OF WORKS ACCOMPLISHMENT
PHYSICAL ACCOMPLISHMENT
THIS ACCOMPLISHMENT TOTAL
AMOUNT % QTY AMOUNT
P - 0.0% 0.00 P -
Approved by:
T OF WORKS ACCOMPLISHMENT
PHYSICAL ACCOMPLISHMENT
THIS ACCOMPLISHMENT TOTAL
AMOUNT % QTY AMOUNT
0.85% 7,000.00 99,374.56
3.74% 1,260.00 435,457.94
12.54% 1,205.00 1,459,939.60
0.87% 7,000.00 100,878.12
13.17% 750.00 1,532,810.50
7,578,458.33 66.83% 5,000.00 7,778,964.75
148,640.93 1.28% 42.00 148,640.93
83,933.60 0.72% 40.00 83,933.60
P 7,811,032.86 100.0% 22297.00 P 11,640,000.00
Approved by:
INSPECTION REPORT
As of: February 06 2014
Project: Construction of 1 Unit 2 Storey-8CL Sch. Bldg. Location: Ganassi, Lanao del Sur
DATU ALEEM BALINDONG MNHS Source of Fund: #REF!
Date Started : Target Date : Contract Price:
Contract Time : Date Completed: Contractor :
WORK ACCOMPLISHED
Item No. DESCRIPTION PER CONTRACT CUMMULATIVE
Quantity Unit Unit Cost % Amount Quantity % Amount
0 0 REVISED ORIGINAL #VALUE! #REF! - #VALUE! #VALUE! #VALUE!
100(10) Clearing and Grubing - 7000 #DIV/0! #REF! 99,374.56 #REF! #REF! #REF!
102(1)a Roadway Excavation (Surplus Common) - 1260 #DIV/0! #REF! 435,457.94 - #DIV/0! #DIV/0!
104(1)a Embankment(From Borrow) - 1205 #DIV/0! #REF! 1,459,939.60 - #DIV/0! #DIV/0!
105(1) Subgrade Preparation - 7000 #DIV/0! #REF! 100,878.12 - #DIV/0! #DIV/0!
201 Aggregate Base Coarse - 750 #DIV/0! #REF! 1,532,810.50 - #DIV/0! #DIV/0!
311(1)a Portland Cement Conc. Pavement - 5000 #DIV/0! #REF! 7,778,964.75 - #DIV/0! #DIV/0!
505(1) Cross Pipe Culvert 910mm (38" diam.) - 42 #DIV/0! #REF! 148,640.93 - #DIV/0! #DIV/0!
8 Roofing Works - 40 #DIV/0! #REF! 83,933.60 - #DIV/0! #DIV/0!
9 Carpentry Works #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
10 Electrical Works #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
11 Painting Works #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
12 Plumbing Works #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
13 Sanitary Works #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
14 Tile Works #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
WE HEREBY CERTIFY that we actually inspected the work accomplished by LGU-ganassi, Lanao del Sur in connection with the Const. of 1 Unit 2 Storey 8CL Sch. Bldg. @ DATU ALEEM BALINDONG MNHS, Ganassi,
Lanao del Sur and was inspected on February 6, 2014 and was found to have accomplishment of 70.41% in accordance with the Approved Program of Works, Plan and Specification.
In consideration thereof, the INSPECTORATE TEAM hereby recommends the acceptance of the items of accomplisment.
Republic of the Philippines
Autonomous Region in Muslim Mindanao
OFFICE OF THE DISTRICT ENGINEERING
Bongao Tawi-Tawi
Item No. Descreption Unit Total Contract Unit Price Total Contract Cost wt.% TOTAL QUANTITY Balance of Quantity
100(1) Clearing and Grubbing (w/ Stripping) sq.m. 208,800.00 16.25 3,393,776.58 1.72% Previous This Billi To Date
102(2)a Roadway Excavation (Surplus Common) cu.m. 268,611.70 131.58 35,344,271.17 17.92%
103(1)a Structure Excavation (Common Soil) cu.m. 1,424.70 261.99 373,254.41 0.19%
103(3) Foundation Fill cu.m. 471.62 908.99 428,697.08 0.22%
103(6) Pipe Culvert and Drain Excavation cu.m. 527.10 259.31 136,684.72 0.07%
104(1)a Embankment (From Borrow) cu.m. 54,732.10 573.94 31,413,167.04 15.92%
105(1) Subgrade Prep. ( Common Excavation) sq.m. 173,500.00 16.14 2,800,904.26 1.42%
200 Aggregate Subbase Course cu.m. 33,434.50 1,188.30 39,730,364.83 20.14%
300 Aggregate Surface Course cu.m. 4,420.00 2,144.38 9,478,145.40 4.80%
311(1)a PCCP(Plain-Using Conven'l Method 200mm thk.) cu.m. 39,650.00 1,507.20 59,760,437.97 30.29%
404c Reinf. Steel Bar, Grade 40(Minor Structure) kgs. 24,614.30 76.36 1,879,429.36 0.95%
405 Structure Concrete Class A cu.m. 196.00 11,934.05 2,339,073.89 1.19%
500(1)c Pipe Culvert #36" diam. l.m. 240.00 5,944.60 1,426,703.67 0.72%
505(1) Riprap (Class A) cu.m. 2,625.40 2,470.79 6,486,820.44 3.29%
506 Stone Masonry (Heavy Wall) cu.m. 163.39 5,212.38 851,650.40 0.43%
SPL-1 Temporary Facilities lot 1.00 291,298.11 291,298.11 0.15%
SPL-2 Rental of Service Vehicle mos. 12.00 31,800.00 381,600.00 0.19%
SPL-3 Construction Health and Sefety days 356.00 731.65 260,466.97 0.13%
SPL-4 Mobilization/Demobilization days 4.00 125,724.48 502,897.92 0.25%
197,279,644.22 100.00%
68,400.00
44,525.00
114,390.00
69,340.00
13,310.00
10,010.00
109,575.00
23,650.00
453,200.00 31,800.00
103,200.00
71,400.00