Professional Documents
Culture Documents
<Other Clause>
Copyright @ 2003 Holcim Services (Asia) Ltd.
APBM
Document Control
Document Name Time-Phased Planning Procedure Training Document
Author Ha Tran
File Name & Path
Created 15-Jun-04
Last Edited
Printed on
Document Approval
Role Name Signature Date
Distribution List
Role Name Signature Date
Table of Contents
TIME-PHASED PLANNING ................................................................................................................. 4
Time-Phased Planning
Time-phased planning is a MRP procedure where the materials are planned in a particular time
interval. If, for example, a vendor always delivers a material on a certain weekday, then it makes
sense to plan this material according to the same cycle, adjusted to the delivery date.
To plan a material with time-phased planning, it is a must that the MRP Type shall be entered in the
material master record for time-phased planning and the planning cycle. The latter is defined in the
form of a planning calendar in the Planning Cycle field.
For time-phased planning materials, the planning file entries NETCH and NETPL in the planning file
are not important, so are not set for MRP changes. Materials that are planned according to a time-
phase are provided with an MRP date in the planning file. This date is reset on the creation of a new
material master data, and then after every planning run. This date corresponds to the day that the
material will next be planned; it is calculated on the basis of the planning cycle specified in the
material master. The material will only be planned on the days that have been specified by the
planning cycle. Noted that to have control of this procedure and plan a material before the intended
MRP date, it is possible to specify a MRP date in the planning run. For example, if the MRP run is
planned for Monday, it is probable to execute the run for Monday on Saturday.
The lot-sizing procedure for a time-phased planning material is the exact lot size, so optimizing lot-
sizing procedures can also be applicable for time-phased planning.
When the planning run is triggered, the system uses the MRP date in the planning file to check
whether the materials are to be planned. The MRP date is calculated from the planning cycle. The
system calculates the requirement. It also determines a time interval according to the following
algorithm:
MRP date + planning cycle + purchasing processing time + planned delivery time + goods receipt
processing time.
The system compares the forecast requirement in this time interval with the stock and both the fixed
and firm receipts in this time interval. It then calculates the quantity to be ordered. During
calculation, the system assumes that the fixed receipts lie at certain intervals. It does not matter
whether the fixed receipts are available at the start or at the end of the interval. This means that
there may be a temporary shortage.
Noted that Time-phased planning can be combined with a reorder point. The material is not only
planned on the MRP date in the planning file, but also when the reorder point is fallen short of due to
a good issue. If the reorder point has shortage, the material is flagged for planning, as is the
planning cycle. During requirements calculation, the system creates a time interval that spans from
the time of the reorder point shortage to the availability date of the next regular MRP date. For this
time interval, the ordered quantity must suffice. On the next MRP date, the material is again planned
at regular intervals.
Fig-01
Fig-02
Fig-03
1.4. On the pop up screen, select ‘Months (week days)’ alternative option and click on
icon:
Fig-04
1.5. Supposing it is agreed between purchasing and vendor that all shipments will be
delivered to the warehouse on every Monday of each week, on “Create Planning
Calendar” screen, make the setting and press ‘ENTER’:
Fig-05
1.6. On the pop up screen, maintain the appropriate validity period (normally 12 month
period) and then click on icon:
Fig-06
1.7. On “Create Planning Calendar: Periods” screen, click on icon to save this newly-
defined planning calendar:
Fig-07
Fig-08
2.2. On “Change Material (Initial Screen)” screen, fill in the data as below:
Fig-09
Click on icon
Legend: R = Required, O = Optional, C = Conditional, D = Display
2.3. On the pop up screen, select appropriate User views (MRP Views) and click on icon:
Fig-10
Fig-11
2.5. On “Change Material XXXXXXXXXXXX (TH –Spare Parts1)” screen, fill in the data as
below:
Fig-12
Fig-13
Fig-14
Fig-15
3.2. On “Stock/Requirements List: Initial Screen” screen, fill in the data as below:
Fig-16
Fig-17
Fig-18
Fig-19
4.3. On “Planning Result: Individual Lines” screen, click on icon to save the result of MRP
run for this material:
Fig-20