Overview:
The difference between cost consumed in a production order and finished goods dispatched from production
operation to stock is treated as Work in Progress. This will be calculated every month as a month end activity. Once
the order has been completed, status of same will be changed to Technically complete after which Work in progress
calculated as of now will be reversed and difference between consumption and stock produced (i.e. variance) will be
charged to Profit & Loss as price difference.
Procedural Steps
Via Menus Accounting Controlling Product Cost Controlling Product Cost by Order
Period-End Closing Single Functions Overhead Individual Processing
Via Transaction Code KGI2
From the main menu SAP Easy Access screen as shown below
On screen “Actual Overhead Calculation: Order Basic List”, enter information in the
fields as specified in the table below:
CLICK
Procedural Steps
Via Menus Accounting Controlling Product Cost Controlling Product Cost by Order
Period-End Closing Single Functions Work in Process Individual
Processing Calculate
Via Transaction Code KKAX
From the main menu SAP Easy Access screen as shown below
EXECUTE
Procedural Steps
Via Menus Accounting Controlling Product Cost Controlling Product Cost by Order
Period-End Closing Single Functions Work in Process Individual
Processing Display
Via Transaction Code KKAY
EXECUTE
Via Menus Accounting Controlling Product Cost Controlling Product Cost by Order
Period-End Closing Single Functions Variance Individual Processing
Via Transaction Code KKS2
From the main menu SAP Easy Access screen as shown below
EXECUTE
For BSNL telecom factory scenario variance calculation is not applicable as COPA is not applicable for Telecom Factory.
Financial variance will get posted automatically during settlement.
Procedural Steps
Via Menus Accounting Controlling Product Cost Controlling Product Cost by Order
Period-End Closing Single Functions Settlement Individual Processing
Via Transaction Code KO88
From the main menu SAP Easy Access screen as shown below
EXECUTE
Click on
1. Difference between Finished good created to production order at estimated cost and actual consumption will be posted
as price difference in profit and loss account.
2. Settlement for all the order may it be production or maintenance or internal order will get settle through tcode KO88,
only receiver object will be different:
Go to Display Production order screen (tcode – CO03) and check the cost analysis:
-------------------------------------------------------------End of Document----------------------------------------------------