Professional Documents
Culture Documents
Limited Project
Detailed Project report JAKEDA Department of science & Technology
Table of Contents
Part – I
Executive Summary
Hydropower is one of the prime resources of Jammu and Kashmir and the state
Govt intends to accelerate harnessing this potential as an integral part of its economic
development. vide Order No.10-PDD of 2017 dated 11.01.2017, Govt has enhanced
Jammu & Kashmir Energy Development Agency (JAKEDA) Hydro Power development
mandate from 2MMW to 10 MW to implement all Mini/Small Hydro projects up to 10
MW capacity in Jammu and Kashmir Province of the State. (JAKEDA) as a nodal agency
under Science and Technology Department shall be co-ordinating and promoting
development of these schemes and has planned to invite private entrepreneurs to
undertake hydroelectric power generation with fetching incentives allowed by the
Government of India and fully supported / reinforced by State Government. The nodal
agency through two tier tendering process has awarded the Dudhpathri SHP in favour of
M/s Rouf Infra Energy Pvt. Ltd. Company for implementation/Development under policy
referred hereafter. Small Hydro Power Program is one of the thrust areas of power
generation from renewable sources in the Ministry of New and Renewable Energy as it
has been recognized that these projects can play a critical role in improving the overall
energy scenario of the country and especially in remote areas of the state. The Ministry
is encouraging development of small hydro projects both in the public as well as in the
private sector.
3% interest subsidy would be payable on the working capital facilities available from the
commercial banks to IPPs for a period of 5 years initially from the date of allotment and
this will be reviewed after 5 years.
10% subsidy on capital investment subject to the ceiling of Rs.60.00 lacs would be given
in addition to the central subsidy for the power projects from 1 MW to 25MW after
successful installation & commissioning of the project.
Royalty @ 12% would be charged after the period of 10 years from the date of
commissioning of the Hydro Projects up to 25 MW capacities.
IPP would be eligible for central financial assistance as per the standing guide lines of
MNRE, GOI.
The projects awarded under this policy would be exempted from the “Water User
Charges” for a period of initial 10 years from the Commercial operation Date (COD) and
furthermore on the plea of Developers Forum, the matter has been taken up by the state
Government to provide relaxations for the projects involving Design discharge up to 25
Cumecs.
With these incentives the economics of Small and mini hydro-electric schemes
has substantially improved for public utility organisations and private entrepreneurs
proposing to take up such schemes. The development of energy from renewable
resources is a very important step in the reduction of CO2 emissions and also a heavy
demand of power in the country and in particular for Jammu and Kashmir has increased
the need to utilize renewable energy sources at a top priority.
It is proposed to develop a small hydro power project (Dudhpathri SHP as a run-
off-the-river scheme) on a small tributary of Shaliganga Nallah at Dudhpathri in District
Budgam. The various essential steps that have been followed to evaluate the proposed
scheme for its feasibility and successful completion do include Evaluation of the water
resource and its generating potential, Site selection and basic layout, Type and selection
of Hydraulic turbines and generators and their control, environmental issues with
mitigation measures, Economic evaluation of the project with financing potential, and
the detailed discussions with civil contractors and Electro- mechanical equipment
suppliers to obtain their necessary consents along with civil, electrical and mechanical
Some of the important features included in the Project report are enumerated as under:
All the minor issues relating to environment, related with the project have been taken
into consideration while conceiving the scheme including necessary release of
sacrificial discharge for aquatic life/irrigation requirement beyond Diversion site.
There is no. Submergence of any land at u/s of Head works even during floods.
JAKEDA has been in touch with Jammu and Kashmir Power Development Depart to
facilitate the infrastructure facilities for evacuation of power from such projects,
Though as per the requirement the proposed transmission line has been placed at
11KV but due to the system voltage and availability of receiving stations concerns in
Jammu & Kashmir, provisions in the project report relating to the cost of 33 KV line
and other connected items as such, have been taken care while framing the estimated
cost of Project.
CHECK LIST
Location
Geology
Have the geological surveys for Head Works power house and
tail-race etc been carried out for report on general
Geology of site of principal structures : appended
Foundation Investigation
Have the foundation investigation for the Major civil structure : Yes
and of the scheme etc. been carried out?
Hydrology and Meteorological Investigation
Hydrology
Have the provisions for land acquisition and resettlement been : Yes
considered?
Have the socio-economic problem seen : no such problem is anticipated
Design
Power Benefits
Have the following points been discussed?
i. Total energy production & installed capacity of the grid system Production generated shall be
& How does the scheme fit into Existing system? fed in the existing grid at Arizal
ii. Energy generation from the generation Projects firm power, : estimated annual Gross energy
seasonal Power and total power. based on 90%, 75% and 50%
dependable years shall be 28.01,
30.50 and 31.66MUs
iii. Proposal for transmission and /or Connection to the existing : The transformer located in the
system Etc (wherever applicable) project switchyard shall be
connected to the Arizal sub-
station of JKPDD Via proposed
10 km long transmission Line
supported on steel poles.
iv. Cost of project per KW of installed per generated as compared : Cost of project per KW installed
to the various Micro-Hydel Project & various services. is Rs 90000/-The project is
economically viable.
Construction Program
Estimate
Have the analysis of rates for various Major items of work prepared upon the analyzed
Is the area likely to have any environmental and ecological : Not applicable
problems due to the altered surface water pattern and
preventive/corrective measures discussed? (Wherever
applicable)
Camps and Building,
Has the planning of the camps/building been done : Yes
Soil Conservation
cm - Centimetre (s)
mm - Millimetre(s)
Km/hr - Kilometre per Hour
Cumecs - Cubic meters Per Second
Cusecs - Cubic Feet per Second
m3/sec - Cubic metres Per Second
Sq.km -Square Kilometres
NA - Not Applicable
MDDL -Minimum Draw Down Level
HFL - Highest Flood Level
EL - Elevation (Above Mean Sea Level)
0C -Degree Celsius
RCC - Reinforced Cement Concrete
RD - Reduced Distance
FSL - Full Supply Level
DPR - Detailed Project Report
U/S - Upstream
D/S - Downstream
GTS - Great Trigonometrically Survey
G-D - Gauge –Discharge
T&P - Tools &Plants
IDC - Interest during Construction
Rs - Indian Rupees
O&M -Operation and Maintenance
% -Percent
WDV - Written Down Value
SLM - Straight Line Method
LS - Lump Sum
IRR - Internal Rate of Return
PBDT -Profit before Depreciation &Taxes
DSCR - Debt Service Coverage Ratio
SALIENT FEATURES
1. Location
ii District Budgam
2. Geographical Coordinates
D/B 74°33'6.81"E
33° 50'30.25"N
F/B 74°33'36.24"E
33° 50'50.47"N
P/H 74°33'47.15"E
33° 50'49.55"N
3. River Catchment
ii Nallah/Stream Shaliganga
4. Hydrology
Catchment area of Nallah up to Diversion
i 70 Sq-Km
Weir site
ii Climate Data :-
a) Max. 30 0C
Weir
iii. Width 2m
9. Forebay
iv. Size
a) Length 45.00 m
b) Width 6.1 m
10. Penstocks
i. Number 1 No
a) Gross 157.96 m
b) Net 153.51 m
v. Turbines :-
b) Number 2 no.
12. Tailrace
13. Power
iii. Size :-
ii. Length 10 Km
PART I
Chapter 1
Introduction
1.0 Introduction
1.1 Hydro power is a renewable, economic and non-polluting source of energy. Hydro
power stations have inherent ability of quick starting, stopping and load variations offering
operational flexibility and help in improving reliability of power system. Hydro stations are
the best choice for meeting the peak demand. The generation cost is not only inflation free
but reduces with time. Hydroelectric projects have long useful life extending over 50 years
and help in conserving scarce fossil fuels. They also help in opening of avenues for
development of remote and backward areas. Development of hydro power resources is
important for energy security of the country. It is therefore necessary to prepare a long term
plan of hydropower development.
Central Electricity Authority (CEA) has already covered planning of hydro power projects
during 11th & 12th Plan period. This is one of the major sources of energy throughout the
world and is considered to be a cheapest option. India is particularly interested in this source
of power.
The first systematic and comprehensive study to assess the hydro-electric resources in
the country was undertaken during the period 1953-1959 by the Power Wing of the erstwhile
Central Water and Power Commission. This study placed the economical utilizable hydro
power potential of the country at 42100 MW. The Reassessment study completed in 1987
revealed that the Hydro Electric Power Potential of the country was of the order of about
84,000 MW. In the 11th Plan of Hydro Development a capacity addition of 78,700 MW
comprising of 59,693 MW from thermal projects, 15,627 MW from hydro projects and 3380
MW from nuclear projects was approved during the 11th Plan period. Out of 15,627 MW
hydro projects, 8654 MW was proposed in Central Sector, 3482 MW in State Sector and
3491 MW in Private Sector.
Latest as per the studies carried out by CEA to assess the requirement of additional capacity
during the 12th Plan (2012-2017), the requirement of installed capacity to meet the all India
peak demand and energy requirement at the end of 12th Plan would require a capacity
addition of over 90,000 MW in the 5 years period of 2012-17. In pursuing low carbon growth
strategy, it would be our endeavour to maximize exploitation of hydro power potential. This
is also necessary for energy security of the country. Availability of Hydro Projects for benefits
during 12th Plan
To meet the requirement of additional capacity during 12th Plan(2012-17), a shelf of 109
candidate hydro projects aggregating to30920 MW under Categories ‘A’ and ‘B1’ having
higher level of confidence for realizing benefits during 12th Plan, based on their present
status of preparedness, has been finalised. List of these schemes is given at Annexure 1.1.
The status of these projects (sector-wise) State-wise (sector-wise) break up of identified H. E.
Projects for benefits During 12th Plan is given below:
Annexure 1.1
S.no States Central Sector State Sector Private Sector Total
No MW No MW No MW No MW
1 Himachal 2 816 7 892 6 749 15 2457
Pradesh
2 Jammu & 4 2450 4 1473 0 0 8 3923
Kashmir
3 Uttarakhand 12 4370 7 1655 5 829 24 6858
4 Punjab 0 0 1 168 1 75 2 243
5 Madhya 3 166 0 0 0 0 3 166
Pradesh
6 Andhra 0 0 3 1560 0 0 3 1560
Pradesh
7 Kerala 0 0 6 373 0 0 6 373
8 Karnataka 0 0 2 400 0 0 2 400
9 West Bengal 1 120 2 66 0 0 3 186
10 Sikkim 1 520 0 0 10 1935 11 2455
11 Arunachal 3 1610 0 0 23 7969 26 9579
Pradesh
12 Assam 0 0 1 150 0 0 1 150
13 Manipur 2 1566 0 0 0 0 2 1566
14 Tamil Nadu 0 0 1 500 0 0 1 500
increasing power demand of the state in particular & the Northern region whole in general
need to be picked up fast.
Total Generation capacities in the state build so far.
Annexure 1.2
STATE SECTOR
Anantnag 2x3+2x4.5 15
Karnah 2x1 2
Chenab Basin
Chennai-II 2x1 2
Bhaderwah 2 x 0.5 1
Ravi Basin
Sewa-III 3x3 9
Indus Basin
Igo-Mercellong 2x1.50 3
Haftal 2x0.50 1
Stakna 2x2 4
Total 759.2
CENTRAL SECTOR
Total 1560.0
Annexure 1.3 Projects being taken up for the development in State/Central Sector.
Estimated Capacity (
S.No. Name of the Project Name of the Basin
MW)
Ujh
10. Multipurpose Ravi 280
Project
PakulDul
11. Chenab 1000
(Central Sector)
Bursar (Central
12. Chenab 1020
Sector)
Kishenganga
13. Jhelum 330
(Central Sector)
Name of the
S.No. District Capacity MW
Project
10.00
2. Athwatoo Bandipora
(commissioned)
1.3 JAKEDA
JAKEDA has invited various agencies to bid for identified projects for the development of this
sector. These will be termed as Independent Power Producers (IPP). These would include any
of the private sector entities, central power utilities, state governments or any other
government entities and their joint ventures. The Projects have been reserved for execution
by IPPs that are permanent residents of State of Jammu and Kashmir. This would include
such IPPs in which permanent residents of J&K hold majority stake. This condition shall,
however, be relaxed, in case the bidding process of the projects so reserved does not result in
adequate & competitive response. The eligibility of the interested parties is being evaluated
on the basis of pre-qualification criteria. Proposals of only those parties are being considered
for bidding who qualify the pre-qualification criteria.
With the incentives allowed by the Government of India and fully supported / reinforced by
State Government, the private sector has been invited to participate in Mini hydro power
development in the State. The State has decided for selective privatisation of its hydro-
electric potential. The state because of its mountainous topography, snow covered ranges,
many major rivers with large numbers of tributary streams, possesses vast hydroelectric
potential for schemes of all magnitudes, large and small.
MOU’s are being signed by the JAKEDA with private entrepreneurs for development of more
than 100 sites of Small/Mini Hydro projects. Dudhpathri SHP, for which this Detailed Project
Report has been prepared, is one of these. It is a scheme envisaging development of the
hydroelectric potential available on the Shaliganga Nallah, a tributary of River Jhelum, in
Budgam district of J&K state. The features of this stream had earlier been identified by the
JAKEDA as suitable for Mini hydro power development and now the revised project report as
desired by the Developer has been prepared ensuring all technical and financial viabilities as
are in vogue and befitting the given situation.
1.3.2 The Project will be developed by M/S Rouf Infra Energy Private Limited, a company
registered under Companies Act 1956, in year 2012 headed by
Rouf Infra Structures Pvt limited was specially formed in 2012 to carry on infrastructure
related work in J&K which involved the Kupwara-Handawara Bye-Pass Road contracts along
with other projects. Most recently company has ventured into the hydro power sector with
project allotted by JAKEDA for the development of the small hydro power plant . Since the
company’s inception, it has been growing at a rapid pace across all parameters of growth
and is on a steady course to becoming one of the most reputed and socially responsible
companies of the valley. The management structure of the company involves directors who
are highly motivated.
1.4 Location
DudhiPathri SHP scheme has been identified as a run of the river scheme on Shaliganga
Nallah at village Dudhi Pathri. Proposed Power House is located at village Dudhi Pathri on
Khan Sahib/ Dudhi Pathri road. The site is 17.5 km away from Tehsil head quarter Khan Sahib
and 34.5 km from District head quarter Budgam and 45 Km from Srinagar. Dudh Pathri small
hydropower project is one of the sites identified by JAKEDA for harnessing the hydro
potential of the Kashmir region. The location of the Dudh Pathri SHP and adjoining villages is
shown in the site plan. The scheme proposes to generate 30.50 million units of power in a
75% dependable year. The installed capacity of the scheme is proposed to be 6000 KW from
4.60 Cumecs of discharge with 153.51 m net head.
Shaliganga is primarily a snow melt based stream with some contribution from rain
falls during some months of the year which improves seasonal flows. The duration curve of
the assessed flows in a 75% dependability year is shown in figure 3.2 which gives the
characteristics of the flow. Very lean monsoon flow and substantial summer flow is received
over nearly 35% of the year followed by a 'knee zone' leading to much lower level of dry
season flow over nearly 35% of the year. A comparative examination has been made of the
energy generation possible with different installed capacities and corresponding different
values of installed capacities. Table 4.2 to 4.4 which give the details of energy generation
possible in years of 50%, 75% and 90% dependability for utilisation with some selected
design discharges and corresponding installed capacity.
A comparative examination has been further made of the energy generation with different
installed capacities in Table 4.5. The stream discharge in a year of 75% dependability have
been taken as representative of long term average discharge (in representative range of
values) for carrying out the optimisation studies. the maximum available discharge as per
this series is 6.44 Cumecs and if all available discharges of 75% year up to this maximum
value were to be utilised, the maximum restricted average generation will be 30.50 MU. The
energy generation corresponding to different installed capacities are summarised in the
proceeding tables.
house location of slightly flatter terrain is available on left side of the Nallah. As per the
contour map of the area, it has been found that the optimum advantage is obtained by
location of the reach with diversion weir at El 2960.0 m and power house at an elevation EL
2802.0m. The modifications to the earlier project report were desired by the developer keeping
in view to safe guard the project with respect to the discharge and head that shall be adopted
for designing the scheme in conjunction to the financial viability within the overall power tariff
scenario of the country. After a review of all these factors, a weir site at new location which is
around 500 m upstream of previous diversion site and power house site at El 2802m was
chosen to have benefits by way of exploring additional length of Nallah which has resulted in
enhancement of generation capacity from 1.6 MW to 6.0MW.
choked up under in particular stream having narrow widths. Since diversions are interference
to natural flow regime of the river, the extraction of water changes the flow conditions
downstream of the intake. Undesirable sediment deposition occurs downstream of weir
when too much water is extracted. Conversely, severe erosion downstream of the diversion
occurs when remaining river flow passing downstream is carrying less sediment than its
transport capacity. Moreover, any structural component that protrudes out of the river-bed
(like top of a weir) can get damaged easily by the force of large sediments rolling down with
high velocities during floods due to Stream being narrow and steep.
As such to overcome the above problems associated with raised-crest weir, the most
common type of weir adopted in such boulder streams for MHP was found trench weir. This
is a weir by way of having a Reinforced Cement concrete Trench almost throughout width of
stream. The top of the weir is covered with bottom rack bars, Water while flowing over it,
passes through the bottom racks and enters into the trench and collected in an intake well
located at left bank at the end of the weir. The top edge of the diversion weir has almost
been flushed with the natural bed slope of the stream. The bottom racks shall be consisting
of heavy flat steel bars laid on edge over structural steel Z piece members securely fixed in
concrete side walls and placed parallel with the river flow on the bed level. The bottom rack
bars have been proportioned to carry the weight of the heaviest boulders that are likely to
flow down during the maximum probable flood.
This type of weir has the definite advantage as it does not affect the general bed level of
the stream. Post-Flood clearance of the boulders and debris collected in the trench of the
weir may be found obligatory. It needs to be mentioned here that in spite of the annual
maintenance requirement, this type of weir has been widely adopted in the SHP/MHP
schemes, built in Arunanchal Pradesh, Sikkim, Himachal Pradesh, and Uttaranchal and in few
projects of J & K.
The estimated peak discharge using various methods and take the most
reasonable of them as design discharge for trench weir for a conservative design. Flow in the
stream at its different stages is analysed using the Manning’s equation with appropriate
value of rugosity coefficient along with Flows over broad crested weir. Water while passing
over the bottom rack, enters into the trench due to gravity and remaining flow in the
downstream of the trench in the streams beyond the required discharge max as designed
flow. The flow in the stream with bottom rack is a case of spatially varied flow with
decreasing discharge. The rack is made of parallel bars in panel form with Fixed to MS
channels placed along the direction of flow. Main variables involved in computing the
diverted discharge into the trench are flow characteristics of the stream, geometry and
dimension of the rack, free and submerged flow conditions etc. The racks have been placed
inclined with reference to the approach bed of the river. The inclination of the rack, which is
normally of the order of 1 in 10, is provided at a reasonable slope as per site conditions to
facilitate easy movement of bed load of stream moving over the rack.
It has been assumed that the specific energy of flow shall be constant all over
the longitudinal bottom rack, and from the structural consideration, flat bars have preferred
over rounded bars as flat bars have more flexural rigidity. There is considerable effect of
ratio of thickness of bars t and their clear spacing, i.e. t/s and inclination of bars, the value of
Cd increases with increase of t/s ratio; however, it decreases with the increase of inclination
of bars (SL) for constant value of t/s ratio. Thus for the design flat bars have been adopted.
arrest the entry of the shingles moving along the bed of the trench weir into the inlet
channel. Near this end, the trench weir bed has been given a curved profile to facilitate
rolling down of the bed load (shingles) into a pit. A 1000 mm wide lip, in the form of a
projecting slab may be provided to prevent shingles and other particles collected in the pit to
enter the Feeder Channel. From time to time, shingles accumulated in the pit will be flushed
back into the stream through a shingle flushing MS Pipe of 700 mm diameter, provided at
about right angle to the trench weir axis. The pit may be provided with a slope of 1:11
towards the flushing pipe.
The flushing Pipe also has a slope of about 1 in 40, which is considered to be adequate to
generate non-settling velocity for particles up to 30 mm size. The flushing channel runs along
the left bank of the Stream for a length of about 45m before it discharges back into the
source stream, at about El 2955.90.
To facilitate intermittent flushing, a- 1 m x 1.0 m (H) gate is provided in the shingle flushing
channel. The gate will normally be kept closed and will be fully opened to flush the shingles.
The gate will be operated using a Chain pulley arrangement. A 0.6 m x 3.0 m opening in the
hoist floor slab provides access to the intake bed. It may be noted that, the water conductor
system is on surface; all the structures will be of cut-and-cover type in adjacent to Intake
structure. The maximum flow which shall pass through the intake shall be 6.44 Cumecs.
water as 1.6m. Freeboard in the tunnel will be 0.4m, which shall accommodate 10%
overload flow easily.
Most of the Himalayan Rivers and rivulets carry a lot of sediment during Rainy seasons and
some times during periods of heavy snow melt. For run-off-the-river plants located on such
streams, it is essential that a de-silting arrangement be provided to trap and exclude
sediment particles in excess of a selected size so as to minimize damage to underwater
turbine components.
The maximum particle size needed to be excluded from the diverted water before
channelized into the water conductor system and finally leading to the turbine is directly
linked to the potential wear of turbine parts due to sediment abrasion, which depends on the
following factors:
• Hardness of particles
• Size of particles
• Shape of particles
• Turbine head
While the conventional settling basin has almost always been employed as preferred de-
sander in hydroelectric projects, use of vortices for removing sediment load from water has
largely been restricted to irrigation projects, with very limited application in hydroelectric
projects. In recent years, merits of using vortex tube type de-sanding arrangement at hydro
project with small design discharges have been recognized and they have been employed at
few hydroelectric projects in Himachal Pradesh and are also being considered at few other
projects.
Between the two settling type basin arrangements, the Du-Four type is not found suitable at
places. Design calculations show that the length of Du-four type de-sanding basin is more
than the single bay hopper type arrangement and does not suit the topography of head
works area. The structure will extend into higher natural ground and would entail
significantly higher quantity of excavation.
Design calculations for the conventional hopper type basin arrangement are presented
hereafter. The system would have the following characteristics.
One settling basins is provided to improve reliability and enhance operating flexibility, basin
in the form of rectangular tank and provided with sectional area to reduce the velocity of
flow comprising of bed raft laid at 45 degrees each , with a total length of 61.25 m on either
side of the tank inclined towards gutter at the centre of De-silting Basin. This bed raft has
been considered below the water level of full supply depth adopted in tank to slip all silt
contents into the gutter. The Gutter shall be provided with 2% bed slope which is found
sufficient to carry the silt particles along with flushing discharge.
• The flow through velocity in the tank has been taken as 0.2 m/sec.
• The settling velocity for 0.2mm size particle is taken as 2.5 cm/sec at 0º C (the water in the
stream is mostly from snowmelt.)
• The flushing discharge is taken as 20% of the plant discharge. And mostly the operation shall
be required during period when discharges are high in the stream as otherwise silt content in
the stream is found to be in significant.
• In order to dispense with the conventional 90ᶿ bend in flushing pipes (which makes it difficult
to clean in case of choking of the pipes), a 0.8m wide and 1.0m high flushing gallery with a
silt flushing channel (cunette) is proposed at the end of Gutter which will be laid
underground. The flushing flow will remain concentrated in the silt flushing channel.
A RCC single Bay underground De-silting basin has been proposed at RD 139.55
m to 200.80 m including U/S and D/S transitions. It has been designed to remove 0.20 mm
and above size particles to avoid its entry to Forebay and Turbines. The size of the main Tank
shall be 45m x 6m x 4.68m with upstream Transition of 8.25 m. However the overall depth of
tank is 6.68 m with Flushing duct at a 2% slope to flush out the silt. The silt finally shall be
carried 600 mm dia. MS pipe to the main stream at an elevation above HFL therein. The
flushing pipe shall be provided with 600mm dia. Sluice valve for its operation. It has been
assumed that during lean seasons the operation shall be minimal. The Design Discharge for
the Tank shall be taken as 5.52 Cumec.
Like Intake Tunnel, the Head race Tunnel is proposed beyond the De-silting Basin with D-
shape to provide a rectangular section for flow of water having 0.4 m free board and semi
circular Crown. Free board shall absorb the 10% extra discharge required for over load
capacity of power plant machinery, HRT shall be provided with Plain cement concrete lining
covering raft and side walls including freeboard,, However the crown part of the tunnel shall
be provided with shotcrete of 50mm thickness. Tunnel has been provided as an appropriate
section keeping in view the topography and other features of the reach through which open
channel could not be made possible due to terrain being very steep. The HRT shall have a
length of 1064 m up to Forebay. The Design discharge for HRT shall be 4.6 cumec. The Bed
width shall be 2.25 m and the full supply depth 1.6m.
1.4.2.6 Forebay
The Forebay tank has been adopted as simple RCC Rectangular section. It will have an overall
depth covering minimum water seal required to avoid any vortex formation in the tank.
Further the tank is provided with sufficient bottom seal under the bell mouth in Forebay pool
to prevent entry into penstock of any undue material that may go into Forebay including
provisions for silt depositions. The tank has the basic purpose of absorbing the fluctuations in
the water supplies providing cushion for sudden tripping of the machines. The Forebay is
designed for a storage capacity time of 2 minutes with live storage full supply water level
and minimum draw down water level. The design discharge for Forebay shall be 4.6 Cumec.
The Forebay is provided with an Intake gate arrangement to control flow into Penstock as
per the size of Bell mouth, the hoisting arrangement will be of Double Rope drum electrically
as well as manually operated. Besides provision for removal of silt accumulated in the
Forebay pool has been kept by way of providing 300mm diameter MS pipe with control
arrangement of same diameter Sluice valve. The silt flushing pipe shall be dropped directly
into source Nallah.
The average width available for the Forebay from the toe of the excavated slope on the hill
side is limited to an excavated depth of 4 m to 8 m at an appropriate location on the valley
side where ground level is not lower than the floor level of the Forebay. The sill level of the
intake has been fixed on the basis of requirement of water cushion above the intake opening.
Retaining walls forming the intake structure connect to the excavated slopes to form the
Forebay. The retaining wall has a maximum height of 7.0 m. The Forebay is lined with
Reinforced cement concrete. The Forebay intake is provided with a bell mouth opening for
the penstock and would be of RCC construction. An earth fill cover has also been provided on
the downstream of the retaining walls of the Forebay. LDPE film sheets may be used for the
walls and sides of the Forebay structure to serve as a water proofing membrane. The
excavated hill slope behind the Forebay is also proposed to be stabilized without causing any
damages to an existing road passing nearby to Forebay site on hill side. Further these
safeguards are done as an abundant measure of caution to minimize distress due to seepage
Dudhpathri SHP Project ( 2 x 3 MW) Part I Page 19
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
and provide additional stability for the critical Forebay structure. The FSL of the Forebay is EL
2957.46 m and the surplus escape located near the Forebay comes into operation to release
the discharges during the sudden rejection of the load by the turbines.
A sharp crested Escape Bowl stands provided in Forebay for collection of any over flows during
emergency shutdown or for other reasons. The collected water shall be taken to source Nallah
nearby through proposed MS Pipe arrangement. Individual part of forebay is proposed to be
of size 45m x 6.1m, having an overall depth of 7.0 m.
1.4.2.7 Penstock
Single line Penstock with 1200 mm diameter and 8 to 14mm thickness MS Plates having
symmetrical bifurcation at the lower end of 850 mm diameter for feeding two machines in
the powerhouse has been proposed. The penstock shall be exposed and is made to rest on
saddles with anchor blocks at any change of alignment. Since the penstock is exposed as
such expansion joint of approved brand shall be placed at each down side end of anchors.
The Y piece bifurcation shall be laid in plain with proper anchor block as shown in drawing.
1.4.2.8 Powerhouse
The proposed power house has been placed at relatively flat and stable terrace with turbine
centre line level 2799.5m. The Power house shall be of RCC framed structure with brick work
in form of panels in walls. The power house is surface type with Bed Raft/Floor of Reinforced
cement concrete M20 grade. Walls of power shall be of RCC 0.6m above maximum tailrace
water or backfill level. A single leaf gate shall be provided for 2 number openings with chain
pulley arrangement for lifting. The power house shall have to be safe guarded by providing
flood protection Bund. The power house building has been dimensioned in such a way so that
full space is utilised for accommodating two number units of 3.0MW each along with
connected arrangements of Hydro mechanical and Electro mechanical equipment’s and the
structure has been divided into three parts i.e. service bay , Machine hall and Control room
with HT/LT room. The battery bank has also been provided adjacent to Control room and
further more office and on one number wash room has also been adjusted as well.
A control room housing all the electrical panels required for the operation of the units
including HT and LT Panels.
An unloading bay and service bay.
Annexe space and auxiliary space for auxiliary equipment
Transformer deck.
Outdoor switchyard.
The centre of turbine is fixed taking into consideration of the hydraulic parameters of the
horizontal Pelton type turbine and the minimum/Maximum tailrace water level has been
provided accordingly with respect to the bottom level of Turbine casing. The floor layout is so
designed to accommodate the trenches to run the power cables from the generators to the
control panels in the control bay. One number E.O.T. crane 28T capacity is provided in the
power house with facility to operate in longitudinal and transverse directions, to handle the E
and M equipment during construction as well as operation stages.
M/S Rouf Infra Energy Private Limited has been allotted implementation of Dudhpathri SHP.
The objective of this Detailed Project Report (DPR) is to study, evaluate and establish the
technical feasibility and economic viability of the proposed SHP. During detailed study for the
purpose, it was revealed that in view of the tourism department’s observations, the Weir had
to be shifted upstream and the final alignment worked out thus suited an underground
water conductor scheme in place of an surface water conductor channel. Under the
circumstances, the DPR was required to be revised and as such the same has been got done
by the developer which envisages that the proposed Headwork’s shall be Trench type weir
with 300m long penstock.
1.6.1 Location
The Powerhouse site is located on left side of Nallah Shaliganga at Village Dudhpathri at the
end of Srinaga-Budgam-Khansahib-Dudhpathri road, 17.5 Km from Tehsil headquarter
Khansahib and 34.5 Km from district headquarter Budgam. The powerhouse site shall be
approached through an extension of 0.5 k m approach from the existing road which needs to
be constructed.
1.6.2 Communications
The project site shall be directly connected by the link road discussed above. During the
construction of the project; existing path from Powerhouse to Forebay and to Headwork’s
shall be strengthened for uninterrupted access to all components. The proposed headwork’s
is presently approachable from the main road through a bridle path. As such new access
road is needed for the Headwork’s.
The project area is sparsely populated with the people mainly involved in agriculture
activities. The population of Dudhpathri and its nearby villages is 5000. The resources of the
area are mainly green virgin forests clustered with Kail and Fur trees and deodar in upper
catchment area. The per capita consumption of electricity in Jammu and Kashmir is low and
is far below the national average of 270 kW.
The standard of living of people and status of industrialisation of the state largely depends
upon the extent of the usage of electricity. In order to achieve higher per capita
consumption of electricity, concerted efforts are being made by the Government of J&K for
enhancing substantially the power generation both in medium and large size hydro schemes
as well as in several small size hydro schemes. The share in mini and small schemes has not
been significant. With the availability of more funds for various development works in the
backward and hilly regions in the state, there has been gradual increase in the use of
electricity for various purposes including starting of cottage industries based on local
produce and such other industries which have special significance considering the climatic
conditions and availability of labour at economic rates. As a result, the utilisation of
generated potential shall improve considerably.
The central focus of the state planning is to ensure that the needs of the ordinary people
are met and the quality of their life, especially in the rural areas like this place, is improved.
The state plan seeks to promote rapid overall development and diversification of the
economy and also to strengthen the infrastructure base especially in the hilly region and far
flung areas where the pace of development has been very slow. The implementation of
DudhPathri SHP scheme in the backward interior region of Khansahib Tehsil and surrounding
area will greatly improve the infrastructure and communication facilities and as a result, the
local economy will get the much needed boost thereby improving the quality of life of the
rural mass. Moreover this scheme will have negligible environmental effect and minimum
disturbance to population and other related factors.
Both skilled and un- skilled labour is available locally in the nearby villages. Particular skilled
workmen and technicians for various important works at the power house, Forebay and
diversion weir intake, penstock etc, are not likely to be available in and around the project
area and may have to be brought from the other parts of the state or neighbouring areas.
1.6. 4 Topography
The source Nallah viz. Shaliganga Nallah joined by other small sub-tributaries of the
catchment forms one of the major tributaries of River Jhelum. It starts from Mountain peaks
having latitude of 33ᶿ45′0.01″E and Longitude 74ᶿ28′0.05″E and elevation of 4694 above
MSL. The Shaliganga Nallah is perennial flow Nallah fed by glacial / snowmelt. The Nallah is
flanked by steep mountain slopes on either side or traverses through Dudhpathri and other
nearby villages of negotiating a length of 12.93 Km up to headwork's site. The bed gradient
of the Nallah is fairly steep encountering a number of rapids in negotiating a fall of 1734m
up to Headwork’s Site.
Catchment area up to the project site is of the order of 70 Sq. Km. The portion above
the winter snowline of elevation 3500 m feeds the Nallah by snow and glacier melt.
Minimum discharge in the Nallah occurs during December, January & February. Relatively
high flows during summer months are contributed by snowmelt as well as rainfall in the
catchment.
1.7 Climate
The climate of Jammu and Kashmir varies greatly owing to its rugged topography. In
the South in the Jammu region the climate is typically monsoon very hot and can reach up to
45°C. In the Jammu region towards North-west in the lap of the Pir Panjal range South Asian
monsoon is not longer a factor and most precipitation falls in the spring from Southwest
cloud bands. Annual average rainfall of Dudhpathri region is taken as 1200 mm with winter
precipitation falling in the form of snow depending upon altitude and other meteorological
conditions. As the catchment is located in high altitudes the maximum temperature does not
go beyond 300C, the winters being severe with minimum temperature of -150C.
1.7 Hydrology
For correct estimation of hydrology and selection of proper site for the power plant,
especially in case of a hill schemes, about 15-18 months time are required for recording the
discharge of two seasons. For the purpose of preparation of the Project Report and with a
view to reduce the duration of project development, lean discharge is calculated by
correlation of the discharge data having similar geographical and geological features based
on the catchment area.
DudhPathri is a perennial Nallah starting from an attitude of 4694 m above MSL
and is joined by a number of small tributaries. The precipitation in the area is seasonal/flashy
rainfall during summer and spring: The run-off contributed by melting of snow starts
increasing from April and gradually reaches its peak in the month of July and August. This
gradual increase in the runoff from April to August coincides with the increasing trend of air
temperature. In October the discharge starts diminishing and by the remaining months of
the winter, the discharge fluctuates and shows a minimum discharge sometime in the month
of Dec and Jan.
Due to low winter temperatures, the glacial sources of the Nallah freezes.
However, the water continues to flow underneath. Total catchment area of the Nallah up to
the proposed diversion site has already and previously has been established to b 70 Sq Km.
This has been confirmed by satellite imagery and internet maps. Discharges at Head works
site stand recorded for the minimum required period with help of a temporary Gauge.
Dudhpathri SHP Project ( 2 x 3 MW) Part I Page 25
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
About 48 months discharge data has been used to formulate the project report. Firm
discharge series of this period has been used for dependability and optimization calculations.
During the stage of execution, the hydro- logical data series will have to be updated by the
Developer. For computing the dependability of the discharge, the ten daily mean discharges
have been tabulated and unrestricted energy has been calculated.
The 10 – daily discharges of the 75% dependable year have been used to arrive at the
optimum and the best beneficial installed capacity of 6.0 MW.
1.11.1 Needs
Inadequate power infrastructure has been the major factor for the underdevelopment of
the State. The local area of DudhPathri is economically backward with no industrial
Dudhpathri SHP Project ( 2 x 3 MW) Part I Page 26
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
PART I
Chapter 2
PART I
Chapter 3
HYDROLOGY
3.0 HYDROLOGY
3.1 General
Shaliganga Nallah is a small tributary of River Jhelum and the hydrological study of the
Nallah has been carried out in order to assign the design discharge for determining the
optimum Power potential of the scheme, to work out the design flood discharge and other
related hydrological issues in respect of the DudhPathri SHP.
3.2 Shaliganga Nallah
The stream called as “Shaliganga Nallah” is one of the tributaries of river Jhelum. The
Nallah is Glacier melt and is found perennial. The Nallah is flanked by hills and valleys on
either side and is devoid of any vegetation. Upper catchment area is mostly under snow.
The bed gradient of the Nallah is fairly steep encountering a number of rapids in
negotiating a drop of 1734m up to Headwork’s Site. Catchment area up to the project site
is of order 70 Sq km. The lower slopes are under dry crop cultivation. The portion above the
winter snowline of elevation 3050m feeds the Nallah by snow and glacier melt. Minimum
discharge in the Nallah occurs during December, January & February. Relatively high flows
during summer months are contributed by snowmelt as well as rainfall in the catchment.
3.3 Catchment Area
The catchment area comprises high and steep mountains with elevation varying from
EL 4694 m to EL 2960 m at Dudhpathri village. It starts at latitude 33ᶿ45′0.01″E and
Longitude 74ᶿ28′0.05″E. The source of Nallah is glacier melt. Upper catchment area is
mostly under snow.
The catchment area up to 3200m is covered under fir and birch forests. The
lower slopes are under dry crop cultivation. The portion above the winter snowline of
elevation 3200m feeds the Nallah by snow and glacier melt. Minimum discharge in the
Nallah occurs during December, January & February. Relatively and considerable high flows
during summer months are contributed by snowmelt as well as rainfall in the catchment.
3.4 Precipitation
Precipitation is in the form of snowmelt during winter months and some rainfall during April
to June and November months. The water from this Nallah is free from any uses for water
supply (drinking) in the project reach i.e.; from Headwork’s to downstream of the proposed
powerhouse.
Dudhpathri SHP Project ( 2 x 3 MW) Part I Page 32
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Table 3.1
73.10 128.00 115.00 33.20 66.60 35.90 174.40 224.60 273.00 17.90 176.60 89.8 99.18 115.94
1 Jan
156.50 106.70 65.70 73.20 138.40 224.40 83.00 360.60 128.90 96.20 124.80 122.2 86.76 135.95
2 Feb
136.30 160.10 123.30 81.10 170.50 316.20 23.40 152.40 109.90 328.40 21.70 135 112.5 143.91
3 Mar
146.30 59.70 70.60 117.80 121.70 177.80 171.80 112.70 105.50 14.80 118.50 130 101.52 111.44
4 Apr
158.00 79.00 57.40 80.50 64.00 142.20 75.80 125.00 44.30 56.80 111.70 150 130.5 98.09
5 May
66.80 40.20 106.70 118.70 107.80 39.40 85.50 44.30 83.60 124.90 73.90 110.4 86.04 83.71
6 Jun
128.30 109.80 142.60 158.10 57.10 100.50 74.40 137.60 142.60 72.30 77.90 135 112.5 111.44
7 Jul
60.40 97.40 89.10 109.60 88.60 138.50 92.80 45.30 194.40 107.90 94.30 80.5 99 99.83
8 Aug
101.00 57.20 87.20 53.10 153.20 155.60 49.80 42.90 155.70 62.10 66.30 75 94.5 88.74
9 Sep
45.90 11.40 0.80 35.80 17.20 32.10 77.90 28.50 43.90 1.80 37.70 42 31.5 31.27
10 Oct
2.60 125.30 27.40 92.80 2.00 33.70 38.10 22.40 91.70 0.00 38.40 25.2 26.1 40.44
11 Nov
0.00 0.00 36.10 66.90 15.00 86.60 29.70 4.40 141.20 38.10 96.40 45.4 67.68 48.27
12 Dec
Annual 1075.2 974.8 921.9 1020.8 1002.1 1482.9 976.6 1300.7 1514.7 921.2 1038.2 1140.5 1047.78 1109.029
TABLE 3.2
MONTH RAINFALL MM
Jan 115.94
Feb 135.95
Mar 143.91
Apr 111.44
May 98.09
Jun 83.71
Jul 111.44
Aug 99.83
Sep 88.74
Oct 31.27
Nov 40.44
Dec 48.27
ANNUAL 1109.03
TABLE: 3.3
1514.7
1 7%
1482.9
2 14%
1300.7
3 21%
1140.5
4 29%
1075.2
5 36%
1047.78
6 43%
1038.2
7 50%
1020.8
8 57%
1002.1
9 64%
976.6
10 71%
974.8
11 79%
921.9
12 86%
921.2
13 93%
Therefore,
1038.20
50%Dependable Rainfall
Which is , 0.94
Which is , = 0.888 mm
Comparison of annual rain fall for year 2010 with annual rain fall of 50%
Dependability the annual rainfall recorded in the year 2010 is the same as the annual rainfall
with 50% dependability, the annual rainfall in 2010 shown in table may be considered to
represent monthly rainfalls of 50% dependability.
Table 3.4
Jan 99.18
Feb 86.76
Mar 112.50
Apr 101.52
May 130.50
Jun 86.04
Jul 112.50
Aug 99.00
Sep 94.50
Oct 31.50
Nov 26.10
Dec 67.68
ANNUAL 1047.78
The Nallah has not been gauged earlier. The Stream gauging for one or two years is not
adequate to make assessment of long term flow patterns in a stream. However, to take up
small hydro electric projects urgently, short term stream flow data provides valuable
information on which indirect methods can be super–imposed to work out design discharge for
assessing power potential.
The Shaliganga stream flows adjacent to the Surasyar & Bahramgalla streams. All the
three streams are being measured for a reasonable period. These three streams are located
in the same hydro-meteorological & topographical regions. The mean monthly discharges for
the three streams are presented in Table 3.7.
The catchment areas of these three streams are 44, 71 & 78 Sq.km for Surasyar,
Shaliganga and Bahramgalla respectively. The mean (X), standard deviation (S) coefficient of
variation (CV) & mean flow per sq.km for the three flow series are available. The statistical
parameters of flow for the three streams have been generally comparable. The statistical
analysis of the above referred streams is produced hereafter.
Table 3.5
10
1-10 1.10 1.00 1.20 1.30 1.15
January 10
11-20 1.20 1.05 1.20 1.20 1.16
11
21-31 1.25 1.05 1.30 1.70 1.33
10
1-10 1.50 1.65 1.50 1.90 1.64
February 10
11-20 1.80 1.60 1.60 2.00 1.75
8
21-29 2.30 2.20 2.00 2.40 2.23
10
1-10 3.10 3.10 4.50 4.80 3.88
March 10
11-20 4.00 4.50 5.00 5.50 4.75
11
21-31 5.30 5.10 6.50 6.30 5.80
10
1-10 4.70 4.70 7.00 6.50 5.72
April 10
11-20 5.90 5.50 8.90 7.80 7.03
10
21-30 6.00 5.80 8.00 9.10 7.23
10
1-10 7.10 7.20 11.00 10.60 8.98
May 10
11-20 9.80 8.90 12.30 14.00 11.25
11
21-31 11.00 9.90 13.00 13.90 11.95
June 10
1-10 10.20 10.00 10.00 11.00 10.30
10
11-20 9.50 9.30 9.00 8.30 9.03
10
21-30 8.90 9.00 9.60 8.00 8.88
10
1-10 7.25 7.40 7.00 7.20 7.21
July 10
11-20 6.40 6.10 6.50 6.70 6.42
11
21-31 5.80 5.75 5.50 5.70 5.69
10
1-10 5.00 5.05 4.00 4.30 4.59
August 10
11-20 4.60 4.50 4.00 4.20 4.33
11
21-31 4.10 4.35 4.10 3.90 4.11
10
1-10 3.45 3.65 3.40 3.20 3.43
September 10
11-20 3.10 3.00 3.20 3.00 3.08
10
21-30 3.05 2.85 3.00 2.90 2.95
10
1-10 2.20 2.25 2.60 2.45 2.38
October 10
11-20 1.75 1.80 2.50 2.30 2.09
11
21-31 1.60 1.70 2.50 2.20 2.00
10
1-10 1.60 1.70 2.00 1.90 1.80
November 10
11-20 1.80 1.30 2.20 1.85 1.79
10
21-30 1.35 1.50 2.00 1.35 1.55
10
1-10 1.00 1.20 1.60 1.20 1.25
December 10
11-20 1.10 0.95 1.30 1.30 1.16
11
21-31 1.10 0.90 1.10 1.00 1.03
January 1.21
February 1.87
March 4.81
April 6.66
May 10.73
June 9.40
July 6.44
August 4.34
September 3.15
October 2.15
November 1.71
December 1.15
The monthly flows for the period from Jan 2011 to 2014 have been compared in table and
correlation is developed for assessment of flows in DudhPathri small hydro Electric project.
Where the constant 1.59 represents the ratio of catchment areas at the gauging sites on
Surasyar & Dudhi Pathri Nallahs i.e.; 70/44.
The two streams being in the similar hydro-meteorological & topographical region &
adjoining to each other, the mean monthly specific discharges would be of the same order,
though these values may differ from year to year. The assumption is confirmed by plotting the
straight line correlation on a catchment area pro-rata basis the observed & estimated mean
monthly discharges based on the correlation equation and subsequently in this chapter specific
discharge comparison for similar hydrological parameters of Nallah has also been compared so
as to reach to the conclusions for deriving 50%,75%,90% dependable discharges.
Jan 1.21
Feb 1.87
Mar 4.81
Apr 6.66
May 10.73
Jun 9.40
Jul 6.44
Aug 4.34
Sep 3.15
Oct 2.15
Nov 1.71
Dec 1.15
78 70 44
Table 3.8 Observed and Estimated Mean Monthly Flows of Dudh Pathri MHP
SD -S 3.24 5.60
Statistical Tests
The test is carried out to test the significance of the difference between two
sample values, for example observed & estimated flows.
t = X /√S2/n
Where
N= size of sample
January -0.28
February -0.93
March -1.33
April -5.37
May -4.76
June -8.22
July -5.35
August -4.15
September -2.29
October -1.37
November -0.49
December -0.80
SD -S 2.55
The computed value of t is higher than the tabulated value of t, Therefore, the
differences between observed & estimated discharges are not significant at 5% level of
probability.
F – Test
This test is carried out to test if the two samples belong to the same population. The
basis for testing the hypothesis is the ratio (F) of two sample variances i.e.; squares of the
standard deviation
F= S 12
S 22
S1 & S2 are the standard deviations of the two samples. The greater of the two
variances is to be taken as the numerator. In the present case,
F = S12/S22
Where, S12 = 10
Where, S22 = 31
Therefore, F = 0.3
The tabulated value of F for the given degree of freedom of samples is higher at 5% level
of significance. The calculated value of F = 0.3 is less than the tabulated value.
The statistical tests show that the mean monthly flows of Shaliganga Stream
during the observed period as estimated from the catchment area proportion basis from the
corresponding monthly observed other stream flows are significantly different from the
observed Shaliganga stream flows at 5% level of significance . Hence it may be assumed that
the catchment area proportion approach be adopted for computing the flows from the
corresponding Shaliganga flows.
Mean Monthly Flows With 50%, 75% & 90% Dependability’s
The stream flow measurements of Shaliganga stream are available only for the period
from 2011 to 2014. The data are not adequate to forecast monthly patterns of flow with
certain dependability. The available data are to be supplemented with the records available in
the near-by catchments to favour reliability of observed/estimated discharges. The mean
monthly flows at 50%, 75% & 90% dependability’s have been computed while preparing the
project report for the DudhPathri Small hydro-power project.
50% Dependable
Month Dependability 75% Dependability 90% Dependability
Jan
1.213 1.140 1.076
Feb
1.871 1.758 1.661
Mar
4.808 4.519 4.268
Apr
6.658 6.257 5.909
May
10.725 10.079 9.519
Jun
9.400 8.834 8.343
Jul
6.442 6.054 5.717
Aug
4.342 4.080 3.854
Sep
3.150 2.960 2.796
Oct
2.154 2.025 1.912
Nov
1.713 1.610 1.520
Dec
1.146 1.077 1.017
Flows in Cumecs
1 10.73 1 8%
2 9.40 2 15%
3 6.66 3 23%
4 6.44 4 31%
5 4.81 5 38%
6 4.34 6 46%
7 3.15 7 54%
8 2.15 8 62%
9 1.87 9 69%
10 1.71 10 77%
11 1.21 11 85%
12 1.15 12 92%
In view of the reason that discharge data of longer period for the Shaliganga stream is
not available, the comparison of specific discharges of Shaliganga and Surasyar Nallah have
been worked out to ascertain the reliability of observed discharges in tabular form as under.
The specific discharges were found by dividing the mean flows with catchment area.
Surasyar Nallah is a small tributary of River Jhelum, the flows of Surasyar have been
measured for the same period as in case of Shaliganga, with the rain fall. Snowfall and
catchment characteristics of the two basins being more or less the same, the specific
discharges have been compared in Table . The respective catchment area of Surasyar Nallah up
to gauge site has been established as 44 Sq.kms and the specific Discharges for this Nallah are
produced in Tabular form hereunder.
The specific discharges have been compared in the Table 3.14 and it is observed that
mean 10 day specific flows of Surasyar are higher than those of Shaliganga. The higher
discharges are perhaps due to larger snow melt and slightly steeper and higher catchment
elevation. The specific discharges of two streams in some lean months Dec. Jan and Feb is
more or less the same which is very important from hydrological analysis point of view. The
stream flow measurements for surasyar are available for around two years only. The data may
not be adequate to forecast monthly patterns with certain dependability; however it does
cover the minimum requirement of two lean seasons and one summer discharge besides the
availability of rain fall data of ten years. The nearest rain gauge station at Pahalgam by
comparing areal distances from Project site has been adopted. Pahalgam largely has the same
metrological parameters. In the Chapter 1 it has already been mentioned that rainfall in 2010
may be considered to represent rainfall in a 50% dependable Year.
Based on the overall analysis above, the flow duration curve using the mean
dependable has been developed and the design discharge for DudhPathri SHP. Project has been
adopted as 4.60 Cumecs. Flow duration curve for Shaliganga Nallah is shown in Figure-3.1 and
this discharge shall be taken as the discharge, which is available for more than 100 days in a
year from 50% dependable year which is close to the mean flows of four observed period of
discharges. Thus, the design discharge has been fixed as 4.60 Cumecs after keeping provision
of 0.5 Cumecs as sacrificial discharge. The flow duration analysis at the site evaluates the
proportion of time during which the discharge equals or exceeds certain values. For such an
analysis, the discharges are arranged in a descending order. Each discharge magnitude is
assigned a rank m, which are varying from 1 to N, where N is the number of variants selected.
The maximum value is assigned m = 1 and lowest value is assigned m=N. Each discharge is
given a Weibul plotting position, which is expressed as m/N+1. This position expresses the
percent of time a given discharge is equalled or exceeded. By this method flow duration
computation has been worked out at DudhPathri diversion site for 10 –day discharge of 50%
dependable year series for each month.
Figure 3.1
12.00
10.00
8.00
Discharge in Cumec
6.00
4.00
2.00
0.00
0% 20% 40% 60% 80% 100% 120%
-2.00
%age time exceedence
Figure 3.2
12.00
10.00
8.00
Discharge in cumec
6.00
4.00
2.00
0.00
0% 20% 40% 60% 80% 100% 120%
-2.00
age time exceedence
Figure 3.3
12.00
10.00
8.00
Discharge in cumec
6.00
4.00
2.00
0.00
0% 20% 40% 60% 80% 100% 120%
-2.00
%age exceedence Time
Q = C. (A)3/4
Where,
Q is the Estimated Peak Flood in Cumecs for a probability of 1 in 50
C is a constant depending upon type of catchment and for hilly terrains varies from 11 to 14.
A is catchment area up to Headwork’s site of the Project.
We have ,
Catchment Area up to Head Works Site = 70 Km2
Constant "C' has been adopted for type of catchment = 13
Therefore from above Equation
Q = 13 x (70 )3/4 = 315 Cumecs
Therefore Flood Discharge is taken as = 315 Cumecs
2. Ryves formula-1884
This formula is based upon investigations carried out during a dam project on Beas river and is
Particularly applicable to Himachal Pradesh. And now being used in J&K also.
According to this formula, flood is estimated using the following relationship.
Q = CA2/3
Where
Q is the estimated peak flow in m3/sec
C is constant whose value is 18.19 for a return period of 25 Years and 20.78 for a return period of
50 Years.
Peak Discharge at Headworks Location.
Constant "C' has been adopted for type of catchment =20.78
Catchment area = 70 Sq-km
Therefore Peak Discharge from above equation is as Q50 =
353 Cumecs
3. Inglis Formula
According to this formula, flood is estimated using the following expression:
Q = 124 A/(A+10.4)
Where,
Q= estimated flood in m3/sec
A= catchment area in km2= 70
Therefore Flood Discharge Q = 107.96 Cumecs
Ali Nawabjung Formula and Inglis formula have been developed in the coastal areas of
Maharashtra and Tamil Nadu. Thus, the multiplying coefficients adopted in these formulas are not
truly applicable to North India hill streams. Keeping in view the medium size of catchment & its
location being in North Indian hills, flood discharges as computed form Dickens formula can be
safely adopted.
Point Rainfall
From CWC Report 1/73 for 50 Year return period , rainfall for 24 hrs in the location
for flood peaks is
= 120 mm
RT24 = 120 mm
Den. 39.19
P= 0.926
H= 4.376 Inches
Runoff
= 0.048 inches/hr
= 1.209 mm/hr
Where,
107.57 Cumecs
qtc = 1.54
flood peak.
( QTC/A)0.9
TC = 3.272 hr.
RTC = 61.76 mm
2.43 inches
57.21 mm
0.16 inches
2.10 inches
7962.87 Cusecs
225.51 Cumecs
1.1
PART I
Chapter 4
POWER POTENTIAL
4.1 General
DudhPathri SHP project is a run- off- river scheme utilising the Shaliganga Nallah for
power generation. The details have been discussed in detail in the Chapter 3 on hydrology. The
discharge data so collected has been utilized for computing the 50% (average year), 75% and
90% dependable year discharges for Project.
Q = Design discharge
Which is = 5.30Cumecs
Sacrificial discharge 15% of Lean Flow = 0.5 Cumecs
Provision for Irrigation discharge = 0.2 Cumecs
Therefore Discharge available at headwork’s site= 4.6 Cumecs
Therefore, the design discharge for the project has been chosen as 4.60Cumecs.
Hydrology data series for 50%, 75% and 90% dependable years have been worked out
(for detail refer Chapter -3, Part –I: Hydrology).
A sacrificial discharge of 0.5 Cumecs shall be allowed to flow into the Shaliganga Stream
owing to ecological and environmental considerations.
P = 8.47*Q *H (kW)
= 8.47*4.60*153.51= 6.0 MW
Hydrology Chapter details the data base utilised for the hydrological assessment.
It considers the discharge data collected in the stream in which 15 months are covered in
accordance with the requirements stipulated for the project and conforming to practices for
Mini schemes, More pertinently the rainfall data available for much longer periods for nearby
stations and catchments of similar hydro meteorological region and similar catchment
characteristics is utilised for hydrological conservative studies to arrive at the probable
discharges at different degrees of dependability. This approach helps in probable
determination of the relative flows in the years of different dependability. This in turn would
enable the power potential in years of different dependability of the relative flows to be subject
to lesser magnitudes of deviation. It is pertinent to recall that guidelines and practices for
Mini-hydro electric projects recommend such an approach of short term discharge data
collection considering the time frame for developing a Mini scheme, cost of investigations and
overall impact of probable variations. In the present case a substantial relevant data base
could not be gathered which could be subjected to scientific analysis in accordance with best
hydrological practices of today. But an assessment has been found to reveal the correctness of
recorded discharges and adopt the same for design purposes.
generalities of features of the flows of Himalayan streams provide the important basis for
deciding on discharge which may be suitable for utilisation with the help of only short term,
substantiating, discharge measurement.
4.7.2 Pondage
Diversion of the stream flow into the hydro electric power station of schemes of this
nature has been done through Trench weir which possesses a set of advantages for this
application both from environmental consideration as well as reliability of operation. This is
also detailed in discussion of the weir design. This diversion arrangement does not provide any
pondage capacity and thus has no environmental impact.
4.7.3 Head
The design of the hydraulic elements of the scheme is outlined in the following chapters
and comprises the RCC Trench type diversion weir, a water conveyance system consisting of a
Trench across the stream with intake well on right bank, an RCC Box channel sections in Water
conductor system right up to Forebay with Desilting Basin arrangement, escapes to ensure
water level in channel and Forebay. Penstock takes off from the Forebay and feeds the
generating units in the power station through 2 branches. A short tail race channel is provided
to lead the water back into Shaliganga Nallah. The levels at various points from head to tail
and the head loss in the system have been worked out accordingly.
The Power potential and energy generation computation is made for net head of
153.51m, with factor 8.47 covering combined efficiency of turbine and Generator.
P = 8.47*Q *H (kW)
Q = 4.60 m3/s
P = 6.0 MW (SAY)
Table 4.2 Power Potential Studies for DudhPathri SHP at 50% Dependable Year
Jan-02 1.213 0.70 0.513 0.51 0.67 0.160 10.000 0.667 0.160
Jan-03 1.213 0.70 0.513 0.51 0.67 0.176 11.000 0.667 0.176
Feb-01 1.871 0.70 1.171 1.17 1.52 0.365 10.000 1.522 0.365
Feb-02 1.871 0.70 1.171 1.17 1.52 0.365 10.000 1.522 0.365
Feb-03 1.871 0.70 1.171 1.17 1.52 0.292 8.000 1.522 0.292
Mar-01 4.808 0.70 4.108 4.11 5.34 1.282 10.000 5.342 1.282
Mar-02 4.808 0.70 4.108 4.11 5.34 1.282 10.000 5.342 1.282
Mar-03 4.808 0.70 4.108 4.11 5.34 1.410 11.000 5.342 1.410
Apr-01 6.658 0.70 5.958 5.96 7.75 1.859 10.000 6.000 1.440
Apr-02 6.658 0.70 5.958 5.96 7.75 1.859 10.000 6.000 1.440
Apr-03 6.658 0.70 5.958 5.96 7.75 1.859 10.000 6.000 1.440
May-01 10.725 0.70 10.025 10.03 13.03 3.128 10.000 6.000 1.440
May-02 10.725 0.70 10.025 10.03 13.03 3.128 10.000 6.000 1.440
May-03 10.725 0.70 10.025 10.03 13.03 3.441 11.000 6.000 1.584
Jun-01 9.400 0.70 8.700 8.70 11.31 2.715 10.000 6.000 1.440
Jun-02 9.400 0.70 8.700 8.70 11.31 2.715 10.000 6.000 1.440
Jun-03 9.400 0.70 8.700 8.70 11.31 2.715 10.000 6.000 1.440
Jul-01 6.442 0.70 5.742 5.74 7.47 1.792 10.000 6.000 1.440
Jul-02 6.442 0.70 5.742 5.74 7.47 1.792 10.000 6.000 1.440
Jul-03 6.442 0.70 5.742 5.74 7.47 1.971 11.000 6.000 1.584
Aug-01 4.342 0.70 3.642 3.64 4.74 1.136 10.000 4.735 1.136
Aug-02 4.342 0.70 3.642 3.64 4.74 1.136 10.000 4.735 1.136
Aug-03 4.342 0.70 3.642 3.64 4.74 1.250 11.000 4.735 1.250
Sep-01 3.150 0.70 2.450 2.45 3.19 0.765 10.000 3.186 0.765
Sep-02 3.150 0.70 2.450 2.45 3.19 0.765 10.000 3.186 0.765
Sep-03 3.150 0.70 2.450 2.45 3.19 0.765 10.000 3.186 0.765
Oct-01 2.154 0.70 1.454 1.45 1.89 0.454 10.000 1.891 0.454
Oct-02 2.154 0.70 1.454 1.45 1.89 0.454 10.000 1.891 0.454
Oct-03 2.154 0.70 1.454 1.45 1.89 0.499 11.000 1.891 0.499
Nov-01 1.713 0.70 1.013 1.01 1.32 0.316 10.000 1.317 0.316
Nov-02 1.713 0.70 1.013 1.01 1.32 0.316 10.000 1.317 0.316
Nov-03 1.713 0.70 1.013 1.01 1.32 0.316 10.000 1.317 0.316
Dec-01 1.146 0.70 0.446 0.45 0.58 0.139 10.000 0.580 0.139
Dec-02 1.146 0.70 0.446 0.45 0.58 0.139 10.000 0.580 0.139
Dec-03 1.146 0.70 0.446 0.45 0.58 0.153 11.000 0.580 0.153
Table 4.3 Power Potential Studies for Dudhi Pathri MHP at 75% Dependable Discharges
Table 4.4 Power Potential Studies for Dudhi Pathri MHP at 90% Dependable year Discharge
Jan-01 1.076 0.70 0.000 0.00 0.00 0.000 10.000 0.000 0.000
Jan-02 1.076 0.70 0.000 0.00 0.00 0.000 10.000 0.000 0.000
Jan-03 1.076 0.70 0.000 0.00 0.00 0.000 11.000 0.000 0.000
Feb-01 1.661 0.70 5.209 5.21 6.77 1.626 10.000 6.000 1.440
Feb-02 1.661 0.70 8.819 8.82 11.47 2.752 10.000 6.000 1.440
Feb-03 1.661 0.70 7.643 7.64 9.94 1.908 8.000 6.000 1.152
Mar-01 4.268 0.70 5.017 5.02 6.52 1.566 10.000 6.000 1.440
Mar-02 4.268 0.70 3.154 3.15 4.10 0.984 10.000 4.100 0.984
Mar-03 4.268 0.70 2.096 2.10 2.73 0.719 11.000 2.725 0.719
Apr-01 5.909 0.70 1.212 1.21 1.58 0.378 10.000 1.576 0.378
Apr-02 5.909 0.70 0.820 0.82 1.07 0.256 10.000 1.066 0.256
Apr-03 5.909 0.70 0.317 0.00 0.00 0.000 10.000 0.000 0.000
May-01 9.519 0.70 8.819 8.82 11.47 2.752 10.000 6.000 1.440
May-02 9.519 0.70 8.819 8.82 11.47 2.752 10.000 6.000 1.440
May-03 9.519 0.70 8.819 8.82 11.47 3.027 11.000 6.000 1.584
Jun-01 8.343 0.70 7.643 7.64 9.94 2.385 10.000 6.000 1.440
Jun-02 8.343 0.70 7.643 7.64 9.94 2.385 10.000 6.000 1.440
Jun-03 8.343 0.70 7.643 7.64 9.94 2.385 10.000 6.000 1.440
Jul-01 5.717 0.70 5.017 5.02 6.52 1.566 10.000 6.000 1.440
Jul-02 5.717 0.70 5.017 5.02 6.52 1.566 10.000 6.000 1.440
Jul-03 5.717 0.70 5.017 5.02 6.52 1.722 11.000 6.000 1.584
Aug-01 3.854 0.70 3.154 3.15 4.10 0.984 10.000 4.100 0.984
Aug-02 3.854 0.70 3.154 3.15 4.10 0.984 10.000 4.100 0.984
Aug-03 3.854 0.70 3.154 3.15 4.10 1.083 11.000 4.100 1.083
Sep-01 2.796 0.70 2.096 2.10 2.73 0.654 10.000 2.725 0.654
Sep-02 2.796 0.70 2.096 2.10 2.73 0.654 10.000 2.725 0.654
Sep-03 2.796 0.70 2.096 2.10 2.73 0.654 10.000 2.725 0.654
Oct-01 1.912 0.70 1.212 1.21 1.58 0.378 10.000 1.576 0.378
Oct-02 1.912 0.70 1.212 1.21 1.58 0.378 10.000 1.576 0.378
Oct-03 1.912 0.70 1.212 1.21 1.58 0.416 11.000 1.576 0.416
Nov-01 1.520 0.70 0.820 0.82 1.07 0.256 10.000 1.066 0.256
Nov-02 1.520 0.70 0.820 0.82 1.07 0.256 10.000 1.066 0.256
Nov-03 1.520 0.70 0.820 0.82 1.07 0.256 10.000 1.066 0.256
Dec-01 1.017 0.70 0.000 0.00 0.00 0.000 10.000 0.000 0.000
Dec-02 1.017 0.70 0.000 0.00 0.00 0.000 10.000 0.000 0.000
Dec-03 1.017 0.70 0.000 0.00 0.00 0.000 11.000 0.000 0.000
Period Days capacity MW 3.00 3.50 4.00 4.50 5.00 5.50 6.00 6.50 7.00 7.50 8.00
Discharge Power
Month No Cumecs MW MUg MUg MUg MUg MUg MUg MUg MUg MUg MUg MUg MUg
Jan 31 0.44 0.57 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43
Feb 28 1.06 1.38 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92
Mar 31 3.82 4.97 3.69 2.23 2.60 2.98 3.35 3.69 3.69 3.69 3.69 3.69 3.69 3.69
Apr 30 5.56 7.23 5.20 2.16 2.52 2.88 3.24 3.60 3.96 4.32 4.68 5.04 5.20 5.20
May 31 9.38 12.20 9.07 2.23 2.60 2.98 3.35 3.72 4.09 4.46 4.84 5.21 5.58 5.95
Jun 30 8.13 10.58 7.62 2.16 2.52 2.88 3.24 3.60 3.96 4.32 4.68 5.04 5.40 5.76
Jul 31 5.35 6.96 5.18 2.23 2.60 2.98 3.35 3.72 4.09 4.46 4.84 5.18 5.18 5.18
Aug 31 3.38 4.40 3.27 2.23 2.60 2.98 3.27 3.27 3.27 3.27 3.27 3.27 3.27 3.27
Sep 30 2.26 2.94 2.12 2.12 2.12 2.12 2.12 2.12 2.12 2.12 2.12 2.12 2.12 2.12
Oct 31 1.32 1.72 1.28 1.28 1.28 1.28 1.28 1.28 1.28 1.28 1.28 1.28 1.28 1.28
Nov 30 0.91 1.18 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85
Dec 31 0.38 0.49 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36
Total Energy Mus 40.00 19.21 21.42 23.63 25.76 27.57 29.03 30.50 31.96 33.40 34.29 35.02
Installed Capacity - Pi - MW MW Pi 12.20 1.00 1.50 2.00 2.50 3.00 3.50 4.00 4.50 5.00 5.50 6.00
Total Units generated - Mus 40.00 19.21 21.42 23.63 25.76 27.57 29.03 30.50 31.96 33.40 34.29 35.02
Percent Units generation - %Ug 48% 54% 59% 64% 69% 73% 76% 80% 83% 86% 88%
Incremental Units generated - dUg 19.21 2.21 2.21 2.13 1.81 1.46 1.46 1.46 1.44 0.89 0.73
Units generated/Installed capacity - Ug/MW 19.21 14.28 11.81 10.30 9.19 8.29 7.62 7.10 6.68 6.23 5.84
Table 4.6
Installed Capacity Annual Generation Ratio to Max. Incremental Energy Generation Per
MW MU Generation Generation MU MW.
40.00
35.00
30.00
25.00
20.00
Annual Energy MU
15.00
10.00
5.00
0.00
0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00
Capacity in MW
Energy in MU Chart
1.00
0.90
Ratio to maximum Generation
0.80
0.70
0.60
0.50
0.40
0.30
0.20
0.10
0.00
0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00
Capacity MW
2.5
Incremental Generation MU
1.5
0.5
0
0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00
Capacity in MW
Incremental Energy
1- The ratio of annual Generation to max generation increase steadily up to installed is steady up
to 6.00MWs after which the increase is slow.
It is seen while the cost of the electro mechanical installation as also the cost of civil works
required to feed the desired discharge to the power house will go on increasing with increase in
installed capacity the net benefit in terms of energy generated will decrease relatively and
sharply in case increase in installed capacity beyond the limit is considered say like 6MWs.
PART I
Chapter 5
Geology
5.0 GEOLOGY
DudhiPathri Small Hydro Electric project in Budgam district of Jammu and Kashmir is
located at famous tourist spot Dudhpathri at 17.5 Km from Khan Sahib Tehsil head quarters
and 34.5 Km south of Budgam district head quarters. The project site forming part of survey of
India Topographic sheet no 43 K/9 placed at 33ᶿ50′49.55″N and Longitude 74ᶿ33’47.15″E. The
location is accessible from Tehsil and District Head Quarters through all weather roads.
The scheme envisages the development of hydro power from Shaliganga Nallah. The
proposed scheme comprises construction of diversion headwork’s, underground approach
channel and Desilting tank, headrace tunnel, surface Forebay, Penstock and power house
located at village at an elevation 2802m above MSL.
The megascopic description of the rock types encountered along the different
Components of the propose project can be summarized as
The recemented scree has a strong resemblance to the usual fault brachia & its weathered
product resembles the fault gauge material. A distinction can however be made from the
embedded pebble Pieces which are somewhat rounded in the recemented scree.
5. Karewas
The Karewa formations of Kashmir find a wide distribution in the main valley and occupy it
from end to end. In the subsidiary Valley like North –Western part of Valley, Karewa are
continuous and form patches on the hill slopes along the foot Hills Pir Panjal Range wherever
they have survived the intense denudation of the Young and vigorous streams coming down
from the upper reaches.
Regional Seismicity As per the bureau of Indian standards the seismic zone map prepared
first time in1962 along with recommendations for earthquake resistant design of structures.
This map has under gone revisions in 1966,1970 and 1975,its revision is due after the Kashmir
earthquake of 2005.As per the classification of this map the area under report falls in seismic
zone V that can expect earthquake shocks of more or less same intensity in future as that of
the recent one of October 2005.
The proposed Weir Site is located on the Nallah borne flovioglacial boulders of Panjal
volcanic series. The Nallah at Weir Site flows from North West to South East through a V-
Shaped narrow valley. Both the banks rise steeply from the Nallah bed. The axis of the
diversion Weir is in the North East-South West direction. The Nallah floor at the site shows
scattered boulders and angular to sub angular rock fragments of slates, pangal trap and a few
pieces limestone and Quartzite are also seen.
been very costly and difficult. The proposal of tunnel has been adopted after comparing various
alternatives with their respective cost analysis which revealed that the conveyance of water
through tunnel in this reach would only be ideal and cheap. As such the entire water conductor
system including de-silting basin has been placed underground to suit the topographical and
geological features of the site.
The tunnel alignment in both the reaches will pass through hard rock of Salkhala series
mostly Phyllites with soapy touch, Carbonacious as well as schistose Phyllites with typical Slaty
cleavage. The rock formation in the stretch is under soil cover and slope debris material at
places with exposures of hard rock trending NW-SE direction dipping in slope. This type of rock
is expected in 100% of total length of tunnel. Based on rock mass classification, it is anticipated
that 80% to 90% of tunnelling will be carried out in fair rock which may require systematic
bolting and RCC lining and remaining length is estimated to be in poor category of rock. These
stretches will need extra steel rib support.
5.6.4. Forebay
The Forebay shall be laid on surface with compact and solid rock on either side. Rock
surface expected during excavation will be fresh free from weathering effect, however, joints
and other local cracks are to be taken care of in order to avoid seepage of water.
5.6.5 Penstock
The single tube penstock pipe, 300 m long shall be placed partly underground and partly
along the slope from forebay to power house on sub-recent Alluvium and flovioglacial material.
5.6.6. Powerhouse
The power house is proposed on the left bank of Nallah and shall be located on a flood
plain river terrace reworked by the talus and scree comprising Panjal trap boulders of
different sizes having glomoporphyretic texture with angular to sub angular rock chips of
panjal volcanic embedded in slit clay and sandy matrix. The boulders are litho logically similar
to the country rock exposed in the vicinity as indicated by their roundness are river borne. of
about litho unit exposed near the power house site comprises glacial out wash material and
morines composed of unsorted boulders of Panjal trap with sub angular rock fragments of
inter trapium beds embedded in silt and sand besides Sub recent Alluvium reworked with
glacial morines flovioglacial material and Karewa mixed with loose unconsolidated soil. The
Nallah cuttings on the right bank expose the bed rock.
Short tail race channel is proposed from power house up to Nallah. Geological features
along the proposed alignment of TRC would be same as that of power house.
LOCATION: FOREBAY
LENGTH: 1.0 m
BREADTH: 1.0 m
DEPTH: 2.00 m
ELEVATION: 2959m
METHOD OF
EXCAVATION: MANUAL
LOG CHARACTERISTICS:
Pit excavated at about R.L.2959m in the Forebay area following log characteristics:-
0.0m to 0.60m : - Medium grained sand & silt with clay matrix.
0.60m to 1.00m : - Rock fragments and cheeps embedded in sand and silt.
LENGTH: 0.80 m
BREADTH: 0.80 m
DEPTH: 2.00 m
ELEVATION: 2801m
METHOD OF
EXCAVATION: MANUAL
LOG CHARACTERISTICS:
Pit excavated at about R.L.2801m in the power house area following log characteristics:-
0.60m to 1.00m : - Rock fragments and chips embedded in sand and silt
Surface Geological investigation by way of taking geological traverses along and around
the proposed project components has been carried out to investigate the project features and
to collect required Geological data for the design of main civil structures. Detailed geotechnical
investigations by way of drilling shall be carried out at detailed design stage.
The weir located on Nallah borne deposits is at a suitable place. Other components
downstream of weir shall be placed with proper measures like lining along the tunnel
alignment and rock bolting and shortcreting where ever warranted to stabilize the slopes as
the strata that will be encountered during tunnel boring may be pervious at places thus
susceptible to seepage of water. Also stabilization measures like grouting shall be taken at
places the rock has multiple sets of joints and cracks besides some structural displacement was
also located during the course of investigation.
The slope stretch has been found favourable for penstock alignment. Due care shall also
be taken for mitigation of soil creep which was also observed during the course of
investigation.
The Power House is located on left bank of Nallah. The entire area comprises of Nallah
borne material boulders of hard rock (Panjal trap) debris of cobbles, gravel, sand admixture,
and soil & flovioglacial material.
The deepest elevation of power house would be around EL 2794.0m. While carrying out
the excavation of the power house, the ground water level at this location has to be taken into
consideration and the foundation treatment in the form of proper drainage of the power house
area shall be provided. Back hill slope of power house shall require proper stabilization
measures.
The proposed Dudhpathri SHP shall be laid more or less on stable and suitable Geological
formations and apparently shall have no adverse effect on the foundation of the proposed
project. There is no geological threat in and around circumference of the project area. Hence, it
is recommended for implementation.
PART I
Chapter 6
6.1.1 All components of the project including the diversion weir, intake well and Intake
tunnel, underground desilting tank, headrace tunnel, Forebay, penstock, switchyard,
powerhouse and tail race have been located at village DudhPathri on Shaliganga
Nallah on the basis of topographical, geological, soil, ecological and environmental
study. The layout has been fixed to maximize the exploitation of available discharge
and head.
6.1.2 Diversion weir site has been proposed at appropriate location on the topographic
survey sheet on a stable and relatively flat bed slope of the Nallah.
6.1.3 The location of Intake Forebay and the alignment of water conductor system,
desilting tank, and penstock are primarily based on the geology and topography of
the area using the optimum hydraulic computation for water conductor system.
6.1.4 Although many possibilities of the water conductor system alignment exist but the
final alignment has been based on the most efficient and cost effective system after
studying the geology, topography and hydraulic features. The proposed alignment is
based on the techno-economic comparisons of all the possibilities available at the
site.
Conventional types of raised-crest weir have not been found suited for steep and narrow
hilly streams. If such a weir is constructed across the stream, the rise in water level upstream of
the weir may bring a remarkable change in the flow conditions upstream. The sediments may
get deposited upstream of the crest as a result the intake can get easily choked up under in
particular stream having narrow widths. Preferably the trench across the stream been has
provided in the straight reach of the stream to avoid effect of curvilinear flow. The length of
the trench is provided over whole width of the stream. Steep slope of the trench has been
adopted to provide to facilitate the movement of the trapped sediment in the trench to intake
well. The depth of the trench has been fixed on the basis of water surface profile in the trench
with a bed slope of 1:10
Hydraulics design of Trench weir consist of fixing the dimension of the bottom rack,
trench, intake well, flushing arrangement, protection works upstream and downstream of the
trench etc. The dimensions of different components have been standardized on the basis of
certain empirical methods as per prevailing practices. Estimation of peak discharge in the
stream has been found to be 6.44 Cumecs to design the civil works of the Trench weir.
However, cross-section of the stream and resistance equation with appropriate value of
roughness coefficient have been analyzed to check the flow in the streams at its different
stages, the computation of flow parameters and design of various components of a trench
weir. The top width of the trench has been taken equal to optimum length of the bottom rack
as 2 m. The shape of the trench is proposed to be rectangular on the basis of economy.
Flow in the trench will be spatially varied with increasing discharge. For
hydrostatic pressure and uniform velocity distributions, the most common equation of spatially
varied flow has been adopted. Water passing through the racks in the trench meets normally
to the flow of water in the trench. This causes generation of vortex flow in the trench, which
goes like swirling flow into the intake well. Thus sufficient space in the intake well has been
provided to stabilize the flow. The length of the intake well has been taken equal to 2 times of
the width of the trench Sufficient space has also been provided for accumulation of sediment in
the intake well. The bed level of intake well is fixed at 2956.90m lower than the bed level intake
tunnel. Sufficient space has been provided for installing the gates. About 15% of design
discharge of trench weir has been taken as flushing discharge in the flushing pipe. It has been
ensured that at least 4 to 5 m/s or higher velocity in the flushing pipe that is found sufficient to
flush the sediment. Invert level of flushing pipe at its outfall has been kept lower than the invert
level of pipe at its inlet (2956.90m) so that in the no flow condition undesirable silting should
not occur in the pipe. Flushing of sediment is done in high flow condition in the streams. Under
such condition, head available to flush the sediment is equal to difference of HFL in the intake
well and HFL in the streams at the outfall of the pipe.
Protection Works
Trench weir has a definite advantage as it does not change the general contour
of the stream bed. As an added protection to such weirs, bed pitching in concrete blocks and/or
boulders in wire crates with retaining walls on the sides is provided for at least 15m to 20m
upstream and downstream of the trench. Boulders should be structurally strong enough to
sustain the impact of the boulders. Recent trend is also to provide granite layer on the boulders
surface to minimize the abrasion. Some stones filled sausages are required additionally to
provide the necessary protection in downstream during high floods. The minimum size stones
of relative density 2.65 are used for protection works.
Validity of Lacey’s scour depth equation to fix up the cut-off of the structure in mountain
stream is questionable. The cut-off depth been provided more than the calculated by Lacey’s
equation.
Diversion Structure
The width of the stream at this location at the pond level elevation of 2960.00m
is around 15 m. The abutments are solid boulder strata and hence provide necessary
anchorage at the ends. The intake structure is at the end of the trench weir adjacent to the
Right bank. The trench is below the bed level EL 2960.00 with a top width of 2.0m and bottom
width 2.0m and a depth uniformly varying from 1.0m at the right abutment to 2.5 m at the left
abutment where the intake structure is located. RCC key of 1.1m height with top width 1.5m
and bottom width of 0.5m is provided below the intake structure. A trash rack grill has been
provided on top of the trench opening sloped in the flow direction so that stones and pebbles
do not settle but would roll away with the stream flow. The trench itself is provided with a bed
slope of 1 in 10 in the flow direction of the diverted water so that sufficient velocity is
generated to carry away heavy silt that may find entry into the trench through the trash
opening. The intake structure is located on the right bank sufficiently away from the midstream
so that the regime of the river is not affected during normal high flood level conditions. Two
openings are provided in the intake structures, one of 2.25m x 2.0m for carrying the design
discharge to the desilting tank and the other of 0.6m dia. for carrying directly the silt collected
in the trench weir to a suitable location in the stream downstream. The intake well opening at
trench end is designed to carry 145% of the design discharge i.e.; 6.44 Cumecs to allow for the
additional requirements for flushing silt etc. Entry to these ducts is controlled by gates
operated from the top of the intake structure. The intake structure permits the release of water
to the desired extent. The top of the intake structure has been kept at EL 2966.06.m which is
above the maximum high flood level EL 2965.06 m. The 0.6m opening is continued as MS pipe
to terminate at a suitable location in the river at a level above the normal HFL. Such a location
is met within a length of pipe of about 63m.
The protection works in the river bed both upstream and downstream of the weir
consist of wire boulder crates 1250 mm x 1250 mm x 1250 mm with a topping of 100 mm
concrete M15 in case found feasible during implementation. The concrete protects the wire
mesh from tearing. These extend 7.18m on the upstream and 9.0m on the downstream. One
Concrete toe wall of 2.25m height, on the upstream and two on the downstream of the trench,
of 2.25m & 3.0m height serve as a safeguard against dislodging of the blocks and consequent
erosion. Further 3 rows of PCC Blocks of size 1.5 x1.5 x 0.9m over 600mm thick stone filling
shall be provided on the downstream side of the trench.
Design
The water diverted by the weir is fed into a rectangular, gated intake structure. This intake
structure is located on the left bank of the weir. The location of the intake structure has been
selected ensuring that the regime of the stream is not disturbed. The intake structure performs
the following functions.
E= (Q/CL)2/3 ii
Where,
L is Width of Stream
E1 = ratio of opening/Total area of trash rack
surface over trench = 0.5
E2 is area of opening in the trash rack likely to be
clogged = 0.5
Area =Txd = 2 xd
Velocity head at the end of Trench hσ is given as,
hσ = n/(n+1) xA/2T
where A = 2 xd
g = 9.81
h = 0.167 xd
Provided (d) = 1 m
which is = 1 10.0
Manning’s Formula is
Q =A* R2/3S1/2/n
Q = 45.492 Cumecs
Safe
Area = 1.75 sq m
OK
Width = 2.25 m
Design Calculations
Intake shall be equipped with a Gate arrangement to prevent excessive flows entering
the water conductor system. The capacity shall be designed for 6.44 Cumecs.
6.3.1 General
To fix in De-silting basin to the nearer location a reasonable length of 139.55 m has been
provided from Head regulator to de-silting basin in the form of Intake Tunnel to supply
discharge into water conductor system. It is recommended to have rectangular section for flow
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 100
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
of size 2.25x2.0 m at a bed grade of 1 in 700. The Tunnel is provided with a free board f 0.4 m
and found sufficient to absorb all the fluctuation in this part of WCS.
The FSD is 1.6 m worked out after apply manning’s equation with manning’s no
as 0.018 as per the guide lines for Small Hydel projects. The velocity produced for flow has
been adopted as 1.59 m/sec which is found to be sufficient to carry fine silt which later is
flushed out in De-silting Basin. The Design Discharge for the tunnel shall be 5.52 Cumec.
Likewise HRT in D shape has been proposed as power channel with hydraulic design features as
shown in design hereunder.
Slope = = 0.001429
Area =(BD+0.5D2)
velocity = V R2/3S1/2/n =
1.59m/sec
Where
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 101
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
R2/3 0.758m
S1/2 0.038
3.60 X 1.59
5.73 Cumecs
Which is Ok
6.4 Desilting Tank (RD 139.55m to RD 200.80m including U/S and D/S transitions)
6.4.1 Generals
For most part of the year silt content in Banihal Nallah water is almost insignificant with
the silt factor of 6-6.5. Monsoons have very marginal effect on the flow in Nallah but in storms it
carries boulders, small stones / pebbles and silt particles. Since it is proposed to keep bed level
of shingle flushing duct below the invert of water conductor system by 0.6m, boulders /pebbles
and debris shall not enter the Supply channel and only the silt particles suspended in water
shall enter the approach channel. These silt particles need to be removed from water
before its entry into Forebay For this purpose considering project capacity a simple single bay
de-silting tank has been proposed. Flushing of silt shall be done through 600 mm Diameter MS
pipe and shall discharge back into main stream above HFL.
The location of de-silting basin has been adopted at a place wherein comparatively
shorter length for an edit is available and is found ideal to pass silt flushing pipe/channel and is
placed very near to intake structure, the deepest level in de-silting duct as shown in drawing,
where from silt flushing pipe has been proposed to carry away the silt to meet Nallah (above
HFL) with sufficient grade in pipe line. The effort has been made to minimise the length of
flushing pipe, as it has been observed that during the operation of projects the longer lengths of
flushing pipes has the tendency to get choked making cleaning an uphill task and at times
impossible particularly when the diameter is small. Therefore the basin has been fixed at
location as shown in General Layout, starting at RD 139.55 m.
It is recommended as per the standard guide lines to remove silt particles of size 0.2mm
and above through the process in which flow through velocity and moderate settling velocities
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 102
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
have been adopted as 0.197m/sec and 0.025m/sec respectively. The length of the main tank is
worked out to be 45.0 m with de-silting basin width of 6.0 m, the depth of flow is 4.68 m. All
these dimensions have been adopted in such a way so as to suit the site conditions besides
requirements from Forebay stand point.
Where,
= 0.0254m/sec
6.4.3 The desilting basin for this scheme is proposed at RD 139.55m to 200.80m including U/s
and D/s Transitions, wherein U/s transition is 8.25 m
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 103
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
6.4.4 Another 8.0m long transition (contraction) has been provided to reduce the width to
meet up with the width of Power Channel.
Total length of the desilting tank including the transitions is 61.25 m with 600 mm Dia.
MS flushing pipe and 600mm Dia. sluice valve.
6.4.5 Along the centreline of desilting tank, a trench wide with its depth increasing from 0.2m
at the beginning to 1.2m at the end has been provided for passing the silt which shall be
flushed through MS pipe 600 mm dia. back to Nallah by opening the sluice Valve. Most likely
regular operation of Desilting basin shall be in summer months only.
The FSD is 1.6 m, worked out after apply manning’s equation with manning’s no
as 0.018 as per the guide lines for Small Hydel projects. The Construction of Tunnel has been
preferred due to the reasons mentioned in above chapters. The Crown part of Tunnel which has
been put as Semi circle shall be shotcrete of 50 mm thickness optionally with wire mesh in it.
Rock bolting shall be done wherever is it may be required. Rock is supposed to be stable inside
as Rib support may not be needed inside the tunnel.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 104
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Slope = 0.001
Area = (BD+0.5D2)
Where,
R2/3 = 0.758m
S1/2 = 0.032
3.60 X 1.33
4.8 Cumecs
Which is Ok
6.6 Forebay
Forebay has the basic purpose of providing water regulation in case of load rejection
fulfilling the immediate water demand at the start of generating units. For Dudh Pathri
small hydropower project it is proposed to have surface forebay Tank at the end of HRT.
It shall provide a minimum storage volume above Minimum Draw down Level (MDDL) for
120 seconds at the minimum water demand of 4.6 Cumecs. . The proposed Forebay tank
shall be rectangular in shape of Size 45x 6.1 m size with an overall depth of 7.0m in
forebay pool. However bed of Forebay has been adopted in slope as per requirement.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 105
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
The FSL and MDDl in Forebay shall 2957.46 m and 2955.46 m respectively. The
placement of Forebay has been considered in line with Geology of the location and to
limit internal width of Forebay to 6.1m. The structure shall be provided with intake
arrangement having Forebay pool with provisions for silt flushing arrangement and
Intake service gate to control flow into penstock having length of 300 m.
The Forebay Tank shall be of RCC grade M20 and shall have an Escape Bowl as
well which could have been avoided in this case but has been included from
environmental point of view along with laying of Escape arrangement kept in form of a
short length of Escape Pipe and is constructed in monolithic to the structure with height
equal to the Forebay pool height. In Forebay a depressed part called as Forebay pool has
been provided to accommodate height of intake bell mouth which in this case is 1.92m
fixed in proportion to the penstock diameter of 1.2 m, further bottom sill of 0.55m and
Water seal measuring from FSL to MDDL which will avoid any vortex formation in pool
along with creation of live storage. The Forebay pool is also equipped with Trash rack
arrangement for full height of Intake to avoid and trash entry into penstock. An air vent
pipe of 300 mm diameter will be fixed downstream of Intake service gate in the Intake
wall. Design of Forebay has purely been made of section to suite site conditions which
shall involve overall cutting depth of 4 to 8 m as available soil condition should not of any
major critical issue.
Discharge Q = 4.60Cumecs
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 106
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Allow Storage =
Discharge Q = 4.60
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 107
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
proposed to have Spillway Bowl at Forebay itself which shall collect and guide flow into the
said Escape pipe. As the discharge is very small, this free flow MS pipe proposal in place of
conventional spillways has been found as efficient working solution and economical as well
especially for a mini hydro project. The MS pipe shall be made of 6mm thick MS plates and is
proposed to be rested on RCC Saddle blocks.
We know Q = 1.7*L*H1.5 =
Discharge Q = 4.60Cumecs
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 108
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Area == BD+0.5D2
Area = 2.94sm
velocity , V= R2/3S1/2/n
= 1.62 m/sec
Where,
R2/3 == 0.651m
S1/2== 0.045
X 1.62
= 4.75Cumecs
Which is ok
= 0.002
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 109
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Area = BD+0.5D2
Where =
R2/3 = 0.448m
S1/2 = 0.045
1.05 X
= 1.11
6.7 Penstock
6.7.1 General
Penstock— a pipe used for the conveyance of water under pressure from Forebay tank to
the turbine is proposed to be of MS Grade B. IS 2062 to be adopted for DudhPathri small
hydropower project. The penstock installation proposed is surface with well designed saddle
blocks and on the bends anchor blocks have been proposed.
The radius of curvature in penstock profile is proposed to be three times the diameter of
the penstock for efficient hydraulic flow and the bends are proposed to have successive
segments of curved portion with optimum deflection angles avoiding sharp changes in the
direction of flow. Air vent is proposed to be provided in the intake wall of Forebay avoiding the
development of negative pressures also accelerating the draining.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 110
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
A single penstock aligned on the hill slope takes off from the forebay. The single
penstock 1.20 m in diameter is fitted with a bifurcation near the power house to feed two
generation units located in the power house. The branch pipes of the bifurcation are of 850
mm dia. each. The diameter has been selected on the basis of optimisation studies. The
penstock has been designed for maximum discharge of 4.6 Cumecs. The steel liner for the
penstock is proposed to be manufactured out of IS-2062 stock. The thickness of the still liner
shall be 8 to 14 mm. Anchor blocks have been provided at the bends.
P= Rated HP.
P= 8042.9 HP
H= 518.23 Feet
P/H = 15.52
D= 3.59 Feet
P/H = 0.04
Therefore D = 1.55 m
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 111
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
The parameter used to indicate the circumstances under which the water hammer
should be considered is called the critical time.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 112
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
h= steady head =
Gate closure
aT/2L = 16.45
Hence Ok 30%
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 113
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Safe
Thickness t = (D+50)/400 =
Where D is diameter in cm =
Therefore t = 0.425 cm
4.25 mm
Therefore hf = KsxV1.9/D1.1x(1/1000)
0.34 206.82 x 1
D2xD1.1 1000
4.9
8.53 ÷ D
(Per Rft.)
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 114
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Bend Loss
hb = KV2/2g
D2
837 ÷ D4
..= 73057.30617 x HL
Diameter D4 Entrance Bend Loss D4.9 Friction Total Loss Power Loss
Feet Loss Loss
47.6 837 8818 73057 HL
D4 D4 D4.9
1.31 2.97 16.06 282.10 3.79 2327.50 2625.66 191823319.93
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 115
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
H= 947 Feet
t= WHD/2ns = 0.081 D
Absolute
Dia Min. Thk. Corrosion T.Thk. In
Thk.
Feet .03D+.05 .04D 0.063
1.3124 0.089372 0.052496 0.063 0.115496
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 116
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Weight of Penstock
W = Л D*L*t/12*unitwt
L= 1033 Feet
D= DIA.
t= Thickness In inch.
W= 37.37 Dt
Capital = 7690536 Dt
Interest = 14%
Interest = 1076675 Dt
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 117
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 118
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
The foundation of the Anchor blocks shall be designed so that the maximum pressure on
the foundation shall not exceed the allowable bearing capacity of the soil determined as
specified in IS 1904-1978. The permissible bearing capacity shall be increased in
accordance with IS: 1893-1975 for seismic condition.
Since the support pier is not designed to resist significant longitudinal forces and remains
therefore unaffected by the component of this weight parallel to the pipe. IS 11639 Part-I have
been followed for the design of saddle supports.
For DudhPathri project the spacing between any two saddles, structural stability and
safety against sliding and overturning have been found in order. The Saddle support spacing
for the Penstock shall be adopted as 6 m.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 119
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
6.9.1 General
The layout of the power house has been prepared as per relevant IS Codes including IS
12800 (Part 3); 1991 and in terms of manuals in practice.
It is proposed to have a surface power house on a relatively plain terrain and are large
enough to accommodate the electrical and mechanical equipment. The site for the power
house is geologically stable on the left bank of the river. The power house is indoor type so
that all erection and maintenance of the machines is done within the power house itself.
The size of the power house has been arrived at after the detailed layout plan of the units,
control panels and service space and other requirements. The size and location of the power
house also takes into consideration the surface drainage, ventilation, lighting etc. The location
of the gantry columns has been based on the economy and the machine layout.
The location of power house site and the fixing of the machine hall floor level and the setting
level of turbines have been determined by the HFL and minimum tail water level in the stream
and tail pool, with the machine floor having been kept above the HFL ensuring that the power
house is not flooded.
a. Superstructure
b. Substructure
i. Roof
ii. Roof support system
iii. Gantry Girder
iv. Gantry Columns
v. Cross Beams or Braces
vi. Panel Walls
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 120
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
vii. Floor
Dead Loads: This includes the self load of the structure and permanent superimposed
loads
Crane loads: Weight of the fully loaded crane and longitudinal and lateral impact forces.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 121
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
The permissible stresses for rivets, bolts, etc are increased by 25% only in all the cases
from serial 2 to 6.
In view of the site conditions, location, power house size and the economy in the
construction truss of structural steel with CGI sheeting has been proposed. The thickness
of the sheets has been determined on the spacing of the purlins. The CGI sheets shall
conform to IS: 277. It is laid on purlins and is secured by hook bolts 8 to 10 mm diameter
spaced at 400 mm Centre to centre. Joints along the length have an overlap of 150 mm
and joints along the sides of the sheet overlap two corrugations and rivets /screws have
been proposed at 300 mm c/c. The holes will be provided through the ridge and curved
washers have been provided to prevent leakages.
6.9.6 Columns
From the economy of construction and the speed of construction RCC columns are ideally
suited to the site. Columns are subject to moments in longitudinal and transverse
directions and direct thrusts and are designed for biaxial bending and direct thrust using
the design procedure of IS: 4247-Part II and the reinforcement as per IS:456. The
columns are supported by RCC raft floor to ensure that the pressure below the base is
limited to safe bearing capacity.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 122
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
6.9.8 Substructure
This is the part of the structure below the machine hall floor and is proposed to be rigid
gravity structure. The stability analysis therefore considers the following:
The analysis is done in both longitudinal and transverse directions and the loads for
design are as:
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 123
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Out flow from two numbers draft tube openings shall be flown into a common tailrace
pool which shall finally be led to the stream through a tail channel. The channel shall be RCC
structure or random rubble masonry structure. The channel is designed to have a discharging
capacity of 20%% of one unit discharge under minimum tail water level condition and 120% of
full design discharge of both the turbines under normal and maximum tail water level
conditions. The discharging capacity in each case is determined by Manning's formula which
shall be rectangular in shape with RCC bed raft laid in reverse slope in pool, to form the crest at
its end. The crest level has been provided in conjunction to the flow depth in Tailrace Channel to
maintain minimum tailrace water level during lowest power generation from the plant during
lean flow condition to avoid cavitations’ of turbines. Tail race channel shall be directly connected
to the converged pool. This structure is used for sending the tailrace waters from power house to
Source stream. The tail race channel has been designed as RCC structure with for required
discharge capacities with free board of 0.6 m. The channel has been designed as a rectangular
RCC structure up to the bank of the stream and thereafter on crate construction in the stream
bed making it flexible and repairable after flood seasons. The size of the tail race is 4.20 m wide
with the full length made of RCC with Tailrace pool size as shown in Drawing. The FSD in the
channel shall be 0.7 m at a bed grade of 1 in 500.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 124
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
PART I
Chapter 7
Electro-Mechanical Works
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 125
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
7.1 General
7.1.1 The gross head available for the power plant is 157.96 m and the net head work out to
153.51 m. An installed capacity of 6000 kW comprising 2 generating units of 3000 kW
capacity each would be provided at the surface type power station located on the left
bank of Shaliganga Nallah.
7.1.2 For the available discharge and the head, reaction turbine of Francis type is appropriate
as the prime mover. The turbines will be coupled to synchronous generators shaft
directly. The particulars of layout of the power station equipment and of the turbine,
generator, controls and other associated equipment to be installed inside the power
station and outdoor switchyard given in the following sections.
7.2.1 The generating unit will have a horizontal shaft arrangement with two units having a
longitudinal arrangement parallel to the length axis of the power house. The reaction
turbine has the characteristics that due to the head, the water entering the turbine
casing is under pressure and passing through the passages between the guide vanes
having acquired a velocity. Energy partly in kinetic form and partly in pressure form is
responsible for the rotation of the runner. The water leaving the runner possesses kinetic
energy and a large portion of which is recovered in the draft tube. Each unit will
discharge water through a draft tube into a common tail race pool. The two draft tubes
from the two units will lead into a common pool/channel at the downstream end of the
power house which will discharge water directly into source Nallah. The service bay is
placed at the Front end of the power house where road access is contemplated. The
generating units are located well above the expected flood level in Source Nallah.
The turbine shall be horizontal shaft, reaction turbine of Francis type suitable for
coupling to horizontal shaft synchronous generator of Turbine output 3000 kW
capacities. The turbine shall be capable of giving output higher than the rated output to
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 126
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
match the 10% overload capability of the generator. The specific speed of the turbine
shall be as per the best modern practice and proven design and operation, however in
the design sheet the specific speed has been adopted at 89.67 RPM. The turbine will be
provided with suitable electro-hydraulic / mechanical governor to ensure control of
speed under all conditions of loading. Speed response elements, restoring mechanism
and load limiting devices will be integral parts of the governing system.
7.2.3 The turbine shall also be provided with emptying water system, safety devices
instrumentation, etc. A relatively moderate speed of 750 rpm of the turbine has been
chosen as this will be helpful in reduction of erosion damage which is an important
maintenance problem for the run-of-the-river schemes in the region and this speed
avoids any deep cutting in power in respect of fixing minimum tailrace water level. The
turbine design shall permit quick and easy replacement of wearing parts and interchange
ability. Material and composition shall be resistant to wear with seals having good
safeguard against erosion.
7.2.4 The turbine runner is precision ground cast 13% chromium and 4% nickel stainless steel
which is invariably secured to the shaft with standard self centering ring feeders for ease
of assembly and dismantling with the runner cast in one piece. The guide vanes are of
fabricated steel with stainless steel trunnions. The guide vane bushes are of self
lubricating material. The regulating mechanism consists of levers secured to trunnions
and interconnected by self aligning links. A hydraulic cylinder forms the servomotor shall
be used for controlling the guide vane openings. The spiral casing, stay ring, draft tube,
top and bottom covers are fabricated from steel plate. A radial thrust cum guide bearing
is provided and mounted on top cover. The main shaft is either a hollow forging or
welded tubular construction. Self lubricating type bearings with external circuits for oil or
cooling water will be incorporated.
Number of turbines = 2
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 127
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
7.2.6 Generators
The generators shall be horizontal shaft, alternating current, synchronous type for
coupling direct to water driven prime mover turbine as described in the preceding paras.
Number of Generators = 2
Rated Output = 3000 kW
Overload capacity (optional) 10%
Power factor = 0.9
Rated voltage = 3.3 kV + 10%
Frequency = 50 Hz.
Range of frequency variation = + 3%
Number of phases 3, star connected
Inertia constant Not less than 1.0
Short circuit ratio not less than 1.0
7.2.7 As in the case of turbine, nearest standard rating of the manufacturers would be
considered if advantageous otherwise. The generator shall be star connected and all the
six main and neutral leads shall be brought out for both grounded and ungrounded
operation. Necessary CTs, PTs surge protection, neutral grounding equipment shall form
part of the supply of the generator. Brushless shaft driven exciter system shall be
provided with the generators together with all equipment required for control of voltage,
output, power factor etc. All required instrumentation, the generator winding, as well as
rotor shall be insulated with class ‘F’ insulation however, the temperature rise for normal
operation shall be limited to those for class ‘B’ insulation to ensure long life of the plant.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 128
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
The generator shall be natural air cooled, self-ventilated type provided with cooling
system based on closed circuit air circulation principle. The cooling system shall be
complete with temperature and flow indicators, thermostats, relays, alarm and
annunciations devices etc. The generator shall be provided with operated brakes for
operation automatically at the desired speed rise of 30%.
7.2.9 Stator
The stator frame shall be of fabricated steel construction designed to withstand bending
stresses and deflections due to its self weight and weight of the complete core to be
supported by it. The stator core shall be built up of segmental hunching of low loss, non-
oriented steel sheets. The design and construction of rotor shall be in accordance with
the best modern practice. Adequate factor of safety at maximum runaway speed based
on yield point of material shall be ensured by the manufacturer and shall be not less than
1.5. The stator winding shall be of the type which will minimise losses and heating due
to circulating currents. The strands shall be of annealed copper, free from splinters,
flaws, rough spots, or sharp corners. The end portions of the coils and the connections
shall be rigidly supported and braced to prevent vibration and distortion under stresses
caused by the most severe short circuit conditions to which the generator may be
subjected.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 129
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
vibrations or distortion with the generator shaft being single shaft. The Generator shall
be single shaft directly joined to Runner.
7.3 Penstock
A single penstock from the Forebay will carry water to the prime mover and shall
bifurcate at the lower end before entering the power station will the help Y-piece to two
pipes which will feed water to the Francis turbines duly controlled by the Main inlet
valves.
7.5.2 The 6.6 kV and 33 kV switch gear will be the main control centre at the power station on
which the required instruments for operation and monitoring will be mounted. The
paralleling of the generating units will be done on 33 kV outdoor buses. Transmission
Power at 11 kV shall have to be synchronized with 11 kV systems of Power Development
department.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 130
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
In addition one 100 KVA 11 kV /0.415 KV step down transformer will also be installed in
the outdoor switchyard for taking supply from JKPDD system for power station auxiliary
supply equipment in the event of complete shutdown of power station under emergency
conditions. The switchyard will be fenced to prevent entry of unauthorised persons.
7.9 Transformers
Transformers of the following particulars will be installed:
Step-up Transformer
(2 No) Main Transformer 400 0KVA at Switchyard
(1 No) Auxiliary Transformer in switchyard 100 KVA
(1 No) Dry Transformer (50 KVA) inside Powerhouse
Rated output = 4000KVA , 50 KVA
Rated voltage 3.3 KV / 11 KV 3.3 KV / 415 V 3.3 KV / 415 V
Voltage range + 10% + 10% + 10%
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 131
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
bars etc. shall be made according to the measured soil resistivity at the planning stage of
construction activity. Earthing busses of steel bars / flats shall run in all locations where
equipment is to be installed.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 133
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 134
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Choice of Turbine
Proposed Turbine is chose as Francis Horizontal where,
Ns , Specific speed = n . ( P)1/2 / H5/4
and
n = Speed of Turbine in rpm
H = Rated Head = 153.51 m
P = Rated Turbine out Put in metric Horse Power
= 0.9863xHorse Power
H= 153.51 m
P= 4173.61 m-hp
Therefore ns 89.67 rpm
Therefore n/ns = 8.36
Therefore specific speed of Turbine ns = 89.67 rpm
Now Turbines available in commercial market and as per Code IS: 12800
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 135
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Ns
(Specific
Type speed)
Also n = 120xf/p
From the above equation p = 8
Therefore provided no. of poles = 8
and adopted speed = 750 rpm
Turbine Size
1/3
Runner diameter = 4.48x(Q/n)
Therefore Runner diameter from above equation
Taking Designed Discharge = 2.30 Cumecs
and Rational speed n = 750 rpm
Therefore Runner Diameter = 0.651 M
So Provide Runner Diameter as 651 mm
Dimensions and arrangement of Francis Turbine
As per Manual Dimensions shall be,
Diameter = 651 mm
mm
K= 1497.3
mm
J= 1302.00
mm
A= 1432.20
mm
B= 961.40
mm
C= 781.20
mm
E= 2473.80
mm
H= 2278.50
mm
J= 1302.00
mm
K= 1300.00
mm
L= 3929.50
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 136
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Hs = Hb-σcH
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 137
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
PART I
Chapter 8
CONSTRUCTION METHODOLOGY
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 138
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
8.1 General
The construction programme of a hydroelectric project involves the planning,
management of personnel, material, equipment and financial resources, strict
adherence to time schedule and foresightedness. The entire work should be divided into
different planned activities to manage efficiently for their timely completion. The inter-
phasing between different activities should be carefully identified and monitored.
The practical hindrances and unavoidable shortfalls should be critically examined
and carefully monitored to overcome any bottlenecks. All the different activities
should be assigned their due share of importance in over all construction and
management keeping site position and climatic condition into consideration.
Construction methodology of DudhPathri SHP has been finalized keeping the above
requirements in mind.
8.2 Working Period
DudhPathri SHP is located in an area of very heavy snowfall, bulk of which occurs
during the months of November, December, January and February. Temperatures are very
low during these months. Keeping this in view the construction of DudhPathri SHP has
been planned in such a manner that work does not suffer on account of adverse weather
conditions. There will be stoppage of activities during peak snowy period and the
completion time of the Project shall be planned accordingly. The main working period shall
be from May to October months only
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 139
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
The main civil works have been assumed to be started from A p r i l 2018 and shall
include construction of Trench weir, Intake well, Shingle Flushing Pipe, Intake tunnel and
Headrace tunnel, U/G de-silting tank, Forebay, Steel Penstock and its bifurcation,
powerhouse, tailrace, switchyard and transmission lines for evacuation of power to Arizal
Sub-station. These shall be constructed using appropriate machinery and predominantly
by deploying labour force.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 140
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
After approaching the weir site, coffering will be taken up for the right half width of the
river to facilitate the construction of the weir intake structure and the Shingle flushing
structure in the first lean season. Since river discharges remain heavy up to mid
September end, coffering shall commence from 15th September 2018.
Concurrently, with the construction of intake structure and the weir portion
within the coffer dam area shall be carried out from October 2018 until ending March
2019. Gates and hoists for the intake structure and flushing outlet structure shall also be
completed in all respects before the coffer dam is removed or gets washed – off as the
discharge increases.
Left-over works if any of the intake structure along with its gates and trash
racks will be completed in the second lean season viz. August 2019 to October 2019.
The gates shall be lowered so that water cannot enter the under construction
water conductor system. Thereafter, coffer dam shall be removed and coffering shall
be done to isolate the left bank.
8.3.2.2 Intake Tunnel & Headrace tunnel
The tunnel boring by way of excavation shall be started simultaneously from two end
portals i.e. at start of intake tunnel and exit portal at the downstream end of Headrace
tunnel. In this way the rock excavation can be completed first for intake tunnel which will
be preceded further for de-silting basin from intake side and for headrace tunnel from exit
side. Assuming an advancement of 2m per day per face and excavating only from two
ends, the tunnel excavation could be completed in about fifteen months. The activity
started in May 2018 can be completed by the end of July 2018 in respect of Intake Tunnel
and Headrace tunnel by end of July 2019. Other items of shortcreting or cement concrete
lining can be completed in another six months time and completed by December 2019
. 8.3.2.2 Desilting Tank
Length of De-silting Tank is 61.25m including transitions. Construction of the
desilting tank shall be carried out in overburden material in the first working season, viz.
July 2018 to October 2018. Excavation shall be carried out using conventional means.
Side slopes shall be retained temporarily by strutting / shoring till such time RCC could be
poured.
Concurrently with the construction of the desilting tank, construction of silt flushing
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 141
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
8.3.2.4 Forebay
Construction of forebay, being an independent activity Excavation can be taken up
from the first season itself. However, considering the fact that steel penstock ferules
may have to be lowered on downward slopes from the forebay location, construction of
forebay can be started as per the actual progress achieved in conjunction to other work
fronts including penstock.
After excavation and stabilization of side slopes, RCC raft for the forebay
tank shall be cast. RCC retaining walls shall rise from the RCC raft and connection with
power channel and steel penstock shall be carried out and completed in 2nd year. The
entire forebay construction work shall be completed September 2015.
8.3.2.5 Penstock
The total length of penstock has been worked out to be 300 m as and runs down along the
left bank slope of Shaliganga Nallah. It is proposed that a path for carrying the penstock
ferrules shall made all along the alignment to facilitate the transportation and speedy
execution. The first activity to be taken up for penstock civil works is the creation of a
strip of land measuring about 6 m in width all along the penstock alignment. After
Boulder and Jungle clearance, stripping of over burden shall take place. Thereafter the
excavation shall be carried out with help of a hydraulic excavator to achieve the desired
levels as per Plan and sectional. This shall be done in the period December 2018 to April
2019 besides procurement of steel and some fabrication.
Penstock ferrules shall be fabricated at factory site using steel plates of 8/14 mm
thickness. The ferrules shall be carried to the site and installed over saddle blocks. Bends
shall be laid over the designated places and encased in RCC anchor blocks. The penstock is
proposed to be buried with minimum soil cover in form of Backfill almost for entire length.
Fabrication of Ferrules shall be commenced in the above mentioned period and
completed by May 2019. Erection of Penstock ferrules, alignment, welding and testing
of the completed penstock shall be carried out from May 2019 and completed by
April 2020. Penstock bifurcation shall be constructed along with powerhouse construction.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 142
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 143
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
PART I
Chapter 9
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 144
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
The Specifications are intended for general descriptions of the work, quality and
workmanship. The specifications are not intended to cover the minute details and the
work shall be executed according to the relevant Indian Standard Codes, in the
absence of the latter the work shall be executed according to the best prevailing
practices.
The layout and levels of all structures, etc shall be worked out and fixed from the
general grid of the area and bench marks
9.2.1 MATERIALS
Bricks
(a) Bricks for general masonry work shall conform to IS: 1077-1976 and for face brick
work shall conform to the specifications in IS: 2691-1972.
(b) Bricks for general masonry work shall be well burnt, of uniform size, shape and colour,
free from cracks, flaws or nodules of free lime and emit clear ringing sound when
struck. Fractured surface shall show uniform texture free from grits, lumps, holes etc.
compressive strength shall correspond to class designation 50 as per IS: 1077-1976
giving minimum compressive strength of 50 kg/cu. cm for general masonry work.
Water absorption after 24 hours immersion shall not exceed 20% by weight for
common brick and 15% by weight for face bricks. Dimensional tolerance shall not
exceed 8% of the size mentioned in drawings for common bricks and 3% for face
bricks. All bricks shall have rectangular faces and sharp straight edges. Maximum
permissible chip page for face bricks shall be 6mm at the edges and 10mm for corners.
The bricks shall show no efflorescence after soaking in water and drying in shade.
Stones
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 145
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
All stones shall be from local quarries, hard, tough, and durable, compact grained,
uniform in texture and colour and free from decay, flaws, veins, cracks and sand holes.
The surface of freshly broken stone shall be bright, clean and sharp and shall show
uniformity of texture, without loose grains and free from any dull. Chalky or earthy
appearance. Stones with round surface shall not be used. Stones showing mottled
colours shall not be used for face work. Water absorbed by the stone after 24 hours of
immersion shall not be more than 5% of its weight.
Cement
Coarse Aggregates
a) Coarse aggregates shall be as per IS: 383 (latest edition) consisting of hard, strong and
durable pieces of crushed stone having angular shape and granular surface and shall
be free from organic or clay coatings and other impurities like dis-integrated stones,
soft flaky particles, adherent coatings, clinkers, slag, mica and any other materials
liable to affect the strength, durability or appearance of concrete.
b) Aggregate other than crushed stone conforming to the provisions of specification may
be used depending upon type of component of work.
d) Grading of coarse aggregates shall generally conform to IS: 383 and shall be such as
to produce a dense concrete of the specified proportions and strength and of
consistency that will work readily into position without segregation.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 146
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Sand
Sand shall consist of siliceous material having hard, durable, clean particles free from
adherent coatings or organic matter and shall not contain clay balls or pellets. The sand shall
be free from impurities such as iron pyrites, alkalis, salts, coal, mica, shale or other laminated
materials, in such forms or quantities as to affect adversely to hardening, strength, durability
or appearance of mortar, plaster or concrete or to cause corrosions to any metal in contact
with such mortar, plaster or concrete. In no case the cumulative percentage of impurities in
sand shall be more than 5% by weight. All sand shall be properly graded. Unless otherwise
directed by the Engineer-in-Charge all sand shall pass through IS Sieve No. 240 and 15% to
35% of sand for masonry mortar and 5% to 50% of sand for plaster shall pass through IS Sieve
No. 30. Sand for concrete shall conform to IS: 383 b (latest edition).
Water
Water shall be clean, fresh and free from organic matters, acids or soluble salts and other
deleterious substances which may cause corrosion, discolouration, efflorescence etc. Portable
water is generally considered fit for use. Water to be used shall comply with requirements of
IS: 456 (latest edition). Average 28 days compressive strength of at least three 15 cm. Cubes
of concrete prepared with proposed water shall not be less than 90% of average strength of
three similar cubes prepared with distilled water.
Reinforcement
Reinforcing steel shall be clean and free from loose mill scales, dust, loose rust, oil and
grease or other coatings which may impair proper bond. Structural steel shall conform to IS:
226 (latest edition). Hard-drawn steel wire for concrete reinforcement shall conform to IS:
432 (Part-I). Cold twisted steel bars shall conform to IS: 1786 (latest edition). Hard drawn
steel wire fabric shall conform to IS: 1566 (latest edition). All steel bars including and above
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 147
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
6 mm diameter shall be of tested quality. The steel reinforcement shall conform to IS:
432-1982 and its latest revisions for mild steel bars and IS: 1786-1985 and its latest revisions
for TMT bars.
Steel shall be free from loose mill scale, rust, coats of paints, oil, grease, dirt, paint or other
deleterious matter when examined immediately before concrete being placed in situ.
All materials arising from clearing and grubbing operations shall be the property of the
project and shall be disposed in proper manner and as per requirement from
environmental considerations.
Excavation
Setting Out
After the site has been cleared as detailed, the limits of excavation shall be set out true
to lines, curves, slopes, grades and sections as shown on the approved drawings.
Description
The description shall consist of excavation removal and satisfactory disposal of all
materials necessary for the construction of permanent works in accordance with the
requirements of these specifications and the lines, grades and cross sections shown in
the drawings.
Rock Excavation:
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 148
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Rock, when encountered in the excavation shall be removed up to the foundation level
or as otherwise indicated on the drawing. Where, however, unstable shale’s or other
similar materials are intercepted at the foundation level, these shall be excavated to
the extent 500 mm below the foundation level or as otherwise specified in all cases,
the excavation shall be so carried out that at no point on cut formation, the rock
protrudes above the specified level provided, however that a negative tolerance of 300
mm shall be permissible. Where the excavation is done to levels lower than those
specified, the excess excavation shall be made good by hand packing with lean
concrete to the designated level.
Slopes in rock cutting shall be finished to uniform lines corresponding to slope lines
shown on the drawing. Notwithstanding the fore going, all loose pieces of rock on
excavated slope surface which move when raised by a crow bar shall be removed.
BACKFILL
After completion of foundations, footings, walls, and other construction below the
elevation of the final grades and prior to backfilling, all forms, temporary shoring,
timber etc, shall be removed and the area to be backfilled shall be cleaned of all trash,
debris, and other perishable materials.
Backfilling shall be done with clean materials obtained from excavation after approval.
Backfill shall not be dropped directly upon or against any structure or facility where
there are possibilities of displacement or damage.
Backfill shall be placed in horizontal layers, with each layer not exceeding 20 cm in
thickness. Each layer shall be compacted with proper moisture content and with such
equipments to obtain satisfactory densities.
The degree of compaction of the compacted fill shall be subjected to tests as the work
progresses. If any test indicates less value than that specified degree of compaction, it
shall be re-compacted.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 149
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Scope
This specification deals with cement concrete. Plain or reinforced for general use and
covers the requirements for concrete materials, handling, grading, main design,
strength and quality requirements, protection, curing, finishing and other associated
miscellaneous works.
The provision of IS: 456 & its latest revision shall be complied with unless permitted
otherwise and any other Indian Standard Code (latest revision) shall form a part of this
specifications to the extent it has been referred to or is applicable to this specification.
Materials
Material requirements for coarse and fine aggregates, Cement, reinforcement, water
etc shall be as per above.
Admixtures
Grades of Concrete
Ordinary Concrete
“Ordinary Concrete” is recommended only when concrete is used for filling purposes or
for grading and leveling. Trial mix is not insisted for this grade of concrete.
Concrete mix proportions for ordinary concrete shall be as per IS: 456.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 150
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
The water cement ratio shall not be more than those specified in IS: 456. The cement
content of any nominal mix proportion shall be increased if the quantity of water in a
mix has to be increased to overcome the difficulties of placement and compaction, so
that the water-cement ratio specified above for a particular mix is not exceeded Also if
ordinary concrete, made in accordance with the proportions given above for a
particular grade, does not yield the specified strength and fails to satisfy the
requirements of “Acceptance Criteria for Concrete” as specified in IS: 456-1978, to
obtain a specified strength.
Controlled Concrete
Controlled concrete shall be used on all concrete works, except where specified
otherwise. Controlled concrete for use in plain and reinforced concrete structures shall
be in grades M-15, M20, M25 and M-35.
The mix proportions for all grades of concrete shall be designed to obtain strengths
corresponding to the values specified in table I below respective grades of concrete.
Table – I
M10 10 N/Sq.mm
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 151
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
M 15 15 N/Sq.mm
M 20 20 N/Sq.mm
M 25 25 N/Sq.mm
M 35 35 N/Sq.mm
The maximum water cement ratio for all controlled concrete works shall be as specified in IS:
456 (latest Edition)
Preliminary tests, as specified, in the relevant I.S. Codes shall be carried out sufficiently ahead
of the actual commencement of the work with different grades of concrete made from
representative samples of aggregates and cement expected to be used on the job to ascertain
the ratios by weight of cement and of total quantity of fine and coarse aggregates and the
water cement ratio required to produce a concrete of specified strength and desired
workability.
The minimum cement content for each grade of concrete shall be as per Table – II below. If
the requirement of cement is found to be more than that specified below, then such excess
quantities of cement shall be used for which no extra payment shall be made.
Table – II
M 10 275
M 15 310
M 20 350
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 152
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
M 25 400
M 35 450
In designing the mix proportions of concrete, the quantity of both cement and aggregate shall
be determined by weight.
To keep the water – cement ratio to the designed value, allowance shall be made for the
moisture contents in both fine and coarse aggregates and determination of the same shall be
made as frequently as directed by the Engineer-in-Charge. The determination of moisture
contents shall be according to IS: 2386 (part III).
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 153
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
TABLE – III
M 10 70 130
M 15 100 200
M 20 135 260
M 25 170 320
M 35 200 400
Workability
The workability of concrete shall be checked at frequent intervals by slump test. Alternatively,
where facilities exist and if required by the Engineer-in-Charge, the compacting factors test in
accordance with IS: 1199 shall be carried out.
The degree of workability necessary to allow the concrete to be well consolidated and to be
worked into the corners of formwork and around the reinforcement to give the required
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 154
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
surface finish shall depend on the type and nature of the structure and shall be based on
experience and tests. The limits of Consistency for structures are as specified Table IV below:
TABLE IV
LIMITS OF CONSISTENCY
REINFORCEMENT
Scope
This section of the specifications relates to reinforcement steel and covers, furnishing of
working drawings with bar bending schedule and the furnishing, cleaning, bending, placing,
binding, with arrangements for chair supports as required for both structural and
architectural works, below and above ground level as per drawings and specifications.
Cleaning
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 155
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
All steel for reinforcement shall be free from loose scale, oil, grease, paint or other harmful
matters immediately before placing the concrete.
Bending
Unless otherwise specified, reinforcing steel shall be bent in accordance with procedure
specified in IS: 2502. Bends and shapes shall comply strictly with the dimensions in the
approved bar bending schedule. . Only bars correctly bent shall be used. Bars shall not be
straightened in manner that will injure the material. Reinforcement bars shall be bent by
machine or other approval means producing a gradual and even motion. All the bars shall be
cold bent unless otherwise approved.
Placing in Position
Laps and anchorage lengths of reinforcing bars shall be in accordance with IS: 456, unless
otherwise specified. If the bars in a lap are not of the same diameter, then the smaller
diameter will guide the lap length. The laps shall be staggered.
FORMWORK
Scope
This specification deals with supply of drawings, materials, cleaning, treatments and removal
of all formwork and staging both below ground level and above ground level for all types of
concrete works.
Formwork shall be composed of steel and / or best quality shuttering wood of non
absorbent type. Timber shall be free of knots and shall be of medium grain as far as possible.
Hard wood shall be used as caps and wedges or over posts. Plywood or equivalent shall be
used, where specified, to obtain smooth surfaces for exposed concrete work. Materials for
staging and bracing shall generally be mild steel tubes, and strong sale ballis 150 mm in
diameter or above, bamboos, small diameter ballis etc.,
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 156
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
The centering and staging shall be true and rigid and thoroughly braced both
horizontally and diagonally. The forms shall be sufficiently, strong to carry without undue
deformation, the dead weight of the concrete at the time of casting as well as working load.
Where the concrete is vibrated, the formwork shall be strong enough to withstand the effects
of vibration without appreciable deflection, bulging distortion of loosening of its components.
The joints in the formwork shall be sufficiently tight to prevent any leakage of mortar. The
formwork shall be such as to ensure a smooth uniform surface free from honeycombs, air
bubbles, bulges, fins and other blemishes. For exposed interior and exterior concrete surfaces
of beams, columns and walls, plywood or other approved forms, thoroughly cleaned and tied
together with approved corrosion resistant devices shall be used. Rigid care shall be exercised
in ensuring that all columns are plumb and true and thoroughly cross braced to keep them so.
All floor and beam centering shall be crowned not less than 8 mm in all directions for every 5
meters span.
Removal of Forms
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 157
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Note: For Portland Puzzolona cement the removal time should be suitable increased over the
time given for ordinary Portland cement
The formwork shall be so made as to produce a finished concrete, true to shape, lines, level,
plumb and dimensions as shown in the drawings, subject to the following tolerances, unless
otherwise specified in this specification or drawings & directed by the Engineer-in-Charge.
For
a. Sectional dimensions = + 5 mm
EMBEDDED PARTS
Material
Metal parts to be embedded in first stage concrete shall be in accordance with the
requirement and shall of material IS 2062.
Embedded steel parts shall include items such as anchor bolts, pipe sleeves through floors and
walls, steel plates for setting in or attachment to gates / stop logs, hoist structures, ladders,
steel pieces set in concrete or for trench edging, concrete edge protection angles, frames and
floor plate covers, concrete inserts, expansion bolts, lugs etc.
Installation
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 158
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
During erection, it shall be provided with necessary temporary bracing or supports to ensure
proper installation of the materials. All materials shall be erected in the true location shown in
the drawings plumb and level.
General
a) Base plates, anchor bolts, rails and accessories for the transformer foundations and
for cable trenches;
b) Base plates and anchor bolts for the rail beam of the overhead crane;
c) Embedded parts for anchorage systems of the superstructure column and roof truss
foundations;
d) Column superstructure, roof truss, corrugated galvanized iron sheets, drainage gutter
complete with all accessories;
e) Anchor bolts required for stairways, platforms, walkways, handrails and lamp posts;
g) other embedded metal works such as frames for hatch covers gratings, duct openings
and louvers, protection angles, non-skid stair nosing’s, assemblies required for the
permanent support or welding of non embedded metal work;
Metalwork shall be fabricated from materials conforming to the most recent edition of
the following standards:
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 159
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Anchors ASTMA307,
Grade 300 W
Bolts and nuts ASTMA307, IS6639
Installation
Metalwork shall be accurately set in accordance with the alignments shown on the drawings
and the tolerances specified herein. Embedded parts shall be fixed firmly in place during
concreting, using methods, in order to prevent any displacement.
Welded Connections
Connections shall be in accordance with the most recent edition IS-2062/800/816 and with
this specification.
All welders and welding procedures shall be approved by a qualified well known authority.
Only operators qualified in accordance with the Indian Standards requirements, as applicable,
shall be engaged for the work tests necessary to satisfy the requirements of this Specification.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 160
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Welding electrodes shall conform to the requirements of IS 814. be adapted to the material to
be welded and have a low hydrogen content. Electrodes that have absorbed moisture shall be
rejected.
No welding shall be carried out when the temperature of the base metal is below 5º C, unless
all surfaces within a radius of 75 mm around the point to be welded are preheated in
accordance with Indian Standard Specifications and maintained at that temperature
throughout the duration of the welding.
A 20 mm wide strip shall be cleaned to eliminate rust, paint, grease and burrs on each side of
the joint to be welded. Weld preening is not permitted.
Bolted Connections
All bolts shall be galvanized high strength steel and installed in accordance with the
requirements of the most recent edition of IS 2062/800.
The types of bolted connections are generally identified. The main roof trusses may have
either bolted or welded joints. Bearing connections shall have the bolt threads excluded from
the shear plane of the connected members.
Beam connections, for which forces are not indicated, shall be designed for the reactions due
to the uniformly distributed load capacity of that beam having the support conditions shown
on the drawings.
Unless otherwise indicated, the depth of end plates and/or header angles, used for
connections resisting only shear forces, shall be at least three quarters ¾ of the depth of the
connected member.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 161
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Radiographic inspection may be carried out by means of either X-ray machines or radioactive
isotopes. Limitations on the use of each method are outlined in the ASME Standards. X-ray
machine shall be used in preference to isotope cameras as far as possible. Single control
kilovolt-mille-Ampere X-ray machines shall not be used.
All non-galvanized metalwork supplied shall be prepared and painted in the shop in
accordance with the paint manufacturer’s recommendations and the requirements of this
Specification.
No paint shall be applied on humid surfaces. Unless otherwise indicated on the drawings,
surface cleaning and preparation shall be by commercial blast cleaning process in accordance
with the requirements of this Specification. Surfaces shall be thoroughly cleaned of mill scale,
rust, oil, grease or any other substance that may affect the paint.
The surface preparation shall be done by commercial blast cleaning process, meeting the
most recent edition of Standard SSPC-SP602 or a relevant Indian Standard Specification
This specification covers the item of providing and erecting corrugated galvanized iron
sheeting including supply, delivery and erection with corner and ridge pieces, eaves, filler
pieces, north light curves, flashing, gutter eaves, boards, skylight and all necessary screws,
bolts, nuts washer and all leads and lifts for a complete installation. Only factory painted
corrugated sheets shall be used. The sheet shall be 0.8 mm thick and painted Forest Green
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 162
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
outside and Light Grey inside. Touching up of painting shall comprise of two coats of approved
quality synthetic enamel paint over a base coat of zinc chromate / red oxide primer.
The work to be done shall conform to the latest edition of the following Indian specification:
Code of practice for laying and fixing of sloped roof coverings using plain and Corrugated
galvanized steel sheets.Detailed specification pertaining to structural steel, fabrication,
erection and painting enumerated in Specification for steel work of superstructure shall apply
to this work to the extent they are relevant. The material shall conform to relevant IS
specifications. The railing shall be fabricated as per design furnished by the DLIPL. M.S. pipes
of 32mm NB shall be used. The railing shall be fixed firmly to the concrete floor by welding to
embedment fixed in concrete at the time of laying the floor.
Rolling Shutters
Specification includes providing and fixing mild steel push and pull type of rolling shutter of
clear dimension of approximately 5 m X 5 m including all necessary fixtures, painting etc.
complete for the main entrance to the storage shed buildings.
Providing, fabricating and fixing of rolling shutters shall conform to the latest revision of IS –
6248. Metal rolling shutters and rolling grills
All specifications of structural steel fabrication, erection and painting mentioned under item
for steel roof trusses shall apply to this work also to the extent they are relevant.
The rolling shutters shall be fabricated from 18 SWG x 7.5cm MS steel laths. The rolling
shutter shall be in one part
For the rolling shutter, provision shall be made for a wicket door of size 1.2 m x 1.2 m for the
normal movement. The shutter shall have a grill portion for about 1.5 m depth from the top
Painting shall comprise of two coats of approved quality synthetic enamel paint over a base
coat of zinc chromate / red oxide primer.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 163
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 164
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
PART I
Chapter 10
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 165
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
During the construction stage of the project existing bridal path of about 0.5 km
length shall have be upgraded from main road up to the Power house site and to be further
extended by 0.70 km length to reach out to forebay site. The proposed headwork’s is
presently not approachable from the main road. As such a new access road is needed for
the Headwork’s. This road shall need to be developed all along the bank of the nallah
above HFL.
The construction materials availability can be explored locally with abundance of good
quality stones and boulder available locally and can be got in good quantities from
excavation itself as well. However materials like cement and steel shall have to be brought
directly from the open market from Srinagar or Jammu. Small quantities of Fine aggregates
like sand is available in nearby areas and in case of shortages sand the same can be
brought form Khansahib which is 10 km away from project site. Coarse aggregates like
Bajri can be produced by installation of a portable crusher plant to be used during
construction only as raw material like stones are available locally; otherwise the material
can be brought from surrounding areas like Budgam and other adjacent area. At various
places on the downstream side of Nallah sufficient quantity of gravel/ Nallah Bajri can be
made available for its use in the project.
Other materials for day to day use shall be brought from Srinagar and Bricks
to be used in Power house building shall be carried from Budgam where good quality bricks
can be made available. The construction materials need to be dumped at proper places in
sufficient quantities as in winter due to the snow fall approach roads will have
interruptions to the movement of vehicles.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 166
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
PART I
Chapter 11
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 167
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
11.1 General
DudhPathri SHP is proposed to be set up on the left bank of Shaliganga Nallah in
Budgam District of Jammu and Kashmir. Project area does not fall into any major inhabited
area, but some rural households exist near the project site which will have minimal effect
due to the construction activities. The villages in the surrounding areas outside the project
influence and on the mountain slopes are well populated.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 168
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 169
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed
Project report JAKEDA Department of science & Technology
Annexure-11.1
Project Plan
1. Provide a general project plan and its schedule and Requisite drawings are appended with the Project report.
provide two maps drawn on scale, one of the
general area and the other for the project area
Climate
2. Describe climate type and meteorological data for In general, project area has pleasant climate.
temperature, rainfall (seasonal), wind 9direction, Maximum temperature = 300 C
speed, seasonal) Minimum temperature = -130 C
Maximum annual rainfall = 1900mm
Average annual rainfall = 1200 mm
Wind speed = 80 KMPH (Max)
Geology
3. Describe land morphology, topography and The area around the proposed DudhiPathri H.E. Project lies in a seismically active region
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 170
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed
Project report JAKEDA Department of science & Technology
geologic structure. Is project located in an where moderate to great earthquakes have occurred in the past. The Kangra, Kinnaur
earthquake zone? If so, provide quantitative data and Dharamshala earthquakes, which occurred in the neighbouring Himachal Pradesh,
for the frequency and intensity of earthquakes. are some of the most important and devastating earthquakes recorded so far in this
region. The recent earthquake of October 2005, which occurred right in the project area
and caused maximum damages in the neighbouring POK calls for detailed
examination of all the components of Dudhi Pathri H.E. Project. Details of the
October 2005 earthquake as well as the details of earthquakes, which had occurred in
Himachal Pradesh and which could affect Dudhi Pathri Project are shown below:
Of the above earthquakes, the most severe one, viz., Kangra earthquake (4.4.1905) was
felt over an area of 4,16,000 sq.km and about20,000 lives were lost. The intensity close to
the epicentre of the earthquake was "X" on Modified Marcella (MM) scale. The
occurrence of earthquakes in this region is attributed to the presence of several thrusts
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 171
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed
Project report JAKEDA Department of science & Technology
and faults in the Western Himalayas. The project area falls in Zone V of Seismic zoning
map (IS: 1893), which has been developed on the basis of these tectonic features of past
earthquakes. It is broadly associated with maximum intensity of “IX" on MM scale.
Keeping in view the devastating earthquake of 2005 occurring very close to the
DudhPathri Project area, it is recommended that the project components shall be
designed corresponding to 0.15 g acceleration.
Hydrology
4. Provide river/ stream flow rates (monthly maxima Design flow = 4.60 Cumecs
and minimal from historical records)
Historical records of discharge are not available, however from the recorded flows,
the following details are available
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 172
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed
Project report JAKEDA Department of science & Technology
5. Provide data covering water availability in all Shaliganga Nallah is perennial. It carries smaller discharges for about three months
seasons and if available, give surface and every year during winter months.
groundwater quality data during all seasons.
Indicate surface and groundwater recharge areas,
all use of water (including irrigation, industrial and There is no consumptive use of water in the project area vicinity.
other uses), sources of water for drinking, bathing,
clothes washing.
6. If the water availability for the different uses is Since adequate amount of water is being released (sacrificial discharge) in the stream,
impaired by the project, describe the impact and water availability for sustenance of aquatic life is not affected.
proposed mitigation measures to provide this
water at the same quality.
7. Describe river flow disruption during the dry season No disruption of flow would occur because of project construction.
caused by the project. Describe high sedimentation
Project construction and its operation would not cause any siltation since adequate
during construction and immediately after
flushing arrangements have been proposed to flush out sediments which may deposit
construction and measures proposed to mitigate
u/s of weir.
the situation. Describe the impacts on aquatic
organisms during construction (with high Proposed RCC Trench weir top is flushed with bed level of Nallah and would permit
sedimentation) and after implementation of the free movement of aquatic life.
project.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 173
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed
Project report JAKEDA Department of science & Technology
8. A minimum flow of 100 litres/second should be This shall be provided through the flushing duct of the weir. A sacrificial discharge of
maintained in the bye-passed river section during 0.5Cumecs (minimum) and 0.2 Cumecs for irrigation purpose is being released.
normal plant operation.
9. Describe land suitability, adaptability, layer and Private land required for civil structures shall be purchased through Government of J
use, land allotment, protected lands and soil types, & K. 13% land required is private.
structures and texture.
Fairly stable rocks, which are suitable for adaption of civil structures, exist at project
site.
10. Does the project have an impact on the land Land stability shall not be affected by the construction of the project. Wherever
stability? If so, describe measures to stabilize the necessary, hill slopes shall be stabilized by check dams and retaining walls.
land.
11. Describe types of flora and fauna (land and water) The wild animals / birds reported in the forest area are Snow Leopard, Markhor etc.
and types of protected flora and fauna But these are reported in the very high mountainous reaches of the catchment.
12. Describe impact of project on wildlife. The project area does not fall in any wildlife habitat. However bare minimum use of
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 174
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed
Project report JAKEDA Department of science & Technology
explosives shall be ensured so as not to disturb the wild life habitats even remotely.
13. Are surveys available describing endangered No such surveys are available. In any case utmost care shall be taken to protect all
biological species that might be threatened by the wild life by adopting means such as: bare minimum use of blasting heavy machinery.
proposed mini Hydel project?
Health
14. What are the local health facilities and are there Khan sahib 10km in the vicinity of the project have adequate hospitals and health
surveys of communicable diseases in the local centres run by the State Government.
communities that could be affected especially
No surveys are available regarding the communicable diseases in the area and hence
during the construction phase of the project?
have not been reported.
15. Will imported labour force be checked on Imported labour shall be checked for communicable diseases before deployment at
communicable diseases? site.
16. What will be the impact of the project on water Being run-of-the-river project, no pondage of water is involved. Hence, question of
borne diseases and parasites, especially for those water borne diseases and growth of parasites does not arise.
sections of the river that will fall dry during
Sacrificial discharge @ 0.5 Cumecs (minimum)
construction periods, or that the project will fully
use available water?
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 175
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed
Project report JAKEDA Department of science & Technology
Construction
17. Provide a list of project activities, including Project involves small areas.
construction, land clearing, land excavation, access
Land clearance and excavation for RCC weir, approach channel, desilting tank, power
road construction, transmission line installation etc.
canal, forebay, penstock and powerhouse areas are involved.
Water conductor system platform shall be used approach road for light machineries
to connect components like forebay and Desilting Basin. Access road for powerhouse
may be constructed on the right bank of the Nallah. Existing paths shall be
strengthened to reduce unnecessary excavations.
18. Provide an estimate of the size of the area used for Approximately 3.45 hectare of area shall be utilized as permanent land for all the
the project activities, including the main structures, project activities and about 0.2 hectares shall be needed as temporary land.
roads, transmission lines and penstocks. Indicate
Trees shall be planted in the powerhouse area and overall environment shall be
what percentage of the area, allocated for the
improved around the project area.
project will be restored to conditions prevailing
prior to commencement of construction activities. No fencing is proposed for the restored land, which shall be used temporarily during
Restored land should not be fenced and / or the construction period.
considered the project developers property.
19. List the heavy equipment to be used in the project Project being small in nature, only the small JCB type / equivalent other hydraulic
excavator will be used in a controlled fashion so as not to have any adverse impact on
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 176
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed
Project report JAKEDA Department of science & Technology
20. Describe the impact of this equipment on existing Small JCB type / equivalent other hydraulic excavators are a normal daily routine
roads and measures to be taken to repair any around the project area. Hence no adverse impact shall be developed by the use of
damage. this equipment.
21. Describe in a general way the various building Cement, sand, boulders, coarse aggregate, steel and bricks shall be the main
materials, mainly construction aggregates to be materials to be used for construction of the project.
used (type, quantity, volume), where these
Most of the material like sand, stones or boulders shall be available around source
materials are to be found and how collected, their
Nallah area or procured from open market and transported to site by trucks / tractor
means of being transported to the site and their
trolleys. Sand is available nearby Khan sahib. However Coarse aggregates can make
storage and the final disposal system for any
available by installing a portable crusher plant.
wastages generated.
Material like cement and steel shall have to be brought directly from Jammu and shall
be stored in project stores till used.
Wastes generated shall be removed from the site and disposed at designated places
only.
22. Describe the environmental impacts on the sites No major impact is envisaged , However due care shall be taken to avoid any
where these materials are collected or quarried. disturbances to the environment .The material which are to be fro quarried area shall
be mostly from the excavation of project components, and this getting covered under
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 177
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed
Project report JAKEDA Department of science & Technology
23. Describe how the hydropower plant will be Plant will be operated manually and with fully automated controls using PLC system.
operated, including any special environmental No special environmental management controls are needed. However maintenance
management controls. as per routine shall be taken care as per the approved methods in view of
environmental obligations and shall have to be got adhered to by trained staff.
24. Describe the type of equipment used in operating The project shall have 2 horizontal Francis turbines, each of 3000KW. Generators
the generation system, including giving the plant’s shall be of synchronous type.
rating.
Computer controlled PLC system shall be used for operating the plant with additional
facility for manual operation.
25. Describe fully the environmental impact of the Project being small, no environmental impact is foreseen during its construction.
construction activities.
26. Describe the number of construction workers and Maximum number of workers (about 150) shall be deployed. Skilled and semi-skilled
the education and expertise required, whether or workers would be needed. Mostly these are locally available.
not these workers can be hired locally, where they
Both men and women aged 18 years and above shall be employed for construction.
will be residing during the construction and their
ages and sex.
27. Describe any training that will be given to workers. Special training is envisaged relating environmental issues.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 178
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed
Project report JAKEDA Department of science & Technology
The current regulations applicable to the companies' activities are listed below shall have
to be addressed.
1. The Air (Prevention and Control of Pollution) Act 1981 as amended time to
time.
2. The Water (Prevention and Control of Pollution) Act 1974 as amended time to
time.
3. The Water (Prevention and Control of Pollution) Cess Act as amended time to
time.
4. The Environment (Protection) Act, 1986 as amended time to time.
5. The Noise Pollution (Regulation and Control) Rules 2000 Amended 2002.
6. The Explosives Act 1884 & Rule 1983, amendment Rule 2002.
7. The Electricity Act, 2003.
8. The Factories Act 1948 (as amended till 2001) & State Govt. Factories Rules,
1963.
9. Contract Labour (Regulation and Abolition) Act.
10. State Govt. Power Policy.
28. Describe the number of operating employees and One graduate electrical engineer fully trained in operation and maintenance of plant
the education and expertise required and whether and one diploma civil engineer shall be employed after commissioning of the project.
some people can be hired locally.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 179
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed
Project report JAKEDA Department of science & Technology
29. Describe any training that will be given to Training in control systems shall be imparted to the electrical engineer.
operators.
30. Describe noise intensity around the power house, Being a small hydroelectric project, no noise shall be created.
how much it is over ambient noise levels and what
measures will be taken to mitigate a noise problem.
31. Describe any existing activities adjacent or near the Agriculture and horticulture is the main occupation of people living around the project
project that could have a positive or negative effect area. The project will not create negative impact on the existing activities. It shall
on the project. definitely encourage the population to set-up agro based industries.
32. Do project plans provide for an adequate buffer Project shall be constructed within the small land belonging to Government as well as
between project (construction and operation) and Private land owners. Government land is 87% whereas the private land is 13%. No
any conflicting adjacent land use? What mitigation conflicting adjacent land use is envisaged.
is planned for such cases (vegetative screening)?
Cultural-Socio-Economic-Aesthetic Impacts
33. Describe population profiles (age, sex, education, Project area is thinly populated. Population in the vicinity of the project comprises of
religion, income, health) attitude and perception of mainly semi-illiterate people (higher literacy rate in young generation) both males and
the community towards development, condition of females. Their attitude towards the project is positive as it would generate
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 180
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed
Project report JAKEDA Department of science & Technology
the socio-cultural heritage and other relevant employment during its construction phase and provide additional electricity to them.
information.
34. Are there surveys for the area’s archaeological, There are no archaeological resources in the project area.
aesthetic and cultural resources that might be
The project shall improve the aesthetics of the adjoining area since trees are proposed
threatened by the hydropower plant?
to be planted and regular maintenance of roads and plants shall be ensured.
35. Describe cultural impacts (including on local No cultural impacts would be felt on local religion etc. and the project would not
religion, on local archaeological treasures and loss affect riparian rights.
of riparian vegetation used for artisan or medicinal
purposes)
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 181
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed
Project report JAKEDA Department of science & Technology
Annexure- 11.2
Key words:
1. Provide a general project plan and its schedule and provide two maps Requisite drawings are appended with the Project report
drawn on scale, one of the general area and the other for the project area
2. Give details of the proposed location of the project State/ District/Village Proposed Power House is located at village Dudhpathri on
KhanSahib-Dudhpathri road. The site is 17.5 km away from
Tehsil head quarter KhanSahib and 34.5 km from District
head quarter Budgam. And 45 km from Srinagar.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 182
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed
Project report JAKEDA Department of science & Technology
Land Details
3. Give the total area of the land required for the physical components of About 3.45 Hectares of land is proposed to be utilized for
the project. locating various components of the project.
4. Describe the type of land (e.g. agricultural, residential), the crop, Most of the land involved is government & private having no
vegetation etc. significant land use at present. Private land involved is
partly residential and partly agricultural.
5. Ownership of land (Government, Private), traditional population, Partly government and partly private land
encumbrance details etc.
6. Current land use in the proposed area and surroundings Only a small part of land located in the project area is being
used for agricultural and residential purposes.
7. Possible land use change expected after project implementation. Agro based industries are likely to come up in the area
because of increase in availability of power.
8. Proposed strategy for procurement of land, Government lease, Government land proposed to be acquired through lease
negotiated settlement or compulsory acquisition etc. Give detailed agreement shall be signed with the government. Private
description of the area falling under each category. land shall be purchased from the owners through
negotiations in the Name of CEO JAKEDA.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 183
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed
Project report JAKEDA Department of science & Technology
People Affected
9. Number of people and families affected (give details as necessary) None of the people and families is affected and no homes or
livelihood are likely to be lost. Though some minor
agricultural and residential land may have to be acquired
against fair compensation, this will not have any adverse
effect on the people.
b). those deriving benefits (employment, electricity etc) from the sub-
project
10. Describe the nature of impacts expected (positive and negative) Positive impacts such as generation of employment during
construction phase, encouragement to setup agro based
industry, improvement of roads and culverts over the
streams and improvement of aesthetic beauty are foreseen.
11. Identify and describe cultural impacts, if any, in the population due to the No cultural impacts are foreseen due to the proposed
land acquisition and the proposed project. project.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 184
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed
Project report JAKEDA Department of science & Technology
12. Establish the need for rehabilitation and resettlement based on the above R and R is not involved
descriptions and any other issues.
13. Explain the actions taken and proposed for the above so as to ensure Not applicable
restoration / improvements to living standards
14. Describe the existing national and State legal framework, quoting the Not applicable
relevant provisions and applicability for the specific use as identified
above.
15. Give a flow chart of actions for the entire RAP along with the relevant Not applicable
provisions and applicability for the specific use as identified above.
16. Provide the entitlement calculations for payment of compensation for Not applicable
various losses at replacement value.
PEOPLE’S PARTICIPATION
17. Existing and proposed mechanisms / efforts for public consultation and Gazette notification in local newspapers as per section 29 of
discourse of information. Statutory requirements if any for the above the Electricity Act would be issued by JAKEDA about the
may also be explained. proposed construction of the project.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 185
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed
Project report JAKEDA Department of science & Technology
18. Explain how public participation is ensured during the entire project Frequent meetings with village Sarpanchs would be held
cycle? during the entire project.
19. Mention the requirement of RAP and where appropriate IPDP. Not applicable
Grievance Mechanism
20. Describe the grievance redressal mechanism legally available as well as Close liaison with village Sarpanch would be maintained
socially acceptable during the entire project cycle.
21. Remedies available through Lok Adalats, Village Panchayats, NGO’s etc. --------------------do------------------------
Institutional Arrangements
23. Manpower, system and costing for the above activities Not applicable
24. Please mention whether the estimated costs have been incorporated in Not applicable
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 186
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed
Project report JAKEDA Department of science & Technology
Conclusions
25. Conclude with the overall view with respect to Social Impacts and Action DudhPathri SHP shall be constructed on the left bank of
Taken covering the following points: Shaliganga Nallah using mostly Govt Land.
a). Register all people to be affected by land acquisition Shall be taken care of by the Promoters. A separate cell
shall be constituted to register names of all people whose
land is proposed to be acquired.
b). Inform and consult the affected population and organize appropriate
-------------------do---------------------
grievance mechanism.
c). Monitor the formal process of land acquisition and payment of The special cell to be setup by the Promoters shall monitor
compensation and provide relevant assistance if needed the formal proceedings of land acquisition and payment of
compensation to the Owners.
e). Establish collaboration with local NGO’s which represent the --------------------------do-------------------
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 187
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed
Project report JAKEDA Department of science & Technology
developer’s employees and their families and other local interest groups.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 188
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
RATE ANALYSIS
AND
COST ESTIMATE
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 189
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
CHAPTER - 12
COST ESTIMATES & ANALYSIS OF RATES
12.1 GENERAL
12.1.1 Construction of this small hydro Electric Project involves civil engineering works such
as Diversion weir, intake structure, shingle excluder, Underground Desilting tank, comprising of,
water conductor (Underground ), Surface Forebay tank, penstock & its bifurcation, Switchyard civil
structures, powerhouse and tail race Channel. Other than the above, works of smaller magnitude viz.,
flood protection works, slope stabilization, switchyard structures, E&M and transmission line etc. are
also required to be constructed.
12.2 ANALYSIS OF RATES FOR MAIN ITEMS OF CIVIL WORKS
1.2.1 Quantities for different items of work have been computed from the drawings. For
estimating the cost of various items of work, rate analyses have been carried out. While carrying
out the analysis of rates, guidelines issued have been generally followed.
12.2.2 Rates for labour and construction material have been adopted as per actual on
lowest market rates and as per prevailing market rates in the area of Jammu & Kashmir in
general.
12.2.3 Rate analyses for various items of civil works are appended hereunder. Various
rates of material and labour have been in the rate analysis have been adopted as the rates
applicable in surrounding areas.
12.3 ANALYSIS OF RATES FOR MACHINERY
12.3.1 Rates for hire charges of machinery, in general, have been based upon hourly use
rates recommended as per the Guidelines.
12.3.2 Due to relatively small size of the project components and remoteness of the site,
no major heavy machinery or equipment are proposed to be deployed and in some places like
Forebay, Ropeway arrangement are proposed to be adopted as per actual requirement.
12.3.3 While analysing the rates of Excavation combined rate for soft earth and soft rock
on %age basis as per the consultant’s assessment and an average rate have been derived in
general and it is assessed that these rates shall not vary beyond reasonable limit.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 190
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
12.3.4 The Developers do not envisage procurement of any major T & P or machinery
item since the work will be executed through Contractors who will deploy their own Equipment
and machinery.
12.3.5 Since the quantities of concrete are small, only small Tilt Concrete mixers shall be used
and at places concrete can be carried through Ordinary Tractors to places where ever required.
However in case of powerhouse small Batching plant and small tower crane may be used.
12.3.6 Project being small access road along the penstock alignment up to Forebay may
be explored during execution only .The local PWD road going across the hill touches penstock
alignment at three different places as such activities are manageable from these existing road
positions as well. Activities have been planned in such a way that plat form of Power channel
shall be used as access to Forebay.
12.3 COST ESTIMATES
12.3.1 In general, the total cost of Project has been worked out based on the guidelines
contained in Manuals. As such Cost of the scheme is worked out in sufficient details so as to
arrive at realistic cost estimate.
12.3.2 Cost of Civil works and Hydro-Mechanical works has been computed by calculating the
quantities of various items of these works and multiplying the same with analysed rates.
12.3.3 The cost of Electro-Mechanical Works and Transmission Works have been computed by
utilizing prevalent market rates and in discussion with several suppliers and reasonable rates
have been derived.
12.3.4 Abstract of cost of Civil and Hydro-Mechanical works including Land, Buildings,
Plantations, Special T&P, Communications, Establishment and Audit & Accounts Charges are
shown in the cost Estimation and are as per the prevailing guidelines.
12.4 DETAILS OF COST ESTIMATES
12.4.1 Provisions have been made for
i. Establishment charges at the rate of 5% of the cost of Civil and E&M Works.
ii. Audit and accounts charges at the rate of 1% of the cost of I-Works.
iii. Losses on stock at the rate of 0.25% of the cost of civil Works.
iv. Interest rate on term Loan has been taken at 13%.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 191
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 192
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Dudhpathri MHP (2 x 3 ) MW
ABSTRACT OF COST
S.no Description Amount Rs
A DIRECT CHARGES
I-Works
A-Preliminary 6,920,000
B-Land 5,991,500
C-Civil Works. 42,208,837
J -Civil works of power plant 221,512,342
K- Buildings 6,825,000
M-Plantation 150,480
O-Miscellaneous 3,230,000
P-Maintenance during construction 1% of (civil works+K-Buildings) 2,705,462
Q-Special Tools and Plants 700,000
R-Communication 8,600,000
X-Environment and ecology 275,000
Y-Losses in stock 0.25 % of C-works, J civil works power plant and k-buildings 676,365
TOTAL OF I-WORKS 299,794,987
II-Establishment 6% of ( I-Works less B- Land + E & M) 25,373,523
III-Tools and Plants 500,000
IV-Suspense 0
V-Receipts and Recoveries @ - 0.1% of C-Works -263,721
TOTAL DIRECT CHARGES 325,404,789
2 Indirect charges
I-Capitalized Value of Abatement of Land revenue ( 5% of Cost of Land) 299,575
II-Audit and accounts charges ( 0.25 % of I-Works) 749,487
TOTAL INDIRECT CHARGES 1,049,062
TOTAL CIVIL WORKS 326,453,852
B ELECTRO MECHANICAL WORKS. 129,088,569
C TRANSMISSION LINE 15,000,000
TOTAL COST ( Civil Electrical) 470,542,421
Interest during construction +Soft Costs (At Debt: Equity ratio of 70:30)
TOTAL COST (Including) IDC
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 193
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Abstract of costs of C-Civil Works and for power plant Dudhpathri MHP (2 x 3 ) MW
S.no Description Amount( in Rs)
Head works, weir and under sluice inch diversion 42208837
Desilting Basin 29349889.73
Water conductor system 81969851.75
Forebay 21440815.41
Penstock 28510932.59
Power house , tail race and switch yard 41170452.16
Escape pipe ( spill way) 19070400.8
Total civil works 263721180
1 Preliminary 2.00
2 Generating Plant and equipments
a) Generator, Turbine and Accessories 531.96
b)Auxiliary equipment and services for power station 176.59
c)Auxiliary electrical equipment for power station 273.33
d)Central sales Tax-(as applicable) on 2(a), (b) , ( c) @ 2% 19.64
e)Transportation ,handling insurance charges @6% of 2 (a) , (c), 48.32
f) Erection and commissioning charges @ 8 % of 2(a), (b) , ( c) 78.55
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 194
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Total 1290.89
Grand Total 129088569
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 195
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 196
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 197
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Total 42208837
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 198
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 199
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
15 Supply and fixing of 600 mm dia. sluice valve No. 1 200000 199001.25
for controlling arrangement with all
arrangements like flanges bolts etc as per
technical specifications including dewatering if
any for fixing complete job inch concrete
chamber
TOTAL 29349889.73
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 201
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 202
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 203
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 204
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
1 Excavation in all kinds of soil and rock by drilling cum 2700 436.72 1179143.261
and blasting including dressing the sides,
transporting the excavated materials, stacking the
serviceable material and returning the stacked soil
in 15cm layers whenever required into sides of
foundation and trenches etc. consolidating each
deposited layer by ramming and watering and
disposal of unserviceable material beyond the
working area for all leads and lifts complete as per
specifications & drawings or as directed by the
Engineer-in-Charge. Including dewatering charges
complete job.
2 Providing, laying, compacting and curing plain cum 116 6963.80 807801.2483
cement concrete of M-7.5 grade or by nominal mix
as per IS:456 with max. 40 mm size aggregates, in
foundations, pipe lines, under floors, protective
course, filling etc. at all depths as per
specifications, inclusive of cost and carriage of all
materials, admixtures and dewatering if required
but excluding reinforcement steel cost complete.
3 Supplying, laying, compacting and curing cum 890 10297.92173 9165150.338
reinforced cement concrete of M-20 grade (350 kg
of cement per cum) as per IS:456 using 20 mm
down aggregates at all leads and depths as per
Specifications including formwork, scaffolding
dewatering and cost and carriage of all materials.
4 Providing and fixing TMT/tor steel reinforcement MT 45 63250.225 2846260.125
Fe 500 grade for RCC works including handling,
storage, straightening, cutting, bending, binding,
welding the joints, placing in position wire clips,
separators, Chairs,Laps,anchors and other
fastening devices using 18 SWG black annealed
binding wire wherever required for all leads & lifts
complete in all respects as per specifications and
drawings or as directed by the Engineer-in-Charge
inclusive of all material cost and carriage and
dewatering if any complete job.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 205
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
5 Gabion walls placed in position with boulders cum 540 1877.673609 1013943.749
weighing minimum 30kg in wire crate made of
wire mesh 100x100mm panels as per IS:1556,
made by 5mm dia. Steel wire having yield strength
of 225Mpa, including all labor, materials &
equipments , dewatering as per drawings & l
Technical Specifications complete job..
PENSTOCK/STEEL LINER
Supply, fabrication and Erection other Jobs
6 Supply, rolling, fabrication, erection welding and MT 98 127,493 12444633.87
transportation to the project site the following
items conforming to specifications material ASTM-
A-516 Gr. 70 or IS 2002 grade II including
handling, plate marking, cutting, edge
preparation, rolling, welding, machining etc., as
per specifications inclusive of cost of all materials,
all applicable taxes and duties and carriage
complete job including dewatering. Ultrasonic
examination of welds in shop comprising 100%
weld length of circumferential joints as per
technical specifications, repair of defective joints,
if any, and retesting until satisfactory results are
obtained complete job. Ultrasonic examination of
welds in shop comprising 100% weld length of
circumferential joints as per technical
specifications, repair of defective joints, if any, and
retesting until satisfactory results are obtained
complete job Hydrostatic testing etc. Surface
preparation by sand blasting and painting of
interior surfaces of all items covered under 18
excluding a band of 150mm on both ends of each
shell/pipe assembly. The painting shall include two
coats of Zinc rich Primer followed by two coats of
coal tar epoxy paint, complete job.
7 Earth back fill cum 2100 300 630000
8 Providing and filling of Boulders by laying & Sqm 530 800 424000
compacting boulders including carriage and
material cost and dewatering of required as
specified in drawings or as directed by Engineer-
In-charge at locations wherever required or as
specified in relevant drawing and as per
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 206
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
TOTAL 28510932.59
Quantity and Rate Schedule of Power House, Tailrace, switchyard for Dudhpathri MHP (2 x 3 ) MW
1 Excavation in closed form from all sides i.e. Cum. 18500 436.72 8079314.936
excavation in pits, foundation, trenches and cut
offs etc. in al types of soil/ sand murum/ sand
and murum with boulders, gravels, kankar, soft
rock, hard rock, weathered and disintegrated
rock manually or mechanically including in wet
condition and removal thereof. Excavated spoils
will be disposed up to a lead of 2.5 KM at
specified places including stacking of selective
re-usable material as directed by Engineer-in-
charge and as per specifications ,inclusive of
cost and carriage of all materials required ,
dewatering . Complete as per technical
specifications.
2 Supplying, laying, compacting and curing plain Cum. 44 6963.80 306407.37
cement concrete of M-7.5 grade or by nominal
mix (230 kg of cement per cum) as per IS:456
with max. 40 mm size aggregates, in
foundations, pipe lines, under floors, protective
course, filling etc. at all depths as per
specifications including shuttering, cost and
carriage of all materials and dewatering..
3 Supplying, laying, compacting and curing Cum. 1230 10297.9217 12666443.73
reinforced cement concrete of M-20 grade ( 350
kg of cement per cum) as per IS:456 using
maximum 20 mm down aggregates at all depths
as per Specifications including cost ,carriage of
formwork, scaffolding and dewatering, curing
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 207
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
4 Providing and laying of second stage RCC M-35 Cum. 15 11097.9217 166468.8259
(wherever required) including cost and carriage
of graded aggregate and coarse sand from
approved source to site of work, including
cleaning, screening and washing of sand and
aggregate, laying, mixing and compaction by
vibrators, shuttering and other charges for
complete job, including cost and carriage of
cement but excluding cost and carriage of
reinforcement, including dewatering if any
complete job.
5 Providing and fixing TMT/tor steel MT 73.8 63250.225 4667866.605
reinforcement Fe 500 grade for RCC works
including handling, storage, straightening
cutting, bending, binding, welding the joints,
placing in position wire clips, separators, chairs,
laps and other fastening devices using 18 SWG
black annealed binding wire wherever required
for all leads & lifts complete in all respects as
per specifications and drawings or as directed by
the Engineer-in-Charge including cost and
carriage of all materials and dewatering. as per
technical specifications.
6 Flood protection in form of Plain Concrete walls. Cum. 650 8848.7 5751665.217
7 Brickwork in 1:4 cement sand mortar including Cum. 210 8477.93 1780365.147
cost of materials, carriage and scaffolding etc as
per specifications complete job
8 Gabion walls placed in position with boulders Cum. 460 1877.67361 863729.8603
weighing minimum 30kg in wire crate made of
wire mesh 100x100mm panels as per IS:1556,
made by 5mm dia. Steel wire having yield
strength of 225Mpa, including all labor,
materials & equipments , dewatering as per
drawings & l Technical Specifications complete
job..
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 208
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 209
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 210
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 211
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 212
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
S.no.
Item Unit Qty Rate Amount
1 Earthwork excavation of all sorts of soil under all conditions of
saturation including jumper work, breaking of boulders, cutting
of rocks of all types, including cost and carriage of blasting
materials, shoring, strutting, hire charges of machinery if any,
dewatering charges, cost and carriage of mechanical equipment
to the site of work, including all lifts involved for the
simultaneous deposal of slopes complete job, including
dewatering and as per technical specifications with all lead and
3
lifts. M 9450 436.72 4127001.413
2 Providing and laying of PCC M-7.5 mix including cost and
carriage of graded aggregate, coarse sand from source to site of
work, cleaning, screening, washing, excluding dewatering if any,
boxing, shuttering, scaffolding charges mixing and carriage of
admixtures as per requirement curing and all other connected
charges for complete job, including cost and carriage of cement
3
as per relevant codes and technical specifications. M 19 6963.80 132312.2734
3 Providing and laying of RCC M-20 including cost and carriage of
graded aggregate and coarse sand from approved source to site
of work, including cleaning, screening and washing of sand and
aggregate, laying, mixing and compaction by vibrators,
shuttering and other charges for complete job, including cost
and carriage of cement but excluding cost and t, including
3
dewatering if any complete job. M 805 10297.9217 8289826.991
4 Supplying, cutting, straightening, bending and fixing
reinforcement bars, using 18 SWG black annealed binding wire MT 45 63250.225 2846260.125
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 213
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Total 19070400.8
A-PRELIMINARY
Amount
( In Rs)
S.no. Description
1 Expenditure incurred on previous investigations 0.00
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 214
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
3.4 Consultants fee including charges for preliminary design work etc. 200000.00
Consultancy charges for preparation of prequalification bid/documents &
3.5 evaluation 500000.00
4 General
4.1 Training of engineers 200000.00
Govt/Forest/Private
ABSTRACT OF COST
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 215
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
ABSTRACT OF COST
K-BUILDING
S No Description of items Amount (In Rs)
1 Construction of permanent residential building . 3500000.00
M- PLANTATION
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 216
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
0- MISCELLANEOUS
Amount
S.no. Description of items (In Rs)
1 Provision of water supply, sewerage disposal and storm water drains etc. 200000
2 Furnishing & supply of equipment of 200000
3 Purchase of equipment for quality control lab. And field laboratories 600000
4 Fire, fighting equipment 150000
Provision of telecommunication system including wireless sets, Telex and telephone
5 system. 80000
6 Running and maintenance of Equipment and facilities 300000
7 Provision of security arrangements 200000
11 Boundary pillars & bench marks etc. 200000
12 Inauguration & other ceremonies etc. 200000
15 Photography & publicity 50000
17 Water tanker for dust suppression 100000
18 Canteen facilities 300000
21 Maintenance of roads for 2 years 400000
22 Construction Power 250000
Maintenance of roads for 5 years @ Rs. 0.50 lac/year/km for 10km and 0.40
23 lacs/year/km for 4 km of colonies.
Total 3230000
Q- SPECIAL T & P
Particulars Amount (In Rs)
Special T & P (Proposed as per Standard Guide lines)
L. Sum 700000
Total Amount 700000
R- COMMUNICATION
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 217
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Amount
S. No Description of items Qty Unit Rate/Unit ( In Rs)
Y – LOSSES ON STOCK
Amount
Particulars (In Rs)
Losses on stock provided @ 0.25% of C-Works, J-Power Plant Civil Works and K-buildings
Total amount 676365.45
II – ESTABLISHMENT
S.no. Particulars Amount (Rs)
Establishment charges to be provided @ 5% of( I-works less B-
1 Land.+E&M)
Total amount 25373523.37
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 218
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
1 Provision for T&P ordinary (proposed as per standard guidelines) in L.S 500000
Total amount 500000
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 219
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
b) Structural Steel (plates, beams, angles, channels, etc.) conforming to IS: 800
MS Steel Plates (Thickness/Size average) 52000
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 220
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
3 STONE BALLAST
(i) 40 mm Stone ballast
Cost of 40 mm Stone ballast at source per cum 1050
Cartage up to site per cum 1400
Basic rate per cum 2450
5 FINE SAND
Cost of find sand at source per cum 1100
Cartage up to site 650
Basic rate per cum 1750
6 BOULDER (150 mm to 300 mm size)
Cost of boulder up to road head per cum 600
Cartage up to site 250
Basic rate per cum 850
7 STONES
Cost of stones including carriage for 2.83 cum (100 cft) load. 2800
Cost of stone per Cum 989.40
Basic rate per cum 2800
8 BRICKS-First class.
Cost of bricks including carriage one truck load of 3000 nos. 22000
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 221
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Cost of rolling shutter including all accessories with two coats of paint/Sq.
m and labor for fixing 5500
EXCAVATION IN SOFT ROCK / HARD ROCK OR EARTH MIXED WITH BOULDERS FOR ALL LEADS AND
LIFTS
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 222
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
7 Sub-total 37975
Total 38544.625
Add OH and Contractor’s
profit @ 10%. 3854.4625
Say Rs 436.72
a) MATERIAL
Stone ballast 40 mm and down
gauge Cum 0.89 2450 2180.5
Cement
Cum 0.12 15,435 1852.25
Sand
Cum 0.47 1750 822.5
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 223
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
b) Labour
Total 6054.75
Total 6145.57
Add OH and Contractor’s profit
@ 10%. 614.56
a) MATERIAL
Stone ballast 40/20 mm and
down gauge Cum 0.85 2475 2104
Cement
Cum 0.226 15,435 3488
Sand
Cum 0.45 1750 787.5
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 224
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
b) Labour
Total 7694
Total 7810
Say Rs 8849
a) MATERIAL
Stone ballast 40/20 mm and
down gauge
Cum 0.85 2450 2082.5
Cement
Cum 0.283 15,435.4 4368.2239
Sand 2,300
Cum 0.43 989
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 225
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
b) Labour
Total 8954.2239
Total 9088.5372
Say 10297.92
a) MATERIAL
Bricks
CM 1 3483 3483.33333
Cement
Cum 0.064 15,435 987.9
Sand
Cum 0.26 2300 598
b) Labour
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 226
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Total 6506.70
Total 7482.71
Say 8477.93
a) MATERIAL
b) Labour
Total 5127
Total 5204
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 227
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Say 5897
Total 4771.515
Add OH and Contractor’s profit
@ 10%. 477.15
Total per 2.88 Cum 5248.67
Rate per Cum 1822.45
Say 1877.6736
REINFORCEMENT STEEL
Unit rate per MT
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 228
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
STRUCTURAL STEEL
Unit rate per MT
Analysis of 1 M.T.
Total 60025.72
A) Materials
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 230
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
B) Fabrication
Fabrication, transportation to
ii) site complete MT 21500
c) Erection
Erection of penstock at site
complete in all respect as per
iii) given site conditions and testing MT 24000
Prime Cost (i) + (ii) + (iii) 107026.65
Add for Painting, Testing
complete 5500.00
Add for overhead charges &
Contractor's profit @ 10% of
prime cost 11252.665
Say 127,493
A MATERIAL
Stone boulder Nallah
no 0.475 850 403.75
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 231
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Cement
Cum 0.155 15,435.4 2392.4901
20 mm aggregate
Cum 0.94 2500 2350
Sand 2300
Cum 0.47 1081
Labour 0
Total 7466.74
Total 7578.74
Add OH and Contractor’s
profit @ 10%. 757.87
Say 6870.08
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 233
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 234
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
PART I
CHAPTER 13
FINANCIAL EVALUATION
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 235
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
CHAPTER - 13
FINANCIAL EVALUATION
13.1 standards
The financial analysis of the Project has been carried out based upon following parameters:
1. Hydrology of the project as worked out under Chapter 3 of Part-I of this Project report
have been adopted.
2. Energy calculations have been carried out for the dependable flow as described under
Chapter 4 of this Project report. It is proposed to install 2 machines of 3000 kW each
capacity, which would produce about 30.5 gross million units of energy annually in a 75%
Dependable year.
3. Cost of civil and hydro-mechanical (H-M) works has been computed based upon the
quantities worked out from the drawings and multiplying the same with rates analysed
by using market rates of materials and prevailing rates of skilled / semi-skilled workers.
4. Total Cost of Civil and Hydro-Mechanical Works is Rs. 3264.5 Lacs.
5. Cost of electrical-mechanical (E&M) works has been estimated from our experience and
quotations received from reputable equipment manufacturers.
6. Total Cost of Electrical-Mechanical Works including Erection, Testing, Commissioning,
Trial Runs, Freight, Insurance, CST, Excise etc. works out to Rs. 1290.89Lacs.
7. Cost of Transmission Works (T) including terminal equipment at interconnection in the
sub-station is Rs. 150 Lacs.
8. Total Cost of E&M and T works is Rs. 1440.89 Lacs.
9. Total Capital Cost of Civil, H-M and E&M works including cost of Switchyard equipment
and transmission line to PDD sub-station works out to Rs. 4705.4 Lacs.
10. Construction period of 36 months has been considered.
11. Component of Loan and Equity have been kept as 70:30 respectively.
12. Income Tax holiday for the first ten years has been considered.
13. Interest Rate on Loans has been considered at 13%.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 236
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
14. Repayment has been considered at 8 years, with 3 years moratorium during the period of
construction (2.5 years) and after commercial operations (0.5 year), as per Institutional
Norms.
15. Return on Equity @ 19.6% has been considered for calculating the cost of generation.
16. Financial Evaluation Period has been considered as 37 years.
13.2 FINANCIAL ANALYSIS
13.2.1 Capital cost of the Project including cost of the E&M, T&D and Civil & H-M works
has been computed as Rs. 4705 Lacs. Total cost of the project works out to Rs. 5420 Lacs,
including Interest during Construction (IDC) of Rs. 541.64 Lacs, Financial Charges of Rs. 18.97 Lacs
.
13.2.2 O&M Cost, including Insurance costs, have been considered @ 1.5% of the Project
Cost, as per industry norms. An escalation @ 2.5% per annum has been provided.
13.2.3 Depreciation
Annual depreciation @ 3.17% SLM basis has been adopted on cost of Civil and H-M as well as for
E & M costs.
13.2.4 Taxation
As per present Tax laws, a Income tax holiday of 10 years is permitted for power projects.
However, Minimum Alternate Tax (MAT) is applicable on the Book Profit @ 18.33%. Income Tax
beyond 10 years is @ 30.0%. Surcharge on Income Tax and MAT has been considered @ 10%.
Education Cess on Income Tax and MAT has been considered @ 3%.
13.3 Results
15.3.1 Cost of generation per kWh
Analysis has also been carried out to calculate the cost of generation per kWh over a period of 37
years. It would be seen that the cost of generation per unit works out to Rs. 4.94 per unit in the
first year, as full repayment has not been considered. It is Rs. 3.43 per unit in the next year.
Thereafter, it reduces gradually on account of lower interest charges, (consequent to repayment
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 237
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
of loans) till the tenth year to Rs 2.45/unit. As the payment of taxes starts thereafter, the cost of
generation increases rapidly rising from Rs. 2.45 per unit to Rs. 3.13/unit per unit. Cost of
generation for 37 years shall be Rs. 3.16per unit.
The Plant Load Factor (PLF) works out to 58%. Cost per kW works out to Rs. 90000/-. Cost per
MW works out to Rs. 9 crores.
13.3.2 Cash Flow
The Financial workings of the project envisage (a) Repayment of loans in 8 years with a
moratorium of 3 years during the period of construction and after commercial operations,
13.3.3 Debt Service Coverage Ratio
The Debt Service Coverage Ratio (DSCR) indicates an average of 1.8.
13.3.4 Internal Rate of Return
Analysis reveals that the Internal Rate of Return of the project over a period of 37 years is 19.6%.
The project is, therefore, viable considering the unit rate at Rs 3.9.
13.4 CONCLUSIONS AND RECOMMENDATIONS
Project is financially viable and should be implemented for generation capacity of 6.0 MW with.
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 238
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
S.no Particulars
1 Designed Capacity 6 MW
5 Equity 0.3
6 Debit 0.7
20 Receivables 2 months
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 239
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
21 O&M 1 months
30 ROE 18.0%
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 240
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
Repayment schedule
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 241
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project
Detailed Project report JAKEDA Department of science & Technology
474.26 315.97
237.13 11.56
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 243
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
Sales Realisation
1 2 3 4 5 6 7
2 Auxiliary consumption @0.5% 1.52 1.52 1.52 1.52 1.52 1.52 1.52
3 Transformer losses @ 1.0% 1.52 1.52 1.52 1.52 1.52 1.52 1.52
5 12% royalty to GOVT from 11th year 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8 Net Sale in Lakhs 1177.45 1177.45 1177.45 1177.45 1177.45 1177.45 1177.45
Sales Realisation
8 9 10 11 12 13 14 15
S.no Particulars Year Year Year Year Year Year Year Year
1 Units Generated 304.96 304.96 304.96 304.96 304.96 304.96 304.96 304.96
2 Auxiliary consumption @0.5% 1.52 1.52 1.52 1.52 1.52 1.52 1.52 1.52
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 244
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
3 Transformer losses @ 1.0% 1.52 1.52 1.52 1.52 1.52 1.52 1.52 1.52
4 Net Units 301.91 301.91 301.91 301.91 301.91 301.91 301.91 301.91
5 12% royalty to GOVT from 11th year 0.00 0.00 0.00 36.23 36.23 36.23 36.23 36.23
6 Saleable units 301.91 301.91 301.91 265.68 265.68 265.68 265.68 265.68
7 Saleable Rate 3.90 3.90 3.90 3.90 3.90 3.90 3.90 3.90
8 Net Sale in Lakhs 1177.45 1177.45 1177.45 1036.16 1036.16 1036.16 1036.16 1036.16
Sales Realisation
16 17 18 19 20 21 22 23
S.no Particulars Year Year Year Year Year Year Year Year
1 Units Generated 304.96 304.96 304.96 304.96 304.96 304.96 304.96 304.96
2 Auxiliary consumption @0.5% 1.52 1.52 1.52 1.52 1.52 1.52 1.52 1.52
3 Transformer losses @ 1.0% 1.52 1.52 1.52 1.52 1.52 1.52 1.52 1.52
4 Net Units 301.91 301.91 301.91 301.91 301.91 301.91 301.91 301.91
5 12% royalty to GOVT from 11th year 36.23 36.23 36.23 36.23 36.23 36.23 36.23 36.23
6 Saleable units 265.68 265.68 265.68 265.68 265.68 265.68 265.68 265.68
7 Saleable Rate 3.90 3.90 3.90 3.90 3.90 3.90 3.90 3.90
8 Net Sale in Lakhs 1036.16 1036.16 1036.16 1036.16 1036.16 1036.16 1036.16 1036.16
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 245
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
Sales Realisation
24 25 26 27 28 29 30
2 Auxiliary consumption @0.5% 1.52 1.52 1.52 1.52 1.52 1.52 1.52
3 Transformer losses @ 1.0% 1.52 1.52 1.52 1.52 1.52 1.52 1.52
5 12% royalty to GOVT from 11th year 36.23 36.23 36.23 36.23 36.23 36.23 36.23
8 Net Sale in Lakhs 1036.16 1036.16 1036.16 1036.16 1036.16 1036.16 1036.16
Sales Realisation
31 32 33 34 35 36 37
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 246
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
2 Auxiliary consumption @0.5% 1.52 1.52 1.52 1.52 1.52 1.52 1.52
3 Transformer losses @ 1.0% 1.52 1.52 1.52 1.52 1.52 1.52 1.52
5 12% royalty to GOVT from 11th year 36.23 36.23 36.23 36.23 36.23 36.23 36.23
8 Net Sale in Lakhs 1036.16 1036.16 1036.16 1036.16 1036.16 1036.16 1036.16
Particulars 1 2 3 4 5 6 7
1 Interest on term loan 489.37 439.28 377.63 315.97 254.32 192.67 131.01
5 Provision for Taxation 0.00 0.00 0.00 0.00 87.96 110.62 131.19
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 247
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
9 Variable cost of Generation Rs/unit 0.27 0.28 0.28 0.29 0.30 0.30 0.31
Cost of Generation in Rupees
Particulars 8 9 10 11 12 13 14 15
1 Interest on term loan 69.36 11.56 0.00 0.00 0.00 0.00 0.00 0.00
3 SLM Depreciation 171.82 171.82 171.82 171.82 171.82 171.82 171.82 171.82
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 248
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
5 Provision for Taxation 150.12 166.99 173.89 265.36 271.80 277.30 282.02 286.09
6 Total Charges 780.62 742.11 739.93 831.39 837.83 843.33 848.05 852.13
7 Units available 301.91 301.91 301.91 265.68 265.68 265.68 265.68 265.68
8 Cost of Generation 2.59 2.46 2.45 3.13 3.15 3.17 3.19 3.21
9 Variable cost of Generation Rs/unit 0.32 0.33 0.34 0.38 0.38 0.38 0.38 0.38
Particulars 16 17 18 19 20 21 22
1 Interest on term loan 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5 Provision for Taxation 289.63 292.73 295.44 297.82 299.93 301.79 303.45
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 249
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
9 Variable cost of Generation Rs/unit 0.38 0.38 0.38 0.38 0.38 0.38 0.38
Particulars 23 24 25 26 27 28 29 30
1 Interest on term loan 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3 SLM Depreciation 171.82 171.82 171.82 171.82 171.82 171.82 171.82 171.82
5 Provision for Taxation 304.93 306.24 307.41 308.46 309.40 310.24 310.99 311.67
6 Total Charges 870.96 872.27 873.44 874.49 875.43 876.27 877.02 877.70
7 Units available 265.68 265.68 265.68 265.68 265.68 265.68 265.68 265.68
8 Cost of Generation 3.28 3.28 3.29 3.29 3.30 3.30 3.30 3.30
9 Variable cost of Generation Rs/unit 0.38 0.38 0.38 0.38 0.38 0.38 0.38 0.38
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 250
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
Particulars 31 32 33 34 35 36 37
1 Interest on term loan 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5 Provision for Taxation 312.27 312.27 312.82 313.31 313.75 314.14 314.50
9 Variable cost of Generation Rs/unit 0.38 0.38 0.38 0.38 0.38 0.38 0.38
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 251
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
CALCULATION OF DEPRECIATION
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 252
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 253
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 254
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 255
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
Sno Year Land and Site development Civil Cost E&M Total Lakhs
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 256
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 257
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 258
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 259
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
Service 1 2 3 4 5 6 7
3 Interest on Term Loan 489.37 439.28 377.63 315.97 254.32 192.67 131.01
Debit 1 2 3 4 5 6 7
1 Instalment of term Loan 237.13 474.255 474.255 474.26 474.255 474.3 474.3
2 Interest on Term Loan 489.37 439.28 377.63 315.97 254.32 192.67 131.01
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 260
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
6 ADSCR 1.50
Service 1 2 3 4 5 6 7
4 Interest on Term Loan 489.37 439.28 377.63 315.97 254.32 192.67 131.01
Debit 1 2 3 4 5 6 7
1 Instalment of term Loan 237.13 474.26 474.26 474.26 474.26 474.26 474.26
2 Interest on Term Loan 489.37 439.28 377.63 315.97 254.32 192.67 131.01
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 261
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
Service 1 2 3 4 5 6 7
1 Interest on Term Loan 489.37 439.28 377.63 315.97 254.32 192.67 131.01
2 Net sale realisation 1177.45 1177.45 1177.45 1177.45 1177.45 1177.45 1177.45
Debit Year 1 2 3 4 5 6 7
1 Instalment of term loan 237.13 474.26 474.26 474.26 474.26 474.26 474.26
2 Interest on term loan 489.37 439.28 377.63 315.97 254.32 192.67 131.01
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 262
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
Service 8 9 10 11 12 13 14 15
3 Interest on Term Loan 69.36 11.56 0.00 0.00 0.00 0.00 0.00 0.00
5 Sub Total
Debit 8 9 10 11 12 13 14 15
4 Sub Total
6 ADSCR
Service 8 9 10 11 12 13 14 15
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 263
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
3 Cash Accruals 861.34 899.84 902.03 669.27 662.82 657.33 652.61 648.53
4 Interest on Term Loan 69.36 11.56 0.00 0.00 0.00 0.00 0.00 0.00
Debit 8 9 10 11 12 13 14 15
1 Instalment of term Loan 474.26 237.13 0.00 0.00 0.00 0.00 0.00 0.00
5 Gross ADSCR
Service 8 9 10 11 12 13 14 15
1 Interest on Term Loan 69.36 11.56 0.00 0.00 0.00 0.00 0.00 0.00
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 264
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
2 Net sale realisation 1177.45 1177.45 1177.45 1036.16 1036.16 1036.16 1036.16 1036.16
3 O&M Cost 96.64 99.06 101.53 101.53 101.53 101.53 101.53 101.53
4 Administrative expenses 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Debit Year 8 9 10 11 12 13 14 15
1 Instalment of term loan 474.26 237.13 0.00 0.00 0.00 0.00 0.00 0.00
2 Interest on term loan 69.36 11.56 0.00 0.00 0.00 0.00 0.00 0.00
Service 16 17 18 19 20 21 22
3 Interest on Term Loan 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5 Sub Total
Debit 16 17 18 19 20 21 22
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 265
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
4 Sub Total
5 DSCR
6 ADSCR
Service 16 17 18 19 20 21 22
4 Interest on Term Loan 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Debit 16 17 18 19 20 21 22
1 Instalment of term Loan 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 266
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
4 DSCR
5 Gross ADSCR
6 Net DSCR
Service 16 17 18 19 20 21 22
1 Interest on Term Loan 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 Net sale realisation 1036.16 1036.16 1036.16 1036.16 1036.16 1036.16 1036.16
Debit Year 16 17 18 19 20 21 22
1 Instalment of term loan 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 Interest on term loan 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 267
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
Service 23 24 25 26 27 28 29 30
3 Interest on Term Loan 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5 Sub Total
Debit 23 24 25 26 27 28 29 30
4 Sub Total
5 DSCR
6 ADSCR
Service 23 24 25 26 27 28 29 30
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 268
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
3 Cash Accruals 629.70 628.39 627.21 626.17 625.23 624.39 623.63 622.96
4 Interest on Term Loan 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Debit 23 24 25 26 27 28 29 30
1 Instalment of term Loan 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4 DSCR
5 Gross ADSCR
6 Net DSCR
Service 23 24 25 26 27 28 29 30
1 Interest on Term Loan 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 269
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
2 Net sale realisation 1036.16 1036.16 1036.16 1036.16 1036.16 1036.16 1036.16 1036.16
3 O&M Cost 101.53 101.53 101.53 101.53 101.53 101.53 101.53 101.53
4 Administrative expenses 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Debit Year 23 24 25 26 27 28 29 30
1 Instalment of term loan 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 Interest on term loan 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Service 31 32 33 34 35 36 37
3 Interest on Term Loan 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5 Sub Total
Debit 31 32 33 34 35 36 37
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 270
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
4 Sub Total
5 DSCR
6 ADSCR
Service 31 32 33 34 35 36 37
4 Interest on Term Loan 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Debit 31 32 33 34 35 36 37
1 Instalment of term Loan 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 271
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
4 DSCR
5 Gross ADSCR
6 Net DSCR
Service 31 32 33 34 35 36 37
1 Interest on Term Loan 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 Net sale realisation 1036.16 1036.16 1036.16 1036.16 1036.16 1036.16 1036.16
Debit Year 31 32 33 34 35 36 37
1 Instalment of term loan 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 Interest on term loan 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 272
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
1 Total sale realisation 1177.45 1177.45 1177.45 1177.45 1177.45 1177.45 1177.45
2 Carbon Credits 0 0 0 0 0 0 0
7 Interest on term loan 489.37 439.28 377.63 315.97 254.32 192.67 131.01
9 Provision for Tax 0.00 0.00 0.00 0.00 87.96 110.62 131.19
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 273
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
1 Total sale realisation 1177.45 1177.45 1177.45 1036.16 1036.16 1036.16 1036.16 1036.16
2 Carbon Credits 0 0 0 0 0 0 0 0
3 O&M Cost 96.64 99.06 101.53 101.53 101.53 101.53 101.53 101.53
5 Depreciation SLM 171.82 171.82 171.82 171.82 171.82 171.82 171.82 171.82
7 Interest on term loan 69.36 11.56 0.00 0.00 0.00 0.00 0.00 0.00
9 Provision for Tax 150.12 166.99 173.89 265.36 271.80 277.30 282.02 286.09
11 Retained Profit 689.52 728.03 730.21 497.45 491.01 485.51 480.79 476.72
1 Total sale realisation 1036.16 1036.16 1036.16 1036.16 1036.16 1036.16 1036.16
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 274
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
2 Carbon Credits 0 0 0 0 0 0 0
7 Interest on term loan 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9 Provision for Tax 289.63 292.73 295.44 297.82 299.93 301.79 303.45
1 Total sale realisation 1036.16 1036.16 1036.16 1036.16 1036.16 1036.16 1036.16 1036.16
2 Carbon Credits 0 0 0 0 0 0 0 0
3 O&M Cost 101.53 101.53 101.53 101.53 101.53 101.53 101.53 101.53
5 Depreciation SLM 171.82 171.82 171.82 171.82 171.82 171.82 171.82 171.82
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 275
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
7 Interest on term loan 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9 Provision for Tax 304.93 306.24 307.41 308.46 309.40 310.24 310.99 311.67
11 Retained Profit 457.88 456.57 455.40 454.35 453.41 452.57 451.82 451.14
1 Total sale realisation 1036.16 1036.16 1036.16 1036.16 1036.16 1036.16 1036.16
2 Carbon Credits 0 0 0 0 0 0 0
7 Interest on term loan 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9 Provision for Tax 312.27 312.27 312.82 313.31 313.75 314.14 314.50
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 276
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
TAXATION AS PER COMPANY LAW Year Year Year Year Year Year Year
S.no Particulars 1 2 3 4 5 6 7
3 Tax Norm Depreciation 794.937 652.210 539.565 450.040 378.360 320.517 273.460
5 Qualifying amount for Tax 0.00 0.00 0.00 0.00 455.03 572.29 678.70
6 Rebate during first 10 years 0.00 0.00 0.00 0.00 455.03 572.29 678.70
9 Tax as per MAT 0.000 0.000 0.000 0.000 87.958 110.623 131.192
10 Provisions for Taxation 0.00 0.00 0.00 0.00 87.96 110.62 131.19
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 277
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
TAXATION AS PER COMPANY LAW Year Year Year Year Year Year Year Year
S.no Particulars 8 9 10 11 12 13 14 15
2 Depreciation SLM 171.82 171.82 171.82 171.82 171.82 171.82 171.82 171.82
3 Tax Norm Depreciation 234.860 202.933 176.309 153.931 134.977 118.808 104.925 92.930
5 Qualifying amount for Tax 776.59 863.90 899.61 780.69 799.65 815.82 829.70 841.70
9 Tax as per MAT 150.115 166.992 173.895 150.908 154.572 157.697 160.381 162.700
10 Provisions for Taxation 150.12 166.99 173.89 265.36 271.80 277.30 282.02 286.09
TAXATION AS PER COMPANY LAW Year Year Year Year Year Year Year
S.no Particulars 16 17 18 19 20 21 22
3 Tax Norm Depreciation 82.510 73.414 65.439 58.420 52.221 46.732 41.858
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 278
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
5 Qualifying amount for Tax 852.12 861.21 869.19 876.21 882.40 887.89 892.77
7 Profit/loss subjected to Tax 852.12 861.21 869.19 876.21 882.40 887.89 892.77
8 Income Tax Amount 289.634 292.726 295.436 297.822 299.929 301.795 303.452
9 Tax as per MAT 164.714 166.472 168.014 169.371 170.569 171.630 172.572
10 Provisions for Taxation 289.63 292.73 295.44 297.82 299.93 301.79 303.45
TAXATION AS PER COMPANY LAW Year Year Year Year Year Year Year Year
Sno Particulars 23 24 25 26 27 28 29 30
2 Depreciation SLM 171.82 171.82 171.82 171.82 171.82 171.82 171.82 171.82
3 Tax Norm Depreciation 37.522 33.657 30.207 27.123 24.363 21.891 19.675 17.687
5 Qualifying amount for Tax 897.10 900.97 904.42 907.50 910.26 912.73 914.95 916.94
7 Profit/loss subjected to Tax 897.10 900.97 904.42 907.50 910.26 912.73 914.95 916.94
8 Income Tax Amount 304.925 306.239 307.412 308.460 309.398 310.238 310.992 311.667
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 279
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
9 Tax as per MAT 173.410 174.157 174.824 175.420 175.954 176.432 176.860 177.244
10 Provisions for Taxation 304.93 306.24 307.41 308.46 309.40 310.24 310.99 311.67
TAXATION AS PER COMPANY LAW Year Year Year Year Year Year Year
S.no Particulars 31 32 33 34 35 36 37
3 Tax Norm Depreciation 15.90 15.904 14.302 12.863 11.571 10.409 9.364
5 Qualifying amount for Tax 918.72 918.72 920.32 921.76 923.05 924.22 925.26
7 Profit/loss subjected to Tax 918.72 918.72 920.32 921.76 923.05 924.22 925.26
8 Income Tax Amount 312.274 312.274 312.818 313.307 313.746 314.141 314.496
9 Tax as per MAT 177.589 177.589 177.899 178.177 178.426 178.651 178.853
10 Provisions for Taxation 312.27 312.27 312.82 313.31 313.75 314.14 314.50
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 280
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
1 Debt 3794.04
2 Equity 1416.02
3 Incentive 10
4 Subsidy 200
6 Total inflow 5420.06 1096.15 1094.12 1092.04 1089.90 1087.71 1085.47 1083.17
7 Cash outflow
10 Interest on term loan 489.37 439.28 377.63 315.97 254.32 192.67 131.01
12 Total outflow 5420.06 726.50 913.53 851.88 790.23 816.53 777.54 736.46
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 281
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
CASH FLOW Year Year Year Year Year Year Year Year
S.no Particulars 8 9 10 11 12 13 14 15
1 Debt
2 Equity
3 Incentive
4 Subsidy
6 Total inflow 1080.81 1078.40 1075.92 934.63 934.63 934.63 934.63 934.63
7 Cash outflow
8 Capital expenditure
10 Interest on term loan 69.36 11.56 0.00 0.00 0.00 0.00 0.00 0.00
11 Provision for Tax 150.115 166.992 173.895 265.358 271.801 277.296 282.015 286.092
12 Total outflow 693.73 415.68 173.89 265.36 271.80 277.30 282.02 286.09
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 282
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
13 Opening balance 2015.88 2402.96 3065.68 3967.70 4636.97 5299.79 5957.12 6609.73
15 Closing Balance 2402.96 3065.68 3967.70 4636.97 5299.79 5957.12 6609.73 7258.26
Sno Particulars 16 17 18 19 20 21 22
1 Debt
2 Equity
3 Incentive
4 Subsidy
7 Cash outflow
8 Capital expenditure
10 Interest on term loan 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11 Provision for Tax 289.634 292.726 295.436 297.822 299.929 301.795 303.452
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 283
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
CASH FLOW Year Year Year Year Year Year Year Year
S.no Particulars 23 24 25 26 27 28 29 30
1 Debt
2 Equity
3 Incentive
4 Subsidy
6 Total inflow 934.63 934.63 934.63 934.63 934.63 934.63 934.63 934.63
7 Cash outflow
8 Capital expenditure
10 Interest on term loan 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11 Provision for Tax 304.925 306.239 307.412 308.460 309.398 310.238 310.992 311.667
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 284
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
12 Total outflow 304.93 306.24 307.41 308.46 309.40 310.24 310.99 311.67
13 Opening balance 11719.85 12349.55 12977.93 13605.15 14231.31 14856.54 15480.93 16104.56
15 Closing Balance 12349.55 12977.93 13605.15 14231.31 14856.54 15480.93 16104.56 16727.52
S.no Particulars 31 32 33 34 35 36 37
1 Debt
2 Equity
3 Incentive
4 Subsidy
7 Cash outflow
8 Capital expenditure
10 Interest on term loan 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11 Provision for Tax 312.274 312.274 312.818 313.307 313.746 314.141 314.496
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 285
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
Balance Sheet
Year Year Year Year Year Year Year
S.no Particulars 1 2 3 4 5 6 7
A Assets
4 Cash & Bank Balances 369.65 550.24 790.39 1090.07 1361.25 1669.17 2015.88
B Liabilities 1 2 3 4 5 6 7
4 Incentive 10 10 10 10 10 10 10
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 286
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
S.no Particulars 8 9 10 11 12 13 14 15
A Assets
1 Gross Block 5420.06 5420.06 5420.06 5420.06 5420.06 5420.06 5420.06 5420.06
2 Less Depreciation 1374.53 1546.34 1718.16 1889.98 2061.79 2233.61 2405.42 2577.24
3 Net Block 4045.53 3873.72 3701.90 3530.09 3358.27 3186.45 3014.64 2842.82
4 Cash & Bank Balances 2402.96 3065.68 3967.70 4636.97 5299.79 5957.12 6609.73 7258.26
5 Total Assets 6448.49 6939.39 7669.60 8167.05 8658.06 9143.58 9624.37 10101.09
B Liabilities 8 9 10 11 12 13 14 15
4 Incentive 10 10 10 10 10 10 10 10
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 287
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
C Total Liabilities 6398.49 6889.39 7619.60 8117.05 8608.06 9093.58 9574.37 10051.09
Balance Sheet
Year Year Year Year Year Year Year Year
S.no Particulars 16 17 18 19 20 21 22 23
A Assets
1 Gross Block 5420.06 5420.06 5420.06 5420.06 5420.06 5420.06 5420.06 5420.06
2 Less Depreciation 2749.06 2920.87 3092.69 3264.50 3436.32 3608.14 3779.95 3951.77
3 Net Block 2671.01 2499.19 2327.37 2155.56 1983.74 1811.93 1640.11 1468.29
4 Cash & Bank Balances 7903.26 8545.16 9184.34 9821.15 10455.84 11088.67 11719.85 12349.55
5 Total Assets 10574.26 11044.35 11511.72 11976.71 12439.59 12900.60 13359.96 13817.84
B Liabilities 16 17 18 19 20 21 22 23
1 Term Loan 0 0 0 0 0 0 0 0
4 Incentive 10 10 10 10 10 10 10 10
C Total Liabilities 10524.26 10994.35 11461.72 11926.71 12389.59 12850.60 13309.96 13767.84
S.no Particulars 24 25 26 27 28 29 30
A Assets
4 Cash & Bank Balances 12977.93 13605.15 14231.31 14856.54 15480.93 16104.56 16727.52
B Liabilities 24 25 26 27 28 29 30
1 Term Loan 0 0 0 0 0 0 0
4 Incentive 10 10 10 10 10 10 10
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 289
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
Balance Sheet
Year Year Year Year Year Year Year
S.no Particulars 31 32 33 34 35 36 37
A Assets
4 Cash & Bank Balances 17349.87 17972.22 18594.03 19215.35 19836.23 20456.71 21076.84
5 Total Assets
B Liabilities 31 32 33 34 35 36 37
1 Term Loan 0 0 0 0 0 0 0
4 Incentive 10 10 10 10 10 10 10
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 290
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
Capital Cost
1-A. Civil Works
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 291
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
4 Y-Losses in stock 0.25 % of C-works, J civil works power plant and k-buildings 6.76 Lakhs
D Indirect charges
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 292
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
3-C Interest during construction +Soft Costs (At Debt: Equity ratio of 70:30)
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 293
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
Dudhpathri MHP (2 x 3 ) MW
COMPUTATION OF WORKING CAPITAL
2 O&M EXPENSES OF ONE MONTH 6.78 6.94 7.12 7.30 7.48 7.67 7.86
RECEIVABLES ( 2 MONTHS) OF FIXED
3 CHARGES 172.53 164.52 154.59 144.67 149.42 143.30 136.83
4 WORKING CAPITAL REQUIREMENT 179.30 171.46 161.71 151.97 156.90 150.96 144.69
5 INTEREST ON WORKING CAPITAL 17.93 17.15 16.17 15.20 15.69 15.10 14.47
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 294
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
Dudhpathri MHP (2 x 3 ) MW
COMPUTATION OF WORKING CAPITAL
Sno Particulars Year-8 Year-9 Year-10 Year-11 Year-12 Year-13 Year-14 Year-15
1 O & M Expenses 96.64 99.06 101.53 101.53 101.53 101.53 101.53 101.53
O&M EXPENSES OF ONE
2 MONTH 8.05 8.25 8.46 8.46 8.46 8.46 8.46 8.46
RECEIVABLES ( 2 MONTHS) OF
3 FIXED CHARGES 130.10 123.68 123.32 138.57 139.64 140.55 141.34 142.02
WORKING CAPITAL
4 REQUIREMENT 138.16 131.94 131.78 147.03 148.10 149.02 149.80 150.48
INTEREST ON WORKING
5 CAPITAL 13.82 13.19 13.18 14.70 14.81 14.90 14.98 15.05
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 295
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
Dudhpathri MHP (2 x 3 ) MW
COMPUTATION OF WORKING CAPITAL
2 O&M EXPENSES OF ONE MONTH 8.46 8.46 8.46 8.46 8.46 8.46 8.46
RECEIVABLES ( 2 MONTHS) OF FIXED
3 CHARGES 142.61 143.13 143.58 143.98 144.33 144.64 144.91
4 WORKING CAPITAL REQUIREMENT 151.07 151.59 152.04 152.44 152.79 153.10 153.38
5 INTEREST ON WORKING CAPITAL 15.11 15.16 15.20 15.24 15.28 15.31 15.34
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 296
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
Dudhpathri MHP (2 x 3 ) MW
Sno Particulars Year-23 Year-24 Year-25 Year-26 Year-27 Year-28 Year-29 Year-30
1 O & M Expenses 101.53 101.53 101.53 101.53 101.53 101.53 101.53 101.53
2 O&M EXPENSES OF ONE MONTH 8.46 8.46 8.46 8.46 8.46 8.46 8.46 8.46
3 RECEIVABLES ( 2 MONTHS) OF FIXED CHARGES 145.16 145.38 145.57 145.75 145.91 146.05 146.17 146.28
4 WORKING CAPITAL REQUIREMENT 153.62 153.84 154.04 154.21 154.37 154.51 154.63 154.74
5 INTEREST ON WORKING CAPITAL 15.36 15.38 15.40 15.42 15.44 15.45 15.46 15.47
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 297
Consultant: EnCon Group Promoter: JAKEDA
A_ Rouf Infra Energy Pvt. Limited Project Detailed Project report
JAKEDA Department of science & Technology
Dudhpathri MHP (2 x 3
) MW
COMPUTATION OF WORKING CAPITAL
2 O&M EXPENSES OF ONE MONTH 8.46 8.46 8.46 8.46 8.46 8.46 8.46
3 RECEIVABLES ( 2 MONTHS) OF FIXED CHARGES 146.38 146.38 146.48 146.56 146.63 146.70 146.75
4 WORKING CAPITAL REQUIREMENT 154.85 154.85 154.94 155.02 155.09 155.16 155.22
5 INTEREST ON WORKING CAPITAL 15.48 15.48 15.49 15.50 15.51 15.52 15.52
Dudhi Pathri M.H. Project 2 x 850KW) Stage 1st Part I Page 298
Consultant: EnCon Group Promoter: JAKEDA