TIMELINE
Preliminary Design,
Stakeholder Meetings
Fall 2017 - Fall 2018
Confirming Vision
& Understanding Trade-offs
March 2016
Phase 1 Construction
109 Street to 114 Street
2020 - 2022
TWO JASPER AVENUE PROJECTS: DRAINAGE WORK
Jasper Avenue 110 to 111 Street
ONE UNIFIED VISION
As part of the Imagine Jasper project, EPCOR
will be completing upgrades to the storm
Imagine Jasper Avenue sewer on Jasper Avenue between 110 Street
(124 Street to 109 Street) and 111 Street to address flooding risks in the area. This work
will be completed as a stand alone project and is anticipated
to take place starting in the fall of 2019 and continue through
Jasper Avenue New Vision the spring of 2020. Road closures will be required during this
time. Additional information will be available prior to the work
(109 Street to 92 Street) being undertaken.