You are on page 1of 3

START DATE 1-Dec-17

EXPRO LOCATION Egypt.


SCAN ENGINEER Mohamed Etman
WELL TEST SUPERVISOR

CUSTOMER GPC
WELL NAME N-FANAR-1X
TEST No. 1
DRILLING RIG ADM # 3
FIELD AREA N-FANAR
INTERVAL
FORMATION
TEST TYPE DST

CLIENT REPRESENTATIVE Mohamed Sawan


S E Q U E N C E   O F  O P E R A T I O N S

   CUSTOMER : GPC
              WELL : N­FANAR­1X
    RIG NAME : ADM # 3
 TEST TYPE. : DST
DATE & TIME OPERATIONS
12/1/2017 14:00 EXPRO well test crew arrived at ADM # 3 ( Mohamed nashat , Mohamed Rashad ) Well test Engineer , well test operator .
12/2/2017 15:30 The two burner booms for EXPRO arrived at GPC port .
12/3/2017 8:30 EXPRO equipment arrived at GPC port ( ESD , Choke manifold , heater , separator , coflexip hose , 3 transfer pumping , 2 compressor , 2 generator , surge tank , atmospheric tank ,4 propane rack , 4 diverter , 2 burner boom , 2 pipe rack )
12/3/2017 9:00 Held safety meeting ( TBT, risk assessment ) prior to start hanging the 1st burner boom ( board side ).
12/3/2017 9:10 EXPRO crew started hanging for the 1st burner boom ( board side ).
12/3/2017 10:00 EXPRO crew finished hanging for the 1st burner boom ( board side ).
12/3/2017 14:00 EXPRO well test crew arrived at ADM # 3 ( mohamed Etman , Hassan Moawad , Ahmed Khalad ) well test supervisoer , well test engineer , well test operator
12/3/2017 15:30 Held safety meeting ( TBT, risk assessment ) prior to start hanging the 2st burner boom ( Star board side ).
12/3/2017 16:00 EXPRO crew started hanging for the 2st burner boom (Star board side ).
12/3/2017 17:00 EXPRO crew finished hanging for the 2st burner boom ( Star board side ).
12/3/2017 20:30 EXPRO equipment arrived at GPC port ( ESD , Choke manifold , heater , separator , coflexip hose , 3 transfer pumping , 2 compressor , 2 generator , surge tank , atmospheric tank ,4 propane rack , 4 diverter , 2 burner boom , 2 pipe rack )
12/4/2017 2:00 Held safety meeting ( TBT, risk assessment ) prior to start rigging up for well test equipment .
12/4/2017 14:00 EXPRO completed for well test equipment
12/4/2017 14:30 Started flushing well test surface lines and equipment to gas line of burner boom port side.
12/4/2017 15:00 Started pressure test against upstream choke manifold upto 2500 psi.
12/4/2017 15:20 Pressure test Ok
12/4/2017 15:30 Started pressure test against Separator manifold up to 800 PSI.
12/4/2017 16:00 Pressure test Ok
12/4/2017 16:30 OPENED X-TREE MASTER VALVE, RIH W/ 1.5" CT TO 940 MT WHILE LIFTING THE WELL W/ N2 , HAD OBSTRUCTION @ 940 MT.
12/4/2017 18:30 INCREASED LIFTING RATE F/ 350 T/ 800 SCF/MIN, S.O.W F/ 3000 LB T/ 4000 LB & MANY TRIALS TO PASS W/ 1.5" CT (NO SUCCESS).
12/4/2017 20:30 POH W/ 1.5" CT T/ 904 MT (E.O.S) & MIXED 150 BBLs BRINE WATER W/ 5% KCL.>> ADDED 8 GAL CLAY STAB T/ BRINE WATER.
12/4/2017 22:30 RIH BACK W/ 1.5" CT TO 940 MT WHILE DISPLACE THE WELL W/ BRINE WATER , MANY TRIALS TO PASS W/ NO SUCCESS.
12/5/2017 0:00 CLOSED THE WELL & INCREASED SURFACE PRESSURE T/ 800 PSI FOR 30 MIN.
12/5/2017 0:30 BLEED OFF PRESSURE , DISPLACED THE WELL W/ BRINE WATER , MANY TRIALS TO PASS W/ 1.5" C.T W/ NO SUCCESS.
12/5/2017 2:00 POOH W/ 1.5" SLB C.T T/ SURFACE & PURGED C.T REEL W/ N2.
12/5/2017 3:30 R/D SLB ( INJECTOR HEAD, STRIPPER & BOP) , R/D IN PROGRESS.
12/5/2017 7:30 N/D (THARWA BREDA 3 1/8" - 5K) X-TREE & EXPRO SURFACE LINES .
12/5/2017 9:30 HPJSM, UNSET 13 3/8" HALL RTTS M. PKR. W/ 15 KLBs OVER PULL & OBSERVED THE WELL ( STATIC).
12/5/2017 10:30 POOH W/ TEST STRING
12/5/2017 18:30 EXPRO well test operator realeasd for Rig ADM # 3 ( Mohamed Rashad )
12/6/2017 0:00 CONT'D RIH W/ 12 1/4" CLEANING ASSY T/ BTM @ 1140 MT. >> HOLE IN GOOD CONDITION.
12/6/2017 2:30 HPJSM, FLOW CHECK "WELL STATIC", POOH W/ 12 1/4" CLEANING ASSY. T / 60 MT. POOH IN PROGRESS.
12/6/2017 9:00 P/U, M/U TEST ASSY. & RIH W/ SAME RETRIEVED 13 5/8" THARWA BREDA WEAR BUSHING, INSTALLED TEST PLUG & TESTED TOP PIPE RAM W/ 1500 PSI " OK".
12/6/2017 10:30 RIH W/ TEST STRING
12/6/2017 20:30 N/UP THARWA BREADA 5K X-TREE & TESTED SAME AGAINST CERAMIC DISC W/2000 PSI "OK".
12/6/2017 22:30 R/U SAPESCO S/L EQUIPMENTS & TESTED SAME (OK).
12/6/2017 4:30 SPOTTED SLB EQUIPMENT ON CANTILEVER DECK & STABBED IN C.T WITH INJECTOR HEAD.
12/6/2017 7:00 R/U SLB ( INJECTOR HEAD, STRIPPER & BOP), FLUSHED C.T REEL W/ SEA WATER & P/T( INJECTOR HEAD, STRIPPER & BOP) AGAINST SWAB VALVE W/ 2500 PSI.
12/6/2017 12:00 HPJSM, P/T EXPRO UP STREAM LINE W/ 2500 PSI & DOWN STREAM W/1000 PSI "OK".
12/7/2017 14:00 EXPRO well test operator arrived at Rig ADM # 3 ( Mahmoud Elsayed )
S E Q U E N C E   O F  O P E R A T I O N S

   CUSTOMER : GPC
              WELL : N­FANAR­1X
    RIG NAME : ADM # 3
 TEST TYPE. : DST
DATE & TIME OPERATIONS
12/7/2017 13:30 OPENED X-TREE MASTER VALVE, RIH W/ 1.5" CT TO 940 MT .
12/7/2017 23:30 C/T started RIH,Opened the well through Expro separator to Admrin #3 trip tank.
12/8/2017 0:30 C/T at depth 1620 ft,Started pumping Nitrogen with rate 350 scf/m.
12/8/2017 1:00 Water and N2 at surface .
12/8/2017 1:30 N2 only at surface.
12/8/2017 1:50 C/T at depth 2268 ft, pumping Nitrogen with rate 350 scf/m.
12/8/2017 2:00 N2 only at surface.
12/8/2017 2:30 N2 only at surface.
12/8/2017 2:35 C/T at depth 3014 ft, pumping Nitrogen with rate 350 scf/m.
12/8/2017 4:00 N2 and water and oil base mud at surface .
12/8/2017 7:30 N2 only at surface.
12/8/2017 7:40 C / T countinue RIH at depth 3706 ft
12/8/2017 10:00 Stoped pumping N2 C / T start POOH
12/9/2017 0:00 wiating for pumping acid
12/10/2017 0:00 wiating for pumping acid
12/11/2017 9:45 Opened the well through Expro Separator's bypass to burner boom.
12/11/2017 9:51 C/T at depth 1698ft,Started pumping Nitrogen with rate 400 scf/m.
12/11/2017 9:55 C / T start RIH
12/11/2017 10:00 acid & N2 at surface.
12/11/2017 11:00 water & oil & N2 at surface.
12/11/2017 11:20 Diverted flow to test separator .
12/11/2017 11:42 C / T stopped RIH at Depth 3088 ft ,Continue pumping N2 with rate 400 scf/m.
12/11/2017 15:36 Decrease N2 pumping to 350 scf/min at depth 3051 ft .
12/11/2017 19:00 Continue pumping N2 350 scf/min at depth 3084 ft .
12/11/2017 22:30 Close the well and start build up .
12/12/2017 2:45 Start shipping oil from surge tank to the boat .
12/12/2017 3:15 Stop shipping ( total shipping = 45 bbl ) .
12/12/2017 3:30 Opened the well through Expro equipment .
12/12/2017 3:45 C/T Started pumping Nitrogen with rate 350 scf/m.
12/12/2017 14:30 Start shipping oil from surge tank to atmospheric tank ( 30 bbls )
12/12/2017 17:00 End off test
12/12/2017 18:00 Stoped pumping N2 C / T start Kill the well
12/13/2017 4:00 EXPRO well test crew start R / D
12/13/2017 12:00 EXPRO well test crew completed R / D

You might also like