TITLE : Improvement Of Bua-Gumatdang Ecotourism Footrail

LOCATION : Barangay Tuding – Gumatdang Itogon, Benguet

CONSTRUCTION SCHEDULE & S-CURVE

ITEM NO. DESCRIPTION


% BY
AMOUNT
DURATION 20 WORKING DAYS
WEIGHT
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

I BILLBOARD 0.50 1,500.00


II CONSTRUCTION OF PATHWAY 97.33 291,848.28
III TRANSPORTATION 2.17 6,500.00
TOTAL 100.00 299,848.28
QUARTERLY ACCOMPLSIHMENT (%) 26.45 26.58 26.58 20.39
COMMULATIVE ACCOMPLISHMENT (%) 26.45 53.03 79.61 100.00
QUARTERLY ACCOMPLISHMENT (P) 79,309.87 79,699.67 79,699.67 69139.07
COMMULATIVE ACCOMPLISHMENT (P) 79,309.87 159,009.54 238,709.21 299848.28

Prepared/ Submitted By : Engr. Ronnie A. Malicdan


Designation: Proprietor/ Manager
Name of Firm: GRACERON CONSTRUCTION

TITLE : Improvement Of Bua-Gumatdang Ecotourism Footrail


LOCATION : Barangay Tuding – Gumatdang Itogon, Benguet
PERT-CPM
ITEM DESCRIPTION
NO. I
Spl,I Billboard

101 Construction Of Pathway II


II II
103 Transportation START END
III

Prepared/ Submitted By : Engr. Ronnie A. Malicdan


Designation: Proprietor/ Manager
Name of Firm: GRACERON CONSTRUCTION

TITLE : Improvement Of Bua-Gumatdang Ecotourism Footrail


LOCATION : Barangay Tuding – Gumatdang Itogon, Benguet
MANPOWER SCHEDULE

DURATION 30 WORKING DAYS


DESCRIPTION

10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
1
2
3
4
5
6
7
8
9
CONSTRUCTION FOREMAN x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x
SKILLED LABORER x x x x x x x x x x x x x x x x x x x x x x x x x x x x
LABORER x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x

EQUIPMENT UTILIZATION SCHEDULE

DURATION 30 WORKING DAYS


DESCRIPTION

10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
1
2
3
4
5
6
7
8
9
Dump Truck x x x x x x x x x x x x x x x x x x x x x x x

Prepared/ Submitted By : Engr. Ronnie A. Malicdan


Designation: Proprietor/ Manager
Name of Firm: GRACERON CONSTRUCTION