HYpact Product PDF
HYpact Product PDF
HYpact
Volker JANICH
02/11/2010
GRID
Agenda
1 Circuit breaker
2 Disconnector / Earth switch
3 Bushing current transformer
2
3
1
4 Drive mechanism
4 5 Central control cubicle
5
6 Steel stands
6
E = ½ m v²
d2 dnotroff30.07.2010
UK-specific, hidden in the standard presentation
dnotroff; 30.07.2010
d3
d3 dnotroff30.07.2010
UK-specific, hidden in the standard presentation
dnotroff; 30.07.2010
d4
d4 dnotroff30.07.2010
UK-specific, hidden in the standard presentation
dnotroff; 30.07.2010
Indicating devices / Interlocking
Support
− Steel stands
− Drive mechanisms
• Mounted on steel stands
− Central control cubicle (if
applicable)
• Mounted on steel stands
Three phase switchgear unit
− Completely assembled and
factory-tested
− SF6 piping completely mounted
− Interphase linkages installed and
adjusted
− CT connection box, pre-wired
To do at site
− Coupling of drive rods
− Mounting of current transformer
connection box
− SF6 density monitor wire
connection
− Top up gas to service pressure
− Commissioning test
With HYpact, conventional AIS disconnectors and earthing switches become obsolete,
thus no frequent DS/ES maintenance required anymore
HYpact disconnectors and earthing switches are based on GIS technology
Long maintenance cycles as of GIS reached
Inspection
− Visual inspection on occasional base during station tours, latest after 6
years
• Corrosion
• SF6 gas pressure
• Ventilation ports and heating system
Maintenance
− Every 12 years
• Gas quality
• Cable joints and connecting linkages
• Function of electric control circuits
• Operation time
• Contact resistance
Reconditionning (normal service conditions)
− After 2.500-3000 operations at rated normal current or
− After a total current, i.e. 15 x rated breaking current