculated pressure. B1.3. There is a misconception that the test pressure should
be maintained while the joints are examined. This is not
1.5PST correct. As B31.3 explains, pressure is increased gradually
PT (eq. 1) until the test pressure is reached. At that point the test
S pressure is held until piping strains equalize throughout the
system. (eq. 1.1)
Where:
PT = Test Pressure, psi After allowing a sufficient amount of time for piping
P = Internal design gage pressure, psig strains to equalize the pressure is then reduced to the design
ST = Stress value at test temperature, psi (see B31.3 Table A-1) pressure (refer to article II for design pressure). While
S = Stress value at design temperature, psi (see B31.3 Table A-1 holding design pressure all joints are examined for leaks. It
is not required that the examination take place while holding
test pressure.
Eq. 1 represents the equation for that calculated
pressure. However, as long as the metal temperature of ST There is more to the entire procedure that I did not
remains below the temperature at which the allowable stress include here. Please refer to B31.3 or B31.1 for full details
value for ST begins to diminish and the allowable stress on pneumatic leak testing.
value of S and ST are equal then ST and S cancel each other
leaving the simpler eq. 2: Sensitive leak test: This leak test is performed when
there is a higher than normal potential for fluid leakage, such
(eq. 2) as for hydrogen. I also recommend its use when a fluid is
PT 1.5P classified as a Category M fluid service. B31.1 refers to this
test as Mass-Spectrometer and Halide Testing.
Unlike initial service testing, pressure variations due to
static head differences in elevation have to be In B31.3 the process for sensitive leak testing is as
accommodated in hydrostatic testing. What I mean by that is follows:
the calculated test pressure is the minimum pressure required
for the system. When hydrostatically testing a multi-floor The test shall be in accordance with the gas and bubble
system the minimum calculated test pressure shall be test method specified in the BPV Code, Section V, Article 10,
realized at the highest point. This is not stated, but is inferred or by another method demonstrated to have equal sensitivity.
in B31.3. Sensitivity of the test shall be not less than 10 -3 atm-ml/sec
under test conditions.
Pneumatic leak test: This test is performed using air or a
preferred inert gas. This is a relatively easy test to perform (a) The test pressure shall be at least the lesser of
simply from a preparation and cleanup standpoint. However, 105kPa (15 psi) gage, or 25% [of] the design pressure.
this test has a hazardous potential because of the stored

10
(b) The pressure shall be gradually increased until a intermediate restraints, and falls within the limitations of
gage pressure the lesser of one-half the test pressure or 170 empirical equation (eq. 6).
kPa (25 psi) gage is attained, at which time a preliminary
check shall be made. Then the pressure shall be gradually Dy (eq. 6)
K1
increased in steps until the test pressure is reached, the (L U )2
pressure being held long enough at each step to equalize
piping strains. Where:
D = outside diameter of pipe. in. (mm)
In testing fluid services that are extremely difficult to y = resultant of total displacement strains to be
seal against, or fluid services classified as a Category M absorbed by piping system, in. (mm)
fluid service I would suggest the following in preparation for L = developed length of piping between anchors, in.
the process described under B31.3: prior to performing the (mm)
sensitive leak test perform a low pressure (15 psig) test with U = anchor distance, straight line between anchors,
air or an inert gas using the bubble test method. Check every ft. (m)
mechanical joint for leakage. K1 = 208,000 SA/Ea, (mm/m)2
= 30 SA/Ea, (in./ft.)2
After completing the preliminary low pressure SA = allowable displacement stress range per
pneumatic test, purge all of the gas from the system using equation (1a) of ASME B31.3, ksi (MPa)
helium. Once the system is thoroughly purged, and contains Ea = reference modulus of elasticity at 70°F
no less than 98% helium, continue using helium to perform (21°C), ksi (MPa)
the sensitive leak test with a helium mass spectrometer.
One example in which an alternative leak test might be
Helium is the trace gas used in this process and has a used is in making a branch tie-in to an existing, in-service
molecule that is close to the size of the hydrogen molecule line using a saddle with an o-let branch fitting with a weld
making it nearly as difficult to seal against as hydrogen neck flange welded to that and a valve mounted to the
without the volatility. Test each mechanical joint using the flange. Within temperature limitations, the fillet weld used
mass-spectrometer to determine leak rate, if any. to weld the saddle to the existing pipe can be examined
using the dye penetrant or magnetic particle method. The
Alternative leak test: In lieu of performing an actual circumferential butt or groove weld used in welding the weld
leak test, in which internal pressure is used, the alternative neck and the o-let fitting together should be radiographically
leak test takes the examination and flexibility analysis or ultrasonically examined. And the flange joint connecting
approach. the valve should have the torque of each bolt checked after
visually ensuring correct type and placement of the gasket.
This test is conducted only when it is determined that
hydrostatic or pneumatic testing would be detrimental to the There are circumstances, regarding the tie-in scenario
piping system and/or the fluid intended for the piping we just discussed for alternative leak testing, in which a
system, an inherent risk to personnel, or impractical to hydrostatic or pneumatic test can be used. It depends on
achieve. what the fluid service is in the existing pipeline. If it is a
fluid service that can be considered a Category D fluid
As an alternative to testing with internal pressure it is service then it is quite possible that a hydrostatic or
acceptable to qualify a system through examination and pneumatic leak test can be performed on the described tie-in.
flexibility analysis. The process calls for the examination of
all groove welds, and includes longitudinal welds used in the By capping the valve with a blind flange modified to
manufacture of pipe and fittings that have not been include a test rig of valves, nipples and hose connectors, you
previously tested hydrostatically or pneumatically. It can perform a leak test rather than an alternative leak test.
requires a 100% radiograph or ultrasonic examination of As mentioned this does depend on the existing service fluid.
those welds. Where applicable, the sensitive leak test shall If the existing fluid service is steam or a cryogenic fluid then
be used on any untested mechanical joints. This Alternative you might want to consider the alternative leak test.
leak test also requires a flexibility analysis as applicable.
Cleaning and Leak Testing Procedures
Very briefly, a flexibility analysis verifies, on a
theoretical basis, that an installed piping system is within the As you can see by equations eq. 1 through eq. 5 above,
allowable stress range of the material and components under the leak test pressure, except for initial service testing, is
design conditions if a system: (a) duplicates or replaces based on design pressure and design temperature. In Article
without significant change, a system operating with a 2 we described design pressure and temperature. What we
successful service record; (b) can be judged adequate by will do here is apply that understanding and describe a few
comparison with previously analyzed systems; and (c) is of general procedures for cleaning and testing.
uniform size, has no more than two points of fixation, no

11
As in all other project functions control and prepared for your contractor. If not you may not get what
documentation is a key element in the cleaning and testing you expect. It’s better to give some forethought to these
of piping systems. It does, however, need to be handled in a activities rather than be surprised at the results.
manner that is dictated by the type of project. Meaning that
you don’t want to bury yourself in unwarranted paperwork Once a menu of these cleaning and testing procedures
and place an unneeded burden on the contractor when it isn’t are developed, using pre-assigned symbols, much as those
necessary. given in the following, they can then be specified in the line
list with the respective fluid services as you require. In this
Building a commercial or institutional type facility will manner there is no second guessing during construction.
not require the same level of documentation and stringent Each piping circuit is assigned a specific clean and test
controls that an industrial type facility would require. But protocol in advance.
even within the industrial sector there are varying degrees of
required testing and documentation. Many pre-developed procedures I have seen over the
years, those developed by Owners in particular, have been
To begin with, documentation requirements in industry very simplistic, and typically out of date. This is an indicator
standards are simplistic and somewhat generalized, as is to most contractors that the Owners Rep will most likely not
apparent in ASME B31.3, which states in Para. 345.2.7: attempt to enforce them. The contractor, in making that
assumption, may simply ignore them and perform their own
Records shall be made of each piping system during the procedures.
testing, including:
(a) date of test What your procedural guidelines should do is be explicit
(b) identification of piping system tested enough and current to the point where the contractors know
(c) test fluid that someone has given some thought as to how they want
(d) test pressure that work accomplished. Making it far more likely they (the
(e) certification of results by examiner contractors) will execute your procedure instead of their’s.

These records need not be retained after completion of It is certainly acceptable to accommodate suggestions to
the test if a certification by the inspector that the piping has a procedure from a contractor when it doesn’t compromise
satisfactorily passed pressure testing as required by this the intent of the Owner’s requirements and improves the
Code is retained. efficiency of the contractor. If a submitted alternate
procedure does not compromise the intent of the Owner it is
ASME B31.3 goes on to state, in Para. 346.3: recommended that they be accepted. This will allow the
Owner to see if that efficiency is really there. With that in
Unless otherwise specified by the engineering design, mind let’s create a couple of general cleaning procedures.
the following records shall be retained for at least 5 years
after the record is generated for the project: A general practice in the flushing and cleaning process,
(a) examination procedures; and also indicated in leak testing, is the evacuation of air when
(b) examination personnel qualifications. using liquids. Always provide high point vents for
evacuating air during the fill cycle and low point drains for
Standards, that cover such a broad array of industrial clearing out all of the liquid when the process is complete.
manufacturing, do not, as a rule, attempt to get too specific
in some of their requirements. Beyond the essential Using the same symbology indicated in Table 3-2 these
requirements, such as those indicated above, the Owner, cleaning procedures will be categorized as follows:
engineer or contractor has to assume responsibility and
know-how for providing more specific and proprietary Category C-1: Flush or Blow Down only (water, air or inert
requirements for a particular project specific to the particular gas)
needs of the Owner. The following will help, to some extent,
fill that gap. C-1.1 These systems shall be flushed with the fluid that the
system is intended for. There shall be no hydrostatic
Cleaning Procedures or pneumatic leak test. An Initial Service leak test will
be performed. Refer to test Category T-1.
This section will describe some fundamental cleaning
procedures as they might appear in a specification or a. Connect system to its permanent supply line.
guideline, and this includes the leak test procedures that Include a permanent block valve at the supply line
follow. This will give you some idea as to what you might connection. All outlets shall have temporary hoses
consider developing for your own set of specifications. run to drain. Do not flush through coils, plates,
Assuming that if your company repeatedly executes projects strainer or filter elements.
you will have cleaning and testing guidelines, in some form,

12
b. Using supply line pressure, flush system through all If no debris is found the system is ready for leak
outlets until water is clear and free of any debris at testing.
all outlet points. Flush a quantity of fluid through
each branch not less than three times that contained Category C2: Flush then clean with cleaning solution,
in the system. Use Table 3-6 to estimate volume of followed by a neutralization rinse. Because of the
liquid in the system. thoroughness of the flush, clean and rinse process there
should be no need to check for transient debris, only for
c. These systems are required only to undergo an neutralization. However, if circumstances dictate otherwise
Initial Service leak test. During the flushing then a final check for debris may be warranted.
procedure, and as the system is placed into service,
all joints shall be checked for leaks. C-2.1 These systems shall be pre-flushed with potable water,
cleaned with (indicate cleaning agent) then a
d. Any leaks discovered during the flushing process, rinse/neutralization followed by leak testing with
or during the process of placing the system into potable water. If it is determined that the system will
service, will require the system to be drained and be installed and tested progressively in segments, the
repaired. After which the process will start over sequence of cleaning and testing can be altered to
with step 2. follow the segmented installation. Thereby leak

Table 3-6 – Volume of Water Per Lineal Foot of Pipe (gal.)


Pipe Sizes (inches)
Sch. 1/2 3/4 1 11/2 2 3 4 6 8 10 12 14 16 18 20 24
5s .021 .035 .058 .129 .207 .455 .771 1.68 ─ ─ ─ ─ ─ ─ ─ ─
20 ─ ─ ─ ─ ─ ─ ─ ─ 2.71 4.31 6.16 7.34 9.70 12.4 15.2 22.2
40 .016 .028 .045 .106 .176 .386 .664 1.51 2.61 4.11 5.84 9.22 9.22 14.5 14.5 ─
80 .012 .023 .037 .093 .154 .345 .60 1.36 ─ ─ ─ ─ ─ ─ ─ ─

testing segments of a piping system as they are


C-1.2 These systems shall be flushed clean with Potable installed without cleaning. The entire system would
Water. then cleaned once installed and tested.

a. Connect a flush/test manifold at a designated inlet a. Hook up flush/test manifold at a designated


to the system, and a temporary hose or pipe on the temporary inlet to the system between the
designated outlet(s) of the system. circulating pump discharge and the system inlet.
Install a temporary hose or pipe on the designated
b. Route temporary hose or pipe from potable water outlet(s) of the system.
supply, approved by Owner, and connect to
flush/test manifold. Route outlet hose or pipe to b. Route temporary hose or pipe from potable water
sewer, or as directed by Owner rep. Secure end of supply, approved by Owner, and connect to
outlet. flush/test manifold. Route outlet hose or pipe to
sewer, or as directed by Owner’s Rep.
c. Using a Once through procedure (not a re-
circulation), and the rate of flow in Table 3-4, c. Close valve between the circulating pump (if no
perform an initial flush through the system with a valve included in the system design insert a line-
quantity of potable water not less than three times blind or install a blind flange with a drain valve)
that contained in the system. Use Table 3-6 to discharge and flush/test rig. Open valve between
estimate volume of liquid in the system. Discharge flush/test manifold and piping system.
to sewer, or as directed by Owner rep.
d. Using the once through procedure (meaning the
d. After the initial flush, insert a conical strainer into cleaning fluid is not re-circulated), and the rate of
a spool piece located between the discharge of the flow in Table 3-4, perform an initial flush through
piping system and the outlet hose. Perform a second the system, by-passing the circulation pump, with a
flush with a volume of potable water not less than quantity of potable water equal to not less than three
that contained in the system. times that contained in the system. Use Table 3-6 to
estimate volume of liquid in the system.
e. After the second flush (step 4), pull the strainer (Note: During the water flush check the system for
and check for debris; if debris is found repeat step 3. leaks. Verify no leaks prior to introducing chemical
cleaning solution to the piping system.)

13
procedures that will suit your company’s own particular
e. Discharge to sewer, or as directed by Owner’s needs.
Rep.
In Article 1 I stated the B31.3 definition for Category D
f. After completing the initial flush, drain remaining fluid services. I then indicated that while Category D fluid
water in the system. Or, retain water if cleaning services qualified for initial service leak testing there are
chemicals will be added to the circulating water. caveats that should be considered.

g. Configure valves and hoses to circulate through Again, this is a situation in which ASME provides
pump. Connect head tank, or other source some flexibility in testing by lowering the bar on
containing cleaning agent, to connection provided requirements where there is reduced risk in failure.
on circulation loop. Provided, that if failure should occur the results would not
cause catastrophic damage to property or irreparable harm to
h. Fill the system with the pre-measured (indicate personnel.
preferred cleaning agent and mixing ratio or % by
volume) and circulate through the system for 48 The Owner’s responsibility, for any fluid service
hours. To minimize corrosion, if anticipated, selected for initial service leak testing lies in determining
circulate cleaning agent at a low velocity rate what fluid services to place into each of the fluid service
prescribed by the cleaning agent manufacturer. Categories. Those Categories being: Normal, Category D,
Category M, and High Pressure.
i. Drain cleaning agent to sewer or containment, as
directed by Owner. Acids, caustics, volatile chemicals and petroleum
products are usually easy to identify as those not qualifying
j. Reconnect as in step #1 for the once through as a Category D fluid service. Cooling tower water, chilled
flush/neutralization, and flush system with potable water, air, and nitrogen are all easy to identify as qualifyiers
water using a quantity not less than three times that for Category D fluid services. The fluid services that fall
of the system volume. Since the (name cleaning within the acceptable Category D guidelines, but still have
agent) solution has a neutral pH the rinse water will the potential for being hazardous to personnel are not so
have to be visually examined for clarity. Rinse until straight forward.
clear. The rinse must be started in as short as
quickly after the cleaning cycle as possible. If Using water as an example, at ambient conditions water
cleaning residue is allowed to dry on the interior will simply make you wet if you get dripped or sprayed on.
pipe wall, it will be more difficult to remove by Once the temperature of water exceeds 140°F (60°C), by
simply flushing. The final rinse and neutralization OSHA standards, it starts to become detrimental to
must be accomplished before any possible residue personnel upon contact. At this point the range of human
has time to dry. tolerance becomes a factor. However, as the temperature
continues to elevate it eventually moves into a range that
k. Test pH for neutralization. Once neutralization is increasing becomes scalding upon human contact and human
achieved proceed to step #12. tolerance is no longer a factor because it is now hazardous
and the decision is made for you.
l. Remove pump and temporary circulation loop
then configure the system for leak testing. This may Before continuing I need to be clear on the above
include removal of some components, insertion of subject matter. The 140ºF temperature mentioned above is
line-blinds, installation of temporary spools pieces, with respect to simply coming in contact with an object at
etc. that temperature. Brief contact at that temperature would
not be detrimental. In various litigation related to scalding it
Those three examples should provide an idea as to the has been determined that an approximate one-second
kind of dialog that needs to be created in providing guidance exposure to 160°F water will result in third degree burns.
and direction to the contractor responsible for the work. An approximate half-minute exposure to 130°F water will
And, as I stated earlier, these procedures, for the most part, result in third degree burns. And an approximate ten minute
are flexible enough to accommodate suggested exposure to 120°F water can result in third degree burns.
modifications from the contractor.
With the maximum temperature limit of 366°F
Leak Test Procedures (185.5°C) for Category D fluid services what the Owner
needs to consider here are three factors: within that range of
As in the cleaning procedures we will keep this general, 140°F (60°C), the temperature at which discomfort begins to
but provide enough specifics for you to develop leak testing set in, to 366°F (185.5°C), the upper limit of Category D
fluids, what do we consider hazardous; what is the level of

14
opportunity for risk to personnel; and what is the level of considered a normal fluid, as defined in B31.3, pending its
assured integrity of the installation. location as listed in Table 3-7.

What I mean by assured integrity is this: if there are Table 3-7 – Areas Under Consideration For Cat. D
procedures and protocols in place that require, validate and Group Description Yes No
document third-party inspection of all pipe fabrication,
installation and testing, then there is a high degree of assured
1 Personnel Occupied Space √
2 Corridor Frequented by
integrity in the system. If some or all of these requirements
Personnel √
are not in place then there is no assured integrity.
3 Sensitive Equipment (MCC,
Control Room, etc.) √
All three of these factors: temperature, risk of contact,
4 Corridor Infrequently Used by
and assured integrity, have to be considered together to
Personnel √
arrive at a reasonable determination for borderline Category
5 Maintenance & Operations
D fluid services. If, for instance, a fluid service is hot
Personnel Only Access √
enough to be considered hazardous, but is in an area of a
facility that sees very little personnel activity then the fluid
service could still be considered as a Category D fluid As an example, if you have a fluid that is operating at
service. 195°F (90.6°C) it would be considered hazardous in this
evaluation. But, if the system is located in a Group 5 area
One factor I have not included here is the degree of (ref. Table 3-7) it could still qualify as a Category D fluid
relative importance of a fluid service, or in other words, if a service.
system failed how big of a disruption would it cause in plant
operation, and how does that factor into this process. After the above exercise in evaluating a fluid service we
can now continue with a few examples of leak test
As an example, if a safety shower water system has to procedures. Using the same symbology indicated in Table 3-
be shut down for leak repair the down-time to make the 3 these leak test procedures will be categorized as follows:
repairs has little impact on plant operations. This system
would therefore be of relative low importance and not a Category T-1: Initial Service Leak Test
factor in this evaluation process.
T-1.1 This Category covers liquid piping systems
If on the other hand a chilled water system has to be categorized by ASME B31.3 as Category D Fluid
shut down for leak repair to a main header, this could have a service and will require Initial Service Leak Testing
significant impact to operations and production. This could only.
translate into lost production and could be considered a high
degree of importance. 1. If the system is not placed into service or tested
immediately after flushing and cleaning, and has set
You could also extend this logic a bit further by idle for an unspecified period of time it shall require
assigning normal fluid service status to the primary headers a preliminary pneumatic test at the discretion of the
of a chilled water system and assigning Category D status to Owner. In doing so, air shall be supplied to the
the secondary distribution branches then leak test system to a pressure of 10 psig and held there for 15
accordingly. You need to be cautious in considering this. By minutes to ensure that joints and components have
applying different Category significance to the same piping not been tampered with, and that the system is still
system it could cause more confusion than it is worth. In intact. After this preliminary pressure check
other words it may be more value added to simply default to proceed.
the more conservative Category of Normal.
2. After completion of the flushing and cleaning
Continuing; if we can consider that there is a high process, connect the system, if not already
assured integrity value for these piping systems there are two connected, to its permanent supply source and to all
remaining factors to be considered. The first would be: of its terminal points. Open the block valve at the
within the above indicated temperature range at what supply line and gradually feed the liquid into the
temperature should a fluid be considered hazardous; and system.
secondly, how probable is it that personnel could be in the
vicinity of a leak, should one occur. 3. Start and stop the fill process to allow proper high
point venting to be accomplished. Hold pressure to
For our purpose here let us determine that any fluid its minimum until the system is completely filled
160°F (71°C) and above is hazardous upon contact with and vented.
human skin. If the fluid you are considering is within this
temperature range then it has the potential of being 4. Once it is determined that the system has been filled
and vented properly, gradually increase pressure

15
until 50% of operating pressure is reached. Hold 1. If the system is not placed into service or tested
that pressure for approximately 2 minutes to allow immediately after flushing and cleaning, and has set
piping strains to equalize. Continue to supply the idle for an unspecified period of time it shall require
system gradually until full operating pressure is a preliminary pneumatic test at the discretion of the
achieved. Owner. In doing so, air shall be supplied to the
system to a pressure of 10 psig and held there for 15
5. During the process of filling the system, check all minutes to ensure that joints and components have
joints for leaks. Should leaks be found at any time not been tampered with, and that the system is still
during this process drain the system, repair leak(s) intact. After this preliminary pressure check
and begin again with step 1. (Caveat: Should the proceed.
leak be no more than a drip every minute or two on
average at a flange joint, it could require simply 2. After completion of the flushing and cleaning
checking the torque on the bolts without draining process, with the flush/test manifold still in place
the entire system. If someone forgot to fully tighten and the temporary potable water supply still
the bolts then do so now. If it happens to be a connected (reconnect if necessary), open the block
threaded joint you may still need to drain the valve at the supply line and complete filling the
system, disassemble the joint, clean the threads, add system with potable water.
new sealant and reconnect the joint before
continuing.) 3. Start and stop the fill process to allow proper high
point venting to be accomplished. Hold pressure to
6. Record test results and fill in all required fields on its minimum until the system is completely filled
the leak test form. and vented.

T-1.2.This Category covers pneumatic piping systems 4. Once it is determined that the system has been filled
categorized by ASME B31.3 as Category D Fluid and vented properly, gradually increase pressure
service and will require Initial Service Leak Testing. until 50% of the test pressure is reached. Hold that
pressure for approximately 2 minutes to allow
1. After completion of the blow-down process, the piping strains to equalize. Continue to supply the
system shall be connected to its permanent supply system gradually until test pressure is achieved.
source, if not already done so, and to all of its
terminal points. Open the block-valve at the supply 5. During the process of filling the system, and
line and gradually feed the gas into the system. increasing pressure to 50% of the test pressure,
check all joints for leaks. Should any leaks be found
2. Increase the pressure to a point equal to the lesser of drain system, repair leak(s) and begin again with
one-half the operating pressure or 25 psig. Make a step 1.
preliminary check of all joints by sound or bubble
test. If leaks are found release pressure, repair 6. Once the test pressure has been achieved, hold it for
leak(s) and begin again with step 1. If no leaks are a minimum of 30 minutes or until all joints have
identified continue to step 3. been checked for leaks. This includes valve and
equipment seals and packing.
3. Continue to increase pressure in 25 psi increments,
holding that pressure momentarily (approximately 2 7. If leaks are found evacuate system as required,
minutes) after each increase to allow piping strains repair and repeat from step 2. If no leaks are found,
to equalize, until the operating pressure is reached. evacuate system and replace all items temporarily
removed.
4. Check for leaks by sound and/or bubble test. If leaks
are found release pressure, repair leak(s) and begin 8. Record all data and activities on leak test forms.
again with step 2. If no leaks are found the system is
ready for service. Those three examples should provide an idea as to the
kind of guideline that needs to be created in providing
5. Record test results and fill in all required fields on direction to the contractor responsible for the work.
the leak test form.
For leak testing to be successful on your project, careful
Category T-3.1: Hydrostatic Leak Test preparation is key. This preparation starts with gathering
information on test pressures, test fluids, and the types of
T-3.1.This Category covers liquid piping systems tests that will be required. The most convenient place for this
categorized by ASME B31.3 as Normal Fluid service. information to reside is the piping line list or piping system
list.

16
Manufacturing Practice (cGMP) and FDA requirements.
A piping line list and piping system list achieve the These CFR Titles and FDA requirements drove the need to
same purpose only to different degrees of detail. On some demonstrate or prove compliance.
projects it may be more practical to compile the information
by entire service fluid systems. Other projects may require a These requirements can cover everything from
more detailed approach by listing each to and from line verification of examination and inspection, documentation of
along with the particular data for each line. materials used, software functionality and repeatability to
welder qualification, welding machine qualification, etc.
The line list itself is an excellent control document that
might include the following for each line item: The cGMP requirements under 29CFR Titles 210 & 211
are a vague predecessor of what validation has become, and
1. Line size continues to become. From these basic governmental
2. Fluid outlines companies, and the pharmaceutical industry as a
3. Nominal material of construction whole, have increasingly provided improved interpretation
4. Pipe Spec of these guidelines to meet many industry imposed, as well
5. Insulation spec as self-imposed requirements.
6. P&ID
7. Line sequence number To a lesser extent, industrial projects outside the
8. from and to information pharmaceutical, food & drug, and semi-conductor industries,
9. Pipe code industries not prone to require such in-depth scrutiny, could
10. Fluid Service Category benefit from adopting some of the essential elements of
11. Heat Tracing validation. Elements such as: material verification, leak test
12. Operating Pressure records, welder and welding operator qualification records,
13. Design Pressure etc.
14. Operating Temperature
15. Design Temperature At face value this exercise would provide an assurance
16. Type of Cleaning that the fabricating/installing contractor is fulfilling their
17. Test Pressure contractual obligation. The added benefit is that in knowing
18. Test Fluid that this degree of scrutiny will take place the contractor will
19. Type of Test themselves take extra pain to minimize the possibility of any
rejects.
Developing this type of information on a single form
provides everyone involved with the basic information And I am not inferring that all contractors are out to get
needed for each line. Having access to this line-by-line by with as little as they can. Just the opposite is actually true.
information in such a concise well organized manner Most contractors qualified to perform at this level of work
reduces guess-work and errors during testing. are in it to perform well and to meet their obligations. Most
will already have their own verification procedure in place.
Test results, documented on the test data forms, will be
maintained under separate cover. Together the line list The bottom line is that the Owner is still responsible for
provides the required information on each line or system and the end result. No one wants to head for the litigation table at
the test data forms provide signed verification of the actual the end of a project. And the best way to avoid that is for the
test data of the test circuits that make up each line or system. Owner to be proactive in developing their requirements prior
to initiating a project. This allows the spec writers and
VALIDATION reviewers the benefit of having time to consider just what
those requirements are and how they should be defined
The process of Validation has been around for longer without the time pressures imposed when this activity is
than the 40 plus years I have been in this business. You may project driven.
know it by its less formal namesakes walk-down and
checkout. Compared to validation, walk-down and checkout Performing this kind of activity while in the heat of a
procedures are not nearly as complex, stringent, or all project schedule tends to force quick agreement to
inclusive. specifications and requirements written by parties other than
those with the Owner’s best interest at heart.
Validation is actually a subset activity under the
umbrella of Commissioning and Qualification (C&Q). It is Validating a piping system to ensure compliance and
derived from the need to authenticate and document acceptability is always beneficial and money well spent.
specifically defined requirements for a project and stems
indirectly from, and in response to, the Code of Federal Wrapping Up
Regulation 29CFR Titles 210 and 211 current Good

17
Before closing out this last of three articles there are just I hope that in writing these articles I piqued enough
a couple of things I would like to touch on. We had interest that some of you will dig deeper into this subject
discussed industry Standards earlier and how they are matter to discover and learn some of the more finite points
selected and applied on a project. What I didn’t cover is the of what we discussed here. I also hope these articles
fact that most projects will actually have a need to comply provided enough basic knowledge of piping for you to
with multiple industry Standards. recognize when there is more to a piping issue than what you
are being told.
In a large grass-roots pharmaceutical project you may
need to include industry compliance Standards for much of Acknowledgement:
the underground utility piping, ASME B31.1 for boiler
external piping (if not included with packaged boilers), My deep appreciation again goes to Earl Lamson, senior
ASME B31.3 for chemical and utility piping throughout the Project Manager with Eli Lilly and Company, for taking the
facility, and ASME-BPE for any hygienic piping time to review each of these three articles. His comments
requirements. help make this article, and the others, better documents than
they otherwise would have been. He obliged me by applying
These and other Standards, thanks in large part to the the same skill, intelligence and insight he brings to
cooperation of the standards developers and ANSI, work everything he does. His comments kept me concise and on
hand-in-hand with one another by referencing each other target.
where necessary. These Standards committees have enough
work to do within their defined scope of work without About the author:
inadvertently duplicating work done by other Standards
organizations. W. M. (Bill) Huitt has been
involved in industrial piping
An integrated set of American National Standards is the design, engineering and
reason that, when used appropriately, these Standards can be construction since 1965.
used as needed on a project without fear of conflict between Positions have included design
those Standards. engineer, piping design
instructor, project engineer,
One thing that should be understood with industry project supervisor, piping
Standards is the fact that they will always be in a state of department supervisor,
flux; always changing. And this is a good thing. These are engineering manager and
changes that reflect updating to a new understanding, president of W. M. Huitt Co. a
expanded clarification on the various sections that make up a piping consulting firm founded
Standard, staying abreast of technology, and simply building in 1987. His experience covers both the engineering and
the knowledge base of the Standard. construction fields and crosses industrial lines to include
petroleum refining, chemical, petrochemical,
As an example, two new Parts are being added to the pharmaceutical, pulp & paper, nuclear power, biofuel, and
seven Parts currently existing in ASME-BPE. There will be coal gasification. He has written numerous specifications,
a Metallic Materials of Construction Part MMOC, and a guidelines, papers, and magazine articles on the topic of pipe
Certification Part CR. This is all part of the ever-evolving design and engineering. Bill is a member of ISPE
understanding of the needs of the industrial community and (International Society of Pharmaceutical Engineers), CSI
improved clarification, through discussion and debate on (Construction Specifications Institute) and ASME
content. (American Society of Mechanical Engineers). He is a
member of three ASME-BPE subcommittees, several Task
Writing these articles was a form of informational triage Groups, an API Task Group, and sets on two corporate
for me. There were definite piping topics I wanted to include specification review boards. He can be reached at:
and others I would have preferred to include, but could leave W. M. Huitt Co.
out without too much of an impact. And then there were the P O Box 31154
extended discussions on some topics that ultimately had to St. Louis, MO 63131-0154
be sacrificed. This is why some topics were briefer than I (314)966-8919
would have liked. wmhuitt@aol.com
www.wmhuitt.com
My attempt at covering such a wide range of discussion
on industrial piping was to provide a basic broad
understanding of some key points on this topic, not, as I said
earlier, to go into great detail on any specific topic.

18

You might also like