Professional Documents
Culture Documents
Power Supply
Power Supply
The Contractor shall furnish all required materials, labor, tools, equipment,
superintendent, inspection testing and services necessary for a complete installation
and workable system of electrical system and ancillary service system in full
conformity with requirements as indicated on the Drawings, Bill of Quantities and
here-in specified.
(1) Proper materials and good workmanship shall be in compliance with this
specification.
(2) All materials / equipment shall comply with the relevant standards and
shall be suitable for continual use in an ambient condition of 80% RH and
40C.
(3) All materials shall be suitable for the local supply system.
(4) All works shall be carried out to the satisfaction of the Engineer.
(1) All installation, material and equipment shall comply with the
requirements of at least one of the Standards, Codes, Guides and other
documents issued by the Authorities, Institutions and Organizations
referred to in this Specification, Drawings and Bill of Quantities, including
but not limited to the following :
(2) In case of discrepancies between the requirements of above and local codes or
legislations, the local codes and legislations shall be followed.
(3) Where alternatives are indicated in any of the above codes, and this entire
specifications does not identify the option required, then the most durable
material shall be used and the most stringent set of tests applied, unless
otherwise approved by the Engineer.
(4) Any details not specifically covered by these standards shall be subject to the
approval of the Engineer. In the event of contradictory requirements between
such standard and this Specification, the terms of this Specification shall
govern.
(1) Before proceeding with the works, the Contractor shall confirm in writing that
all the provisions of space, structural and non-structural openings for
equipment access or installation, plinths, manholes, etc., as shown on
architectural and other relevant Drawings are satisfactory. Wherever
necessary, the Contractor shall furnish additional information on Structural’s
works required.
(2) The contractor shall be deemed to have allowed all costs for hoisting and
maneuvering items of equipment, accessories, in particular, the transformers
HV and LV switchboards and generator, etc., into the areas or spaces of final
positions. The Contractor shall acquaint himself with loading and space
limitations for the above purposes. Exact positions of equipment shall be set
up on site by the Contractor subject to the approval of the Engineer taking into
consideration the latest architectural and structural Drawings, as well as the
requirements of other services.
(1) The Contractor shall obtain the latest technical information, details and
layouts of other services and the latest architectural and structural Drawings
and shall co-ordinate his works with other trades for a neat, workmanlike
installation. The co-ordination shall be reflected in his shop drawings and
actual installation.
(2) The Contractor shall submit the work program and technical information,
details and layout of his installation to the Engineer for approval and shall
co-operate and co-ordinate for the smooth execution of Works on the Site.
(2) The section engineer shall be authorized by the Contractor to receive and
execute efficiently instruction issued by the Engineer.
(3) In addition to the section engineer, foremen and supervisors shall be provided
by the Contractor as required, to the satisfaction of the Engineer.
(4) Details of the section engineer shall be submitted to the Engineer for
approval. The Engineer reserves the right to remove, or cause remove, the
Contractor’s section engineer from the Site and/or his subordinates who, in
the opinion of the Engineer, fails to perform satisfactorily his duties in the
best interest of the Works. Such action may be taken even after details of the
section engineer have been approved by the Engineer.
(1) The Contractor shall be fully acquainted with the space and storage facilities
available on the Site, and shall arrange for delivery of his equipment and
materials carefully so that, they are in phase with architectural or structural
construction’s schedule while at the same time, in keeping with the available
space and facilities on the Site allocated for his equipment and materials.
(2) Off-site storage of equipment and materials by the Contractor shall be entirely
at the expense of the Contractor. Unless such off-site storage has been
authorized, no payment will be made against off-site storage.
(3) Materials, finished and unfinished work on the Site shall be protected against
interference, inclement weather, and other causes of damage.
(4) The Contractor shall at all times keep his installation reasonable clean and
tidy, and shall remove from the Site at his expense all surplus materials and
temporary works as soon as they are not required.
(5) On completion of the Works, the Contractor shall remove all temporary
covers, casing, etc. and shall clean, remove and make good all stains,
blemishes, markings, etc., to a state ready for handing over.
2.1.9 Discrepancy
The Contractor shall bring to the Engineer’s attention during bidding any and
discrepancies between the Drawings, Bill of Quantities and Specifications. In
general, all Works called for by the Drawings even if not by the Specifications and
vice versa shall be fully executed.
(1) All equipment and cables shall be properly shielded to suppress emission
of interference of radio to B.S. 800 and in accordance with the
requirements as laid down on Radio Communication Regulations Part V :
Regulations of Electrical Interference and local regulation.
2.1.11 Maintenance
(1) During the Period of Maintenance the Contractor shall correct and
reconstruct any defects or damages in accordance with General Condition
clause 24.
(2) Such maintenance and service shall include but not limited to the
following during the maintenance period.
The Contractor shall submit to the Employer of a complete set of specified spares
and required tools at the request of a Certificate of Completion.
The technical information can be submitted together with bid as bidder considers
appropriate.
b) The Contractor shall also be responsible for checking and ensuring that his
proposed program of works is properly coordinated with the Structural
program of works and the nominated contractors, if any.
2.1.16 Samples
(1) Not less than 30 days prior to procurement of the equipment or material, the
Contractor shall submit shop drawing including sample board and catalogues
for approval by the Engineer.
(2) Each sample shall be labeled and submitted with detachable left loose so
that they can be taken apart for examination.
(3) Approval of samples does not release the Contractor’s responsibilities
from furnishing materials as required by this Specification.
(1) Bid Drawings are intended primarily to enable bidders to prepare estimates
and submit bids. Layout of piping, cables, ducting etc. as shown in the
Drawings do not necessarily indicate exact positions of works so that they
should not be used as shop drawings.
(2) The following shop drawings shall be submitted for approval prior to
construction within 150 days after receipt of Notice to Proceed. These
drawings shall be based on the Bid Drawings but amended to account for
any modifications to building or installation which may have taken place,
and for any adjustment due to actual equipment offered.
Part 8/Section 2 8-2-5
a) Switch room, meter room and generator room, (layouts and
sections),
h) Control panel layout and wiring diagrams for all control systems
(3) Within 14 days after approval of shop drawing, three (3) sets each shall be
forwarded to the Engineer at his site office.
(1) All equipment shall be tested. The Contractor shall provide all
instruments, labour or other facilities required for such test by his expenses.
(2) The Contractor shall submit the test procedure to the Engineer for approval
14 days before testing.
(3) After the equipment and wiring system have been completed, the
Contractor shall conduct the required tests under the presence of the Engineer
for all operation, control and outputs. Any defects appearing shall be
remedied to achieve the requirements specified in the Contract.
(1) Before commencement of the Maintenance Period and when the Engineer
requests, the Contractor shall submit the operation and maintenance
Manuals and Instructions for all the equipment to the Engineer for
approval.
(2) The Operation and Maintenance Manuals shall include but not limited to
the followings :
(3) Within seven (7) days after the approval from the Engineer, five (5) final
copies of the Operation and Maintenance Manuals with other date as
requested shall be submitted to the Engineer.
2.2.1.1 Standards
The equipment and accessories shall be designed, manufactured and tested where
applicable, in accordance with the following standards, code or approved equivalent
standards.
All switchgear shall be type tested generally in accordance with IEC Publication 298,
clause 6, including full scale arcing test.
Current transformer and voltage transformer shall be type tested according to IEC
185 and IEC 186.
The high voltage switchgear shall have the following type and ratings :
2.2.1.4 Structure
The panel enclosure type shall be in accordance with IEC 298 or equivalent. Each
type of complete switchgear shall be capable of withstanding without damage the
electro-magnetic and thermal stresses resulting from the maximum asymmetrical
value of short circuit current corresponding to the fault level specified in the
Specification.
The switchgear shall be of standard construction and up-to-date design and shall be
designed to give maximum reliability in service, considering the need for speed of
operation and ease of inspection and maintenance. All components shall be accessibly
mounted in the switchboard and shall not impede access to wiring or terminals.
Insulating barriers and bus supports shall be of an approved material.
Each cubicle shall be divided into separate compartments for busbar, cable
connection and switching device and a low voltage section. The cubicle door shall be
provided with a window through which the position of the switching device easily
can be checked. The low voltage section shall be completely separated from the high
voltage section and be housed in a metal-enclosed terminal box that has space for
relays, instruments and terminal. The apparatus for secondary bus wires between
adjacent cubicles and for secondary wiring in individual units shall have grommets to
prevent damage to wires by sharp metal edges.
The construction shall be robust and be designed to prevent the spreading of damage
due to fire, short circuits, open arcs or other causes. The switchgear shall be designed
to prevent live ports from accidental contact.
Door shall be provided at the front of respective cable connection and circuit breaker
compartment to give full access to apparatus and compartments. The front doors
shall be made from sheet steel of thickness not less than 2.5 mm and shall be lockable
with padlocks.
All equipment, materials and fabrication shall conform to the latest applicable IEC 56
or equivalent. The high voltage circuit breaker shall have the following ratings and
features :
c) Rated frequency : 50 Hz
The circuit breaker shall have a motor operated shorted energy, spring-driven
mechanism or solenoid. Tripping power and closing power shall be from a 230 V.
The mechanism shall pre-charge immediately after a closing operation, or upon
insertion of the removable breaker into the stationary structure, so that the breaker
may be tripped and closed manually if controlled power is subsequently lost.
b) One-hand crank
All bus bar shall be made of copper and shall be totally enclosed with long life and
durable insulating material.
Power buses shall be copper having suitable current rating as shown on the Drawings,
and shall be supported by non-hygroscopic insulators designed to withstand forces
due to the momentary short circuit current of the system.
Earth bus shall be of copper and size shall be not less than 6 mm x 50 mm.
A tee connection from the main earth-bus shall project into each circuit breaker
compartment for the automatic earthing of the circuit breaker when it is inserted into
the compartment.
2.2.1.8 Painting
Part 8/Section 2 8-2-10
The switchgear panel shall be painted with double coats of sealing primer and
surface, and not less than double coats of finish paint. Before prime-painting, surface
of the switchgear finish paint. Before prime-painting, surface of the switchgear shall
be treated by sand blast or dipping with acid solution.
2.2.1.9 Wiring
All wiring shall be made with 600 V PVC insulated wire of 2.5 mm2, except for
current transformer circuit shall be 4 mm2. All hinged wiring shall be extra flexible.
Internal wiring of each panel shall be neatly and carefully installed in suitable wiring
durcts with removable cover and complete to conveniently located terminal blocks for
connecting to incoming and outgoing leads.
Every point of terminal block and wire shall be assigned a designation, with identical
designation on each corresponding terminal block and wire. This same designation
shall also be indicated in the schematic and wiring diagrams. As a rule, a
designation will not change until the wire is terminated or connected to other
equipment. All wiring shall be designated at bother ends by permanent printing on
wire designation sleeves.
The switchgear panel shall be provided with terminal blocks for termination of all
wiring devices mounted in the panel and all external circuits. Terminal blocks shall
be of 600 V approved molded-block type with molded insulating barrier between
terminals. Terminal blocks shall be made of nonflammable thermosetting material.
Terminal blocks shall be sized to accept 2.5 sq.mm to sq. mm conductors. Each
terminal block shall have removable white marking strip for marking circuit
designation. One spare blank marking strip shall be furnished with each terminal
block.
The arrangement of all terminal blocks shall be such that incoming and outgoing
leads can be easily arranged for connections to terminals. Terminal blocks shall be
located so that the accessibility to them will not be lessened by interference from
structural members or panel instruments. Ample space shall be provided to terminal
blocks for termination of all external circuits.
Ten percent of spare terminals, not less than one spare terminal, shall be provide on
each group of terminal blocks for future use.
2.2.2.1 Standards
The equipment and accessories shall be designed, manufactured and tested where
applicable, in accordance with the following standards, code or approved equivalent
standards approved.
All switchgear shall be type tested generally in accordance with IEC Publication 298,
Clause 6, including full scale arcing test.
Current transformer and voltage transformer shall be type tested according to IEC 185
and IEC 186.
The high voltage switchgear shall be the following type and shall have the following
ratings:
5) Cover and doors which are parts of the enclosure shall be metallic. When they
are closed, they shall provide the specified degree of protection. Two categories
of covers or doors are recognized with regard to access to high voltage
compartments.
a) Those which need not be opened for the normal purposes of operation or
maintenance, shall not be possible for them to be opened, dismantled or
removed without the use of tools.
8) Partition and pressure relief flaps shall be provided and designed to limit the
damage during internal fault. The pressure relief flaps shall be directed away
from the front.
Switches shall be quick-make, quick-break with the speed of opening or closing entirely
independent of the operator. The Load Break Switches shall be three poles, two
positions, with earthing switch and a stored energy spring mechanism to provide quick
switch operation independent of the handle speed. The interrupt shall be designed for in
air operation of the sliding Contacts are chute type for ease of inspection and
maintenance. Designs which have completely enclosed interrupts or rely on the presence
or absence of a gas shall not be acceptable.
Switch operating handle shall be permanently mounted and ready for immediate use. The
spring sleeve shall permit the handle to fold down when the switch is in the open
position. Provisions shall be available for padlocking the switch in either the open or
closed position. Switch shall have continuous and interrupting rating as indicated on the
Drawings.
A viewing window shall be installed in the switch enclosures and located to enable
visible inspection of the switch poles from outside the enclosure, and so placed that
opening the fuse access door is not required to observe the blown fuse indicator on any
fused switch.
- System voltage 24 kV
- Number of Phase 3
The high voltage fuses and non-disconnection fuse mountings shall be accessible only
through a separate door mechanically interlocked with the Load Break Switch, to insure
the switch is in the open position when the fuses are accessible. Switch designs with full
height fuse access doors shall have a solid barrier covering the area of the main cross bus
and/or line side of the switch. Metal screen barrier shall not be acceptable. No energized
parts shall be with normal reach of the opened doorway. Four single full length inter-
phase barriers shall isolate the three phase of the switch from each other and from the
enclosures.
Four single full length inter-phase barriers shall isolate the three phase of the switch from
each other and from the enclosures.
a) Current limiting type of self contained design to limit the available fault
current stresses on the system.
c) Provided with striking pins to actuate the status indicator or to trigger the
Load Break Switch when fuses are blown.
Potential transformers and current transformers shall be molded epoxy resin insulated.
All equipment, materials and fabrication shall conform to the latest applicable IEC 185
or equivalent approved. Potential transformers and current transformers shall have the
following rating and features:
Current transformers shall have sufficient thermal and mechanical strength to withstand,
without damages, current equal to the momentary and interrupting rating of the breaker.
All bus bar shall be made of copper and shall be totally enclosed with long life and
durable insulating material.
Power buses shall be copper having suitable current rating as shown on the drawing, and
shall be supported by non-hygroscopic insulators designed to withstand forces due to the
momentary short circuit current of the system.
Earth bus shall be of copper and size shall be not less than 6 mm x 50 mm.
A tee connection from the main earth-bus shall project into each circuit breaker
compartment for the automatic earthing of the circuit breaker when it is inserted into the
compartment.
The underground cable shall be three-phase, three single-core cable. The cable shall be
manufactured, materialized and fabrication as present herein.
1) Construction
a) Conductor
Uncoated conductors shall be of soft or annealed copper wire in
accordance with ASTM B3. Concentric stranded conductors shall
conform to ASTM B8, and class B, Part 2 of ICEA Pub. No. S-66-524.
b) Conductor Shield
The conductors shall be shield with an extruded layer of thermosetting
semi-conducting material or the combination of helically wrapped semi-
conducting tape over the conductor and then an extruded layer of
thermosetting semi-conducting material. In either case, the extruded layer
shall be firmly bonded to the insulation.
c) Insulation
The insulation shall be cross-linked polyethylene conforming to the
requirement of ICEA Pub. No. S-66-524 Part 3
d) Insulation Shielding
The insulation shall be shielded with a layer of semi-conducting material
applied directly over the insulation.
e) Shielding
The shielding shall be annealed copper tape of suitable width and shall be
helically applied over the insulation shielding with minimum 10% lap.
The annealed copper tape shall be at least 0.1 mm thickness and
substantially free from burrs.
f) Protective Tape
The protective tape shall be furnished which consists of a compound
filled fabric tape applied over the copper shield.
g) Jacket
The jacket shall consist of a polyvinyl chloride compound conforming to
the requirement of ICEA No. S-66-524.
2) Cable Markings
a) Normal voltage
b) Type of cable
c) Size and number of conductor
d) Name of manufacturer
e) Date of manufacturer
3) Packing
All cable shall be packed on reels. The following information shall be displayed
on the reel.
a) Name of manufacturer
b) Size and number of conductor
c) Type of insulation and voltage classification
d) Length of cable
e) Reel number and other suitable identification for reel and reel size.
f) Date of manufacture.
g) Total weight
4) Cable Ends
The underground cable duct shall be utilized as cable ways or cable supports. The cable
duct shall be high density polyethylene pipe (HDPE). The number and diameter of the
cable duct shall be as specified on the Drawings. The HDPE duct together with
connection accessories shall be manufactured, materialized and fabricated as presented
herein.
1) Description
Unless otherwise specified, all ducts shall be designed for a minimum working
pressure of 6.0 kg/sq.cm.
Duct shall be supplied in standard length of at least 6.00 m and shall be furnished
with plain end. Both ends of the pipe shall be chamfered.
2) Pipe
The raw material from which the pipes are made shall be composed substantially
of high density polyethylene to which may be added only those additives that are
needed for manufacturing of the pipes. The raw material shall contain carbon
black of not less than two (2%) percent by weight.
Unless otherwise specified, the quality requirements of the raw material shall
conform to DIN 8074 and 8075 "Pipes of High Density PE-Type 1 - General
Quality Requirements".
Coupling and reduces shall be supplied from the same manufacturer and shall be
made from the same raw material with the same quality requirements as HDPE
pipe.
4) Dimension
Dimension and tolerance shall comply with DIN 8074 "Pipe of High Density PE-
Tupe 1 - Dimension".
5) Connection
6) Method of Testing
Pipes shall be tested in accordance with DIN 8075 "Pipes of High Density PE-
Type 1 - Testing".
7) Marking
a) Pipe
Each pipe shall be clearly marked on the outside surface at intervals not
exceeding 1.5 m. The marks shall be as follows:
b) Fitting
Each fitting shall be clearly marked showing the nominal diameter.
2.2.3.4 Manholes
The high-tension manholes shall be utilized as junction for high-tension cable pulling.
The manholes shall be made of reinforced concrete and hall have covers shall be of size
and shape as shown on the Drawings. The manhole shall be utilized as three direction
installation of cable.
2.2.3.5 Handholes
The high-tension handholes shall be utilized as junction for high-tension cable pulling.
The handholes shall be made of reinforced concrete and shall have covers made of hot-
dip galvanized steel. The handholes and covers shall be of size and shape as shown on
the Drawings. The handhole shall be used as unidirectional installation of cable.
The termination shall use high strength, wet process porcelain for external
insulation. The porcelain shall be provided with necessary creepage and strike
distance and shall permit for installation in upright position. The termination shall have
thermal, mechanical and electro-magnetic strength sufficient to withstand without injury
short circuit current and thermal expansion.
Mounting bracket for the pothead shall be shaped for mounting on a galvanized steel
supporting structure without inducing eddy current.
The transformers shall comply with the standard, type construction and include the
necessary accessories as presented herein.
1) Standards
The transformers shall be manufactured and tested in accordance with the latest
applicable standard specifications and codes of ANSI C 57.12 or approved
equivalent.
The transformers shall have the following ratings and features when operating at
the Site with an elevation up to 100 m above MSL :
e) Rated frequency : 50 Hz
30 kVA : 500 w
50 kVA : 1,050 w
100 kVA : 1,750 w
500 kVA : 5,500 w
2,500 kVA : 26,800 w
k) Impedance voltage : 5%
p) Audible sound
Below 500 kVA : Not more than 56 dB
2,500 kVA : Not more than 60 dB
3) Transformer Construction
a) Tank
b) Cores
c) Windings
The winding shall be of the best modern design. The coils shall be wound
and supported in a manner to provide sufficient oil ducts which will be
maintained without obstruction. End coils shall have extra insulation.
Coils shall be made up, shaped, and braced to provide for expansion and
construction due to temperature changes in order to avoid abrasion of
insulation and to provide rigidity to resist movement and distortion
caused by abnormal operating conditions. Adequate barriers shall be
provided between windings and core. End coils shall have extra
protection against abnormal line disturbances. The assembled core and
coils shall be vacuum dried, immediately impregnated, and immersed in
dry oil.
The bushings shall conform to the applied standard. All porcelain parts
shall be one piece. Porcelain parts constructed of assembled segments
will not be acceptable. Threaded studs shall be furnished on all bushings.
All bushings shall be interchangeable between items of like voltage. The
H.T. bushings shall have full wave impulse withstand voltage or basic
impulse insulation level (Bil) of not less than 150 kV for 22 kV system.
e) Transformer Oil
The transformer oil shall be pure mineral oil prepared, refined, well
filtered and has the dielectric strength before filling, by vacuum process,
in the transformer tank not less than 35 kV as tested by ASTM D 877 or
approved equivalent. The dielectric strength of the sample of insulation
oil taken from the new transformer shall not be less than 27 kV, when
measured in accordance with latest ANSI standard method of testing
electrical insulating oil.
g) Terminal Arrangement
h) Cooling System
4) Accessories
All tests described below shall be performed by the Provincial Electricity Authority
(PEA):
a) Routine Tests
b) Special Tests
All the special tests described below shall be performed in the presence
of the Engineer.
c) Data to be Furnished
The Contractor shall furnish four (4) certified copies of reports of the test
results, curves and standard application data. The costs of the tests and
report shall be borne by the Contractor.
The instruments for above tests shall be prepared by the Contractor. And
the cost of the tests shall be borne by the Contractor.
The main and supplementary busbars shall be type tested in compliance with
B.S. 5486: 1977, Part 1, Class 3 CM to a fault level of 31 MVA at 380 V for 3
secs. for circuit above 1600A and to 31MVA at 380 V for 1 sec. for circuits
1600A and below or approved equal.
2) Switchboards shall be constructed from zinctec sheet steel angle and channel
sections welded to form a robust, self-supporting structure. The cubicle tops,
floor plates, side panels, front and rear doors, shall be detachable gasketed sheet
metal plat of at least 2 mm. thick.
The bare edges shall be lipped. Each panel shall be divided vertically by isolating
sheet metal and horizontally by insulation between compartments for each
switchgear and/or instrument. The sheet steel of min. 1.2 mm thick shall be used.
a) Cabling chambers,
b) Main busbar chamber,
c) Instrument - protection relay, protection current transformer
d) Metering - voltage transformer, energy meter, selectors,
indication light, measuring current transformer,
e) Battery and charger for trip supply,
f) Switchgear including ACB, fused switch, non-fuse switch, MCCB, HRC
fuse and magnetic contactor
g) Spare for future circuits as shown on the Drawings.
The Contractor shall submit type test certificate to verify both the assembled
switchboard and switchgears/ACBs etc. can meet with the requirements.
6) Copper earth bar of 25 mm. x 6 mm. shall be provided to link all the panels. A
clamp earth terminal shall be provided adjacent to each cable for earth
connection.
7) Busbar shall be air insulated hard drawn electro-tin plate high conductivity
copper bars to B.S. 1432 or 1433 or approved equivalent, properly rated, and
supported by porcelain or other non-hygroscopic material at suitable spacing.
Proper busbar extension shall be provided for ease of cable connection in the
cable chamber. The busbar shall be properly identified by colours in accordance
with Clause 7.6.5 of B.S. 5486 Part I:1977 or approved equal.
8) Cabling chamber shall be ample dimension for ease of cable termination and
shall be provided with:
and suitable for the appropriate size, type and direction of cable entry.
10) All hinged or removable metal doors or plates shall be earthed by flexible earth
tape to the earth bar.
1) Distribution board shall include moulded case circuit breaker distribution board
(MCCB) and Miniature Circuit Breaker distribution board (MCB) and shall be
factory built assembly to B.S. 5486 or approved equivalent.
2) The distribution board shall be totally enclosed by galvanized sheet steel of 1.7
mm for length less than 2m or 2.0 mm thick for length greater than 2m. The
metal enclosure shall be adequately sized to allow for free circulation of air and
Part 8/Section 2 8-2-26
be complete with one (1) coat of anti-corrosion primer and baked enamel painted
in factory. The door shall be hinged 180 deg. C swing gasketed door fitted with
ball catch and chrome-plated handle. For boards allocated in areas accessible by
the public, cylindrical lock shall be provided complete with three (3) keys.
3) Knock out and slot openings shall be neatly provided suitable for
conduit/trunking connection and proper protection by bushes, gourmet, etc. to
protect cable entry from damages shall be included.
4) Busbar shall be hard drawn high conductivity copper properly tinned. For HRC
DB and MCB DB, the busbar shall be rated at 100A minimum for single phase
and 150A for 2 or more phases unless otherwise stated. For MCCB D/B the
busbar shall be rated not less than the rating of main switch or main circuit
breaker.
Neutral connector can be brass block having finished screw terminals equal in
number and in same order as the individual outgoing circuits. Earth terminal shall
be provided.
6) Removable insulating phase barriers and front shields covering live busbar and
terminal, shall be provided by 2.5mm thick paxolin sheet. Operating handle shall
be projected outside the shield for operation purpose.
7) Replacement of fuses, MCB, MCCB and busbars form the front shall be
possible.
8) Except for solderless termination type MCB or fuse holder, all cable termination
shall be by compression cable lug or proper soldered lug.
10) MCB's and HRC fuses shall be arranged in horizontal rows of the same phase.
For TP MCBs, tee off cable shall be used for tapping out from busbars.
11) Each DB shall have a main circuit breaker as per specified in the Drawings.
12) Distribution board shall be provided with 20% spare circuit breaker, unless
otherwise specified in the Drawings.
a) Property of the load center shall conform with "Article 384, NE Code".
The panel and breakers shall be approved or tested by the authorized
Institute accepted by the Engineer.
b) Load centers shall be dead-front type for 380/220 V 3 ph. 4 wire. They
shall be 1 phase or 3 phase as specified in the Drawings and the
description. Front hinged door shall be required. The panel shall be
suitable for not less than 240 volts for 1 phase and 415 volts for 3 phase.
3) Busbar shall be Aluminum at the current capacity not less the size of AF of the
main breaker. Main circuit breaker shall be easily detachable of circuit breaker
either 1,2,3 and/or combination of them.
4) Load center shall be of surface mounting type unless otherwise specified. They
shall be installed at specified height or per NE Code and shall be readily
accessible.
2.2.8 LV Switchgear
1) ACB shall be triple pole, metal clad, flush mounted horizontal draw-out type
with back connection.
2) ACB shall be motorized and with the capability to install protective equipment as
follows or as shown in the Drawings:-
a) Shunt trip
b) Instantaneous over current trip
c) Time delay over current relay
d) Ground fault relay
e) Asymmetrical relay or Phase failure check relay with adjustable +, - 5 to
10% asymmetrical voltage.
f) Under voltage relay with adjustable range from +,- 10 to 20%
symmetrical
3) Isolating and main contact shall be silver plated self aligning cluster type backed
by phosphor bronze spring. The arcing tip shall be specially treated to minimize
erosion and eliminate contact welding under all conditions. Heat resistant are
quenching device shall be provided.
1) MCCB shall be manufactured and test to B.S. 4725 : Part 1 : 1997 or approved
equivalent.
2) All mechanical and live parts, except terminals and toggles shall be contained in
completely sealed molded case of high mechanical strength and non-tracking
phenolic materials.
4) The MCCB shall be "Trip free". The tripping mechanism shall be thermal
magnetic, and shall be fully compensated for ambient temperature of 25ºC to
50ºC and calibrated at 40ºC to carry full load.
5) MCCB shall completed with overload, short circuit, and shall have an inverse
current/time characteristic with time delay inversely proportional to the current
up to seven times full load rating. On higher overcurrent, the breaker shall trip
instantaneously. Wherever specified, additional under voltage relay protection
shall be provided. Clear indication of fault when tripped shall be indicated for all
MCCB.
1) The automatic transfer switch shall be a twin unit consisting of two 3-pole mold
case circuit breaker. Where the rating of switch exceeds 630A, air circuit breaker
2) Automatic transfer switch shall be with double relay control. On detection of the
failure of the main supply by the no-volt relay as well as the built up of the rated
voltage from the emergency generator by the voltage sensing relay. The transfer
switch shall be automatically changed over.
3) The twin unit shall be mechanically interlocked so that it prevents the normal and
emergency sources from ever being in parallel operation.
1) MCB shall be manufactured and type tested to IEC 898 or approved equivalent.
The mechanical and live parts, except terminals and toggles shall be contained in
a completely sealed casing of high mechanical strength and non-tracking
phenolic materials.
4) Double pole or triple pole MCB shall be interlocked internally so that fault on
any one phase shall trip all phases simultaneously. External gauging shall not be
allowed.
5) MCBs for general lighting and power sub-circuits shall be of type 3 category and
for motor circuits shall be of type 4 category tripping characteristic as defined in
B.S. 3871.
6) Short circuit duty category of MCB shall be selected to match with the
anticipated maximum fault level at the installation point but shall in any case not
be less than 5KA (m6 as defined in B.S. 3871 or approved equivalent).
3) The RCD shall be 4-pole for three phase circuit and 2-pole for single phase
circuit. Three phase circuit breaker shall be interlocked internally so that earth
leakage on any one phase shall trip all three phase of breaker simultaneously.
4) Earth leakage current detection shall utilize differential current transformer for
activation of shunt trip coil and total operation time shall not be greater than 0.1
sec in all cases.
5) Operating toggle shall have distinct OPEN, CLOSED and TRIPPED position.
OPEN and CLOSED position shall be clearly labeled.
6) The RCD shall be equipped with durable silver tungsten contacts and complete
with auxiliary switches and alarm switches as required.
7) Test push button shall be provided to simulate earth fault condition to enable
testing of tripping mechanism. A leakage indication lamp or target indicator with
manual reset button for visual indication of earth leakage tripped condition shall
also be provided.
8) Short circuit breaking capacity shall be of 3KV minimum at rated voltage. Rated
sensitivity current shall not be more than 100mA and shall be 30mA if used for
final circuit protection.
1) Fuse Switch shall be metal clad and type-tested in accordance with Table VI of
B.S. 5419:1977 or approved equivalent. The rated fused short-circuit current
shall be 50kA.
2) Fuseswitch shall be of continuous duty and shall be capable of closing onto and
remained closed on a fault without overheading and damage.
4) Fuse link shall be high rupturing capacity cartridge type to B.S. 88 or approved
equivalent. Rewirable fuse shall not be permitted to be used.
5) Live contact shall be shielded from the front so that fuses can be replaced
without damage.
a) Having a maximum voltage not exceeding 1.1 times their rated voltage,
b) Having any prospective current greater than their rated minimum fusing
current up to their breaking capacity rating,
c) Having any power equal or greater than that associated with their
breaking capacity rating.
4) Fuse carries and fuse holders shall be constructed of ceramic porcelain or of high
dielectric phenolic mouldings. Phenolic moulding units shall be complying with
B.S. 771:1959 and non-hygroscopic and unaffected by heat generated by an
overloaded fuse or by a blown fuse.
5) Fuse carriers shall be so designed that there is no risk of touching live parts when
withdrawing a fuse.
6) The maximum rating of the fuse inserted in a fuse holder shall not be greater than
the rating for which the holder is designed.
7) No 'live' metal shall be exposed when the fuse carrier is removed from the base
and the base contacts shall be enclosed by insulating shrouds.
1) The equipment shall comply with B.S. 1650 or approved equivalent and the
admissible ambient temperature shall be ranged from 0 deg. C to 45 deg. C.
2) The capacitor shall be dry type metal film capacitor and provided with an
adequate discharge circuit. The residual voltage shall be reduced to 50V or less
within one minute after the capacitor is disconnected from the source.
6) The reactive power control relay shall be fully electronic and automatically
generate switching impulse to the contractor for increasing or decreasing the
capacitance to the circuit. An automatic discharge to earth mechanism shall be
incorporated.
The unit shall have at least the following characteristics and ratings:-
8) Design
- Fused or circuit breaker protection with suitable rating for each contactor.
- Reactive power regulator, electronic type
- Contactor, heavy duty type
- Discharge coil (if not 'built-in' type)
- Automatic switching device
- Indicator lamps
9) Test
2.2.9 Cable
1) All cable shall comply with the relevant TIS requirements, be used for
appropriate application as defined in the NE Code.
2) PVC insulation and sheath shall have flame retardant characteristic in accordance
with B.S. 4066 or approved equivalent.
Part 8/Section 2 8-2-33
3) 'Loop-in' system is utilized and hence no joints in the cable run shall be
permitted.
4) Cables shall be terminated in the approved form i.e. compression cable lug,
tinned copper cable socket, cable gland, etc.
5) Each core of the cable shall be identified by mean of coloured insulation and
code in accordance with IEE regulation. Overall sheath shall be coloured black.
1) PVC insulated cable shall comply with TIS 11-2531 to 70ºC, 750V grade or
approved equivalent.
2) The cable shall be single or stranded annealed copper insulated by PVC.
3) The cable shall be single core cable suitable for running in conduit or trunking
system. Properly colour-coated cable shall be used.
1) PVC/PVC cable shall comply with TIS 11-2531 70ºC,750V grade or approved
equivalent.
2) Cable shall be single or stranded annealed copper conductor PVC insulated and
sheathed by PVC.
3) The cable shall be single or multicore and shall be suitable for direct burial or
running in underground conduit or free running on cable tray and cable ladder.
2.2.10 Raceway
1) All steel conduits and fittings shall be galvanized iron to B.S. 4568:Part 1 and 2
or approved equal steel. Conduit shall be of heavy gauge, screwed and
longitudinally welded and protected against corrosion to Class 4 (heavy
protection) e.g. hot dipped galvanized both inside and outside.
Rigid steel conduits (RSC) and intermediate conduits (IMC) shall be galvanized
rigid steel with a minimum size of 12.7 mm, unless otherwise noted. Rigid steel
conduits and intermediate metal conduits shall be installed for the following
services and locations: service entrance, underground (in contact feeders over 10
HP, for electrical equipment feeders over 16 KW and in "Wet" locations.
PVC conduit for electrical wiring wherever specified on the Drawings, shall be
rigid PVC conduit and comply with the TIS No. 216-2520. PVC conduit shall be
used in the corrosive area both under ground and above ground installation. The
corrosive area shall be where expressly indicated on the Drawings.
Part 8/Section 2 8-2-34
2) Fittings shall be to Class 4 protection against corrosion-hot dipped galvanized
both inside and outside.
3) Minimum size of conduit shall be 12.7mm inside diameter. Solid or inspection
tee pieces or elbows shall not be allowed to be used in any conduit installation.
Flexible galvanized steel conduits shall conform to B.S. 731 or approved equivalent and
shall be:
2) All bends, tee and flanges shall be of same material and construction as straight
runs bends and tees shall have a minimum inner radius of 50 mm and shall have
a minimum straight run of 100 mm at each end.
3) Fixing of adjoining sections shall be by means of round-head steel bolt and nut.
4) Support shall be steel angle section designed to support weight of both tray and
cable carried.
5) Multi-layer cable tray shall have at least 300 mm between trays and shall not be
more than 3 layers.
6) Cable clip shall be provided for fixing cable on tray. Nylon strapper is acceptable
for horizontal run, but for vertical run, approved type of claw-clip constructed of
aluminium alloy and designed for single or multi-cable clipping similar to the
BICC. make.
7) The cable tray shall be earthed by bare copper conductor of appropriate size
required by the NEC, running along the length of the cable tray and fixed to the
cable tray at 1200 mm interval.
2) In jointing two adjacent lengths, sleeve type coupling and external copper earth
bonding link shall be provided.
3) Every part of trunking shall be equipped with removal cover, held in position by
captive screw, spring-cap or other approved means. Loose screw shall not be
permitted.
4) Trunking internal surfaces including edges shall be smooth and free from and
projection or sharp objects.
5) Space factor shall comply with IEE Regulation and cables shall be retained by
retaining bars of non-hygroscopic insulating material.
8) Openings in trunking where cables pass through shall be provided with rubber
grommet to B.S. 1767 or approved equivalent.
2) All wiring accessories shall be of same manufacturer, colour and design and be
suitable for alternating current application.
3) All wiring accessories shall be suitable for mounting on boxes to B.S. 4662 or
approved equivalent.
1) Lighting switch shall be single pole micro gap rocker operated positive action
type to B.S. 3676 or approved equivalent.
2) Lighting switch shall be rated at 15 ampere suitable for both incandescent and
fluorescent lighting load.
3) Lighting switch shall be PVC cover plate flush pattern, unless otherwise
specified on the Drawings.
4) Lighting switch shall be allowed to be grouped in a single switch plate.
1) Socket outlet shall be rated 15A, universal outlet type 3-pin to B.S. 1363 or
approved equivalent.
2) Socket shall be all insulated, PVC cover plate flush pattern suitable for mounting
on standard B.S. 4662 boxes or approved equivalent.
3) Socket outlet shall be capable of terminating 3 Nos. 4 sq. mm cable.
1) Watertight sockets shall be galvanized iron body shuttered type, complete with
push-on cap and cap retaining ring or a screw on cap with rubber gasket.
3) The socket outlets shall have a degree of protection of at least IP 54 to B.S. 5490
or approved equivalent.
Pull boxes shall be installed at all necessary points, whether indicated on the Drawings or
not, to prevent injury to the insulation or other damage that might result from pulling
resistance of for other reasons related to improper installation. Pull box locations shall
be approved by the Engineer prior to installation. All pull boxes shall be constructed of
galvanized sheet steel, of not less than 2 mm thick. Where boxes are used in connection
with exposed conduits, plain covers stached to the box with a suitable number of
countersunk flathead machine screws may be used.
Where so indicated, certain pull boxes shall be provided with barriers. These pull boxes
shall have a single cover plate, and the barriers shall be of the same gauge as the pull
boxes. Each circuit in pull boxes shall be marked with a tag guide denoting panels to
which they connect. Exposed pull boxes will not be permitted in areas normally
occupied or regularly used by staff and/or visitors.
The Contractor shall furnish and install all luminaires and lamps as shown on the
Drawings. The Luminaire shall be wired to a single point with the approved fixture wire
for proper connection. The Contractor shall ensure that the luminaires furnished are
compatible with the ceiling suspension system being installed. The luminaires schedule
shall be as shown on the Drawings for types, and types of mounting. The Contractor
shall submit complete photometric data, a manufacturer's name, a catalogue number and
type of lamp (s) to be installed together with the shop drawings for approval before
giving the fixture manufacturer a purchase order.
2.2.13.2 Lamps
Lamps shall be at the number and types shown as specified. All lamps installed shall be
new, and all shall operate on the completion of the Works.
a) Clear,
b) Coil filaments above 20W and,
c) Having screw-in E27 base
1) Luminaires for use with tungsten filament lamps, discharge lamps tubular
fluorescent lamps shall comply with B.S. 4533:1971.
3) 70 deg. C Heat resistant cables shall be used inside the luminaires or PVC cables
shall be sleeved with similar heat resistant materials.
5) Luminaires with incandescent lamps shall be suitable for the wattage of lamps
being used, with porcelain lampholders.
2.2.13.5 Lampholders
All fluorescent ballasts shall be preheat-start and low loss with approved dry type
capacitor to correct the power factor up to at least 0.95, Quiet operating ballasts with TIS
approval. The ballasts shall be subjected to at least one year manufacturer's guarantee. It
is the responsibility of the Contractor to fill in the guarantee forms the name of the
Employer and then send those forms to the manufacturers.
2.2.13.7 Starter
The emergency light and exit light shall be of the surface mounted type. Each unit shall
be equipped with the following:
The emergency lights and exit units shall meet the NFPA Life Safety Code and the local
regulation, and can be operated with single phase, 220V, 50 Hz. system.
The batteries of both emergency light and exit light shall be of the maintenance free-seal
lead acid type.
The units, when installed, shall be concealed and the lamps shall be remoted and
installed at the locations as shown on the Drawings.
The High Masts shall consist of a galvanized steel column, a headframe assembly at top
of mast column, an internal winching system and a mobile luminaire carriage ring. The
mobile luminaire carriage ring shall travel concentrically along the axis of the column
and shall be operated by a winching system. Docking of luminaire carriage ring to
headframe incorporates a 3-point self latching and unlatching system which eliminates
the use of multiple levers and springs.
2.2.14.2 Construction
1) General
d) The top end of the section shall have necessary fixing desire for bolted
connection to the headframe. The base section shall be fitted with a base
plate for fixing the mast onto the concrete foundation by anchor bolts.
2) Cross Section
3) Wall Thickness
The wall thickness of each section shall be designed to withstand the loads to
which the pole will be subjected to, but shall not be less than 3 mm.
4) Telescopic Slip-Joint
5) Anchorage
a) The lower section shall be equipped with either a single or double flange
circular base plate with holes drilled for anchor bolt passage. The mast
shall be securely welded to the base plate by full strength welds. Mast
over 40 m in height, the mast shaft welded to the base plate should be
complete penetration weld. Base flange dimensions and thickness and
the number, diameter and length of anchor bolts shall be determined by
calculation.
b) The anchor bolts shall be threaded at one end and each shall be equipped
with three nuts and two washers. One nut and one washer shall be placed
A door opening with heavy reinforced by flat iron bar shall be provided
at the base of the mast of adequate dimensions to permit clear access to
equipment and mounted herein complete with a close fitting weather
proof door and having a vandal resistant lock.
1) General
The top section of the mast shall be equipped with a fixed type headframe. The
headframe assembly shall comprise the followings :-
2) Headframe Assembly
2.2.14.4 Materials
1) Structural Steel
The steel grade used for construction of the high mast shall be in compliance
with BS EN 10 025.
a) The steel grades for the mast shaft be BS EN 10 025 FE 510C having the
following guarantee characteristic :
b) Minimum strength = 355 N/mm2 for thickness < 30 mm
c) Tensile strength ranging from 490 to 630 N/mm2
Part 8/Section 2 8-2-42
d) Minimum elongation for thickness shall be between 3 mm and 30 mm
: 22%
3) Steel For Accessories
a) These shall be of round steel bars. Its size and grade shall be determined
by calculation. Each bolt shall be supplied with three nuts and two
washers.
b) No welding shall be allowed on the anchor and rod body. All holding
down bolts are hot dip galvanized to BS 729.
2.2.14.5 Welding
1) General
2) Welding Procedure
a) All welding shall be electric arc welding using one of the following
processes :-
b) Filler rod used shall be compatible with the grade and chemical
composition of the steel used and have mechanical properties at least
equal to that of the parent metal.
3) Welds
All welding shall be to BS 5135 and having the following basic requirements:-
a) Mast shaft to base flange and longitudinal weld within 150 mm of the
female slip-joint area shall have:-
c) Other Welds
d) Quality Control
2.2.14.6 Galvanizing
1) General
All masts shall be hot dip galvanized in accordance with either one of the
following standards:-
2) Galvanizing Process
3) Quality Control
a) adhesion
b) mass of zinc coating
c) uniformity of coating
1) Each mast shall be provided with single/ double winch suitable for raising and
lowering the luminaries’ carriage ring and its latching mechanism.
2) It shall be of robust design and construction incorporating a self locking worm
and wheel reduction ratio of minimum 53 : 1.
3) Winches uses shall have the approval and certified by manufacturer.
4) The capacity and operations speed of the winch shall be clearly marked on each
winch on an indelible label together with the specification of the recommended
lubricant.
5) Drive input to the winch shall be applied electrically by means of a power tool.
6) Such electrically operated power tool shall be incorporated with positive torque
limiting device.
The mast shall be fitted with flexible stranded stainless steel wire ropes which
shall a factor safety of not less than 5 times of the SWL of the winch and shall be
entirely suitable for the design application.
A stranded 8 cores flexible electrical cable with 2.5 sq. mm conducting area shall
be provided and shall terminate in the base compartment with suitable multiple
pin weather proof plugs and socket coupler fitted with locking screw ring. The
head frame shall be connected to a weather junction box which is mounted on the
luminaires carriage ring.
1) The hoisting winch shall be driven by a single speed reversible power operated
tool. Raising and lowering operation shall be via a hand held operated pendant
control system to allow the equipment to be operated from a distance of five
meters from the column.
b) A power operated tool with pendant control, 5 meters control cable and
accessories.
The pole shall comprise a vertical steel tapered tube made from 4.5 mm thick hot rolled
steel sheet with yield point not less than 25 kg/mm2 and ultimate tensile strength of not
less than 41 kg/mm2 , all joints are securely welded and bracket with single or double
arm to be fit on the top of the straight pole. The pole shall be spigots to suit all
manufacture lanterns provided with a weatherproofs service door with lock screw, in
which terminals for wirings, cartridge fuse for lamp and grounding terminals for wirings,
cartridge fuse for lamp and grounding terminal are to be installed. Each pole shall be
provided with an anchor base plate to be bolts. The base shall be treated by approved
anti-corrosion treatment up to a level of 25 cm above ground level. Poles shall be
protected against corrosion by hot dipped galvanizing inside and outside to ensure rust
free service. No welding, drilling or machine operation shall take place after galvanizing
has been carried out. Any damaged galvanizing at the Site shall be made good with a
coat of zinc rich paint. Mounting plate for cartridge fuse and accessories shall be
supplied with the poles.
The pole for storage and loading area shall comprise a vertical steel tapered
tube made from hot rolled steel sheet and shall be designed to withstand
a distributed wind load corresponding to the maximum windspeed specified.
Requirements for service door, base plate and galvanizing shall be the same as specified
in the preceding clause. The fixture shall be mounted and firmly fixed with bracket at
the top.
1) General
b) The column shall be continuos taper octagonal cross sectional shape with
a square based flange.
2) Materiel
The column shall be of best steel materials of EN10025. Steel for anchor
bolts shall conform to ASTM A307. Other steel for accessories shall conform to
BS 1987 and JIS G3101 SS400. Galvanizing shall conform to BS 729.
3) Wind Loading
a) The pole shall be designed to withstand a basic wind speed of 150 km/hr.
The gust wind speed shall be 1.3 times the basic wind speed. The design
loads shall meet the requirements of AASHTO Standard, 1985.
Deflection at the top of the column, at 150 km/hr basic wind speed wind
speed shall have a maximum deflection of 5% of the total column length.
b) Wind pressure
P = 0.0473 (1.3V)2 Cd Dh
The straightness of the column shall not deviate by 0.6% of the total column
height. The tolerance of the total assembled length shall be within 1%.
5) Slip Joint
6) Anchorage
a) The column shall be securely welded to a square base flange of
minimum 19 mm thick by full strength welds. The base flange shall
have 4 numbers of elongated slot holes to cater anchor bolts for final
adjustments of pole orientation at site.
c) The anchor bolts shall be threaded at one end and each shall be equipped
with there nuts and two washers
7) Service Door
8) Foundation Design
b) The contractor shall provide the design and construction details of the
footing for submission and approval.
9) Mechanical Arrangement
a) The apron shall be manufactured from a single steel sheet. The joining of
2 or more sheets to form a single sheet by longitudinal or transversal
welding is not permitted.
c) The hinge shaft shall be of stainless steel grade. The bearing blocks shall
be incorporated to the apron for operating the hinge shaft.
1) Lighting cubicles with low voltage incoming shall be installed as shown on the
Drawings. The cubicle shall be outdoor type 400 V metal enclosed switchgear
with a lockable door conform to the approved standard. Each cubicle shall
provide the following equipment as specified and shown on the Drawings.
2) All metallic projections, chimneys, ducts, vent pipes, railings, gutters, etc. on the
roof shall be bonded to the conductor network to form part of the protection
system and bonding conductor shall have a cross-sectional area not less than that
employed for the main conductors.
3) The resistance of the whole system shall not exceed 2 ohms and tested after
complete installation to the Engineer’s approval.
4) Joints and bonds shall be mechanically and electrically effective, e.g. clamped,
screwed, bolted, crimped, riveted or welded. With overlapping joints, the length
of the overlap shall not be less than 20 mm for all types of conductor. Contact
surfaces shall first be cleaned then inhibited from oxidation and galvanic action
with a suitable non-corrosive compound.
1) Down Conductor
c) The down conductors shall run in the most direct route possible between
the air termination and earth termination.
2) Horizontal Conductor
3) Earth Electrode
a) The lightning earth electrode shall comprise of earth pit, earth rods driven
into ground and interconnecting earthing conductor.
b) The earthing electrode shall be contained within a concrete lined pit with
removable lid cover and indication plate to enable access to the
connection.
c) The earth rod shall be of mild steel inner core of minimum diameter 12.7
mm with bonded hard drawn copper sleeve of minimum thickness 2 mm.
Each electrode shall be 3 m long. The penetrating end of the electrode
shall be of hardened steel.
d) The portion of the tape connecting the pressure clamp to the test clamp
buried underground shall be 500 mm below ground level.
f) Earth clamp shall comprise a heavy circular base bolted with a heavy
circular cover for clamping the 2 flat conductors one overlapping the
other.
1) General
b) Early streamer emission shall be developed at the tip of the air terminal
and leads the step voltage of lightning to launch a satisfy path of
lightning strike onto the tip of the tip of the air terminal. The protective
areas of early streamer emission shall be extended to the experimentation
radius.
2) Basic Components
c) Grounding System
c) All metal parts of the lightning terminal shall be sharpen, harden, mirror
polished, and weatherproof. The thickness of the metal the lightning
d) The lightning terminal base shall be high voltage terminator shape and
made of high voltage insulation which 70 mm in diameter and 250 mm
high and successfully passed the lightning waves withstand test at
impulse of not less than 150,000 volts.
d) The insulation medium between inner and outer conductor shall be able
to withstand an impulse not less than 200,000 volt.
e) The outer sheath shall be non-conductive sheath and fully insulated for
safety and able to convey lightning charges inside building, under ground
or under water to the beyond grounding system.
5) Lightning Counter
7) Grounding System
9) The down conductor shall be coaxial cable for lightning which can be applied by
the electrical formula of coaxial Cable. Other cables, such as bare copper, low
voltage cable, high voltage cable, or other non-coaxial cable shall not be
acceptable.
10) The installation of the lightning protection system shall be done in accordance
with the standard any know-how supplied by the inventor and manufacturer.
1) All earthing systems and all protective conductors shall be selected and erected
so as to satisfy the requirements of IEEE publicated No. 80, B.S. Code of
Practice CP 1013 for the safety and proper functioning of the associated
equipment of the installation.
2) All exposed conductive parts or metal work associated with an electrical
installation but not forming part of current carrying circuit shall be connected to
the main earthing terminal by means of protective conductor.
6) The metalwork of public gas and water services shall not be used as a sole
protective earth electrode.
7) Main equipotential bonding conductors shall have cross-sectional areas not less
than half the cross sectional area of the earthing conductor of the installation,
subject to a minimum of 6 sq.mm copper. Supplementary equipotential
conductor shall be 4 sq.mm (minimum) PVC sheathed copper conductor.
8) Except for metal conduit wiring system and armoured underground cable system,
separate protective conductor shall be provided, and in any case copper wire
shall not be smaller than 2.5 sq.mm.
9) For metal conduit wiring system and armoured underground cables the
Contractor shall prove to the Engineer the adequacy of the solely use metallic
conduit or armour to serve the purpose of protective conductor to meet the
requirements of NEC. Otherwise separate protective conductor shall be
provided.
15 2.5
20 4
30 6
40 6
60 6
100 10
200 16
400 25
600 35
800 50
1,000 70
1,200 95
1,600 95
2,000 120
2,500 185
3) Dimension and construction of earth pit shall be same as shown in the Drawings.
1) The earth electrode shall be of mild steel inner core with bonded hard drawn
copper sleeve.
2) The diameter of steel core shall not be less than 12.7 mm with the sleeve of at
least 2 mm thick. Each electrode shall be at least 3.0 m long. The penetrating
end of the electrode shall be made of hardened steel.
3) The portion of the tape connecting the pressure clamp to the test clamp buried
underground shall be 500 mm below ground level.
4) Sufficient numbers of electrodes shall be driven into the ground at a distance not
less than 3 m and connected together by bare copper conductor of 70 mm2. cross-
section buried 600 mm underground so that the overall earth resistance shall be
less than 5 ohm for electrical system.
1) Earth clamp shall comprise a heavy circular base bolted with a heavy circular
cover for clamping the 2 flat conductors one overlapping to other.
2) The earthing conductor shall be clamped to the earth electrode, and shall enable
the connection to be removed for testing as often may be necessary.
The standby diesel generating set shall be fully automatic, continuous output rating as
indicated on the Drawings, 400/230 volts, 3 phase, 4 wires, 50 Hz, 1,500 r.p.m. The total
system of generating set, control cubicle and automatic transfer switch shall be complete
built and tested from the manufacture with test certificate.
2.2.18.2 Engines
The engine shall be of heavy duty, four cycle, compression ignition type, direct injection,
turbocharged, developing adequate at 1,500 r.p.m at normal pressure and temperature in
accordance with B.S. and generally to International Specification such as D.I.N. IEC,
NEMA, JIS. The engine shall be arranged to permit 10% overhead for a period of one
hour in any consecutive 10 hour period.
2.2.18.3 Couplings
2.2.18.4 Alternators
2.2.18.6 Switchboard
Fuel level indicator and alarm contracts. Control contact for automatic fuel
transfer pump.
1) When the system in selected to automatic, the plant shall start on a complete
failure or a voltage reduction of one or one more phase of the public mains
supply, automatically take over the load and shall continue to carry the load
until the public main supply has been fully restored. The plant shall close
down transferring the load back to the mains, ready for the next mains failure. A
manual run button shall also be provided and shall enable the set to start and run
for test purposes, when operated in this manner the load shall not be transferred
by the circuit breakers, unless the mains supply fails.
The following timers, which can be switched out of operation if not required,
shall be provided.
Main failure timer shall give a short delay when the mains fails to prevent
unnecessary starting on transient mains failures.
Mains return timer shall give a delay when the mains returns to prevent
unnecessary load transfer on transient mains restorations.
Run on timer shall allow the engine to cool before it stops. Warm up timer
shall give a delay before the set goes onto load, allowing the engine to more
easily accept large on coming loads.
2.2.18.8 Finish
Two coats of primer and finished with two coats of oil proof enamel. All printed circuit
board shall be tropicalized.
1) All of inside wall, except ventilated door, shall install mineral fiber mat density
not less than 80 kg/m3 ; 30 mm. thickness then install glass fiber coated 0.08
mm. thickness. The installation shall be fixed by pin, 20 cm. spacing approx.
2) If ceiling haven't sound reduction, the Contractor shall make same item 1.
3) The Contractor shall install air intake and outlet sound attenuators at air intake
and outlet blockout of engine and outlet blockout of exhaust fan. The attenuator
shall be in accordance with appropriate international standards approved.
5) The Contractor shall provide warranty that all system can completely operate and
can protect sound in accordance with specification by installation shall not be the
cause to ask for change of material, testing or for the extension of the Contract.
6) The mineral fiber mat shall be in accordance with ASTM E-84 or equivalent
such as Keumkang Fiber, Kimm co Fiber etc. The glass fiber coated shall be in
accordance with BS476 or equivalent.
The work shall consist of the supply of all signal heads, supports, controllers.
Detectors, cables, switchgear with all necessary ancillary equipment together
with the transportation, storage, erection, connection reinstatement and
testing in order to supply a complete traffic signal installation in accordance with
the Drawings and specified herein. Design of the system shall be
included.
Items of equipment and part shall have maker’s specifications agreeing with
those of the U.S.A. Standard Institute and practice, the American Society for
Testing Materials, the American Association of State Highway and
Transportation Officials, the National Bureau of Standards, the British
Standards Institute, the British Institution of Electrical Engineers
Regulations for the Electrical Equipment of Buildings or other similar
internationally recognized body. All work shall be done and all goods shall be
made in strict accordance with the requirement of the Electrical Code of the
Kingdom of Thailand.
The Contractor shall be solely responsible for the adequate design and the
coordinated functioning of all goods and constructions furnished under this
contract.
All the component parts shall be selected so as to ensure their proper coordinated
functioning and operation. All equipment shall be of the
maker’s standard models and shall include all recent improvements in
design and materials. All materials used in manufacture and construction
shall be of high quality and fully in accordance with the best modern
practice.
The equipment offered and the work done shall be suitable for continued trouble
free operation under adverse climatic conditions of heavy rain, high humidity and
intense sunlight. The equipment must be able to withstood over long periods
ambient air temperatures varying from a normal of 40 C to a maximum of 50
C.
The Contractor shall ensure that the equipment and parts used shall be entirely
suitable for the work to be performed and that they shall be manufactured to
proper clearances and fit. He shall further ensure that the loading of equipment
shall under all normal circumstances not exceed the maximum laid down or
agreed in writing by the manufacturer.
The Contractor shall be responsible for the inspection of all equipment and
parts before their incorporation in the works to ensure that they comply with
the Conditions of the Contract and that they are not defective in any way as
regards to materials or workmanship. Should any such non-compliance or
defects be found during the inspection, the Contractor shall correct or cause
to be corrected such non-compliance and defects, all at the Contractor’s
expense and to the satisfaction of the Engineer.
4) Maintenance Period
All repairs and replacements required during the Maintenance Period shall be
carries out with dispatch and an adequate supply of spares shall be available for
this purpose.
5) Electricity Supply
The Contractor shall ensure that the equipment supplied function correctly at a
supply voltage of 220 volts, 1 phase, 50 Hz and must allow for normal variations
and surges.
6) Definitions
1) Signal Heads
All signal heads and optical systems shall be of the high intensity (Halogen) type
with dimming facility. Equipment shall comply with, Specification BS 505 (or
equivalent internationals standard) and shall be vermin proof. All lanterns shall
be of 300 millimeter in diameter.
2) Posts
3) Wiring
All power cable shall be copper conductor PVC insulation, PVC Jacket (NYY
Cable) minimum size of conductor shall be 2.5 square millimeters.
Each signal post shall be individually wire direct to controller. Tapping to other
post shall not be permitted.
4) Painting
5) Controller
The controller shall be so designed that temperature variations between 10°C and
70°C shall not change the timing by more than 5% or otherwise the cabinet shall
be artificially ventilated to keep the internal temperature within satisfactory
limits. In the event of power failure, the controller shall shut
down and re-commence operations without the necessity for manual re-
setting.
The controller shall be provided with a suitable mechanism for closing and
opening the signal circuits, which shall be positive and without any dark
intervals, flickering or conflicting signal indications. All contact points which
carry make or break current shall be of fine silver, or an alternative better
material and shall be capable of carrying, making or breaking or breaking a
current of 150% of maximum demand load through one million operations
without electrical or mechanical trouble. The use of hermetically sealed contacts
in preferred.
The controller shall provide for the proper phase intervals and sequences as
herein specified or as may be required by traffic conditions. The setting of time
intervals shall be by means of a positive method against a scale calibrated in
seconds. This timing scale shall be easily accessible and identifiable within the
controller and it shall not be necessary to remove or change wires or contacts to
adjust the time intervals.
c) Switches and Fuses- The controller shall be provided with a main manual
switch and fuse which shall isolate the complete installation. There shall
all be provided one general purpose outlet and fuse. All fuses and
switches shall be adequately and permanently labelled. Two spare fuses
shall be mounted in the cabinet.
f) Records - The following records shall be provided and kept within the
housing, either fixed to the inside of the main door or placed within a
metal pocket provided thereon:
iii) A suitable ruled card shall be fixed within the controller upon
which space is provided to record maintenance undertaken, the
date of visit and the name of the person doing the maintenace.
iii) Allowing a late start or early cut off on one or more phases as
may be required.
vi) The transfer of right of way shall phase only after an adjustable
clearance period, which may differ between phases. (Inter-green
Period)
vii) Provision shall be made for green filter arrows and late-start or
early cut-off facilities on any phase. If there are not required at
the outset, there shall be provision for their inclusion at a later
stage if required.
This sub sections is intended to give general guidance in the principles to be followed by
the Contractor when designing the Traffic Signal System.
(1) The Sequence of Aspects on any one signal face shall be:
- Red
- Green
- Amber
During any aspect, these shall be no visual flicker of the signal illumination,
The Secondary Signal shall be on diagonally opposite side of the junction facing
the approach, that is generally on the back of the primary signal serving the
opposite approach in the case of a four arm junction. The secondary signal may
be opposite the offside of the approach where there is a central medium, but in
any case should not be outside an angle of 30° extended from the centerline of
the approach at the stop line to the offside. The axes of the girders from the
optical system shall be directed at a point 45 meters away from the primary
signal face approximately 1.5 meters above the center line of the approach,
unless sharp gradient changes make this undesirable.
(4) Phases
The number of phases at the intersection shall be kept to the minimum required
to avoid dangerous conflict of traffic. Where additional phases are called for by
unusual traffic conditions at certain times, these additional phases shall be
suppressed when not required. In designing the number of phases and the
details of the cycle, the principle shall be to arrive at the arrangement which shall
at all times give minimum safety to both vehicles and to pedestrians.
Filter signals mounted at the side of the main signals may be used to allow a
movement in one direction. A green filter arrow indication shall always be
followed by a yellow and red aspect, and if this cannot be done on the main
signal, separate yellow and red aspects must provided for the filter signal.
Particular car shall be taken to ensure that filtering traffic does not form an under
hazard to pedestrians crossing guard rails, slip roads, islands or some resting of
the stop line may be required to avoid this. Where an early out-off is used for
offside turning traffic, an offside filter arrow shall be provided to indicate to
turning traffic that it is safe to proceed.
Where required for safety or to allow turning traffic to clear, a longer clearance
period may be introduced gut this should be kept to the shortest period which is
consistent with the demands of traffic and safety at any time.
The system shall be designed such that it can be incorporated within a linked
system with the minimum modification. With fixed time signals, there shall be
the facility to change automatically the program of linking, so as to give
preference to the heavier flows at different times of the days. With vehicle
actuated signals, local controllers shall be free to revert to independent operation
when there ceases to be a continuous demand, providing that this shall not
interfere with the overall progression through the system.
Signal Timing shall be done on the basis of traffic demands as estimated from the
traffic flows. Verification and adjustment shall be required on site after the
system is in operation, but the Contractor shall show by calculations that the
system proposed is capable of handling the estimated maximum and normal
flows in an efficient manner and with minimal delays. With fixed time signals,
he shall submitt details of phase and cycles for each approach throughout the
day. In the case of vehicle actuated signals, he shall give similar details of
maximum cycle time, maximum and minimum green times vehicle extension
periods and inter-green periods.
The rated life of each bulb sued for the signal lights shall be at least 10,000
hours.
Where passing through partitions or floors, fire barrier shall be provided in the following
manner.
(2) IMC conduit shall be rigidly connected between the trays and shall pass through
the partition or floor. Conduits shall afford the same area as the tray. Provide
adequately sized pillboxes as necessary to meet the area requirements.
(3) Firestop material shall be placed at each and around each conduit.
1) Cable shall be laid as shown in the Drawings through the ducts to be provided
under this Section unless otherwise indicated. Cable route might be subject to
modification with due regard to any obstacle.
4) Splices shall be made only in manholes to be approved by the Engineer for the
sake of easy access for maintenance and Wye or splices are not permitted unless
indicated.
5) Horizontal slack approximately 1.00 meter shall be left in each end of cable run,
one each side of manholes, handholes, and at all points where connection are
brought above ground. Where cable is brought above ground, additional slack
shall be left to make necessary connections.
7) High voltage cable splices shall provide insulation and jacket equal in every
respect to that of the cable. High voltage, ozone-resistance, self-fusing tape shall
be used for insulation and epoxy resin which pump by pressure shall be used for
jacket. In order to prevent the splice from the possibility of moisture entering the
jacket shall be cut back sufficiently to expose the required length of insulation
between the jacket and the tapered end of the insulation as recommended by the
manufacturer of splicing materials. Special care shall be taken to insure that all
dirt and wax is removed from the area of jacket to be covered with epoxy resin.
Shielding tape shall be applied to continue the shielding thought the entire splice.
Cable splices shall use design materials and techniques recommended by the
manufacturer of splicing materials.
10) Each cable shall bear cable identification markers of non-corrodable material at
each of manholes and handholes.
11) Before laying cables, cleaning inside the cable ducts and manhole shall be
carried out. Both ends of spare duct shall be plugged by approved means to
prevent them from the entrance of dirt, moisture and vermin.
12) In case of installing on cable racks and trays, cable shall be fastened securely to
transverse members of cable trays. Cable splices made and insulated by
approved methods shall be permitted within a cable tray or rack provided they
are accessible.
1) Excavation for duct lines laying or for foundations and reinstatement shall be
carried out in accordance with the provisions of the relevant Section of Common
Work in the Specifications, Part 1, Section 5.
2) The location of the trench for cable laying in open ground is approximately
shown on the Drawings but the Contractor shall obtain the approval of the
Engineer for each final location before breaking the ground. The actual width of
the trench is left to the discretion of the Contractor but the trenches shall be
cleanly excavated, reasonably straight and free from loose soil or stones or water
before the cable bed is laid. Trenches shall where necessary be adequately
shored.
3) No duct or cable shall be laid in a flooded trench and the Contractor shall be
responsible for dealing with any surface water and any pumping or bailing of the
trenches. Trenches which are flooded after the cables are laid and before
backfilling has commenced shall be carefully bailed or pumped dry.
4) Cables shall not be laid in the trench until the Engineer has inspected and
approved the excavation. Backfilling shall not commence until the Engineer has
inspected and approved the cables and accessories in the trench.
All necessary foundation and footings or other concrete work shall be carried out in
accordance with the provisions of the relevant Section of Common Work in this
Specification, Part 1, Section 2.
Foundation shall be placed in one operation except that top 5 centimeters may be placed
after the superimposed structure in position. The exposed portions of foundations shall
be formed to present a neat and tidy appearance, and sloped to shed water away from the
structure supported. Where existing obstructions prevent the construction of foundation
as shown on the Drawings then an effective alternatives shall be prepared by the
Contractor subject to the prior approval of the Engineer.
Manholes and Handholes shall be constructed where shown in the Drawings with all the
necessary pulling-in irons, duct entrances, end-bells, ground rods, cable racks, and
covers as shown in the standard details. Manholes shall be deep enough to accommodate
the ends of duct banks or as shown on the Drawings. The manholes and handholes shall
be installed with top elevations as directed by the Engineer and shall be cast in place
with monolithic walls, top and bottom slabs. The voids shall be filled in afterwards.
Manhole frames and covers shall be of gray cast iron, and adjusted to grade by meand of
brick inserts. A machine-finished seat shall be provided between frames and covers. All
spaces between the duct banks and the manhole or handhole sidewall duct entrance
openings shall be caulked tight with sealing compound of approved quality. All unused
ducts shall be plugged to prevent entrance of dirt and moisture. All manholes and
handholes shall be marked with identification letters embossed or stamped on the covers.
Frames and covers shall be given two coats of asphalt paint. Manholes to be installed in
road shall bear max. wheel weight of trailer.
1) General :
The top of duct or enclosed concrete shall not be less than 45 cm. below grade
except that under roads and pavement where it shall not be less than 60 cm.
below grade. Changes in direction of runs exceeding a total of 10 degrees either
vertical or horizontal, shall be accomplished by long sweep bends having a
minimum radius of curvature of 8 meters, except that manufactured bends may
be used at ends of short runs of 30 meters or less, and then only at or close to the
end or the run. The long sweep bends may be made up of one or more curved or
straight sections or combinations thereof. Conduits shall terminate in end bells
where duct lines enter manholes (handholes).
Trench shall be opened the complete length before concrete is laid so that if any
obstructions are encountered, proper provisions can be made to avoid them. All
ducts shall be placed on a layer of concrete not less than 7.5 cm. thick prior to its
initial set. Where two or more ducts are encased in concrete, the Contractor shall
space them not less than 20 cm. apart (measured from center to center) using
spacers applicable to the type of the duct. As the duct laying progress, concrete
not less than 7.5 cm. thick shall be placed around the sides and top of the duct
bank. End bells or couplings shall be installed flush with the concrete
encasement where required.
The Contractor shall reinforce the all sides of encasement with steel reinforcing
bar. Where ducts across under roadways, under such conditions, the complete
duct structure shall be supported on reinforces concrete footings, piers, or piles
located at approximately 1.5 m. intervals.
3) Duct markers shall be located at duct turning point and the ends of all duct runs
except at manholes or hanholes and at approximately over 100 meters of straight
duct runs. The marker shall be made of concrete slab and inscribed with the
necessary information; number and size of ducts.
1) Where the switchboard is delivered in more than one section, the sections shall
be joined together to form an integral unit.
2) The switchboard shall be installed with sides, front and back vertical and base
and top level. When the floor is uneven or not level, the base of the switchboard
shall be packed up until truly level before being grouted in position.
3) Before energizing, each switch shall be thoroughly cleaned. Any loose pieces of
packing material or other foreign bodies shall be removed.
4) The metal casings, and other non-current carrying metallic parts of the
switchboard shall be earthed. Unless otherwise specified the connection between
the main switchboard and earth electrode shall be by means of 25 mm x 6 mm
copper tape.
6) The various cubicles housing the respective switch and ACB shall be so arranged
as to give a multi-tier arrangement and shall include a cabling and wiring
chamber of sample dimensions in which terminal blocks, cable boxes and gland
plates can be located.
2) Flush mounting distribution boards shall be arranged so that the box assembly is
flush with the surface of the wall upon which the overlapping front plate is
mounted.
3) Spare ways shall be left in each distribution board. The number of spare ways
shall not be less than 20% of the total No. of ways in the board, unless otherwise
specified on drawing.
1) All surface cables shall be run in a neat and tidy manner, straight and plumb to
the satisfaction of the Engineer, and no diagonal run shall be permitted.
2) All cables shall be adequately protected against any risk of mechanical damage
to which they may be liable in normal conditions of service by adopting one of
the following means:-
3) All cable used as fixed wiring shall be supported in such a way that it is not
electrically sound. Joints in non-flexible cables shall be made by soldering,
brazing, welding, or mechanical clamps, or be of the compression type. All
mechanical clamps and compression type sockets shall securely retain all the
wires of the conductor.
5) Provide steel sleeve where cable passes through wall and floor. Clearance
between sleeve and cable shall be sealed with approved type form sealant with
sufficient fire rating.
6) The Contractor shall identify the ends of all power and control conductors,
circuits, and pull boxes. Each marker shall bear the circuit schedule on the
drawings.
7) All cables shall be carefully checked as to size and length before being pulled
into conduits. Cables pulled into the wrong conduit or cut too short shall be
removed and replaced. Cables removed from conduits shall not be installed in
another conduit without permission of the Engineer.
8) Finishing or pulling shall be done with a nylon rope or other approved devices.
1) All cables shall be run in concealed conduit, surface conduit, or metal trunking.
3) Cables in each sub-circuit, and in each sub-main shall be bunched, and tied or
clipped together inside the trunking.
5) Neutral cables of lighting final circuit shall be routed in conduit direct to the
lighting point and shall not pass through switch boxes.
6) The maximum number of cable shall be run in conduit as the following table.
Maximum Number of Conductor in Conduit or Tubing Table
1.5 5 10 18 31 45 - - - - -
2.5 3 5 9 16 22 28 - - - -
4 3 5 7 13 18 30 47 - - -
6 2 4 5 10 14 23 36 48 - -
10 1 3 4 6 9 15 22 32 44 50
16 1 2 3 4 5 9 14 21 28 37
25 - - - 3 4 7 11 16 22 28
35 - - - 2 3 5 8 13 18 23
50 - - - 1 2 4 6 9 13 16
70 - - - 1 1 3 5 8 10 13
95 - - - 1 1 2 3 6 8 10
120 - - - 1 1 2 3 6 8 10
150 - - - 1 1 2 3 5 7 9
185 - - - 1 1 1 2 4 5 7
240 - - - 1 1 1 1 3 4 6
300 - - - - 1 1 1 3 4 5
400 - - - - - 1 1 1 3 4
500 - - - - - 1 1 1 2 3
1) All cables shall be run in a vertical or horizontal direction. Only cables required
to feed a point on the ceiling may be fixed to the ceiling.
3) Cables shall not be permitted to run as a span between beams, trusses, etc.
without rigid support through their length.
5) Cables crossing expansion joints shall be formed into a loop such that any
movement in the joint shall not stress the cable.
6) Rubber grommets or insulated bushes shall be used to protect the cables when
passing through metal covers of distribution board, fluorescent lighting fitting's
boxes or any other metal work.
8) Cables shall be secured flat to the surface of walls and ceilings by means of
buckle clips or cable saddles.
1) The Contractor shall supply and install the supports, hangers, racks, trays, cleats,
saddles, clips securing devices, and other parts required to carry and secure the
cables without damage to the cables or to other equipments. Supports, cleats,
racks hangers, trays, saddles, and clips to be used shall be subject to the approval
of the Engineer.
2) The design of support and fixing items shall ensure freedom from rough edges,
burrs, and sharp corners and the materials used for the construction and fixing
thereof shall be approved by the Engineer.
4) The cable supports required for the insulation of single core cables forming
three-phase circuits shall permit the cables to be laid in close trefoil formation.
Non-magnetic metal cleats shall be used for this purpose.
5) Each cable termination and cable joint shall be completed with fittings,
terminating and jointing materials respectively and shall be provided with
consumable materials, such as wiper and solvent for cleaning, emery cloth for
insulation surface finishing as well as aluminum foil, mylar tape, fire and heat
resisting tape for cable annealing and straightening, if necessary.
6) Cable termination and cable joints shall be free from any electrical or mechanical
defects and shall be insulated from system shocks and switching surges.
7) The minimum impulse withstand voltage of the insulation section for the cable
joint shall not be less than for the cable.
9) Cables shall be sealed and placed on drums in such a manner that it will be
protected from damages during transportation. The drums are to be lagged with
closely fitted battens bearing a number and particulars of cable including voltage,
length, conductor size, no of cores and weights.
10) All cables, accessories and materials shall be subjected to and shall withstand
satisfactory the construction test, conductor continuity test, high voltage test,
insulation resistance test as required and specified in accordance with IEE
Regulation and British Standard.
3) Plug all open ends of conduits and draw boxes with corks or adequate stoppers to
prevent damage by concrete pouring,
4) Avoid chases on brick walls. Implement only with the Engineer’s approval,
5) Run conduits straight wherever possible. Avoid low level bends and traps where
water may accumulate. Loop in conduit from above,
7) Clean conduits free from dirt, moisture and burrs before pulling of wiring,
9) Provide suitable outlet and draw-boxes to cope with depth of concrete. Use deep
boxes as required,
2) Run surface conduits horizontally and vertically. Avoid diagonal runs. Arrange
conduits in neat and easily traceable routing, even where concealed inside
suspended ceilings,
4) Run conduits straight wherever possible. Avoid low level bends and traps where
water may accumulate. Loop in conduit from above.
1) Cable tray shall only be cut along a line of plain metal, i.e. not through the
perforations and all cut edges of galvanized cable tray shall be prepared and
treated with a cold galvanized paint.
3) Holes cut in cable tray for the passage of cables shall be provided with grommets
to B.S. 1767 or approved equivalent. Alternatively they shall be bushed or lined.
5) Fixings for cable tray shall be disposed at regular maximum intervals 1.2 mm
and at 225 mm from bends and intersections.
7) Cable tray shall be installed neatly on the surface of building and shall run only
vertically or horizontally along walls and not diagonally.
8) A minimum of 100 mm. of straight run shall be provided at each end of the bends
or tees. The inner radius of bend shall be greater than 100 mm.
9) Mushroom-head steel bolt and nuts shall be used for fixing adjacent sections of
tray.
4) Trunkings shall run neatly on the surface of the building and truly vertical or
horizontal along walls and no diagonal run shall be allowed.
6) Nominal lengths of trunking shall be not more than 2.4 m with length of trunking
cover not more than 1.2 m. Each length of trunking shall be equipped with a
sleeve type coupling and external earth bonding copper links on both side of
trunking.
7) Where connection is made between trunking and a distribution board, the cable
entry shall be sized to accept all cables from all used and spare ways.
8) Holes in trunking shall be drilled, punched or cut by ring saw and after cutting,
the sharp edges shall be:-
10) Fixing screws shall be steel for indoors and zinc plated steel for outdoors.
13) Cables for each circuit inside trunking shall be bunched and tied together and
with cable tag for identification.
16) Where cables may fall out when the trunking cover is removed, cable retaining
shall be by means of but joints and electrical and mechanical continuity shall be
maintained.
17) Connection between adjacent straight section, bends and tees of trunking shall be
by means of but joints and electrical and mechanical continuity shall be
maintained. Copper link of minimum cross-sectional area of 6 sq.mm shall be
provided for all trunking joints unless otherwise approved by the Owner.
Flexible earth cable is acceptable only for flexible joints.
18) The space factor for cables in trunking shall not exceed 45%.
20) Fire barriers shall be provided in vertical trunking and compartmentation wall to
prevent spreading heat or fire.
1) Lighting switches, switch sockets, socket and switch for electrical appliances
shall be designed for flush mounting.
5) Locations and mounting heights of switches and sockets shall be as shown on the
Drawings.
7) Switches when mounted adjacent to each other, shall be of same phase and in
groups under a common plate.
8) Sockets in both sides of a wall shall not be mounted back to back, but shall offset
minimum 300 mm.
9) Sockets and switches shall be 2 m away from water or gas pipes or sockets
connected to another phase.
12) All lighting for a public area shall not be wired on a single final circuit.
13) The neutral cable of lighting sub-circuits shall be looped by means of an
insulated connector enclosed in the switch boxes.
The work of all trades involved shall be so coordinated that exact locations may be
obtained for all outlets, apparatus, equipment and wiring.
The locations of outlets and fixtures shown on the Drawings are diagrammatic, and
shall be considered as approximate only. Before installing outlet boxes, all pertinent
Drawings shall be studies and precise information obtained from the Architectural
schedules, scale drawings, large scale and full size shall be understood that outlet
locations may be different from those shown on the Drawings, if so directed by the
Engineer. The Contractor shall make any necessary adjustment of the work to fit
conditions for recessed fixtures and for outlets in the duct chase panels, ceilings or
other special finish materials, in order that all boxes may register flush with the finish
and shall be centered properly. Outlets incorrectly located shall be properly relocated
at the expense of the Contractor.
2) Equipment shall be laid out in a neat and efficient manner to allow adequate and
sufficient maintenance space to all parts of the equipment.
4) Use proper hold down bolt spring washer and lock nut for supporting and fixing
all vibration equipment.
5) Fabricate all duct work to dimension taken on the Site. Erect and construct all
duct work rigidly, free from away, drumming and movement. Provide flexible
duct work connection with flange joint between radiator and connected duct
work.
6) Support oil tank on rigid steel angle frame bolted to the slab. Provide drain pan
for oil tank. Arrange oil tank such that all accessories are easily accessible.
Locate oil pump in an easy and convenient location.
2) The capacitor shall be installed and secured on rigid steel support. Capacitor case
shall be earthed.
4) Responsible for applying to the power companies for the necessary testing and
acceptance of capacitor installation on completion.
5) Complete installation shall be carried out in accordance with the NEC Standard
and to the satisfaction of the Engineer.
7) HRC fuses of adequate rating shall be used to protect each step of the capacitor
bank in the circuit.
2.3.16 Labelling
4) The front plates of switch sockets, control switches feeding essential circuits and
all fixed appliances, e.g. water heaters, cookers, fans radiator, incinerators,
exhaust fans, window units, etc. shall be engraved according to the appliance
being controlled.
5) Each of the outstation and interfacing termination cabinet shall be labeled on the
front cover indicating the field equipment controlled by the unit.
9) All switchgear in the main switchboard shall be labels of the tower block name
they serve.
2.3.17 Painting
1) Before painting the surface of the metalwork shall be completely cleaned and
free from rust, scale and grease.
2) Non-galvanized surfaces other than nuts, bolts and washers that may have to be
removed for maintenance purpose shall receive a minimum of three coats of
paint comprising the primary coat of rust inhibiting paint, one coat of contrasting
colour and one coat of the finished colour.
Excavation for duct or conduit laying or for foundations, and reinstatement shall
be carried out in accordance with the provisions in Section 2.3.2 of these
Specifications. Reinstatement shall be such that the surface is restored to at least
its original standard.
Excavation for cable laying in open ground shall be carried out by the
Contractor.
2) Concrete Work
All the signal post foundations and footings or other concrete work shall be
carried out in accordance with Part 1, Section 2. Foundation shall be placed in
one operation except that the top 5 centimeters may be placed after the
superimposed structure is in position. The exposed portions of foundations shall
be formed to present a neat and tidy appearance and sloped to shed water away
from the structure supported.
Conduits, fittings and boxed shall be provided and installed in accordance with
the provisions of Section 2 of these Specifications, except that chemically stable,
tough plastic conduits, fittings and boxes, according to samples previously
approved by the Engineer, shall be permitted providing that they do not soften
when exposed to high ambient temperature.
The Contractor may use a larger size of conduit that specified, at no extra charge,
if he wishes, but in this case the entire run shall be of the same size. No reducing
couplings shall be permitted.
All conduit ends shall be threaded and capped until wiring is started. When caps
are removed, the threaded ends shall be provided with approved conduit
bushings.
Conduit shall be laid to a depth of not less than 50 centimeters below paved
footwalks and medians and not less than 75 centimeters below the roadway
surface. The location of all conduits and curb lines shall be marked by means of
a “Y” at least 10 centimeters high incision in the face of the curb directly above
the conduit. Conduit terminating in standards, cabinets or pedestals shall extends
at least 5 centimeters inside the box wall and at least 5 centimeters vertically
above the bottom of the box. Wall and at least 5 centimeters vertically above the
bottom of the box. Such conduit shall be sloped towards the hand-hole opening.
Conduit entering pull boxes shall terminate at least 5 centimeters inside the box
wall and at least 5 centimeters vertically above the bottom of the box. Such
conduit shall be sloped towards the top of the box to facilitate puling. Conduit
entering the bottom of the box shall enter near the sides or end to leave the center
clear. All conduit shall enter in the direction of the run.
4) Pull Boxes
Pull boxes shall be installed at not more than 60 meter intervals. The
Contractor any install additional pull boxes without extra charge if
he wishes. Pull boxes shall be of reinforced concrete not less than 15
centimeters thick and may be of approved precuts design. Reinforced
concrete covers, secured by two recessed nickel-plated brass bolts shall be
used on foot walks, the covers being inscribed “Traffic Signals” on the
outside. Under the roadway, covers shall be of steel or cast iron inscribed as
specified above, and laid in a suitable concrete footing to withstand traffic
loads. Metal covers shall be effectively earthen to an earthling rod inside the
box. Tops of pull boxes shall be effectively level with surrounding paved
areas, whether footwork or roadway, but in unpaved areas, the tops of pull
boxes shall be buried 30 centimeters below ground level./ the bottom of pull
boxes shall be bedded in sand and cement. Permanent markers shall be provided
and erected to show the position of all boxes.
2.4.1 General
3) Testing on the entire installation shall be fully carried out in parts or as a whole
to demonstrate that the Works have been set in accordance with requirements of
this Specification.
4) All instruments, plant, supervision and labour required for the equipment and
system commissioning shall be provided by the Contractor. Instruments shall be
accurately calibrated to the satisfaction of the Engineer prior to commissioning.
5) The Contractor shall record all commissioning results on record sheets and
submit testing procedures and test record format to the Engineer for approval.
On completion of commissioning and prior to Final Inspections and Handover,
the Contractor shall submit the commissioning results in a bound volume to the
Engineer who reserves the right to witness such commissioning operations and
procedures as necessary.
6) All tests shall be witnessed by the Engineer and, in the case of routine/type tests
at the manufacturer’s works. The Contractor shall give advance notice (30 days
minimum) for this purpose.
7) All tests shall be properly certified in a format approved by the Engineer and test
certificates shall be submitted in triplicate to the Engineer on completion of
satisfactory tests.
8) The Contractor shall include in this bid all costs associated with all the
commissioning and testing procedures specified, including the costs of making
good any defects arising out of the tests and having the works re-tested as
necessary. Such costs shall include also provision of all commissioning and
testing instruments, test points, water and electricity supply.
2.4.2 Testing
2) The Contractor shall give seven (7) days for major test/inspection, three (3) day,
for minor test/inspection days advance notice before carrying out any test.
3) Test shall be witnessed by the Engineer at his sole discretion. The Engineer shall
reserve the right to request that the test be deferred or postponed if he would not
be available on the day proposed.
4) The Contractor shall adjust all circuit protective devices to produce proper
operation.
2.4.3 Submittals
1) Test Records:
a) The Contractor shall be responsible for all test records.
b) Record all test readings taken and incorporate into report in English.
c) Deliver report to the Engineer of each test period.
d) Arrange sequence of tests so equipment can be energized immediately
after successful completion of applicable test.
e) Schedule all tests as approved by the Engineer.
f) The Contractor shall be responsible for visual inspection of equipment
which shall be made immediately prior to energization of that equipment.
g) Prepare all test reports and have signed by the authorized witnesses.
h) Submit five (5) copies of test reports to the upon competition.
2) Submit four (4) certified copies of calibration tests on test equipment proposed
for testing; equipment shall have been calibrated within six months prior to start
of testing, unless otherwise specified.
Following test equipment shall be provided, used and operated by contractor. The test
equipment shall remain property of Contractor.
1) Wet and dry bulb thermometers.
2) 500 and 1000-volt meggers; 1000 volt megger shall be motor drive.
9) Circuit breaker test set for testing low voltage circuit breakers.
3) Megger between high voltage winding and low voltage winding ,high voltage
winding and ground, and low voltage winding and ground with 1000-volt
megger;
If readings are below 50 mega ohms at 25 deg. C., refer to the Engineer before
energizing transformer.
2) Megger each pole of breaker with 1000-volt megger for freedom from ground.
9) With breaker in switchgear, operate electrically operated breakers and check for
compliance with electrical diagrams on the Drawings.
10) Adjust and set trop units in accordance with coordinating study:
c) Current pick-up.
2) Test shall be accomplished by passing low voltage, high current through each
current sensor to include neutral sensor on circuits having neutral and measuring
time for breaker to trip open.
4) If trip times do not agree with manufacturer’s published curves, relays will be
recalibrated or replaced with ones that will tract curves.
5) Breakers having integral ground fault functions shall be tested with test sets that
will trip breaker and determine time taken to trip.
6) If measured resistance values are lower than above record room temperature and
humidity, submit readings to the Engineer.
8) Megger readings shall be one minute duration using 500-volt megger for all
motors.
10) If motor is free of dirt and dust, rotate motor by hand to determine that rotor turns
freely; clean out motor if necessary.
11) Apply voltage momentarily and note directing of rotation, if direction of rotation
is reversed, interchange two primary leads at motor; reconnect motor to driven
equipment.
12) After being placed in operating, observe motor frequently for heating at bearing
or windings.
3) Check overload relays for proper current range with motor nameplate full load
amperes; adjust relays for manual reset.
7) Check all auxiliary contacts for correct arrangement with coil de-energized,
normally open or normally closed.
8) Megger each pole of starter with 1000-volt megger for freedom from ground.
11) With motor disconnected, energize control circuits and test for correct
functioning.
12) For industrial type timing relays, adjust timing cycle for proper equipment
operation.
1) Annunciator tests:
a) Check each unit of annunciators by closing trouble contact and observing
annunciator operation on panels in control room and other panels having
annunciator.
2) Ammeter tests:
a) Check connections from current transformers for AC, and shunts for DC
to ammeters.
b) Check ammeter scale with current transformer ratio for AC, and shunts
millivolt rating for DC.
4) Voltmeter tests:
a) Check voltmeter with potential transformer ratio.
Physically check polarity mark orientation of all current transformers and potential
transformers with manufacturer’s drawings.
(1) Megger all 750 volt cable with 500-volt megger for one minute.
(2) Values shall be approximately as follows :
0.24 1,000,000
25-50 250,000
50-100 100,000
101-200 50,000
201-400 25,000
401-800 12,000
over 800 5,000
(3) Values shall be determined with all switchboards, panel boards, fuse holders,
switches, and overcurrent devices in place.
(4) Motors and transformers shall not be connected during meggering.
(5) Wire and cable shall not be megged on cable reel but after installation.
2.4.15 Testing of Field Test for Data Communication and Signaling Electronic Cable
(2) Cable connectors shall be installed and splicing and terminations complete
before testing.
(3) Test results shall document date, equipment used, testing personnel, location
by junction box number and resistance reading of each multi-pair or coaxial
cable by color code or coaxial number.
(4) Cables with any conductor resistance greater than 125 percent of
manufacturer’s specifications shall be replaced prior to system acceptance.
(1) Conduct tests in accordance with ICEA S-66-524, IES Standard 502 and
following :
(2) Hi-Pot test instrument shall have been factory calibrated within three months
prior to start of cable testing.
b) De-energize normal source and observe that switch transfers to standby source
and then return to normal source when restored.
d) Observe that all auxiliary contacts which alarm or operate other devices
perform intended functions as shown on the Drawings or as specified.
e) Test control devices for operation, all time adjustments shall be set and tested.
(2) Megger each phase with 100-volt megger for freedom from grounds.
2.4.21 Grounding
(2) Tests shall be made using electrical safety analyzer and results shall be
recorded identifying circuits, equipment, and enclosure locations.
3) a “megger” test shall be made between each circuit and earth and between
each circuit and every other circuit. A voltage of at least 500 volts shall be
applied for at least 30 seconds. During the test, the resistance shall be at least
0.5 mega ohms. The insulation resistance shall be shown to be least that
specified within the relevant Codes. On the completion of testing, the
Contractor shall supply to the Engineer three copies of “as built” plans of
wiring locations and circuit diagrams, which shall clearly indicate any
modifications which have been made to the original design.
2.5.1 Measurement
(1) Cable, Duct Bank, Manhole and Handhole, Conduit or Cable Trench
c) Duct Bank
(2) Substation
Measurement shall be made in number of each type of carpark and fence lighting
installed including flood light luminaries and control gear, steel pole, concrete
foundation, grounding system, lightning protection air terminal, copper wires and
fixing accessories, obstruction light, conduit, wire and all accessories.
Measurement shall be made in lump sum of each type of traffic signal system
installed including controller, detector, lighting head, standard steel
pile, foundation, grounding, wiring and all accessories.
(c) Switch
(d) Outlet
(e) Luminaires
(g) Grounding
Measurement shall be made in lump sum for each building including copper
wire, air terminal wire saddle, down conductor, ground rod, connector and
all accessories.
2.5.2 Payment
Payment shall be made against the unit rates entered into the Bill of Quantities. The unit
rates shall be deemed to include all costs of materials, labor and equipment for
manufacturing, supplying, delivering, installing and testing of all Works.
2.6.1 Introduction
The quality of all material shall comply with the standards specified in, these
Specifications and the details shown on the Drawings and diagrams. They shall further
be of recommended performance suitable for the Works.
(1) 22 KV Switchgear
AEG
ABB
Merlin Gerin
Siemen
Ekarat, Local
Tirathai, Local
GE
Square-D
ABB
Siemens
AEG
Merlin Gerin
Bticino
(4) Panelboard
Square-D
ABB
Merlin Gerin
Bticino
GE
Square-D
ABB
Bticino
Siemens
AEG
National
ABB
Merlin Gerin
Siemens
AEG
Sprechcher & Schuch
Telemecanique
ABB
Gossen
Crompton
Westinghouse
Siemens
ABB
KWK
Merlin Gerin
AEG
Caterpillar
Cummin
FG Wilson
Volvo
MK
National
Bticino
legrand
Eagle
National
Gewiss
(15) Building Luminaire
Philips
Tralux
SECO
Metrolite
WE-EF
(16) Outdoor Luminaire
Part 8/Section 2 8-2-104
WE-EF
Philips
Econlite
Sunny
CEE
Safeguard
(18) Lamp
Sylvania
Osram
Philips
(20) Ballast
May & Christ
Schwabe
Philips
MK
Vosloh
(21) Starter
Sylvania
Osram
Philips
(23) Conduit
Matsushita
TAS
UL
E.F.