MISSION – HOT LP SEPARATOR DRUM- Tag 201-V-04

Scheduling of Job
Serial Description (Activities ) Scheduled Remark
Number Dates
1. NDE of Welds After PWHT – UT/Hardness 28/12/2018 Completed- UT
Balance
2. Blanking of Nozzles 28/12/2018 Completed
3. Water Fill up of Hydrotest 28/12/2018 Completed

4. LPT after PWHT 29/12/2018 Completed


5. Hydrotest Pressure Test 29/12/2018 Completed

6. Draining and drying of Equipment 29/12/2018 In process

7. Blasting/Primer (1st Coat) 30/12/2018 Completed

8. Primer (2nd Coat) 31/12/2018 Completed

9. LPT test after Hydrotest 31/12/2018 Completed

10. Ferroxy test (R/W - TPI) 01/01/2019

11. Pickling and Passivation (SS Surface) 01/01/2019 In Process

12. Silicon Aluminium (3rd Coat) 31/12/2018 Completed

13. Silicon Aluminium (4th Coat) 01/01/2019 Completed

14. Stenciling 02/01/2019

15. N2 Purging 02/01/2019

16. Dispatch /ISSUE OF IRN 03/01/2019


Microscheduling
29/12/2018 -30/12/2018- 31/12/2018 – Round ‘O’Clock
09.00PM to 10.00AM(30/12/18) – Blasting
10.00AM to 11.30 AM (30/12/2018)- Sweep Blasting
11.30AM – 2.30PM (30/12/2018) – Primer Application.
3.00 PM – 7.00PM (30/12/2018)- Pickling Passivation (Balance to be perform
Later)
7.30PM to 10.00 PM (30/12/2018) – Silicon Aluminium Paint (2nd Coat)
10.00PM -1.00 PM – Silicon Aluminium Paint (3rd Coat)