PROCEEDINGS, 1st ITB Geothermal Workshop 2012

Institut Teknologi Bandung, Bandung, Indonesia, March 6-8 , 2012

CONTRIBUTION OF NATIONAL EPC COMPANY


IN ULUBELU 1 & 2 GEOTHERMAL FIELD DEVELOPMENT PROJECT

Deni Syarif H.

Rekayasa Industri
Rekayasa Office Building 4th Floor
Jl. Kalibata Timur I No. 36,
Jakarta, Indonesia
denisyarif@rekayasa.co.id

ABSTRACT Keywords : Contribution, Geothermal, Construction,


EPC, Geothermal Power Plant
Concession work area (WKP) of Ulubelu Geothermal
Field is owned by PT. Pertamina Geothermal Energy
INTRODUCTION
(PGE) with the potential for possible reserves of 380
MW. Development of geothermal field was carried Ulubelu is one of 15 (fifteen) WKP owned by PGE, it
out by PGE together with State Electricity Company is located at Ulubelu District, Tanggamus Regency,
(PLN) in the scheme of Energy Sales Contract (ESC) Lampung Province, Sumatera Island, Indonesia. It
or Perjanjian Jual Beli Uap (PJBU) for first stage. has a distance at least 80 km South East from Bandar
With this scheme, construction of power plant in Lampung, the capital city of Lampung Province as
Ulubelu geothermal field shall be the responsibility shown in Fig. 1. Reconnaissance survey of Ulubelu
of PLN. While the supply of steam shall be the was conducted by Pertamina (Indonesian State Oil
responsibility of PGE. Company) in 1988. Then exploration continued
through more detail survey in 1991 followed by
First development stage of Ulubelu Geothermal research in 1993 and 1995. Refer to data from
Power Plant (GPP) has been planned for a capacity of Directorate General of Mineral, Coal and Geothermal
2 x 55 MW, the construction is carried out by an (Dirjen Minerbapabum) Department of Energy and
Engineering, Procurement, Construction (EPC) Mineral Resources (ESDM) in 2004, Ulubelu has
contractor with a period of 28 months for unit 1 and potential of resources as hypothetical 156 MW,
32 months for unit 2. In this case of constructing possibility reserves of 380 MW, and proven reserves
Ulubelu GPP, PLN has appointed a contractor to of 20 MW as presented in Table 1. While proven
accomplish the project. This contractor is a reserves is about 240 MW refer to the latest news
collaborating company of foreign and national EPC from local newspaper.
company. PT. Rekayasa Industri (Rekind) as a Development field was carried out by drilling of
national EPC company has significant share for this production well started on 2007 to obtain well UBL-
project, the scope of work majoring on Electrical 01. To continue development, a power plant complete
Main Equipments, Civil Works, Balance of Plant, with Steam Above Ground System (SAGS) should be
substations and transmission 150 kV networks. constructed. Under PJBU, SAGS project shall be
Rekind contribution in the development of this developed by PGE while Geothermal Power Plant
geothermal field is technically covers the fields of (GPP) Project is under PLN scope. For construction
engineering design activities as well as engineering work, both PGE and PLN shall select EPC company
drawings, including transportation and logistics to construct the plant. Rekind which has been
procurement, and construction for physical activity. collaborating with foreigner company has been
Another thing observed as Rekind contribution is on selected to execute GPP Project named Ulubelu 1 &
the field of Occupational Safety and Health involving 2 GPP Project (2 x 55 MW). While SAGS
working conditions, working equipment, working construction has been assigned by PGE to another
conditions and situations, as well as safety national EPC company. Currently, Ulubelu GPP shall
procedures. Then the remaining Rekind contribution be the first installed largest geothermal power plant
are Environmental Protection, community in Sumatra Island.
development, labor, and equipment used.
DEVELOPMENT SCHEME PREVIOUS CONTRIBUTION FOR OTHER
GEOTHERMAL FIELD
Ulubelu geothermal field is being under authorization
of PGE, however the Power Plant shall be PLN Contribution of Rekind for geothermal field
scope which the steam is supplied by PGE. This development was initiated in Gunung Salak
business scheme has been agreed between PLN and Geothermal Power Plant Construction Project in
1993. This first entry project in geothermal bring
Rekind to next involvement in Geothermal industries
in Indonesia. Rekind contribution in this first
geothermal project is just supporting development in
SAGS construction. This contribution is a growing of
Rekind competency in gas fluid handling project that
is CO2 removal Subang Project. Experiences in
handling gas fluid project was utilized to provide first
contribution in almost similar project dealing in
handling vapor or mixing of vapor and water, it is
geothermal project. Previous experience and
competency to handle gas fluid project was a basic
foundation to shift into geothermal industries. First
Figure 1: Location of Ulubelu Geothermal Power contribution of Rekind in geothermal field
Plant Project (Courtesy of google map) development was assigned to construct SAGS of
Salak field which the project was owned by Unocal
PGE under PJBU. To develop the field, PGE has Geothermal Indonesia Ltd in 1993. Contribution
been instructed one EPC national company to provided in this project was on SAGS construction
construct SAGS. This SAGS shall be the line to flow only. One year after, Rekind contribution has been
geothermal fluid from well head then supply the enhanced although still on construction but the field
Power Plant by dry steam. This construction work go forward into power plant area. This is a valuable
shall be completed within around 12 (twelve) until 14 trusty of owner to deepen contribution in geothermal
(fourteen) months. industries. Assignment for construction of power
plant still in Gunung Salak area but the project owner
Power plant itself shall be constructed by a was PLN in 1994. After that, various geothermal
collaboration among Rekind as an EPC national project has involved Rekind to enhance the
company and foreigner companies. Power plant contribution. In period of 1994-1995, contribution to
project has 2 (two) units which each capacity is 55 geothermal industries has been served for Site
MW. This project shall be owned by PLN, while Development Work Project of Sarulla Geothermal
under PJBU the power plant will receive steam Field in North Sumatera. Contribution of geothermal
during 30 years. Power plant completion project has project execution had been enhanced by receiving
been scheduled within 32 months. In order Power assignment to be involved in all exploitation aspect
plant could be commissioned, dry steam shall be of geothermal industry. It was on period of 1997 until
ready to supply. Hence both of project owner shall be 2000, Geothermal field development that had
inline coordination to achieve well integration of involving Rekind was Wayang Windu phase 1
these projects execution. Geothermal Project and Lahendong Geothermal 1
Field Project. Rekind contribution in Wayang Windu
Table 1: Geothermal potency in Lampung Province project was assigned to execute Engineering and
based on status 2004 from data of ESDM construction of SAGS and for construction of power
Resources
Reserves (Mwe) plant area. During this period, Rekind also provided
No. Area Regency / City (Mwe)
Spec. Hyp. Possibility contribution in engineering section of Lahendong
Geothermal SAGS. In this period, Engineering and
1 Wai Umpu North Lampung 100 - - Construction aspect were contributed by Rekind into
2 Danau Ranau West lampung - 185 222
two project simultaneously. Perhaps this contribution
3 Purunan West lampung 25 - -
4 Gunung Sekincau West lampung - 100 130 was started to be acknowledged by geothermal
5 Bacingot West lampung 225 - - industries player hence next few years Rekind had an
6 Suoh-Antatai West lampung - 163 300 opportunity to contribute as an EPC company for
7 Fajar Bulan West lampung 100 - -
8 Natar South Lampung 25 - -
geothermal industries. Actually, first EPC geothermal
9 Ulubelu Tanggamus - 156 380 project handled by Rekind was on 2002. This
10 Lempasing South Lampung 225 - - geothermal project was namely Dieng 1 Geothermal
11 Wai Ratai South Lampung - 194 - Power Plant Project 1 x 60 MW owned by Himpurna
12 Kalianda South Lampung - 40 40
13 Pematang Belirang South Lampung 225 - -
California Energy Ltd. In this project, Rekind
contribution was evolving due to increasing of scope bridge of land with deep valleys, etc. With those
of work. Previous contribution is more on conditions, steam flowing should be maintained in
construction then evolve with additional of pressure. Practically it is not as simple as discussed,
geothermal engineering work in Lahendong 1 SAGS to construct pipeline with such requirement is
Geothermal Project. This new experience should be truthfully complicated. Natural challenging that had
contributed in future project specially in involvement to be conquered based on accurate calculations with
of geothermal field development. high precision of applications and excellent
implementations. However, those difficulties and
After evolving to become an EPC company in complication of site condition was able to be
geothermal project, there are considered two major conquered by Rekind through providing satisfied
contribution donated by Rekind for geothermal performance.
development in Indonesia. The first major
contribution was on Kamojang 4 Geothermal Total Some others geothermal project executed by Rekind
Project owned by Pertamina in 2006 until 2008. This is presented in Table. 2. Up to date, there are 11
Kamojang 4 Project was a geothermal project that is geothermal projects which had been completed and 1
purely built by Indonesian company. Pertamina as the Ulubelu GPP Project is under completion.
owner also the field developer then Rekind as a
national EPC company that construct the power plant Table 2: Rekind contribution for Indonesia
and SAGS areas. This was a proof that Indonesia had Geothermal Field
No. NAME OF PROJECT OWNER PERIOD SCOPE OF WORK
been able to develop geothermal power plant and Gunung Salak Geothermal Power Plant UNOCAL Geothermal of
1 1993 SAGS Construction Work
show self reliance of national development of Project
Geothermal Power Plant Gunung Salak
Indonesia Ltd

2 PT. PLN (Persero) 1994 SAGS Construction Work


geothermal field. Capacity of Geothermal Power Unit I/II Project
PERTAMINA (UNOCAL
3 Sarulla Unocal Project North Sumatera 1994-1995 Site Development Work
Plant Kamojang unit 4 is 1 x 60 MW. Rekind as a Lahendong Geothermal Pipe Line
Geothermal of Indonesia)
Basic & Detail Engineering
4 BUD Engineering Pte. Ltd. 1998 - 1999
main contractor has donated a major contribution to Project 85 in Km 10", 18", 22" & 24"
Wayang Windu Geothermal Pipeline
for SAGS
Engineering Construction
PT. Mandala Nusantara Ltd.
providing high local content value. As a national 5 Project 790 in. Km Dia. 18", 24", 30",
36" & 42"
& Sumitomo Corporation
1997 - 2000 for SAGS & Construction for
Power Station
company, Rekind engineer is Indonesian that has Engineering Procurement
competency to build and construct Indonesia 6
Dieng 1 Geothermal Power Plant
Project 1 x 60 MW
Himpurna California Energy
Ltd. Patuha Power Ltd.
2002
Construction
Commissioning for
industries including geothermal. This is a great pride Reconditioning ion SAGS

of Indonesia nation as a whole. Moreover, 7 Lahendong II Geothermal 1 x 20 MW PT. PLN (Persero) 2005 - 2007
Engineering Procurement
Construction
performance of Power plant built is excellent hence Commissioning

could satisfy Pertamina as the project owner. This 8


Total Project Kamojang - 4 1 x 60 MW
PT. PERTAMINA DIT HULU 2006 - 2008
Engineering Procurement
Construction
Geothermal Power Plant
Kamojang 4 GPP project was including one of Commissioning

project inaugurated by President of The Republic 9


Lahendong III Geothermal Power Plant
PT. PLN (Persero) 2007 - 2009
Engineering Procurement
Project 1 x 20 MW Construction
Indonesia Mr. Susilo Bambang Yudhoyono on Commissioning

December 2007. One other GPP project that was 10


Wayang Windu Phase 2 Geothermal PT. Star Energy Holding
2007 - 2008
Engineering Procurement
Power Plant Project, 1 x 110 MW Limited Construction
inaugurated directly by President of The Republic Commissioning for SAGS

Indonesia is Lahendong II GPP project 1 x 20 MW 11


Lahendong 4 Geothermal Power Plant
PT. PLN (Persero) 2009 - 2011
Engineering Procurement
Project 1 x 20 MW Construction
located at Tomohon district, Manado regency, Commissioning

Province of North Sulawesi. This Lahendong II GPP 12


Ulubelu 1 & 2 Geothermal Power Plant
PT. PLN (Persero) 2010 - Current
Engineering Procurement
Project (2 x 55 MW) Construction
project was also built by Rekind. Commissioning

Another project which has enormous contribution of Beside of ability and competency as an EPC
Rekind was Wayang Windu phase 2 Geothermal company in geothermal industry, Rekind contribution
Power Plant Project which has capacity 1 x 110 MW, also donated in local content provision because of
located at Pangalengan district, Bandung regency, company nationality. This local content in
Province of West Java. This project is owned by Star geothermal industry shall be an important issue due
Energy Ltd. Wayang Windu is a largest unit of to government regulation for next project ahead. It
geothermal power plant in the world, this largest will be presented in Table 3 to show material local
capacity of turbine was supplied by one Japan content provided by Rekind in Kamojang 4 GPP
manufacturer that was collaborating with Rekind in Total Project which is around 41,3%. With the
that project. Rekind itself share the contribution to existence of local content provision, it is required to
build SAGS facility for this project. With a large comply with government regulation as stated in
capacity, steam supplied to power plant should be in Ministerial of Industry regulation no. 4 year 2009
large amount and maintained energy content. (permen kemenperin no 04/M-IND/PER/1/2009.
Whereas the field of SAGS is very difficult and
complicated technically. Some of those difficulties
such as steep elevation of pipeline, the need for a
Based on above contribution for geothermal field Portion A : Power Plant capacity of 2 x 55 MW
development, currently Rekind is acknowledged by Portion B : Substations
the “player” of Geothermal Industry. Portion C : 150 kV Transmission Lines

Table 3: Material local content in Kamojang 4 GPP Electric power generated by this power plant shall be
Total Project connected to 150 kV Transmission Line System to
supply South Sumatera Power System. This power
plant is also required directly to supply the adjacent
rural villages through 20 kV existing distribution line
system.

Generally, concept of this power plant shall be based


on single flash cycle. Dry steam supplied by PGE as
steam developer shall be drying from water and
eliminating the particles in a scrubber and demister
before admission to the turbine. Inside turbine, steam
expanding downward condensing pressure. Steam is
condensed in direct contact type condenser using cold
water supplied by cooling tower. Condensing process
triggering Non Condensable Gases (NCG) that shall
be extracted from Condenser using Gas Removal
System. Outflow of condenser is in hot water form,
combined with main steam and ejector steam
condensate are discharged by two hot well pumps to
cooling tower. Fluid discharged to cooling tower is
decreasing the temperature then delivered to re-
injection pump interfacing with PGE scope.
Power plant built shall be designed to cover 30 years
operating time. Overall project scope of work shall
include below:
- Design
- Manufacture
- Inspection and or Testing before material
shipment
- Packing of material shipped
- Material shipment
CONTRIBUTION FOR ULUBELU - Insurance during shipment
GEOTHERMAL FIELD DEVELOPMENT - Custom clearance at Indonesian gate port
whether air port or sea port
As an experienced national EPC company specially - Inland transportation from Indonesian gate
in Indonesia geothermal project, Rekind has wide port to the site
access to enhance his share in Indonesia geothermal - Off loading the material at site
development. Supported by experiences and - Construction of civil works
capabilities, Rekind is contributing for development - Material warehousing or storage
of Ulubelu Geothermal Field in Power Plant EPC - Erection
construction. - Painting
- Setting to work
Overall Project Scope of Work - Site testing
Rekind and his collaboration company is assigned to - Commissioning
complete a turnkey basis project for Ulubelu Power - Test on Completion
Plant construction. However, the assignment for this - Warranty
project not only to construct the power plant but also - Test after Completion (First inspection)
associated with other PLN work. Therefore this prior to issue Performance Certificate.
project scope of work consist of three main portions Other provisions should be completed are :
described as below: - Site development work
- Site preparation
- Clearing the land for site
- Grubbing its flow capacity shall be 50 percent for
- Top soil tripping condensate and hot water.
- Access road to the site 7. Cooling tower that has configuration of
Detailed descriptions of Portion B shall include : mechanical induced draft cross flow or
- Construction of Ulubelu GPP Switchyard counter flow.
- Modification and add some new equipment 8. Auxiliary Cooling Water System to service
of Batutegi Hydro Power Plant (HPP) primary / secondary intercooler heat
Switchyard and Pagelaran Substation exchangers, gas extraction inter and after
- Connection work to 20 kV distribution line condensers and other required plant items.
system 9. Reinjection and waste water system that
Detailed descriptions of Portion C shall include : should service the excess water from cooling
- New towers and 2 circuit feeders up to the tower with flow of 70 m3/h at temperature
Tee Off tower (existing tower no. 22) about 30 until 40 oC.
- One circuit connecting to Batutegi HPP 10. Service water supply for fire fighting water,
Substation cooling tower basin filling, treated fresh
- Another circuit connecting to Pagelaran water and potable water. This water is
Substation. coming from raw water provided from river
by River Water Pumps flowing through sand
Overall project requires also for the responsibility to filters or coming from Deep Wells as result
provide reliability, safety, operability and of Deep Well Pumps. That raw water is
completeness the work comply to specified design stored in a Raw Water Storage Tank or Raw
and layout. Water Storage Pond.
11. Fire fighting water system
Work Related to mechanical process for Portion A 12. Fire detection system
Below mechanical process work shall be provided in 13. Set of handling equipment such as crane.
this project for both unit 1 & 2 : 14. Laboratory with chemical analysis and
1. Condensing steam turbine complete with its environmental equipment
accessories such as stop valves, by pass 15. Warehouse and workshop
valves, governing system, etc. This turbine 16. Ventilation system
shall comply with below specification : 17. Chemical treatment system
- Maximum Continuous Rating at
Generator Terminals : 55 MW Work related to electrical process for Portion A
- Normal rotational speed 3000 rpm Electrical work that shall be accomplished listed
- Minimum turbine inlet pressure generally below :
(tentative) : 6-8 bara. 1. Generating unit that comprise of generator
2. Main steam piping and steam separator / (stator and rotor), bearings, cooling system
demister, including accessories, supports, and excitation system
drainage, heat insulation etc. Steam piping 2. Generator output system that consist of
system and pressure vessels shall keep neutral equipment, generator protection, unit
pressure tentatively minimum at 12.5 barg. metering equipment and auxiliary equipment
3. Direct contact type steam condenser cubicles
equipped by internal features for steam 3. Power Transformers that consist of type :
condensing, condensate cooling and non Oil immersed power transformer, generator
condensable gas extraction. transformer, Unit auxiliary transformer,
4. NCG extraction system complete of full auxiliary transformer, station service
capacity of two unit parallel set of gas transformer, station service auxiliary
extraction system for both unit power plant, transformer
direct contact inter condenser and after 4. Medium voltage service system
condenser. 5. Low voltage service system
5. Main cooling water pipeline made of 6. Emergency service system
Fiberglass Reinforced Polyester (FRP) or 7. Lighting system
SUS304L pipes, complete with suiTable 8. Earthing system and lightning protection
valves, filters, expansion joint and 9. Telephone, internal communication and
accessories, etc. clock system
6. Two hot well pumps for each unit with type
of single stage centrifugal vertical or mixed,
Works for control and monitoring system for project schedule is presented in Fig. 5, it is covering
Portion A design, engineering, procurement such as fabrication
This works are distributed as below: of material until arrival at site, testing, erection and
1. Instrumentation and control system installation in construction phase until overall
2. Distributed control and information system commissioning and acceptance test to obtain TOC.
3. Control and monitoring of system and
function Overall Engineering, Procurement and
4. Panel board to assist operational function Construction
5. Control and instrumentation for field Engineering
6. Sensors for field instrumentation In engineering section, work mostly relate with
7. Instrumentation cables technical documents and drawings. Front End
8. Others such as safety gas monitoring and Engineering Design (FEED) shall be derived to more
detections, instrument test equipment, tool detailed engineering document and classified into
sets, etc. several technical group. There are common diagram
and calculation terms found in engineering phase
Works for plant services for Portion A such as Process Flow Diagram (PFD), Piping &
This works are associated with both unit 1 & 2 of Instrumentation Diagram (P&ID), Heat and Mass
GPP relating with water and air. Those water and air Balance, etc. Above diagram and calculation is very
are required for power plant operational. important for deriving engineering document to more
detail.
Works relate to civil, structural and architectural
for Portion A Ulubelu GPP project classifies technical document in
each common discipline of EPC of power plant: civil,
This section works are classified into below :
electrical, mechanical, piping, process and
1. Infrastructure such as site preparation,
instrument.
excavation and backfilling, access road and
guard house.
Document type used in Ulubelu GPP project is
2. Related works with plant process associated
emphasized in six disciplines as below :
with foundations, structural and
1. Civil : Standard details, geology & soils
architectural, dewatering, preparation, form
exploration & testing, earthwork, plans and
works, reinforcing steel etc are for
profiles, general arrangement, landscaping,
condenser and hot well pump pit, electrical
excavation, site underground, final grading,
building, turbine hall, switchyard, power
drainage and erosion, concrete, rebar,
transformers, cooling tower basins, etc.
embedded metal, structural steel work,
3. Related works with plant services associated
perspectives and isometrics, architectural,
with foundations and any work until finished
fire zone, noise zone and fire protection.
for such administration building, workshop
2. Electrical : single lines diagram, data sheet,
and store, guard house, car shelter, etc.
power wiring, Riser diagrams, schematic
4. Related works with miscellaneous such as
diagrams, grounding wiring layout,
work to construct fencing and gate,
equipment arrangements, lighting wiring
switchyard road, sewage disposal, etc.
and connection diagrams, auxiliary diagram
such as protection and phasing diagrams,
Other remaining scope for Portion A
raceway above & below ground, site plans,
Remaining scope for portion A relate with mandatory communications, grounding, and cathodic
spare parts, consumable materials and personal on- protection.
site training. 3. Mechanical : General arrangements, Data
Portion B and Portion C has been presented in the sheet for mechanical equipment, equipment
previous part. location and strength calculation.
4. Piping : Piping general arrangements, pipe
Overall Project Schedule erection, piping area, isometrics and Test
The project commencement date is started since Block diagram.
contract signed between PLN and EPC company. 5. Process : PFD, P&IDs, Heat & Mass
This project completion shall be within 28 months for Balance and water balance.
GPP unit 1 and 32 months for GPP unit 2. While time 6. Instrument : General specification, control
completion for all substation works all transmission room arrangements, control logic,
lines work is 2 months each. Project completion is instrument installation details, layout central
verified by Taking Over Certificate (TOC). Overall control rooms and data sheet.
Procurement Specific contribution
Supply for this project comprise of two groups, those Generally, contribution of EPC national company in
are materials / equipments and services. Material Ulubelu Geothermal Field Development could be
procurement cover activities generally as following : said appreciable. Usually EPC work in a geothermal
- Manufacturer selection development is comprising of two portion, they are
- Drawing approval SAGS portion and power plant portion. Some of EPC
- Raw material preparation and collection work is combined in one portion called Total EPC
- Manufacturing / fabrication stage Project. In Ulubelu, EPC work is divided into two
- Assembling portion as presented earlier. One portion of EPC
- Testing and inspection work is SAGS that assigned to one national EPC
- Packing company while power plant portion is assigned to a
- Delivery foreigner company collaborating with Rekind as a
While services shall cover works for engineering national EPC company. SAGS portion is clearly
detail, transportation including exportation and contributed by national EPC company, then
importation, warehousing, installation and necessary to evaluate Rekind contribution in EPC
supervision of commissioning. work for construction of Ulubelu GPP Project.

Construction Particularly for Ulubelu GPP project, previous


This scope really executed at project site. The first successful Geothermal Projects that were executed by
activities of construction usually started by site Rekind standard method is being basic and reference
survey and site investigation to collect overview of for Ulubelu GPP project execution. Various project
site location. Such like other EPC project, Ulubelu completed had been satisfying project owner due to
GPP project is executed similarly but there are some achievable performance of Power Plant project. The
special condition to be implemented such as H2S successful of previous project constructed were
handling, etc. appreciated by many. Kamojang 4 and LHD 2 were
recognized by the government's success with the
Ulubelu GPP construction is started on civil inauguration by the President of The Republic of
discipline relate with soil investigation, clearing, Indonesia. The Wayang Windu 2 performance can be
excavation, backfilling, soil replacement / seen by anyone. All of this successful completion
improvement etc. Those activities to prepare the were becoming of standard method implemented by
foundation of next equipment laid down and for Rekind. This standard method also employed in this
building structure foundation. Following are erection Ulubelu GPP Project. Good management, excellent
and installation of main equipment then auxiliary coordination, good approaching handling, pleasant
equipment. behavior, hard work, professional, great willingness
to learn and grow, etc are the Rekind characteristics
General Contribution which are formulated in company values.
Technically, the common working methods in an
As mentioned earlier that project is executed by a
EPC Project has been integrating with company
collaborating EPC company among foreigner
values and culture to obtain satisfactory results is
companies and national companies. Ulubelu SAGS is Rekind standard method. Generally, common
contributed by other national EPC company and working methods employed in Ulubelu GPP project
Ulubelu GPP is contributed by Rekind and his
as below.
partners. Sharing of Rekind is divided into 7 (seven)
classification based on type of share as following :
In Engineering section, Rekind is responsible to
1. Commercial work
generate and issue 2131 set engineering documents.
2. Project management administration
One of documents generated by Rekind could be seen
3. Engineering, design, procurement,
in Fig. 2 and Fig. 3 on the next page as an example.
manufacturing and inspection test for
Previously mentioned that Rekind is responsible in
mechanical and electrical equipment
technical section, it could be said that total
4. Site establishment and temporary work
documents issued are in major portion of document
5. Civil and architectural work
required in this EPC work. Below presented the
6. Electro mechanical work
distribution of documents that shall be generated in
7. Materials for commissioning
Table 4.
Table 4: Distribution of engineering document in Construction activities are not only dealing with
each discipline. project completion but Rekind shall aware of Health,
Safety and Environment (HSE) and community
DOCUMENT TOTAL
NO DISCIPLINE
EXTERNAL INTERNAL DOKUMEN
REMARK surrounding. Rekind HSE contribution in Ulubelu
GPP project is applying project scope of work and
1 Process 49 122 171
2 Instrument 43 137 180
complying with government regulation. The
3 Mechanical 34 58 92 contribution could conduct some activities such as
4 Piping 544 196 740
5 Civil 346 86 432
construct master point assembly, inspection of tools
6 101 76 177
& equipment used in Ulubelu GPP Project,
Electrical (Portion A)
implementation color code for tools and equipments,
Electrical (Portion B) 214 214 EPC Package
HSE coordination with all around personnel at site,
Electrical (Portion C) 125 125 EPC Package
fogging around project location due to Ulubelu
TOTAL 2131 regency is classified into endemic malaria disease,
environment monitoring of project location regularly
Relating with Procurement area, there are about 127 to check temperature, poison gas, humidity and sound
packages consist of civil and subcontractor discipline, level. Organic and inorganic waste and Hazardous &
electrical discipline, mechanical discipline, toxic waste (limbah B3) are handled, and AMDAL
instrument discipline, piping discipline and process (analysis of environment effect) cooperate with local
discipline in head office. One package of head office university is also handled. Relation with local citizen
procurement usually require at least 5 vendors or should be conducted by Rekind to share positive
suppliers then totally at least 635 suppliers. There are impact with them.
some suppliers involved in some packages but not
many. Let say generally there are 500 suppliers
Rekind contribution means every work that is
dealing with Rekind in head office. Procurement area
involving Rekind and or do by Rekind autonomously.
is a work area much dealing with commercial
Due to evaluation of involvement in Ulubelu GPP
administration and paper work. Hence about at least
project within collaboration, percentage of Rekind
127 purchase order (PO) should be administered by
contribution is about 82%, regardless of value of
dealing with around 635 suppliers. This PO should be
work itself. This is not a surprising calculation result
controlled to maintain delivery schedule of material
due to trust from collaboration member and also from
procured. Some of materials are ready stock but
project owner is quite enough to generate the
mostly should be manufactured and fabricated. This
percentage. This percentage could drive other parties
control very critical due to material arrival are
to continue encouraging the local content including
necessary to be installed and constructed properly.
EPC business section. This achievement surely show
Procuring of material start is depending on
the capability and competency of Indonesian
engineering output while the fabrication is still
engineer in front of Indonesia people itself and
contributed by engineering to approve the drawing or
foreign partner.
data sheet of material fabrication of manufacturing.
Local production is considered as priority material
As a national EPC company, actually Rekind also has
due to obligation to achieve local content comply to
advantageous to provide major contribution in local
government regulation as will be presented more
content that is currently required by government
detail later. Transportation of material fabricated
regulation. According to Ministry of Industrial
could be from the whole world, mainly the material
regulation No. 4 year 2009, there are minimum local
or equipment that could not be manufactured locally.
content that shall be achieved in GPP project
Material with the weight more than 30 tons are
execution. Below is citation of the regulation
transported via Selat Panjang, its distance is about
attachment II article IV:
100 km to project location. Some of the material
“Amount of local content value of Geothermal Power
which has weight more than 30 tons are turbine,
Plant with an installed capacity above 10 up to 60
generator, demister, and power transformer.
MW per unit :
1. The minimum amount of local content of
Material arrival at site responsibility transferred to
goods for Geothermal Power Plant is 15,7%
Construction person. Material is storing in warehouse
2. The minimum amount of local content of
of installed straightly depend on the situation and
services for Geothermal Power Plant is
condition at site. Construction of Ulubelu GPP
74,10%
project should involve at least 1000 workmanship.
3. The minimum amount of local content of
This person is directly and concentrating to work
goods and services for Geothermal Power
with project at site.
Plant is 33,24%.”
This above local content value shall be achieved in called SAGS Project. To build Ulubelu GPP, PLN
Geothermal projects that Minister of Industry assign foreign company that is collaborating with
regulation has been prevailed. Execution of Ulubelu Rekind as a national EPC company.
GPP Project is also required to comply with above
regulation. Currently, the above regulation had been Ulubelu GPP Project is executed in EPC basis or
revised with the newer one issued on 2010 that is turnkey basis. This basis majorly constitute by three
Regulation of Ministry of Industry No. 48/M- section they are Engineering, Procurement and
IND/PER/4/2010. However, this revision is not Construction section. Duration to complete this
changing the local content value of a GPP project. project is 32 months, therefore the assigned
This is an advantage for Rekind as a national EPC collaboration should complete the project with their
company by usual supplying local materials and local own way. In the collaboration, each member shall
services to pursue local content value compliance share the work for all project assigned by PLN.
with the regulations. This contribution for local Rekind as a member of collaboration is shared the
content couldn’t be stated in early because the project work from beginning until completion of project.
at the present is under construction. But if we look
back briefly to the Kamojang 4 GPP project, local In Ulubelu GPP project at least three major Rekind
content provided by Rekind could achieve around contributions as national EPC company. Those are
41,3% for capacity of 60 MW. standard method integrated with company values as
proven in previous successful Geothermal projects
In addition to above contribution for standard method practically around 82% involvement of work shared,
for execution and pursuing of local content value, the competency to pursue local content as regulated
Rekind contribution is to handle community around by government, and implementation of effective
project as usually executed through Corporate Social CSR program that is so far has succeeded to run
Responsibility (CSR) program. This program is project execution specially in transmission and
already common to other company also, but refer to distribution scope smoothly. Coupled with
program that had been carried out in previous project contribution in SAGS scope by other national EPC
that Rekind CSR is almost always effective and right company then overall contribution of national EPC
on target. Community around project perceive benefit company in Ulubelu Geothermal field development is
and value added of Rekind presence around their very significant.
environment. As a national company, Rekind so far is
better to understand and comprehend the ACKNOWLEDGEMENT
environment. Even among other national company,
Rekind’s CSR program is being acknowledged by The authors wish to thank the management of Rekind
project owner that is almost always effective to target for their permission to publish this paper. The first
and perceivable by local community around the author gratefully acknowledges all team in SBU
project. This leads to the smooth and ensuring Geothermal & Power of Rekind and Ulubelu GPP
continuity of the project execution. Ulubelu GPP Project team for their fully support the author and for
project has scope of work in transmission and reviewing this paper.
distribution. This has potency of resistances and
conflicts from community around project executed. REFERENCES
There are many issues relating with transmission and Daud, Y., Sudarman, S., Ushijima, K., (2000),
distribution project. Health issues as impact of "Integrated Geophysical Studies of The Ulubelu
electromagnetic wave transmitted from transmission Geothermal Field, South Sumatera, Indonesia,”
line then could inflate to economic issues by Proceedings World Geothermal Congress 2000
downward price of land and property in areas around Kyushu - Tohoku, Japan.
transmission line. This potential had been handled so Suharno, Browne, PRL., (2000), "Subsurface
well through CSR program above then the project Hydrothermal Alteration at the Ulubelu
can run smoothly and so far is success to meet Geothermal Field, Lampung, Southern
contract requirements. Sumatera, Indonesia,” Proceedings Twenty-fifth
Workshop on Geothermal Reservoir Engineering
CONCLUSIONS Stanford University, Stanford, California.
Ulubelu Geothermal field is developed by PGE as Purwono, Novi A., (2010), "Comparison And
concession work area holder. Development scheme is Selection of A Steam Gathering System in
comprising of two section under PJBU, steam Ulubelu Geothermal Project, Sumatera,
supplying by PGE while other is power plant section Indonesia,” Geothermal Training Programme,
under PLN responsibility. PGE assign a national EPC Orkustofnun, Grensásvegur 9, IS-108 Reykjavík,
company to execute EPC project for steam supplying Iceland.
APPENDIX

Figure 2: Plot plan of Ulubelu Geothermal Power Plant Project

Figure 3: 3D Plot plan of Ulubelu Geothermal Power Plant Project


Figure 4: Photos of construction phase of Ulubelu Geothermal Power Plant Project

Figure 5: Overall Schedule of Ulubelu Geothermal Power Plant Project